GRANGE RESOURCES LIMITED. Interim / Quarterly Report 2016

Oct 19, 2016

65014_rns_2016-10-19_fef847fa-020d-4cf4-88be-880cbaf7bdda.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

REPORT FOR THE QUARTER ENDED

==> picture [89 x 22] intentionally omitted <==

----- Start of picture text -----

20 October 2016
ASX: GRR
----- End of picture text -----

REPORT FOR THE QUARTER ENDED 30 September 2016

HIGHLIGHTS

  • Average price received for the quarter of US$78.07/t (A$103.32/t) (FOB Port Latta) compared with US$67.69/t (A$91.16/t) for June 2016 quarter demonstrating continued strong demand for pellets.

  • Cash operating costs for the quarter of A$86.78/t compared with A$89.11/t for June 2016 quarter. Unit cash operating costs consistent with expectations as the operations undertake important maintenance works to sustain production and improve product quality.

  • Cash position of A$128.58 million and trade receivables of A$23.18 million as at 30 September 2016 compared to A$150.43 million cash position and A$8.06 million trade receivables as at 30 June 2016. The Company paid $5.8mil interim dividends and $3.2mil in royalties.

  • Pellets produced in the quarter of 632kt compared with 521kt in the June 2016 quarter.

  • Pellets sold in the quarter of 586kt compared with 765kt in the June 2016 quarter.

  • Continued safety record with no Lost Time Injuries during the quarter in spite of severe weather and a difficult operating environment.

  • Construction of the South Deposit Tailings Storage Facility (SDTSF) continues on plan.

Grange Resources Limited ABN 80 009 132 405 34a Alexander Street, Burnie, Tasmania 7320 | PO Box 659, Burnie, Tasmania 7320 T: + 61 (3) 6430 0222 F: + 61 (3) 6432 3390 E: [email protected] W: www.grangeresources.com.au

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
30 September 2016
----- End of picture text -----

“While the iron ore market remains uncertain, demand for our products and the price premium for pellets continue to remain strong,” Mr. Honglin Zhao, the CEO said.

“We will continue to seek innovation in improving the productivity and the quality of our products.

“The management team and workforce continue to demonstrate their commitment to safely and efficiently running the operations through this uncertain time and we will continue our disciplined approach to cost reduction.”

SAVAGE RIVER OPERATIONS

PRODUCTION

September
Quarter
2016
June
Quarter
2016
March
Quarter
2016
Total BCM Mined 2,170,451 2,127,247 3,240,319
Total Ore BCM 328,447 229,736 302,267
Concentrate Produced(t) 567,132 561,321 664,257
Weight Recovery (%) 40.6 40.2 40.8
Pellets Produced(t) 632,337 520,525 639,517
Pellet Stockpile(t) 221,733 175,753 420,064
Concentrate Stockpile(t) 85,949 186,910 179,516

Severe wet weather conditions have hampered pit movements and operations as we have worked through the September 2016 quarter. High rainfall and flooding has caused delays and created areas of wall instability in the pits. Mining in North Pit has been through a structurally complex area and has required remediation work to ensure safe operations. Short term redesigns are being implemented and remediation of small scale slips are progressing to improve movement rates and to secure access to ore supply in the lower parts of both South Deposit and North Pit.

In spite of these difficult operating conditions, management continue to focus on improving efficiency and maintaining a safe working environment. Grange operations achieved over 540 days lost time injury free for the quarter.

Maintenance work has progressed well on both mobile and fixed plants, with projects being managed and prioritised on a condition basis. Preparations have commenced for the change out of our second Autogenous Mill in 2017. The first Autogenous Mill shell was replaced in 2015 and is performing very well. Construction of the South Deposit Tails Storage Facility (SDTSF) continues to progress on plan.

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 2 of 4

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
30 September 2016
----- End of picture text -----

SHIPPING AND SALES

September
Quarter
2016
June
Quarter
2016
March
Quarter
2016
Iron Ore Pellet Sales(dmt) 586,357 764,836 649,714
Iron Ore Concentrate Sales(dmt) 44 0 41
Iron Ore Chip Sales(dmt) 30,864 30,909 20,678
TOTAL Iron Ore Product Sales(dmt) 617,265 795,745 670,433
Average Realised Product Price
(US$/t FOB Port Latta)
78.07 67.69 59.02
Average Realised Exchange Rate
(AUD:USD)
0.7556 0.7425 0.7319
Average Realised Product Price
(A$/t FOB Port Latta)
103.32 91.16 80.64

The average price received during the quarter was US$78.07/t (A$103.32) (FOB Port Latta), up approximately 15.3% (13.3%) from US$67.69 (A$91.16) in the June 2016 quarter.

This upward movement in prices from the previous quarter reflects an increased demand for Grange’s high quality, low impurity products which has resulted in the pellet premium strengthening. Whilst there is uncertainty to the future direction of the iron ore prices, Grange is confident the market will continue to recognise a premium for higher quality pellets in comparison to benchmark 62% Fe iron ore products.

Grange will continue to deliver into secured term offtake agreements for all products for 2016 and 2017.

SOUTHDOWN MAGNETITE PROJECT

(Grange 70%, SRT Australia Pty Ltd 30%)

All tenements, permits and project assets continue to be maintained in good order. Budgeting and cost control over expenditure on this project continues to secure the investment.

The Joint Venture Partners continue to monitor all ongoing project requirements to ensure that the current status of the feasibility studies allow the full recommencement of the project once Grange is able to secure an equity partner for a strategic share of the Company’s interest in the project.

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 3 of 4

==> picture [557 x 100] intentionally omitted <==

----- Start of picture text -----

REPORT FOR THE QUARTER ENDED
30 September 2016
----- End of picture text -----

CORPORATE

The Company declared and paid an interim dividend of 0.5 cent per share in the quarter.

Shareholders

As at 30 September 2016 there were approximately 4,100 shareholders.

-ENDS-

For further information, please contact: [email protected]

Registered Office: 34a Alexander Street, Burnie, Tasmania 7320

Page 4 of 4