AI assistant
GEOPACIFIC RESOURCES LTD — Investor Presentation 2021
Jun 29, 2021
65008_rns_2021-06-29_928d0fe1-fc9e-4be0-9592-0f0d603aa87d.pdf
Investor Presentation
Open in viewerOpens in your device viewer
==> picture [54 x 52] intentionally omitted <==
==> picture [177 x 52] intentionally omitted <==
==> picture [960 x 301] intentionally omitted <==
Investor Presentation June 2021
Investment overview
==> picture [57 x 398] intentionally omitted <==
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Developing the Woodlark Gold Project in PNG
100% funded though to production. A$143m of cash with A$130m of project financing
Fully permitted to commence operations with all mining and environmental approvals in place
PNG is an established mining jurisdiction with a stable fiscal environment Strong near mine and regional exploration upside potential
Experienced team in place to execute project construction and drive production
Company focused on community engagement delivering a sustainable lasting legacy for our community stakeholders
Investor Presentation | June 2021
2
PNG − a premier gold region
Proven mining jurisdiction with long history of operations
PNG is a large gold producer with 2.4Moz[1] produced in 2020
Democratic Government with stable fiscal environment, 2.50% royalty including levy Island mining well established (Lihir, Simberi, Gold Ridge, Misima) Australia is a major trade partner (daily flights, <2hr )
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [572 x 22] intentionally omitted <==
==> picture [572 x 378] intentionally omitted <==
----- Start of picture text -----
Frieda River
Frieda River
----- End of picture text -----
Investor Presentation | June 2021 3
1: Data sourced from USGS https://pubs.usgs.gov/periodicals/mcs2021/mcs2021-gold.pdf
Significant project economics
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [960 x 398] intentionally omitted <==
----- Start of picture text -----
NPV8 Initial Project Capital Pay Back Period IRR [3]
$347m [1] A$255m [2] 1.8 years 34%
All In Sustaining Cost LoM Production Reserves [4] Mine Life
A$1,239 / Oz 980 Koz 1.04 Moz 13 years
----- End of picture text -----
-
1: AUD Post Tax NPV at 8% at A$2,200/Oz gold price.
-
2: Establishment capital estimate completed to a -2%/8% level of accuracy.
-
3: Post Tax IRR at A$2,200/Oz gold price
-
4: For Mineral Reserve refer to the PFS announcement released on 12 March 2018.
4
Investor Presentation | June 2021
Fully funded and under construction
-
Project is fully funded to construction
-
• Standard mining and conventional CIL Plant provides low technical risk
-
• Construction activity underway: • Key long lead time items such as SAG and ball mills have been ordered
-
• Commencement of construction activities on the processing plant
-
• Community infrastructure construction activities continue with over 80 buildings completed to date
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
| Use of Funds | A$m |
|---|---|
| Remaining Development Costs1 | 222 |
| Financing Costs & Reserve Accounts | 26 |
| Exploration | 3 |
| Corporate & Management Reserve | 22 |
| Total Plant & Infrastructure | 273 |
| Source of Funds | A$m |
| Cash and equivalents2 | 143 |
| Sprott Financing3 | 130 |
| Total Plant & Infrastructure | 273 |
-
1: Total capital costs of $254.8m less project costs incurred to 31 March 2021 2: As at 31 March 2021
-
3 The Sprott Resource Lending Facilities are binding but subject to Conditions Subsequent
Investor Presentation | June 2021 5
Construction progress
==> picture [297 x 224] intentionally omitted <==
----- Start of picture text -----
DSTP Pipeline Route
----- End of picture text -----
==> picture [298 x 222] intentionally omitted <==
----- Start of picture text -----
Plant Footings Excavation
----- End of picture text -----
==> picture [318 x 224] intentionally omitted <==
----- Start of picture text -----
Wharf Road
----- End of picture text -----
==> picture [318 x 222] intentionally omitted <==
----- Start of picture text -----
Construction Camp
----- End of picture text -----
