GRANGE RESOURCES LIMITED. Interim / Quarterly Report 2020

Jan 24, 2021

65014_rns_2021-01-24_8c0ed74e-5ede-4981-948b-79d883fb704c.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

==> picture [557 x 131] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
31 December 2020
25 January 2021
ASX: GRR
----- End of picture text -----

REPORT FOR THE QUARTER ENDED 31 December 2020

HIGHLIGHTS

  • The operation achieved over 1380 days Lost Time Injury Free.

  • COVID-19 controls remain in place with travelling and opening borders monitored closely, as the Company continued to prioritise the health, safety and well-being of our workforce.

  • Pellet production decreased for the quarter with 479kt compared to 639kt for the September quarter due to the planned major shut for the steel pan conveyor installation.

  • Pellet sales increased for the quarter to 754kt compared with 422kt for the September quarter.

  • Increase in average received prices for the quarter to US$174.69/t (A$236.77/t) (FOB Port Latta) compared with US$130.22/t (A$182.49/t) for the September quarter.

  • Unit cash operating cost decreased for the quarter to A$101.13/t compared with A$101.45/t for the September quarter.

  • Cash and liquid investments of A$202.93 million and trade receivables of A$79.32 million compared with cash and liquid investments of A$175.53 million and trade receivables of A$13.15 million for the September quarter.

  • Outlays of approximately A$16.7 million have been made in the quarter on capital projects including Mine Control, Truck Trays, NP Open Pit drilling program and Pellet Plant improvement projects.

Page 1 of 6

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
31 December 2020
----- End of picture text -----

“Grange management are happy with the very strong fourth quarter that completes a strong 2020, particularly delivering exceptional sales volume figures in combination with record sales prices in recent years. This is coupled with the production team’s continued strong performance. The team is to be commended for their efforts and results achieved, especially in the current COVID-19 environment as safety remains our number one priority.” said CEO Mr. Honglin Zhao.

“The great result achieved by our downstream processing and engineering team in successfully installing and commissioning the Steel Pan Conveyer system in a shorter time than planned. This enables higher quality pellets with higher compression strength to be produced, reduced down time and less maintenance and more effective use of energy.”

SAVAGE RIVER OPERATIONS

PRODUCTION

December
Quarter
2020
September
Quarter
2020
June
Quarter
2020
Total BCM Mined 3,281,599 3,512,985 3,710,712
Total Ore BCM 487,279 541,788 222,163
Concentrate Produced(t) 632,817 649,084 649,377
Weight Recovery (%) 43.5 44.0 46.5
Pellets Produced(t) 479,047 639,420 640,922
Pellet Stockpile(t) 119,966 395,391 178,138
Concentrate Stockpile(t) 137,580 0 1,872

The health, safety and well-being of our workforce has remained a key focus with attainment of over 1,380 days Lost Time Injury free. COVID-19 controls remain in place and the operation has been unhindered as we continue to protect our people at work and at home. Border restrictions have eased but conditions vary as cases develop around the country. Hotspots and travel arrangements have been proactively monitored and managed to protect the workforce and sustain safe operations.

Mining activities have been focused on mining ore from the Main Ore Zone in North Pit with some delays encountered contributing to less overall movement for the quarter. Remediation works have been undertaken on the east wall of North Pit, along with additional safety controls installed to reduce the risk of small rockfalls.

Movement from the first stage of Centre Pit continued. The Environmental Impact Statement was submitted to the EPA to seek approvals for subsequent stages of mining in Centre Pit. This is undergoing, with the review process likely to proceed through Q1,2021.

Downstream processing rates were down on the previous quarter due to the scheduled maintenance works and plant shutdown in November. This allowed the installation, commissioning and successful operation of a new Steel Pan Conveyor. This Germanengineered conveyor system is 110-metres-long and takes the hot pellets from the furnaces

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 2 of 6

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
31 December 2020
----- End of picture text -----

discharge out of the plant for stockpiling. It carries hot pellets more than 600 degrees Celsius and allows them to cool more slowly by air, improving their strength. The commission was completed within 23 days, well under half the recommended installation time, through careful planning and well managed execution. The new conveyor is performing well, supporting full production rates and will be monitored continually as part of our commission to full operations strategy . Other projects including the changeout of the Bentonite Baghouse structure, structural repair works on plant infrastructure and the installation of a Sodium Hydroxide system were all completed successfully through the maintenance period.

