AI assistant
GENESIS RESOURCES LIMITED — Interim / Quarterly Report 2018
Apr 29, 2018
64980_rns_2018-04-29_71a103c1-f3aa-4561-a015-60050abf3366.pdf
Interim / Quarterly Report
Open in viewerOpens in your device viewer
Quarterly Activities Report – March 2018
HIGHLIGHTS
Plavica Au-Ag-Cu Project
No drilling was completed during the Quarter. Field work consisted of continued collection of data from water monitoring boreholes, wells and surface monitoring points throughout the project and collection of Flora and Fauna data to be used in an ESIA.
EXPLORATION & DEVELOPMENT PROGRESS DURING THE QUARTER
REPUBLIC OF MACEDONIA
PLAVICA HIGH SULPHIDATION EPITHERMAL GOLD-COPPER-SILVER PROJECT (Figure 1)
Fieldwork in the Quarter consisted of the ongoing monitoring of water bores and surface sites as well as the collection of flora and fauna data for an impending ESIA for the Government of Macedonia. Resource calculations under Macedonian guidelines are also being collated with other material for a mining study. Household surveys are being completed within the 2 major towns of Probistip and Kratovo and the surrounding Villages.
==> picture [458 x 316] intentionally omitted <==
Figure 1 (above) Location of the Plavica Gold-Copper-Silver Project, Republic of Macedonia.
==> picture [483 x 333] intentionally omitted <==
Figure 2 Location of Australian Projects.
AUSTRALIA
ARLTUNGA PROJECT: Copper, Gold (EL25238) (GES 100%)
The Arltunga Gold Project consists of Exploration Licence EL25238 covering 95.2 sq km, is located approximately 110 km northeast of Alice Springs (Figure 2) in the vicinity of the Arltunga Goldfield. Thirty three historical gold mines and prospects are known in the licence area.
A Licence Renewal Application was lodged on the 26 October 2016 and approved on the 21 March 2017 for a further two year period. The new expiry date is the 7 November 2018. All 31 sub blocks were retained.
The 11[th] Annual Technical Report was lodged on 10 November 2017.
The Mining Management Plan (MMP) update was lodged on the 28 February 2018.
The Central Land Council Sacred Site Clearance Certificate was extended on the 30 August 2017. The new expiry date is the 31 December 2018.
A full review of all available data is currently underway, with the aim of defining targets for Reverse Circulation drilling in 2018.
No field work was carried out during the current Quarter.
ALICE SPRINGS PROJECT: Copper, Gold, Iron (EL24817) (GES 100%)
The Alice Springs Project consists of Exploration Licence EL24817 covering 372.59 sq km, is located approximately 110155 km northeast from Alice Springs in the Northern Territory (Figure 2) .
The Mining Management Plan (MMP) update was lodged on the 9 March 2018.
Genesis Resources Limited | Quarterly Activities Report | January 2018 – March 2018
Page 2
A Licence Renewal Application was lodged on 5 April 2016. It was approved on 13 May 2016 for a further term of 2 years and will expire on 17 April 2018. All 118 sub-blocks were retained.
The 11[th] Annual Technical Report was lodged on 21 April 2017 and accepted as satisfactory by the DME on the 26 April 2017.
The Central Land Council Sacred Site Clearance Certificate was extended on the 30 August 2017. The new expiry date is the 31 December 2018.
No field work was carried out. In addition a full review of all available data is underway to define targets for RC drill testing during 2018.
GLADSTONE-MOUNT MILLER PROJECT: Manganese (EPM15771) (GES 100%)
The Gladstone-Mount Miller Project consists of Exploration Licence (EPM15771) covering 42.62sq km and is located approximately 15 km by road from the port of Gladstone on the east coast of central Queensland (Figure 2).
The largest mine on the tenements controlled by Genesis was at Mount Miller. The mine opened in 1895 and operated intermittently until 1916 and then from 1958 to 1960. A total of 21,785 tonnes of ore was mined with a grade which ranged from 71% to 75% MnO2.
A Licence Renewal Application was lodged on the 17 February 2017 and approved on the 17 March 2017. The new expiry date is the 19 June 2019. All 7 sub blocks were retained.
The 10[th] Annual Technical Report was lodged on 23 June 2017.
No field work was carried out. A review of all available data is underway to confirm if more drilling is necessary at the Mt Miller mine and if other prospect areas on the tenement require drill testing during 2018.
Withdrawal of Mining Lease Application
In May 2017, Genesis advised the Queensland Government’s Department of Natural Resources and Mines (DNRM) that Genesis requested to withdraw its Mining Lease 80166 (ML) application. The request was approved by the DNRM.