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [298 x 223] intentionally omitted <==
----- Start of picture text -----
Community Relocation
----- End of picture text -----
==> picture [298 x 223] intentionally omitted <==
----- Start of picture text -----
School Buildings 6
----- End of picture text -----
Low development and production risk
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Straight forward mining and processing route translates to low operating costs
Mining ROM Crushing & Grinding
Leaching 980Koz Dore
==> picture [268 x 124] intentionally omitted <==
==> picture [293 x 96] intentionally omitted <==
==> picture [115 x 69] intentionally omitted <==
Mining
Processing
Conventional truck and shovel operation
-
Conventional Carbon In Leach Plant. Plant design and flow process used Simberi, Misima, Porgera, Hidden Valley
-
Highly experienced contract miner engaged
-
CIL technology used on over 60% of WA Gold mines[1]
-
Mining from 3 pits delivered to ROM stockpile
-
Low power process with power to be sourced from onsite diesel gensets
-
Homogenous nature of ore reduces any major variations in mining ore processing
-
On site storing of key reagents and consumables to reduce logistic risk
Logistics
-
Dore produced on site
-
Exported via plane to Australia
1: Gold Resources and production: Australia in a Global Context, G Mudd, October 2012
Investor Presentation | June 2021 7
Low cost profile operation
Low all in sustainable cost profile
Highly competitive AISC of A$1239/oz Low cost position driven by:
-
Near surface mineralisation and low strip ratio of 4x
-
Simple Conventional Carbon In Leach (CIL) processing plant
-
Favorable metallurgical characteristics ensure low power requirements and low consumable & reagent consumption
==> picture [385 x 188] intentionally omitted <==
----- Start of picture text -----
Corporate Overheads
2%
G&A
20% Mining
36%
Processing
42%
----- End of picture text -----
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
| Life of Mine | Life of Mine | ||
|---|---|---|---|
| Use of Funds1 | (A$/oz) | (US$/oz)3 | |
| Mining | 446 | 325 | |
| Processing | 428 | 312 | |
| G&A | 225 | 164 | |
| Refining | 7 | 5 | |
| Total C1 Costs | 1,106 | 807 | |
| Royalties2 | 55 | 40 | |
| Sustaining Capital | 38 | 28 | |
| Corporate Overheads | 40 | 29 | |
| Total AISC | 1,239 | 904 |
-
1: Based on Woodlark Gold Project Execution Update (ASX release 30 November 2020)
-
2: PNG royalty at 2.5% based on A$2200 gold price
-
3: AUDUSD FX rate of 0.76
Investor Presentation | June 2021 8
Low risk mine plan
Mine Plan
-
12 month pre-strip prior to plant commissioning
-
Multi staged pits allow for targeting of the highest grade ore early in the mining schedule
-
8 years of operations at nameplate with peak material movement of 20.4mt in year 6
-
Mining phase will add 8.8mt of low grade stockpiles over the 9 year mining period
Stockpile Phase (year 10-13)
- 3 year of processing low grade (0.5g/t) stockpiles
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
| Year | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| LOM | Pre | Ramp-up | Year 1 | Year 2 | Year 3 | Year 4 | Year 5 | Year 6 | Year 7 | Year 8 | Year 9 | 10-13 | ||
| MINING | ||||||||||||||
| Strip Ratio (x) | 4.1 | 11.5 | 6 | 2.5 | 2.2 | 3.4 | 3.9 | 5.4 | 11.2 | 4 | 4.2 | 3 | 1.8 | |
| Total Mined (kt) | 156,694 | 5,740 | 2,576 | 11,431 | 13,461 | 14,276 | 20,440 | 19,651 | 20,496 | 19,390 | 16,621 | 11,545 | 1,068 | |
| Ore Mined (kt) | 30,848 | 458 | 369 | 3,254 | 4,230 | 3,219 | 4,199 | 3,065 | 1,684 | 3,857 | 3,217 | 2,913 | 382 | |
| Grade Mined (g/t Au) | 1.11 | 1.50 | 1.51 | 1.35 | 1.22 | 1.03 | 1.09 | 1.06 | 1.12 | 1.08 | 0.99 | 0.89 | 0.97 | |
| Contained Gold (koz Au) | 1,099 | 22 | 18 | 142 | 166 | 106 | 148 | 105 | 61 | 134 | 103 | 83 | 12 | |
| PROCESSING | ||||||||||||||
| Ore Processed (kt) | 30,848 | - | 454 | 2,341 | 2,407 | 2,400 | 2,400 | 2,400 | 2,407 | 2,400 | 2,400 | 2,400 | 8,841 | |
| Grade (g/t) | 1.11 | - | 1.80 | 1.69 | 1.68 | 1.28 | 1.48 | 1.27 | 1.06 | 1.40 | 1.20 | 0.99 | 0.51 | |
