Quarterly Activities Report – June 2016
HIGHLIGHTS
Plavica Au-Ag-Cu Project
-
The extensional drilling program continued at Plavica during the quarter ended 30 June 2016 ( Quarter ). A total of 25 core holes were drilled for a total of 5172.6m and a total of 24 RC holes were also drilled for 2673m. Drilling is ongoing at Plavica and the Company plans to complete a JORC 2012 compliant resource in the following Quarter.
-
Results have been returned for 12 of the holes drilled this Quarter plus outstanding results from the three holes drilled last Quarter. Results were generally encouraging and included:
-
MRDD019: 53m @ 4.07 g/t Au from 0m from the Maricanski Rid prospect.
EXPLORATION & DEVELOPMENT PROGRESS DURING THE QUARTER
REPUBLIC OF MACEDONIA
PLAVICA HIGH SULPHIDATION EPITHERMAL GOLD-COPPER-SILVER PROJECT (Figures 1 & 2)
Following the granting of the 30 year Exploitation Licence at Plavica in May 2015, drilling has since focussed on extending and better understanding the previously known mineralisation at both the Plavica and Maricanski Rid prospects with a focus on the oxide gold potential. During the Quarter, drilling has continued at both these prospects using one core rig and one Reverse Circulation (RC) rig with the aim of re-doing the Inferred Resource at Plavica and completing a maiden Inferred Resource at Maricanski Rid in the following Quarter. Drilling is on track with one core rig and one RC rig currently in operation.
At Plavica a total of 11 core holes for 3063.4m and 12 RC holes for 1505m were completed. Results have been received for six of the core holes and one RC hole. In addition results were received for the 2 holes (PNDD072 and 073) drilled in the March Quarter. Results include:
-
PNDD073: 36m @ 2.12 g/t Au from 11m.
-
PNDD076: 23m @ 0.74 g/t Au from 3m.
At Maricanski Rid a total of 14 core holes for 2109.2m and 12 RC holes for 1168m were completed. Results have been received for five of the core holes. In addition results were received for the core hole (MRDD019) drilled in the March Quarter. Results include:
-
MRDD019: 53m @ 4.07 g/t Au from 0m.
-
MRDD021: 25m @ 1.39 g/t Au from 0m.
-
MRDD023: 43m @ 1.00 g/t Au from 73m.
All intersections listed above are in oxide material. All the afore-mentioned drill hole locations are shown in Table 1 and 2 and Figure 2. Composites from results received this Quarter are shown in Table 3. Three sections from Maricanski Rid showing holes MRDD019, MRDD021 and MRDD023 are shown as Figures 3 to 5.
Genesis aims to finish this round of drilling and then complete a JORC compliant Resource in the 3[rd] Quarter of 2016. Genesis then expects to complete a feasibility study before October 2017, and has agreed to commit up to US $7.5m for these activities.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 1
==> picture [458 x 315] intentionally omitted <==
Figure 1 (above) Location of the Plavica Gold-Copper-Silver Project, Republic of Macedonia.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 2
==> picture [540 x 405] intentionally omitted <==
Figure 2 Location of Holes drilled or assays reported, QTR 2 2016, Plavica Project. Gauss Kruger Co-ordinate System.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 3
