AI assistant
HAWSONS IRON LTD — Investor Presentation 2011
Oct 26, 2011
65053_rns_2011-10-26_3e5348f7-0c26-4e54-a577-4031fb9acb0a.pdf
Investor Presentation
Open in viewerOpens in your device viewer
==> picture [720 x 199] intentionally omitted <==
==> picture [320 x 91] intentionally omitted <==
==> picture [139 x 84] intentionally omitted <==
Oct 27[th] 2011
==> picture [58 x 58] intentionally omitted <==
Carpentaria Exploration Limited We find it. We prove it. We make it possible.
==> picture [64 x 65] intentionally omitted <==
==> picture [64 x 65] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 1
CARPENTARIA
==> picture [160 x 109] intentionally omitted <==
==> picture [123 x 212] intentionally omitted <==
==> picture [173 x 111] intentionally omitted <==
==> picture [250 x 122] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
==> picture [304 x 420] intentionally omitted <==
Slide 2
CARPENTARIA EXPLORATION LIMITED Disclaimer
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
This presentation has been prepared by the management of Carpentaria Exploration Limited (CAP) for the benefit of analysts, brokers and investors and not as specific advice to any particular party or persons. The information is based on publicly available information, internally developed data and other sources. Where an opinion is expressed in this presentation, it is based on the assumptions and limitations mentioned herein and is an expression of present opinion only. No warranties or representations can be made as to origin, validity, accuracy, completeness, currency or reliability of the information. CAP disclaims and excludes all liability (to the extent permitted by law) for loses, claims, damages, demands, costs and expenses of whatever nature arising in any way out of or in connection with the information, its accuracy, completeness or by reason of reliance by any person on any of it. Where CAP expresses or implies an expectation or belief as to the success of future exploration and the economic viability of future project evaluations, such expectation or belief is expressed in good faith and is believed to have a reasonable basis. However, such expected outcomes are subject to risks, uncertainties and other factors which could cause actual results to differ materially from expected future results. Such risks include, but are not limited to, exploration success, metal price volatility, changes to current mineral resource estimates or targets, changes to assumptions for capital and operating costs as well as political and operational risks and governmental regulation outcomes. CAP does not have any obligation to advise any person if it becomes aware of any inaccuracy in or omission from any forecast or to update such forecast.
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 3
Exploration and Value Creation Strategy
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Discovery
-
Explore in areas for favourable for rapid discovery
-
Move projects through pipeline - advance or considered divestment
Development of Hawsons
-
to provide long term cash flows, and
-
near term cash payments
Acquisition
- advanced projects, operations, and other opportunities
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
==> picture [193 x 128] intentionally omitted <==
==> picture [375 x 270] intentionally omitted <==
Slide 4
Achievements to Date
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
2007 - November IPO - $7.5m 2008 - Kept exploring through GFC - Acquisition of Coal tenements in Gallilee 2009 - Discovery Hawsons Iron Project – magnetite iron - Discovery Tin at Mt Euriowie 2010 - Sign JV with BMG on Hawsons ($81m deal- $13m upfront) - Options exercised raises $6m - Inferred Resource at Hawsons 2011 - Prefeasibility delivered at Hawsons - Realized profit on Hughenden Coal Project ($4m + royalty) - Acquired Koonenberry Nickel-Copper Project - Acquired Yanco Glen Tin-Tungsten (resource) 2012 - $25m cash payment from BMG due by May 2012
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 5
Company Snapshot
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
ASX : CAP FINANCIAL 25[th] Oct 2011 Cash A$9.4 million QUOTED SECURITIES 99.0 m shares LARGEST SHAREHOLDERS Aust’ Conglin Int’ Inv’ : 10.6% Conglin Yue : 3.7% Atlas Iron Ltd : 8.7% Directors & Management (inc’ unlisted Options) : 12.61% INVESTMENTS 2.2 m Guildford Coal Ltd fully paid shares – value $2.2m 25[th] Oct
==> picture [404 x 179] intentionally omitted <==
Share Price and Volume 12 months
KEY ASSET – Hawsons Iron Project JV – Carpentaria 60%
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 6
HAWSONS IRON PROJECT Largest Magnetite Project in NSW
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
==> picture [507 x 379] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 7
WHY MAGNETITE ?