| Recovery (%) | 89.2% | 0.0% | 92.4% | 92.2% | 88.9% | 87.4% | 90.2% | 91.3% | 90.0% | 91.2% | 87.8% | 83.7% | 86.6% | |
| Gold Produced | 980,182 | - | 24 | 117 | 116 | 86 | 103 | 90 | 74 | 98 | 82 | 64 | 126 |
1: Based on Woodlark Gold Project Execution Update (ASX release 30 November 2020)
Investor Presentation | June 2021
9
Extending the first 5 years
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
First 5 years
Excellent metrics from initial 5-years of mine plan driven by:
-
Strong upfront grade profile
-
Lower strip ratio
-
Low AISC
Operating metrics deliver average post tax cashflow of A$100m per annum over the first 5 years
Upside
Significant value creation to be driven by the addition of more ore into the resource inventory
High grade (>1.5g/t) ore additions: elongate high grade period Mid grade (1g/t – 1.5g/t) ore additions:
-
Extend mine life and 2.4mtpa production profile or
-
Drive an expansion of the mill
Exploration the key
Woodlark remains relatively underexplored
| Average Year 1-5 Year 6-9 Year 10-13 |
Average Year 1-5 Year 6-9 Year 10-13 |
Average Year 1-5 Year 6-9 Year 10-13 |
|---|---|---|
| Ore Processed (mt) 2.4 2.4 2.2 |
||
| Grade (g/t) 1.5 1.1 0.5 |
||
| Gold (koz pa) 102 79 31 |
||
| AISC (A$/oz) 1,109 1,383 1,548 |
||
| Post Tax cashflow (A$m) 114 69 25 |
||
| Every addition ear of higher gr |
al ade Every additional ear of medium |
|
| y ore drives cA$50m of post tax cash per annum y grade ore drives cA$40m of post tax cash per annum |
Exploration strategy underway to increase ore reserve
1: Based on Woodlark Gold Project Execution Update (ASX release 30 November 2020)
Investor Presentation | June 2021
10
==> picture [960 x 68] intentionally omitted <==
Exploration and Growth Upside
Investor Presentation | June 2021 11
Woodlark growth strategy
==> picture [168 x 398] intentionally omitted <==
-
Growth strategy revolves around increasing reserves and inventory to the current mine plan
-
Optionality exists to debottleneck and expand the mill footprint to accommodate increased ore feed
-
All drill-defined resources remain open along strike, down dip and at depth
-
Three Phase exploration strategy:
-
Pit extension exploration
-
Mineral Lease
-
Regional step out on to exploration leases
-
Exploration budget will be managed with available cashflow and project development timing
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [496 x 398] intentionally omitted <==
Investor Presentation | June 2021 12
Phase 1: near pit potential
-
All 3 operational pits (Busai, Kulumandau and Woodlark King) have significant exploration upside
-
Substantial Inferred material within existing pit shells to be converted to Measured & Indicated via infill drilling
-
Targeting lateral extensions at surface and down dip extensions at depth
-
Deeper drilling to define economic pit limits. Current pit shells constrained by data not economics
-
Definition of additional in-pit ounces reduces strip ratio and increases life of mine production
==> picture [323 x 256] intentionally omitted <==
==> picture [323 x 256] intentionally omitted <==
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [207 x 398] intentionally omitted <==
Investor Presentation | June 2021
13
Phase 2: mineral lease exploration
Substantial land holding available for exploration post completion of pit step out drilling
Numerous highly prospective targets identified within the Mining Lease, with visible gold at surface
All currently identified targets proximal to planned mill location
Rapid conversion of drilling target to mill feed as Mining Lease already in place
Broader Mining Lease exploration scheduled to commence once existing pit limits fully delineated
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [501 x 398] intentionally omitted <==
Investor Presentation | June 2021 14
Phase 3: regional exploration
==> picture [309 x 398] intentionally omitted <==
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
-
Substantial land package extending over a large proportion of the island
-
Significant number of gold and copper surface outcrops to be evaluated