SHIPPING AND SALES

SHIPPING AND SALES
December
Quarter
2020
September
Quarter
2020
June
Quarter
2020
Iron Ore Pellet Sales(dmt) 754,472 422,167 642,299
Iron Ore Concentrate Sales(dmt) 0 0 0
Iron Ore Chip Sales(dmt) 31,526 41,704 20,010
TOTAL Iron Ore Product Sales(dmt) 785,998 463,871 662,309
Average Realised Product Price
(US$/t FOB Port Latta)
174.69 130.22 112.72
Average Realised Exchange Rate
(AUD:USD)
0.7378 0.7136 0.6596
Average Realised Product Price
(A$/t FOB Port Latta)
236.77 182.49 170.89

The average A$ price received during the quarter of A$236.77/t (US$174.69/t) (FOB Port Latta), increased by 29.74% from A$182.49/t (US$130.22/t) for the September Quarter.

Grange continues to deliver into secured term offtake agreements realising higher prices for our lower impurity and high-quality products. Grange has fully allocated all of 2021 production through offtake agreements at an additional premium above the 65% Fe fines and pellet premium indices. This demonstrates the continued strong demand for Grange’s high quality and low impurity products.

MINE DEVELOPMENT PROJECTS

North Pit Underground

Prefeasibility study work continues with designs and schedules being developed to assess different methods of mining. The underground study will be completed in the first half of 2021 and the results will feed into an overall enterprise optimisation to deliver an updated Life of Mine Plan.

Port Latta Improvement Projects

Work continues to redesign and rebuild the fifth furnace to improve the airflow. If successful, this will improve pellet quality and reduce energy consumption. The concept design was

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 3 of 6

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
31 December 2020
----- End of picture text -----

developed through Q4, with detailed design work and review of the procurement of key components being sought in Q1, 2021.

SOUTHDOWN MAGNETITE PROJECT

(Grange 70%, SRT Australia Pty Ltd 30%)

The Project achieved a significant milestone in June 2020 as the Company was granted approval of the Southdown Magnetite Project (EPBC 2011/6053) under the Environment Protection and Biodiversity Conservation Act 1999 .

The Company is carrying out a strategic review of the project under the current strong market conditions.

The process of seeking a strategic investor(s) for the project is ongoing.

All tenements, permits and project assets continue to be maintained in good order. Budgeting and cost control over expenditure on this project continues to secure the investment.

The Joint Venture Partners continue to monitor all ongoing project requirements.

GRANGE ROC PROPERTY

Carter Toorak

The focus continues on selling the remaining units at Carter Toorak.

Brookville

The focus continues on selling the developed land at Brookville.

CORPORATE

Shareholders

As at 31 December 2020 there were approximately 5,300 shareholders.

-ENDS-

This announcement was authorised by the Board.

For further information, please contact: [email protected]

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 4 of 6

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
31 December 2020
----- End of picture text -----

ANNEXURE 1

PRODUCTION

Quarter Ended Quarter Ended Full Year
Mar 20 Jun 20 Sep 20 Dec 20 Dec 20 Dec 19
Total BCM Mined 4,061,862 3,710,712 3,512,985 3,281,599
14,567,158
14,462,931
Total Ore BCM 133,514 222,163 541,788 487,279 1,384,744 2,108,370
Concentrate Produced (t) 600,481 649,377 649,084 632,817 2,531,759 2,117,053
Weight Recovery (%) 51.7 46.5 44.0 43.5 46.1 39.7
Pellets Produced (t) 588,885 640,922 639,420 479,047 2,348,274 2,055,043
Pellet Stockpile (t) 179,515 178,138 395,391 119,966 119,966 147,721
Concentrate Stockpile (t) 3,073 1,872 0 137,580 137,580 5,497

SHIPPING AND SALES

Quarter Ended Full Year
Mar 20 Jun 20 Sep 20 Dec 20 Dec 20 Dec 19
Iron Ore Pellet Sales (dmt) 557,091 642,299 422,167 754,472 2,376,029 2,096,673
Iron Ore Concentrate Sales (dmt) 0 0 0 0 0 122
Iron Ore Chip Sales (dmt) 20,371 20,010 41,704 31,526 113,611 95,291
TOTAL Iron Ore Product Sales (dmt) 577,462 662,309 463,871 785,998 2,489,640 2,192,086
Average Realised Product Price
(US$/t FOB Port Latta)
118.34 112.72 130.22 174.69 136.85 109.95
Average Realised Exchange Rate
(AUD:USD)
0.6450 0.6596 0.7136 0.7378 0.6955 0.6944
Average Realised Product Price
(A$/t FOB Port Latta)
183.47 170.89 182.49 236.77 196.77 158.33

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 5 of 6

==> picture [455 x 264] intentionally omitted <==

Mining in North Pit, Savage River

==> picture [247 x 412] intentionally omitted <==

Steel Pan Conveyor transporting hot pellets

Page 6 of 6

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320