| Prospect | Hole ID | Type | Final Depth |
Dip | Azi Mag |
East_GK | North_GK | RL m | Comments |
|---|---|---|---|---|---|---|---|---|---|
| Plavica | PNDD072 | DD | 236.10 | -60 | 4 | 7597250.0 | 4657058.0 | 1178.0 | Drilled lastQTR |
| Plavica | PNDD073 | DD | 185.10 | -50 | 4 | 7597756.0 | 4656892.0 | 1239.0 | Drilled lastQTR |
| Plavica | PNDD074 | DD | 201.55 | -50 | 4 | 7597845.0 | 4656820.0 | 1265.0 | Results Received |
| Plavica | PNDD075 | DD | 294.55 | -50 | 4 | 7596650.0 | 4656905.0 | 1105.0 | Results Received |
| Plavica | PNDD076 | DD | 353.95 | -60.00 | 4 | 7597850.0 | 4656750.0 | 1240.0 | Results Received |
| Plavica | PNDD077 | DD | 289.80 | -50 | 4 | 7598005.0 | 4656780.0 | 1279.0 | Results Received |
| Plavica | PNDD078 | DD | 328.70 | -50 | 4 | 7597680.0 | 4656570.0 | 1176.0 | Results Received |
| Plavica | PNDD079 | DD | 157.00 | -50 | 4 | 7597554.0 | 4657071.0 | 1219.0 | Results Received |
| Plavica | PNDD080 | DD | 205.31 | -50 | 4 | 7597350.0 | 4656990.0 | 1169.0 | Results Pending |
| Plavica | PNDD081 | DD | 247.10 | -50 | 4 | 7597250.0 | 4656977.0 | 1157.0 | Results Pending |
| Plavica | PNDD082 | DD | 336.95 | -50 | 4 | 7598000.0 | 4656715.0 | 1266.0 | Results Pending |
| Plavica | PNDD083 | DD | 302.25 | -45 | 4 | 7598046.0 | 4656700.0 | 1265.0 | Results Pending |
| Plavica | PNDD084 | DD | 346.20 | -52 | 4 | 7598050.0 | 4656670.0 | 1255.0 | Results Pending |
| Plavica | PNRC097 | RC | 168.00 | -50 | 4 | 7597346.0 | 4657096.0 | 1192.0 | Results Received |
| Plavica | PNRC098 | RC | 96.00 | -60 | 360 | 7597403.0 | 4657100.8 | 1198.0 | Results Pending |
| Plavica | PNRC099 | RC | 160.00 | -50 | 360 | 7597534.0 | 4657034.0 | 1212.0 | Results Pending |
| Plavica | PNRC100 | RC | 150.00 | -60 | 360 | 7597604.0 | 4656960.0 | 1223.0 | Results Pending |
| Plavica | PNRC101 | RC | 132.00 | -60 | 360 | 7597709.0 | 4656914.0 | 1237.0 | Results Pending |
| Plavica | PNRC102 | RC | 108.00 | -60.00 | 4 | 7597681.0 | 4656986.0 | 1248.0 | Results Pending |
| Plavica | PNRC103 | RC | 150.00 | -55 | 4 | 7597650.0 | 4656960.0 | 1235.0 | Results Pending |
| Plavica | PNRC105 | RC | 129.00 | -55 | 340 | 7597480.0 | 4657067.0 | 1200.0 | Results Pending |
| Plavica | PNRC106 | RC | 100.00 | -55 | 4 | 7597790.0 | 4656830.0 | 1240.0 | Results Pending |
| Plavica | PNRC107 | RC | 162.00 | -50 | 4 | 7598390.0 | 4657040.0 | 1282.0 | Results Pending |
| Plavica | PNRC108 | RC | 150.00 | -50 | 184 | 7598390.0 | 4657040.0 | 1282.0 | Results Pending |
Table 1 Details of Holes drilled, QTR 2 2016, Plavica Prospect. Gauss Kruger Co-ordinate System. NB Collars have not yet been surveyed.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 4
| Prospect | Hole ID | Type | Final Depth |
Dip | Azi Mag |
East_GK | North_GK | RL m | Comments |
|---|---|---|---|---|---|---|---|---|---|
| Maricanski Rid | MRDD019 | DD | 172.00 | -55 | 184 | 7597490.0 | 4656235.0 | 1218.8 | Drilled lastQTR |
| Maricanski Rid | MRDD020 | DD | 150.10 | -55 | 4 | 7597540.0 | 4656252.0 | 1211.6 | Results Received |
| Maricanski Rid | MRDD021 | DD | 161.40 | -55 | 184 | 7597540.0 | 4656252.0 | 1211.6 | Results Received |
| Maricanski Rid | MRDD022 | DD | 134.30 | -55 | 4 | 7597440.0 | 4656215.0 | 1211.0 | Results Received |
