HAWSONS IRON LTD Capital/Financing Update 2024

Oct 14, 2024

65053_rns_2024-10-14_4f68588f-cfa7-4be0-92cc-11af53b0a7ec.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

15 October 2024

==> picture [253 x 49] intentionally omitted <==

Optimisation Works – Update


Highlights

  • consumption within the comminution circuit by in excess of 30%.

  • Early (gangue) material rejection of around 20% may be possible using a preliminary magnetic separation stage.

  • Potential exists to reduce water requirements for the Project by 25% utilising this alternative approach to comminution.

  • These outcomes are in line with the program’s focus on capital and operating costs reductions as well as improving the long-term environmental sustainability of the Project.

  • Stantec has commenced the second phase of the optimisation works which will focus on developing CAPEX / OPEX estimates.

____________

Emerging magnetite development company Hawsons Iron Ltd (ASX:HIO) (“Hawsons” or the “Company”) is pleased to provide investors an update on its current optimisation study. This work being carried out by independent engineering firm Stantec Australia (“Stantec”) incorporates a detailed review of the current process plant design and supporting infrastructure.

Hawsons CEO, Tom Revy, commented : “This phase of optimisation work has successfully demonstrated the high-level technical feasibility of an alternate and tailored route for recovering magnetite at the Hawsons Project. Work continues on determining the financial implications while plans are being discussed to pilot the alternate process route to confirm the full potential of energy and water savings.”

The work completed utilised existing process related data derived from the 2023 pilot test work program[1] .

and fine-grained silica sand, early in the process, offering the opportunity to potentially produce a sand-based by-product for sale into the sand and construction industry.

1 - https://hawsons.com.au/wp

content/uploads/2023/09/Pilot_Testing_Program_Validates_New_Stantec_Processing_Design_12.09.23_FINAL.pdf

Page 1 of 2

==> picture [452 x 251] intentionally omitted <==

Minus 1mm Non-Magnetic Tailings Containing Silica Sand Material

As a critical component for derisking the Project, a pilot test work program for this revised comminution circuit, will be required to support further refinement of a final flowsheet which will be undertaken as part of the final DFS.

The information and high-level estimates contained in the Stantec report will be covered as part of ongoing Strategic Investor discussions.

The next phase of work is to liaise with the equipment manufacturers and operators, and to develop 2024 major equipment costing for the alternative processing routes as inputs into the current CAPEX/OPEX estimates.

The study is expected to be completed within the next 3 weeks.

This announcement is authorised by the Board .

For further information contact: Tom Revy Chief Executive Officer [email protected] +61 411 475 376