The Company’s decision not to progress the ML from application to grant stage at this time is consistent with its current strategy of focusing on a program of works for the exploration permit, rather than the ML application itself.
Genesis’ withdrawal of the ML application will allow the area to fall back within the underlying exploration permit held by Genesis, and for exploration activities to continue. The withdrawal will not affect any entitlements that Genesis currently has through the underlying exploration permit, and the permit continues to provide the Company with security of tenure for any future mining lease applications.
The Company intends to continue its exploration programs at this tenement, whilst re-assessing the viability of submitting another mining lease application at a later stage.
PIONEER PROJECT: Gold (EPM15619) (GES 100%)
The Pioneer Project consists of one granted Exploration Permit Mineral (EPM15619) covering 6.23 sq km approximately 70 km by road from Bundaberg via the Bruce Highway in Queensland (Figure 2) .
The project lies within the Gaeta Goldfield and has undergone previous exploration for gold, uranium and base metals, with numerous historical gold workings located throughout the area. Historical mining was primarily focused on the Pioneer Reef which was the largest producer, but mining activities also included several other reefs including Gympie, Lord Nelson, West Yorkshire and Happy Jack.
A Licence Renewal Application was lodged on 28 April 2016 requesting another two year period. The renewal application was approved on the 30 June 2016. The new expiry date is the 2 August 2018. The 2 sub blocks were retained.
The 11[th] Annual Technical Report was lodged on 4 August 2017.
Genesis Resources Limited | Quarterly Activities Report | January 2018 – March 2018
Page 3
No field work was carried out. A review of all available data is underway to compile all geological mapping and define targets for drill testing during 2018.
McARTHUR RIVER PROJECT: Manganese (EL24814) (GES 100%)
The McArthur River project consists of Exploration Licence EL24814 covering 380.88 sq km and is located approximately 850 km south east of Darwin in the Northern Territory and 450 km north-west of Mount Isa in Queensland (Figure 2) .
The project area contains the Masterton No2 manganese occurrence.
The Mining Management Plan Update lodged on the 25 October 2017 was approved on the 13 November 2017.
A Licence Renewal Application was lodged on 5 April 2016. It was approved on 13 May 2016 for a further term of 2 years and will expire on 17 April 2018. All 116 sub-blocks were retained.
The 11[th] Annual Technical Report was lodged on 24 April 2017 and accepted as satisfactory by the DME on the 27 April 2017.
No field work was carried out. A full review of all data available is underway to guide further exploration on the tenement.
LAURA RIVER Au-Pt PROJECT: (EMP15242) (GES:100%)
The Laura River project consists of Exploration Licence EPM15242 covering 82.67 sq km is centered on the Cape York Peninsular township of Laura, 210km north-west of Cairns and 88km west of Cooktown in North Queensland (Figure 4) . The area is prospective for gold. Several historical alluvial workings are found in the vicinity of the Laura River and tributaries.
The 10[th] Annual Technical Report was lodged on the 25 August 2017.
A Licence Renewal Application was lodged on the 19 May 2016 requesting another 2 year term. The renewal application was approved on the 26 August 2016. The new expiry date is the 23 August 2018.
No field work was carried out.
FENN GAP Mn-Fe PROJECT: (EL24839) (GES:100%)
The Fenn Gap project consists of one Exploration Licence EL24839 which covers a total area of 26.93 sq km, is located approximately 25 km south west of Alice Springs in the Northern Territory (Figure 2) . The project is 25 km from major infrastructure such as the Stuart Highway and Alice to Adelaide Railway.
The Mining Management Plan (MMP) update was lodged on the 2 January 2018 and approved on the 10 January 2018.
A Licence Renewal Application requesting another two-year period was lodged on the 26 April 2016. The renewal application was approved on the 25 July 2016. The new expiry date is the 5 May 2018.
The 9[th] Annual Technical Report was lodged on 8 May 2017 and accepted as satisfactory by the DME on the 24 May 2017.
No field work was carried out. A full review of existing data has been completed. A further, more detailed review of drilling data is underway to determine if drilling has adequately tested the known manganese mineralisation.
Genesis Resources Limited | Quarterly Activities Report | January 2018 – March 2018
Page 4
TENEMENTS AS AT 31 March 2108
| PROJECT | TENEMENT NUMBER COMMODITY COMPANY’S BENEFICIAL INTEREST CURRENT AREA (KM2) CURRENT HOLDER COUNTRY/ STATE |
|---|---|
| Alice Springs | EL24817 Copper-Iron- Gold 100% 372.59 Genesis NT |
| Arltunga | EL25238 Gold-PGE 100% 95.2 Genesis NT |
| Fenn Gap | EL24839 Iron- Manganese 100% 26.93 Genesis NT |
| Laura River | EMP15242 Gold-PGE 100% 82.67 Genesis QLD |
| Pioneer | EPM15619 Gold 100% 6.23 Genesis QLD |
| McArthur River | EL24814 Manganese- Base Metals 100% 380.88 Genesis NT |
| Gladstone | EPM15771 Manganese 100% 42.62 Genesis QLD |
| Plavica & Crn Vrv |
19-6648/1 Gold-Silver- Copper 62% 16.85 Silgen Resources Macedonia |
All tenements noted above are Exploration Licences except Plavica in Macedonia which is an Exploitation Licence.