Global Iron Production
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
==> picture [709 x 358] intentionally omitted <==
----- Start of picture text -----
5
7
6
1
4
3
2
8
30 % Contained Iron Produced From Magnetite Sources
Source USGS 2010 Production Rankings Rankings
----- End of picture text -----
2010 Production Rankings Rankings Source USGS
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 8
The Truths the Hematite Producers
Do not want us to know
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
==> picture [411 x 290] intentionally omitted <==
----- Start of picture text -----
Hawsons Magnetite
69.9%
----- End of picture text -----
Macquarie Commodities Research – June 8[th] 2011 Quote :
“suppliers are continually striving to stand still in terms of grades”.
Analysis of Australian export trade values, using the Platt's 62% index (FOB Australia basis) has assessed implied export grade – see graph.
“…it does still suggest average grades are down”
Makes magnetite – high grade low deleterious material - more and more valuable
==> picture [88 x 52] intentionally omitted <==
Slide 9
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
==> picture [108 x 76] intentionally omitted <==
WHY MAGNETITE
Price Premium (Platt’s)
==> picture [432 x 404] intentionally omitted <==
Oct 25[th] : Price /t for 62% Fe – U$138.5 (Hematite)
Thus for 69% Fe ~ U$154.1 (Magnetite)*
- Simple extrapolation but would expect a premium for high quality con’ with low impurities
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 10
AUSTRALIAN IRON PRODUCERS
And Deposits (Generalised)
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
==> picture [638 x 401] intentionally omitted <==
----- Start of picture text -----
Hawsons Project :
Largely H
Power
Rail
Water
No Native Title
Largely M
Largely M
M = magnetite
H = Hematite
Largely M
----- End of picture text -----
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 11
HAWSONS IRON PROJECT
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
==> picture [384 x 227] intentionally omitted <==
-
Prefeasibility Study – positive
-
Resource – very large with potential
-
for 50 year mine life
-
Magnetite – premium price for quality product, strong demand
-
Infrastructure – water, power and transport all available for start up
-
Mining – very low unit costs because low strip ratio, very wide mining widths, low abrasion index and single pit
Native Title has been extinguished
==> picture [120 x 127] intentionally omitted <==
==> picture [94 x 123] intentionally omitted <==
==> picture [120 x 126] intentionally omitted <==
-
Processing - comparatively very low
-
cost because of very soft mineralised rock
==> picture [88 x 52] intentionally omitted <==
Slide 12
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
HAWSONS IRON PROJECT
Exploration Target
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Exploration Target[1] 6 to 11 Billion Tonnes
DTR 14-17% magnetite
- Concentrate Grade of 69-71% Fe
Contained Iron : 700 - 1,700 million tonnes
==> picture [583 x 208] intentionally omitted <==
As big as some of the larger Pilbara resources
==> picture [88 x 52] intentionally omitted <==
1 The potential quantity and grade of the exploration targets is conceptual in nature and there has been Slide 13 Carpentaria Exploration Ltd Oct 27th 2011 insufficient exploration to define a Mineral Resource. It is uncertain if further exploration will result in the determination of a Mineral Resource. We find it. We prove it. We make it possible.
HAWSONS IRON PROJECT Inferred Resource
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Maiden Inferred Iron Resource Published (Dec 2010)
1.4 Billion Tonnes
Davis Tube Recovered Grade (DTR) 15.5% (cut off grade 12%) Concentrate Grade – 69.9% Fe, 2.5% SiO2 Contained Iron : 220 million tonnes
==> picture [720 x 290] intentionally omitted <==
----- Start of picture text -----
Eastern limit of
Inferred Resource
Modelled deposit
(Red, yellow, purple
all iron units)
and PFS Pit Shell
over the
Aeromagnetic image
Slide 14
Carpentaria Exploration Ltd Oct 27th 2011
We find it. We prove it. We make it possible.