-
Longer term focus on the Exploration Lease with numerous gold and copper surface outcrops / soil anomalies identified
-
Regional exploration highly cost effective once project is operational with only incremental down the hole and assay costs to be funded
Investor Presentation | June 2021 15
==> picture [960 x 68] intentionally omitted <==
Communities and Stakeholder Engagement
Investor Presentation | June 2021 16
Developing sustainable local economies
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Our focus is on the development of sustainable local economies and a strategy for maximising local employment opportunities to ensure that the project benefits are shared with the local communities.
==> picture [215 x 352] intentionally omitted <==
==> picture [374 x 352] intentionally omitted <==
----- Start of picture text -----
Key initiatives include:
• Training and development to provide industry
standard skills and qualifications for local employees.
• Partnering with key stakeholders and experts to
identify and develop viable alternative industries on
Woodlark such as agriculture, aquaculture or
tourism.
•
Community development projects with a focus on
long term and responsible economic growth and
standard of living improvements.
•
Supporting the development of Government service
improvements in the areas of health, education and
law and order.
•
Improvement in female workforce participation and
training.
•
Development of a Biodiversity Action Plan.
----- End of picture text -----
==> picture [291 x 186] intentionally omitted <==
==> picture [293 x 162] intentionally omitted <==
----- Start of picture text -----
The Geopacific Board has approved
Environment, Community, Human Rights
and Mine Closure policies.
Environmental and Social Impact
Assessments completed and Environmental
and Social Management System developed
in line with IFC performance standards and
the Equator Principles
----- End of picture text -----
Investor Presentation | June 2021 17
Our communities
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [438 x 182] intentionally omitted <==
==> picture [451 x 182] intentionally omitted <==
Partnering with the local community
Commitment to provide positive and lasting benefits
Commitment to hiring and up-skilling the local workforce
-
Excellent relationship with local community
-
Considerable effort to inform, engage and support the local Woodlark Island community has benefited all stakeholders
-
Construction of churches, classrooms, trade stores and other community facilities form part of the Community’s Relocation Program
-
Specialist team formed to facilitate small business opportunities
-
Woodlark Gold Project already employing and upskilling men and women in the community
-
Recently hired GM of People and Performance, Susan Scheepers, passionate about hiring and developing a PNG workforce
Investor Presentation | June 2021 18
==> picture [960 x 68] intentionally omitted <==
Conclusion
Investor Presentation | June 2021 19
Project execution & timeline
-
First gold targeted for Q4 CY 2022
-
Onsite management team leading contractor engagement
-
Early phase works at the Woodlark Gold Project Woodlark have commenced including:
-
Order placed by GR Engineering Services (GRES) for procurement of the SAG and ball mills
-
Commencement of construction activities on the processing plant with ground improvement works for the Carbon in Leach tanks underway
-
Community infrastructure construction activities completed by October 2021
-
2H CY21 will see commencement of major construction work streams of:
-
Wharf construction
-
Power station
-
Processing plant
-
Mine pre-strip to commence Q4 CY21
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Q2 CY21 Q3 CY21 Q4 CY21 Q1 CY22 Q2 CY22 Q3 CY22 Q4 CY22 Wharf Construction Power Station Construction Process Plant Construction Mining – Pre-strip, ROM pad, ore stockpiles and ore to crusher Start-up Onshore and Offshore Facilities & Gold Production
Investor Presentation | June 2021 20
Investment conclusion
1 2
Fully funded to development