| Maricanski Rid | MRDD023 | DD | 154.75 | -55 | 184 | 7597440.0 | 4656218.0 | 1211.0 | Results Received |
| Maricanski Rid | MRDD024 | DD | 155.50 | -55 | 184 | 7597440.0 | 4656270.0 | 1199.0 | Results Received |
| Maricanski Rid | MRDD025 | DD | 141.35 | -55 | 4 | 7597440.0 | 4656270.0 | 1199.0 | Results Pending |
| Maricanski Rid | MRDD026 | DD | 123.30 | -55 | 184 | 7597290.0 | 4656200.0 | 1169.6 | Results Pending |
| Maricanski Rid | MRDD027 | DD | 167.15 | -60 | 184 | 7597590.0 | 4656292.0 | 1207.8 | Results Pending |
| Maricanski Rid | MRDD028 | DD | 163.40 | -55 | 4 | 7597224.0 | 4656180.0 | 1131.0 | Results Pending |
| Maricanski Rid | MRDD029 | DD | 130.15 | -55 | 184 | 7597224.0 | 4656180.0 | 1131.0 | Results Pending |
| Maricanski Rid | MRDD030 | DD | 178.40 | -55 | 4 | 7597274.4 | 4656298.3 | 1153.0 | Results Pending |
| Maricanski Rid | MRDD031 | DD | 105.00 | -55 | 184 | 7597274.4 | 4656298.3 | 1153.0 | Results Pending |
| Maricanski Rid | MRDD032 | DD | 180.80 | -45 | 325 | 7597250.0 | 4656243.0 | 1154.0 | Results Pending |
| Maricanski Rid | MRDD033 | DD | 163.60 | -55 | 4 | 7597478.0 | 4656337.0 | 1187.0 | Results Pending |
| Maricanski Rid | MRRC001 | RC | 76.00 | -90 | 0 | 7597490.0 | 4656235.0 | 1218.8 | Results Pending |
| Maricanski Rid | MRRC002 | RC | 90.00 | -90 | 0 | 7597540.0 | 4656252.0 | 1211.6 | Results Pending |
| Maricanski Rid | MRRC003 | RC | 90.00 | -90 | 0 | 7597440.0 | 4656215.0 | 1211.0 | Results Pending |
| Maricanski Rid | MRRC004 | RC | 72.00 | -90 | 0 | 7597440.0 | 4656270.0 | 1199.0 | Results Pending |
| Maricanski Rid | MRRC005 | RC | 156.00 | -55 | 4 | 7597760.0 | 4656260.0 | 1193.5 | Results Pending |
| Maricanski Rid | MRRC006 | RC | 150.00 | -50 | 184 | 7597760.0 | 4656263.0 | 1193.5 | Results Pending |
| Maricanski Rid | MRRC007 | RC | 90 | -90 | 0 | 7597274.4 | 4656298.3 | 1153.0 | Results Pending |
| Maricanski Rid | MRRC008 | RC | 95 | -90 | 0 | 7597374.7 | 4656308.0 | 1175.1 | Results Pending |
| Maricanski Rid | MRRC009 | RC | 90 | -90 | 0 | 7597478.0 | 4656337.0 | 1187.0 | Results Pending |
| Maricanski Rid | MRRC010 | RC | 100 | -90 | 0 | 7597289.3 | 4656197.6 | 1169.6 | Results Pending |
| Maricanski Rid | MRRC011 | RC | 59 | -90 | 0 | 7597387.6 | 4656214.0 | 1197.4 | Results Pending |
| Maricanski Rid | MRRC011A | RC | 100 | -90 | 0 | 7597387.6 | 4656214.0 | 1197.4 | Results Pending |
Table 2 Details of Holes drilled, QTR 2 2016, Maricanski Rid Prospect. Gauss Kruger Co-ordinate System. NB Collars have not yet been surveyed.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 5
| Prospect | Hole | From | To | Interval | Aug/T |
|---|---|---|---|---|---|
| Plavica | PNDD072 | NSA | |||
| Plavica | PNDD073 | 11 | 47 | 36 | 2.12 |
| Plavica | PNDD074 | 41 | 45 | 4 | 0.66 |
| Plavica | PNDD074 | 98 | 101 | 3 | 0.5 |
| Plavica | PNDD074 | 106 | 126 | 20 | 0.82 |
| Plavica | PNDD075 | NSA | |||
| Plavica | PNDD076 | 3 | 26 | 23 | 0.74 |
| Plavica | PNDD076 | 190 | 193 | 3 | 0.64 |
| Plavica | PNDD076 | 262 | 269 | 7 | 0.66 |
| Plavica | PNDD077 | 44 | 49 | 5 | 0.56 |
| Plavica | PNDD077 | 57 | 60 | 3 | 1.08 |
| Plavica | PNDD077 | 95 | 99 | 4 | 0.83 |
| Plavica | PNDD077 | 111 | 115 | 4 | 0.8 |