----- End of picture text -----
HAWSONS IRON PROJECT
Mining
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Simple Open Cut
- Waste to ore ratio – 0.26 : 1
+ 600 m mining widths
-
Pre strip – start mining east end
-
Truck and Shovel operation
-
Blasting
==> picture [313 x 213] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Pit Area Pit dimension ~ 3.6 km x 1.4 km Depth 490 m
Slide 15
HAWSONS IRON PROJECT PFS Results (July 20[th] )
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Pre-Feasibility Study (PFS) Base Case produce 20 million tonnes (mtpa) of high grade concentrate (69.9% Fe) over 20 year plus life
-
Start up mine 5mtpa using existing transport and port facilities
-
Development capital expenditure (20 mtpa) estimated at A$2.8 billion Operating cost at mine gate of A$36.64/tonne of concentrate
| Using Sept’ 26 2011 prices annual gross profit averages $2.1bn NPV 9% IRR Annual ave. Gross Profit Payback Base Case Life of Mine $88 US/DMT, (69% Fe) A$0.85:US$1.00 $2.8 Bn 21% $688 m 6.5yrs |
NPV 9% IRR Ann Gros |
ual ave. s Profit Payback |
|
|---|---|---|---|
| Base Case Life of Mine $88 US/DMT, (69% Fe) A$0.85:US$1.00 |
$2.8 Bn 21% $6 |
88 m 6.5yrs |
The positive result from the pre-feasibility study provides confidence to proceed with further development and a detailed feasibility study for the Hawsons Iron Ore Project
==> picture [88 x 52] intentionally omitted <==
Slide 16
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
HAWSONS IRON PROJECT Processing
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
- Use low risk “off the shelf” processing technologies
Ore 50-75% softer and 60-70% less abrasive than other magnetite ores Bond Work Index 6.3 kWh/t (very low cf WA magnetites) Abrasion Index 0.09 cc
==> picture [168 x 53] intentionally omitted <==
Very Low Processing Costs
Test work at CSIRO / ALS produces High grade premium marketable products Pellets using local clay 38 micron fines
==> picture [203 x 156] intentionally omitted <==
==> picture [173 x 155] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Slide 17
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
HAWSONS IRON PROJECT Independent Audit
==> picture [108 x 76] intentionally omitted <==
Independent audit of PFS
PFS based on conventional mining and processing method Cost estimates are reasonable and appropriate
- Identified priority areas to assist in DFS inc’ optimising production schedule
==> picture [302 x 200] intentionally omitted <==
==> picture [177 x 109] intentionally omitted <==
==> picture [133 x 110] intentionally omitted <==
==> picture [136 x 112] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Slide 18
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
HAWSONS IRON PROJECT “Priority Areas” Study
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Objectives:
-
Minimise the trucking hours – the major operating cost in PFS
-
Investigate potential Mining Improvements
-
Revised Mine Planning Options
-
Mining Rates
-
Stockpile Minimisation
-
-
Waste Dump Relocation
-
In Pit Crushing, Conveying & ROM Relocation
Study results to be Optimised
==> picture [303 x 314] intentionally omitted <==
----- Start of picture text -----
12.0
10.0
10.0
9.3
9.1
8.0
6.2
6.0
4.0
2.0
0.0
Total PFS Revised Mine Waste Dump IPCC + ROM
Truck Hours Planning Relocation Relocation
Options
LOM Truck Hours (Million)
----- End of picture text -----
Reduction 3.8 M hrs
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011
We find it. We prove it. We make it possible.
Slide 19
HAWSONS IRON PROJECT Work Program – 6 months
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
-
Undertaking Environmental studies Field measurements continuing
-
Metallurgical studies
-
Determine optimum crushing circuit
-
Develop pilot plant tests
Aim :
-
Reduce Operating costs
-
Reduce Capex
-
Secure Approvals
-
Mining Secure transport Optimising mining scenarios Minimising stockpiles Produce a solid base to start Definitive Feasibility (DFS)
-
Geological study (to commence when Reviewing resource model BMG provides funding)
-
Optimising transport options BMG has until 15th May 2012 to make this election
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 20
HAWSONS IRON PROJECT
JV Deal
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Bonython Metal Group Ltd (BMG) earning in
Advantage to CAP No scrip issued
-
BMG vested 40%
-
$25m cash to CAP and ~ $20m for BFS BMG vests 51%
-
Before 15 May 2012
-
On completion BFS (within 2 years) $23m cash to CAP - BMG vests 80%
-
On decision to mine CAP has free carried to production of 20mtpa CAP receives profits on 20% production at zero cost
Project deal only Cash to CAP Total $53.0m
Free Carried Huge value
CAP to market 4 million tonnes con’ in own right
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 21
HAWSONS IRON PROJECT
CIF China Comparison June 2011
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
==> picture [720 x 443] intentionally omitted <==
----- Start of picture text -----
Carpentaria
PFS – 20mtpa
US$63
Slide 22
Carpentaria Exploration Ltd Oct 27th 2011
We find it. We prove it. We make it possible.