High margin, low development risk project
-
A$143m of cash and US$100m of project financing
-
980koz of gold production over 13 year mine life
-
Conventional open pit mining with standard CIL gold processing plant reduce technology & development risk
-
Remaining capital cost of A$222m
-
Early work packages commenced with purchase of SAG and ball mills and LOI for mining equipment
-
Low strip ratio and good head grade deliver low AISC of A$1,239/oz
-
Construction to commence 2Q CY21 with first gold schedule for 4Q CY22
-
NPV8 of A$347m with an IRR 34%
3
Construction commenced with the team to execute
-
Fully permitted to production
-
Strong community engagement & support
-
The project has completed Environmental and Social Impact Assessments in line with Equator Principles
-
The right team in place with the experience to deliver the project and execute on our strategy
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
4
Significant exploration upside
-
All drill-defined resources remain open along strike and continue under cover
-
Addition of resources has the ability to extend peak processing rate of 2.4mtpa out beyond the initial 9- year period
-
Well balanced approach to exploration spend and budget
Investor Presentation | June 2021 21
==> picture [960 x 68] intentionally omitted <==
Appendix
Investor Presentation | June 2021 22
Corporate snapshot
| Capital Structure | Capital Structure |
|---|---|
| Share Price (at 23 June 2021) A$0.32 |
|
| Shares on Issue 512.8m |
|
| Market Capitalisation A$164m |
|
| Net Cash @ 31 March 2021 A$143m |
|
| Sprott Resource Lending Project Finance US$100m |
|
| Substantial Shareholder1 | |
| Tembo Capital | 16% |
| DELPHI | 16% |
| Franklin Templeton | 10% |
| Spheria | 9% |
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
==> picture [486 x 361] intentionally omitted <==
----- Start of picture text -----
Board Management
Ian Clyne Tim Richards
Non-Executive Chairman Chief Executive Officer
Colin Gilligan Matthew Smith
Non-Executive Director Chief Financial Officer
Ian Murray Susan Scheepers
Non-Executive Director General Manager – People and
Performance
Sir Charles Lepani Graeme Rapley
Non-Executive Director Project Director
----- End of picture text -----
Investor Presentation | June 2021
23
1: Source and date for data baove
The Management Team
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Tim Richards
Chief Executive Officer
Matthew Smith
Chief Financial Officer
Susan Scheepers
General Manager – People and Performance
Graeme Rapley Project Director
-
Mining Engineer with over 20 years’ experience in open pit mining from scoping and feasibility studies, site technical services, operations and mine management
-
In addition to working in Australia, Mr Richards has undertaken roles in Papua New Guinea, Europe, Africa, and the Caucasus
-
Prior to joining Geopacific Resources, Mr Richards was General Manager Operations at Simberi Gold Mine, delivering five record years of gold production and cash-flow performance
-
Chartered Accountant with over 15 years’ experience in the resource industry across precious metals, industrial and bulk commodities
-
Previous roles include CFO at Kingsrose Mining Limited who have gold operations in Indonesia and Company Secretary at Straits Resources Limited who held Gold and Coal operations in Indonesia and precious metals operations in Australia
-
B.Com, Chartered Accountant (CA)
-
Accomplished Human Resource professional with over 17 years’ experience with major resource companies
-
Prior to joining Geopacific Resources, Mrs Scheepers was the Group HR Manager for St Barbara. During her time with St Barbara she assisted with the turn-around of the Simberi Gold Mine in Papua New Guinea
-
MBS, BBA
-
Civil Engineer with over 20 years’ experience in Construction and Project Manager level roles
-
Previous roles include Project Director for Centerra Gold at the Oksut Project in Turkey, Project Manager for True Gold at the Karma Mine in Burkina Faso, Project Manager for the Sadiola Hill Mine in Mali and Project Manager for the Tongon Gold Mine in Coite Ivoire.