| Plavica | PNDD077 | 130 | 136 | 6 | 1.42 |
| Plavica | PNDD077 | 163 | 169 | 6 | 0.71 |
| Plavica | PNDD077 | 183 | 186 | 3 | 0.56 |
| Plavica | PNDD077 | 194 | 199 | 5 | 0.54 |
| Plavica | PNDD077 | 239 | 244 | 5 | 0.97 |
| Plavica | PNDD077 | 275 | 278 | 3 | 1.01 |
| Plavica | PNDD077 | 282 | 286 | 4 | 0.52 |
| Plavica | PNRC097 | NSA |
Table 3 (above): Significant Core Drilling Gold Results received, QTR 2 2016, Plavica Prospect Area. Compositing done with a 0.4 g/t Au cut-off, minimum 3m interval, maximum 3m internal waste. Core samples are all orientated standard HQ size core split in two using a core saw. Half the core was sampled at 1m intervals and the other half retained for reference purposes. All core was logged and photographed prior to sampling. Samples were sent to SGS Laboratories in Ankara, Turkey. Samples were assayed for gold by 30g Fire Assay and other elements by ICP. Standards, Blanks and Duplicates were also submitted for Laboratory Quality Assurance / Quality Control (QAQC). Intercept widths are not necessarily true widths.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 6
| Prospect | Hole | From | To | Interval | Aug/T |
|---|---|---|---|---|---|
| Maricanski Rid | MRDD019 | 0 | 53 | 53 | 4.07 |
| Maricanski Rid | MRDD019 | 68 | 86 | 18 | 0.48 |
| Maricanski Rid | MRDD019 | 135 | 138 | 3 | 1.02 |
| Maricanski Rid | MRDD019 | 155 | 160 | 5 | 0.55 |
| Maricanski Rid | MRDD020 | 0 | 24 | 24 | 1.1 |
| Maricanski Rid | MRDD020 | 29 | 33 | 4 | 2.42 |
| Maricanski Rid | MRDD020 | 50 | 70 | 20 | 0.79 |
| Maricanski Rid | MRDD020 | 99 | 104 | 5 | 0.56 |
| Maricanski Rid | MRDD020 | 144 | 149 | 5 | 0.59 |
| Maricanski Rid | MRDD021 | 0 | 25 | 25 | 1.39 |
| Maricanski Rid | MRDD021 | 61 | 64 | 3 | 0.54 |
| Maricanski Rid | MRDD021 | 106 | 109 | 3 | 0.62 |
| Maricanski Rid | MRDD021 | 126 | 133 | 7 | 0.49 |
| Maricanski Rid | MRDD021 | 154 | 159 | 5 | 0.64 |
| Maricanski Rid | MRDD022 | 0 | 8 | 8 | 0.71 |
| Maricanski Rid | MRDD022 | 17 | 20 | 3 | 0.61 |
| Maricanski Rid | MRDD022 | 33 | 60 | 27 | 0.74 |
| Maricanski Rid | MRDD022 | 88 | 93 | 5 | 0.72 |
| Maricanski Rid | MRDD022 | 105 | 126 | 21 | 0.55 |
| Maricanski Rid | MRDD023 | 0 | 13 | 13 | 1.18 |
| Maricanski Rid | MRDD023 | 23 | 39 | 16 | 0.49 |
| Maricanski Rid | MRDD023 | 53 | 59 | 6 | 0.57 |
| Maricanski Rid | MRDD023 | 73 | 116 | 43 | 1 |
| Maricanski Rid | MRDD023 | 120 | 142 | 22 | 0.78 |
| Maricanski Rid | MRDD023 | 146 | 151 | 5 | 0.92 |
| Maricanski Rid | MRDD024 | 0 | 28 | 28 | 0.69 |
| Maricanski Rid | MRDD024 | 34 | 39 | 5 | 0.43 |
| Maricanski Rid | MRDD024 | 49 | 64 | 15 | 0.52 |
| Maricanski Rid | MRDD024 | 91 | 94 | 3 | 0.74 |
| Maricanski Rid | MRDD024 | 104 | 116 | 12 | 0.53 |
Table 4 (above): Significant Core Drilling Gold Results received, QTR 2 2016, Maricanski Rid Prospect Area. Compositing done with a 0.4 g/t Au cut-off, minimum 3m interval, maximum 3m internal waste. Core samples are all orientated standard HQ size core split in two using a core saw. Half the core was sampled at 1m intervals and the other half retained for reference purposes. All core was logged and photographed prior to sampling. Samples were sent to SGS Laboratories in Ankara, Turkey. Samples were assayed for gold by 30g Fire Assay and other elements by ICP. Standards, Blanks and Duplicates were also submitted for Laboratory Quality Assurance / Quality Control (QAQC). Intercept widths are not necessarily true widths.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 7