Genesis Resources Limited | Quarterly Activities Report | January 2018 – March 2018
Page 5
CORPORATE UPDATES
Securities on issue as at 31 March 2018
CLASS OF SECURITIES NO. OF SECURITIES ON ISSUE Fully paid ordinary shares 751,085,469
Board and Management as at 31 March 2018
Mr Eddie Pang Managing Director / Executive Chairman Mr Deric Wee Non-Executive Director Mr Kim Heng Lim Non-Executive Director Mr Chin Niap Mah Non-Executive Director Mr James Patterson Exploration Manager / Non-Executive Director Mr Yau Young Lim Non-Executive Director Ms Sophie Karzis Company Secretary Ms Patricia Wong Chief Financial Officer
COMPETENT PERSON
The information in this report that relates to Exploration Targets, Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by James Patterson, a Competent Person who is a Member of the Australian Institute of Geoscientists. James Patterson has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. James Patterson consents to the inclusion in the report of the matters based on his information in the form and context of which it appears.
-ENDS
About Genesis Resources Limited
Genesis Resources Limited is an Australian company with a portfolio of quality gold, iron, manganese, uranium and base metal (copper-zinc-silver) in the highly prospective Proterozoic and Phanerozoic metallogenic provinces of northern and central Australia. Genesis has signed a Joint Venture over an advanced copper-gold project (Plavica) within the Former Yugoslav Republic of Macedonia. The Plavica Project lies within Carpathian Volcanic Arc, a major epithermal province running through Eastern Europe, which is highly prospective for gold, copper and silver mineralisation. Genesis’ projects are close to established infrastructure including railways, shipping ports, highways, power stations and populated areas. The Company’s objective is to provide rapid capital growth through mineral discoveries and development of economic deposits in Australia and overseas.
For more information please visit the Company’s website at: www.genesisresourcesltd.com.au
Genesis Resources Limited | Quarterly Activities Report | January 2018 – March 2018
Page 6
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report
++Rule 5.5
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/13, 01/09/16
Name of entity
GENESIS RESOURCES LIMITED
| ABN 22 114 787 469 |
Quarter ended (“current quarter”) |
|---|---|
| 22 114 787 469 | 31 March 2018 |
| Consolidated statement of cash flows | Current quarter $A’000 |
Year to date (9 months) $A’000 |
|---|---|---|
| 1. Cash flows from operating activities 1.1 Receipts from customers 1.2 Payments for (a) exploration & evaluation (b) development (c) production (d) staff costs (e) administration and corporate costs 1.3 Dividends received 1.4 Interest received 1.5 Interest and other costs of finance paid 1.6 Income taxes paid 1.7 Research and development refunds 1.8 Other (provide details if material) 1.9 Net cash from / (used in) operating activities |
(189) - - (128) (143) - - - (1) - - |
(1,433) - - (497) (607) - 1 - (23) - - |
| (461) | (2,559) | |
| 2. Cash flows from investing activities 2.1 Payments to acquire: (a) property, plant and equipment (b) tenements (see item 10) (c) investments (d) other non-current assets |
(8) - - - |
(14) - - - |
- See chapter 19 for defined terms
1 September 2016
Page 1
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report
| Consolidated statement of cash flows | Current quarter $A’000 |
Year to date (9 months) $A’000 |
|---|---|---|
| 2.2 Proceeds from the disposal of: (a) property, plant and equipment (b) tenements (see item 10) (c) investments (d) other non-current assets 2.3 Cash flows from loans to other entities 2.4 Dividends received (see note 3) 2.5 Other (provide details if material) 2.6 Net cash from / (used in) investing activities |
- - - - - - - |
- - - - - - - |
| (8) | (14) | |
| 3. Cash flows from financing activities 3.1 Proceeds from issues of shares 3.2 Proceeds from issue of convertible notes 3.3 Proceeds from exercise of share options 3.4 Transaction costs related to issues of shares, convertible notes or options 3.5 Proceeds from borrowings 3.6 Repayment of borrowings 3.7 Transaction costs related to loans and borrowings 3.8 Dividends paid 3.9 Other 3.10 Net cash from / (used in) financing activities |
- - - - 450 - - - - |
500 - - - 1,924 - - - - |
| 450 | 2,424 | |
| 4. Net increase / (decrease) in cash and cash equivalents for the period 4.1 Cash and cash equivalents at beginning of period 4.2 Net cash from / (used in) operating activities (item 1.9 above) 4.3 Net cash from / (used in) investing activities (item 2.6 above) 4.4 Net cash from / (used in) financing activities (item 3.10 above) 4.5 Effect of movement in exchange rates on cash held 4.6 Cash and cash equivalents at end of period |