-
B.Eng (Civil), BBA
-
B.Eng (Mining), MBA from University of Oxford
==> picture [960 x 81] intentionally omitted <==
24
Investor Presentation | June 2021
The Board
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Experienced Board with considerable public and private sector experience in Papua New Guinea
Ian Clyne
Non-Executive Chairman
Colin Gilligan Non-Executive Director
Ian Murray
Non-Executive Director
Sir Charles Lepani Non-Executive Director
-
35 years’ experience in international banking specialising in emerging markets
-
Strong believer in PNG and has demonstrated a high level of commitment to social & community issues in previous roles
-
Previous roles held include President, Director, Managing Director and Chief Executive Officer with universal banking operations and Group Chief Executive Officer of Bank South Pacific Limited (BSP in PNG) where he lead a highly successful Transformation Project
-
Mining Engineer with 25 years’ experience in the resources sector in Australia, South Africa, North America and Asia
-
Brings to the board a wealth of project development and project financing experience
-
Has held numerous technical, executive and director roles with several resource organisations including Mitsui, Thiess, Anglo, Coalspur Mines and Resource Generation
-
Extensive experience leading and managing EPC contracts, mining contracts and development projects across different commodities
-
Chartered Accountant with over 25 years’ of mining experience in senior leadership positions
-
Previously Managing Director of Gold Road Resources (Gold Road) where he was instrumental in taking the Guyere Project from an exploration play through to a fully funded 8.2Mtpa gold operation
-
Recipient of many awards during his leadership of Gold Road including the Gavin Thomas award for leadership and the Diggers and Dealers Deal of the year award in 2017
-
Over 40 years’ experience in both the public and private sectors representing Papua New Guinea as a Senior Diplomat and Advisor
-
Prior to joining the Board, his most recent roles were as High Commissioner of PNG in Australia from 2005-2017, and as Director General of PNG APEC 2017-2018 Advisor and consultant to successive Prime Ministers of PNG as well as the departments of Treasury, Finance, and the Law and Justice Sector
==> picture [960 x 81] intentionally omitted <==
Investor Presentation | June 2021 25
Mineral resources and ore reserves
Mineral Resources (Fully Diluted)
47.04Mt at 1.04g/t Au for 1.57Moz Au
| Category (>0.4g/t lower cut) |
Tonnes (Mt) |
Grade (g/t) |
Ounces (oz) |
|
|---|---|---|---|---|
| Total Resource |
Measured | 21.24 | 1.10 | 754,000 |
| Indicated | 18.94 | 0.98 | 597,000 | |
| Inferred | 6.80 | 1.00 | 222,000 | |
| Total | 47.04 | 1.04 | 1,573,000 |
86% of Resource in M&I JORC categories
Immediate near-pit resource growth potential
Refer to PFS released 12 Mar 2018
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Ore Reserves
28.9Mt at 1.12g/t Au for 1.04Moz Au
| Category (>0.4g/t lower cut) |
Tonnes (Mt) |
Grade (g/t) |
Ounces (oz) |
|
|---|---|---|---|---|
| Total Reserve |
Proven | 18.6 | 1.17 | 697,000 |
| Probable | 10.4 | 1.02 | 340,600 | |
| Total | 28.9 | 1.12 | 1,037,600 |
3 deposits: Kulumuadau, Busai, Woodlark King
High conversion of Resources to Reserves
Refer to Woodlark Ore Reserve Update released 7 Nov 20181
1: All material assumptions underpinning the production target and forecast financial information continue to apply and have not changed materially.
Investor Presentation | June 2021 26
Disclaimer and competent persons statement
This presentation is for information purposes only. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in any jurisdiction. This presentation may not be distributed in any jurisdiction except in accordance with the legal requirements applicable in such jurisdiction. Recipients should inform themselves of the restrictions that apply in their jurisdiction. Failure to do so may result in a violation of laws in such jurisdiction. This presentation does not constitute financial product advice and has been prepared without taking into account the recipient's investment objectives, financial circumstances or needs and the opinions and recommendations herein are not intended to represent recommendations of particular investments to particular persons. Recipients should seek professional advice when deciding if an investment is appropriate. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments.