----- End of picture text -----
==> picture [108 x 76] intentionally omitted <==
DEVELOPMENT OF HAWSONS Conclusion
==> picture [720 x 5] intentionally omitted <==
==> picture [146 x 137] intentionally omitted <==
==> picture [139 x 125] intentionally omitted <==
-
Hawsons is a very robust project
-
Many advantages over peers including Power, water, rail, near mining culture Soft, low abrasive ore
Many tonnes – long life mine Cash flow early using existing infrastructure Rapid pay back for investors
==> picture [170 x 136] intentionally omitted <==
==> picture [165 x 133] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
==> picture [159 x 120] intentionally omitted <==
Slide 23
Project Pipe Line Status
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
Development
-
Hawsons Iron Project (NSW): Magnetite
-
PFS Finalised, gearing up for DFS
Drilling
-
Koonenberry (NSW) (100% CAP) : Nickel-Copper
-
Drilling post lambing (Nov’ 2011)
-
:
-
Broken Hill Tin-Tungsten Project (NSW) (100% CAP)
==> picture [173 x 178] intentionally omitted <==
-
Drilling –2012
- upgrade tungsten resource
-
Concept Study underway
- Develop economic model – early cash flow ?
-
Torrawangie (NSW) (100% CAP) : Iron ( Mar 2012 ?)
-
Mapping, magnetics drilling
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 24
Project Pipe Line Status (Cont’)
==> picture [108 x 76] intentionally omitted <==
-
Temora (NSW) (100% CAP) : : Gold
-
Awaiting access - drilling (Dec?)
-
Mapping defining other gold targets
Project Generation
-
:
-
Barellan (NSW) (100% CAP) Gold – Awaiting grant
: : Kantappa (NSW) (100% CAP) Tin – Awaiting grant
JV’s
Mt Agate (Qld) (ActivEX Ltd earning in): copper / gold drill targets being defined South Dam (SA) (BMG earning in): magnetite Drill targets defined
Divestment and reappraisal
-
McDougalls (NSW)
-
Hughenden Coal – completed
==> picture [228 x 368] intentionally omitted <==
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 25
CARPENTARIA
In Brief
==> picture [108 x 76] intentionally omitted <==
==> picture [720 x 5] intentionally omitted <==
GROWTH THROUGH SUCCESS
==> picture [88 x 52] intentionally omitted <==
Carpentaria Exploration Ltd Oct 27th 2011 We find it. We prove it. We make it possible.
Slide 26
‘Follow’ us on Twitter @carpexplore ‘Like’ us on Facebook Watch our channel on YouTube Search: carpexplore The information in this presentation that relates to Exploration Results and Resources is based on information compiled by S.N.Sheard, who is a Fellow of the Australian Institute of Geoscientists and has had sufficient experience which is Carpentaria Exploration Limited relevant to the style of mineralization and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. S.N.Sheard is an employee of Carpentaria and consents to the Nick Sheard - Executive Chairman inclusion in the report of the matters based on his information in the form and context in which it appears. Telephone: 617 3220 2022 Level 6, Facsimile: 617 3220 1291 345 Ann Street Email: [email protected] Brisbane, QLD 4000 ~~Web: www.carpentariaex.com.au~~ PO Box 10919, Adelaide St ASX Code: Carpentaria Exploration Ltd Oct 27th 2011 CAP Brisbane QLD 4000 ABN: We find it. We prove it. We make it possible. 63 095 117 981
Slide 27