105 (461) (8) 450 2 |
278 (2,559) (14) 2,424 (41) |
| 88 | 88 |
- See chapter 19 for defined terms 1 September 2016
Page 2
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report
| 5. Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts |
Current quarter $A’000 |
Previous quarter $A’000 |
|---|---|---|
| 5.1 Bank balances 5.2 Call deposits 5.3 Bank overdrafts 5.4 Other (Term deposits - bank guarantee) 5.5 Cash and cash equivalents at end of quarter (should equal item 4.6 above) |
88 - - 98 |
105 - - 98 |
| 186 | 203 |
| 6. | Payments to directors of the entity and their associates | Current quarter |
|---|---|---|
| $A'000 | ||
| 6.1 | Aggregate amount of payments to these parties included in item 1.2 | - |
| 6.2 | Aggregate amount of cash flow from loans to these parties included | - |
| in item 2.3 | ||
| 6.3 | Include below any explanation necessary to understand the transactions included in | |
| items 6.1 and 6.2 | ||
| None |
| 7. | Payments to related entities of the entity and their | Current quarter |
|---|---|---|
| associates | $A'000 | |
| 7.1 | Aggregate amount of payments to these parties included in item 1.2 | - |
| 7.2 | Aggregate amount of cash flow from loans to these parties included | - |
| in item 2.3 | ||
| 7.3 | Include below any explanation necessary to understand the transactions included in | |
| items 7.1 and 7.2 | ||
| None |
- See chapter 19 for defined terms 1 September 2016
Page 3
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
| 8. Financing facilities available Add notes as necessary for an understanding of the position 8.1 Loan facilities 8.2 Credit standby arrangements 8.3 Other (please specify) |
Total facility amount at quarter end $A’000 |
Amount drawn at quarter end $A’000 |
|---|---|---|
| 7,000 | - | |
| - | - | |
| - | - |
- 8.4 Include below a description of each facility above, including the lender, interest rate and whether it is secured or unsecured. If any additional facilities have been entered into or are proposed to be entered into after quarter end, include details of those facilities as well.
(i) In September 2013, the Company entered into a loan agreement with an unrelated Malaysian based financing company pursuant to which the financing company made available a loan facility to the Company, with a $3 million facility limit ( First Loan Facility ) at 8% per annum. In April 2014, the parties reached an agreement to increase the First Loan Facility limit from $3 million to $7 million on the same terms and conditions provided for in the existing loan agreement. Total funds of $7 million remain available for draw down by Genesis under the First Loan Facility.
| 9. Estimated cash outflows for next quarter |
$A’000 |
|---|---|
| 9.1 Exploration and evaluation 9.2 Development 9.3 Production 9.4 Staff costs 9.5 Administration and corporate costs 9.6 Other (provide details if material) 9.7 Total estimated cash outflows |
241 - - 163 156 - |
| 560 |
| 10. Changes in tenements (items 2.1(b) and 2.2(b) above) |
Tenement reference and location |
Nature of interest | Interest at beginning of quarter |
Interest at end of quarter |
|---|---|---|---|---|
| 10.1 Interests in mining tenements and petroleum tenements lapsed, relinquished or reduced |
- | - | - | - |
| 10.2 Interests in mining tenements and petroleum tenements acquired or increased |
- | - | - | - |
- See chapter 19 for defined terms 1 September 2016
Page 4
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Compliance statement
-
1 This statement has been prepared in accordance with accounting standards and policies which comply with Listing Rule 19.11A.
-
2 This statement gives a true and fair view of the matters disclosed.
Sign here: ............................................................ Date: 30 April 2018 (Director)
Print name: Eddie Pang
Executive Chairman
Notes
-
The quarterly report provides a basis for informing the market how the entity’s activities have been financed for the past quarter and the effect on its cash position. An entity that wishes to disclose additional information is encouraged to do so, in a note or notes included in or attached to this report.
-
If this quarterly report has been prepared in accordance with Australian Accounting Standards, the definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report. If this quarterly report has been prepared in accordance with other accounting standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
-
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities, depending on the accounting policy of the entity.
-
See chapter 19 for defined terms 1 September 2016
Page 5