ASX Announcement
C4 Iron Ore Deposit – Production Update & Stage 2 Progress
HIGHLIGHTS
-
Fourth shipment with 52,990 wet metic tonnes (wmt) of iron ore, consisting of 38,300 wmt of lump and 13,990 wmt of fines successfully departed Geraldton Port on 16[th] May 2021. A total of 208,360 tonnes has now been exported.
-
GWR confirms it has secured the “MV Yarrawonga” and this ship is due to commence loading at the Port of Geraldton between the 8[th] and 12[th] June 2021.
-
Recent improvement in haulage volume will enable confirmation of a second vessel for the month of June to deliver 6 shipments in the half year, loading at the Port of Geraldton will likely commence between the 22[nd] and 26[th] June 2021.
-
GWR expects to ship at least twice per month from that point on which will see it on track to complete its 1MT Stage 1 production target by December 2021.
-
GWR has executed an agreement with a large privately owned haulage and logistics group to partner with it and to enable GWR to underpin its haulage operations to the Port of Geraldton.
-
Haulage volumes are now exceeding the company’s daily haulage tonnage target of 2,700 tonnes per day to the Port of Geraldton.
-
Secured additional crushing capacity, which has mobilised to site and has had an immediate effect with increased production and an improvement in fines grade by selective scalping.
-
Mining at the C4 pit has to date only been undertaken on day shift and expanding the mining to 24 hour operation is being reviewed.
Stage 2
-
GWR has finalised a pit design and mine schedule for an expanded Stage 2, C4 pit. Combined Stage 1 and Stage 2 pits will extract approximately 3.2 million tonnes of iron ore at a low stripping ratio of just 1.2:1.
-
Substantial widths up to 130m of high grade mineralisation will be exposed in Stage 2 - C4 pit (Figure 1).
-
GWR with its Alliance Partner Pilbara Resource Group (“PRG”) are currently negotiating the terms for Stage 2 and expect to update the market on this shortly.
GWR Group Limited (ASX: GWR ) (“ GWR Group ” or “the Company ”) is pleased to provide this significant production update to shareholders for the GWR’s 100% owned flagship C4 Iron Ore deposit in Wiluna, involving both Stage 1 and Stage 2 operations.
The Company’s fourth shipment of iron ore departed Geraldton Port upon MV Banasol on the 16[th] May 2021. The ship contained 52,990 wmt of iron ore consisting of 38,300 wmt of lump and 13,990 wmt of fines. A total of 208,360 tonnes has now been exported pursuant to GWR’s offtake agreement with Hong Kong Trader, Pacific Minerals. A fifth ship is scheduled to dock at the Port of Geraldton between the 8[th] and 12th of June.
GWR has been focused on improving the haulage component of its operations and has seen significant recent improvements, for the first time since production commenced. GWR will today book a second vessel for the month of June to deliver 6 shipments in the half year, loading is anticipated to commence at the Port of Geraldton between the 22[nd] and 26[th] June 2021.
GWR expects to ship at least twice per month for the remainder of the calendar year which will see it on track to complete its 1MT Stage 1 production target by December 2021.
Key and significant recent improvements include:
-
The Alliance partners having been able to secure additional crushing capacity, which has mobilised to site and has had an immediate effect with increased production and an improvement in fines grade by selective scalping.
-
With drilling, crushing and haulage operating 24 hours per day, mining at the C4 pit has to date only been undertaken on day shift and expanding the mining to 24 hour operation is being reviewed and has the potential to significantly increase production and reduce fixed cost.
-
The addition of a large hauage contractor to the existing fleet provides critical additional logistics support.
-
The daily haulage tonnage to Geraldton continues to increase and extra capacity continues to be secured with volumes now approaching 3,000 tonnes per day which exceeds the company’s target of approximately 2,700 tonnes per day.
Stage 2
GWR has now received a pit design and mine schedule for the expanded Stage 2, C4 pit. The combined Stage 1 and Stage 2 pits will extract approximately 3.2 million tonnes of iron ore at a stripping ratio of only 1.2:1.
As Figure 1 shows substantial widths up to 130m of high grade mineralisation of will shortly be exposed in the Stage 2 pit at depths of approximately 5 to 10 m below the C4 pit floor as of 30[th] April 2021.
With the addition of a large hauage contractor as mentioned above to the existing fleet, GWR is confident it can continue to take advantage of the buoyant iron ore prices.
GWR with its Alliance Partner Pilbara Resource Group (“PRG”) are now planning to significantly expand production activities, including mining, crushing and haulage and are negotiating the terms for Stage 2.
==> picture [452 x 410] intentionally omitted <==
Figure 1: C4 Deposit showing the outline of the proposed Stage 2 Pit
GWR Chairman Mr Gary Lyons commented “I am delighted to inform shareholders of the significant improvements achieved in Stage 1 operations and with our Alliance Partner Pilbara Resource Group we have and will continue to remain committed to increasing production, haulage and export of our high grade Iron Ore.
Following a significant review process for Stage 2, it became evident with mining and processing efficiencies in particular, it was economically logical to expand Stage 1 and combine it with Stage 2.”
I am pleased that we are able to build on the success we have seen for Stage 1 with Pilbara Resource Group continuing to deliver mining crushing and haulage services, and now the recent addition to our haulage capacity will underpin our Stage 2 expansion with the support we were seeking in that critical area.”
This ASX announcement was authorised for release by Gary Lyons, Chairman of GWR Group Limited
For further information please contact:
Gary Lyons David Utting Mark Pitts Chairman David Utting Corporate Company Secretary Ph: +61 416187462 E: [email protected] E: [email protected] E: [email protected]
Competent Person’s Statement
The information in this report which relates to Exploration Targets, Exploration Results and Mineral Resources or Ore Reserves is based on information compiled by Mr Allen Maynard, who is a Member of the Australian Institute of Geosciences (“AIG”) a Corporate Member of the AusIMM and independent consultant to the Company. Mr Maynard is the Director and principal geologist of Al Maynard & Associates Pty Ltd and has over 40 continuous years of exploration and mining experience in a variety of mineral deposit styles. Mr Maynard has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for reporting of Exploration Results, Exploration Targets, Mineral Resources and Ore Reserves” (JORC Code). Mr Maynard consents to inclusion in the report of the matters based on this information in the form and context in which it appears.
The Mineral Resource Estimate was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported.
Table 2. Wiluna West Iron Ore Project Mineral Resources by Deposit
==> picture [470 x 628] intentionally omitted <==
Note: Differences may occur due to rounding. Refer ASX Announcements 12[th] November 2019, 8[th] July 2011 and 11 April 2013.