Competent Person’s Statement: The information in this announcement that relates to exploration results and exploration targets is based on information compiled by or under the supervision of Jim Kerr, a Competent Person who is a Member of The Australasian Institute of Mining and Metallurgy and Managing Director of Geopacific. Mr Kerr has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and the activity he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Kerr consents to the inclusion in the announcement of the matters based on his information in the form and context in which it appears.
The information in this report that relates to Woodlark Mineral Resources is based on information compiled and reviewed by Mr Nicholas Johnson, a Competent Person who is a Member of the Australian Institute of Geoscientists and a full-time employee of MPR Geological Consultants Pty Ltd. Mr Johnson has sufficient experience which is relevant to the style of mineralization and type of deposits under consideration and to the activity which he has undertaken to qualify as a Competent Person as defined in the JORC Code 2012 and is a qualified person for the purposes of NI43-101. Mr Johnson has no economic, financial or pecuniary interest in the company and consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.
The information in this report that relates to Woodlark Mineral Reserves is based on information compiled and reviewed by Mr John Battista, a Competent Person who is a Member and Chartered Professional of the Australian Institute of Mining and Metallurgy (AusIMM) and a full-time employee of Mining Plus Pty Ltd. Mr Battista has sufficient experience which is relevant to the style of mineralisation and type of deposits under consideration and to the activity which he has undertaken to qualify as a Competent Person as defined in the JORC Code 2012 and is a qualified person for the purposes of NI43-101. Mr Battista has no economic, financial or pecuniary interest in the company and consents to the inclusion in this report of the matters based on his information in the form and context in which it appears.
==> picture [33 x 32] intentionally omitted <==
==> picture [108 x 32] intentionally omitted <==
Forward Looking Statements: All statements other than statements of historical fact included in this announcement including, without limitation, statements regarding future plans and objectives of Geopacific Resources Limited are forward-looking statements. When used in this announcement, forward-looking statements can be identified by words such as ‘may’, ‘could’, ‘believes’, ‘estimates’, ‘targets’, ‘expects’ or ‘intends’ and other similar words that involve risks and uncertainties.
These statements are based on an assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that, as at the date of this announcement, are expected to take place. Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the company, its directors and management of Geopacific Resources Ltd that could cause Geopacific Resources Limited’s actual results to differ materially from the results expressed or anticipated in these statements.
Geopacific Resources Ltd cannot and does not give any assurance that the results, performance or achievements expressed or implied by the forward-looking statements contained in this announcement will actually occur and investors are cautioned not to place undue reliance on these forward-looking statements. Geopacific Resources Ltd does not undertake to update or revise forward-looking statements, or to publish prospective financial information in the future, regardless of whether new information, future events or any other factors affect the information contained in this announcement, except where required by applicable law and stock exchange listing requirements. Woodlark is permitted by the PNG Government, subject to meeting the conditions of the licence.
Non-IFRS Financial Information: Investors should also be aware that certain financial data included in this presentation may be 'non-IFRS financial information' under Regulatory Guide 230 Disclosing non-IFRS financial information published by ASIC. The Company believes this non-IFRS financial information provides useful information to users in measuring the financial performance and condition of the Company. The non-IFRS financial information does not have a standardised meaning prescribed by Australian Accounting Standards and, therefore, may not be comparable to similarly titled measures presented by other entities, nor should they be construed as an alternative to other financial measures determined in accordance with Australian Accounting Standards. Investors are cautioned, therefore, not to place undue reliance on any non-IFRS financial information and ratios (if any) included in this presentation.
Investor Presentation | June 2021 27
==> picture [50 x 47] intentionally omitted <==
==> picture [158 x 47] intentionally omitted <==
Contact
Tim Richards CEO [email protected]
This presentation has been approved for release by the CEO of Geopacific Resources Limited
==> picture [556 x 540] intentionally omitted <==