==> picture [540 x 405] intentionally omitted <==
Figure 3 Maricanski Rid Section 7597440E Gauss Kruger, looking East.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 8
==> picture [540 x 405] intentionally omitted <==
Figure 4 Maricanski Rid Section 7597490E Gauss Kruger, looking East.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 9
==> picture [540 x 405] intentionally omitted <==
Figure 5 Maricanski Rid Section 7597540E Gauss Kruger, looking East.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 10
==> picture [483 x 333] intentionally omitted <==
Figure 6 Location of Australian Projects.
AUSTRALIA
ARLTUNGA PROJECT: Copper, Gold, (GES 100%)
The Arltunga Gold Project consists of Exploration Licence EL25238 covering 95.2 sq km, is located approximately 110 km northeast of Alice Springs (Figure 6) in the vicinity of the Arltunga Goldfield. Thirty three historical gold mines and prospects are known in the licence area.
The Licence Renewal was approved on 6 February 2015 for a term of 2 years and will expire on 7 November 2016. All 31 sub-blocks were retained.
A full review of all available data is currently underway, with the aim of defining targets for Reverse Circulation drilling in Q3 2016.
The 9[th] Annual Technical Report was lodged on 9 November 2015 and accepted as satisfactory by the DME on the 19 November 2015.
An updated Mining Management Plan (MMP) was lodged on the 8 March 2016.
No field work was carried out during the current Quarter.
ALICE SPRINGS PROJECT: Copper, Gold, Iron (GES 100%)
The Alice Springs Project consists of Exploration Licence EL24817 covering 372.59 sq km, is located approximately 110155 km northeast from Alice Springs in the Northern Territory (Figure 5) .
A Licence Renewal Application was lodged on 5 April 2016. It was approved on 13 May 2016 for a further term of 2 years and will expire on 17 April 2018. All 118 sub-blocks were retained.
The 10[th] Annual Technical Report was lodged on 18 April 2016 and accepted as satisfactory by the DME on the 9 May 2016.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 11
An updated Mining Management Plan (MMP) was lodged on the 23 February 2016 and accepted as satisfactory on the 20 June 2016.
No field work was carried out. In addition a full review of all available data is underway to define targets for RC drill testing during Q3 2016.
GLADSTONE-MOUNT MILLER PROJECT: Manganese (GES 100%)
The Gladstone-Mount Miller Project consists of Exploration Licence (EPM15771) covering 42.62sq km and Mining Lease Application (MLA80166) covering 32.24 Ha and is located approximately 15 km by road from the port of Gladstone on the east coast of central Queensland (Figure 5) .
The largest mine on the tenements controlled by Genesis was at Mount Miller. The mine opened in 1895 and operated intermittently until 1916 and then from 1958 to 1960. A total of 21,785 tonnes of ore was mined with a grade which ranged from 71% to 75% MnO2.
The Licence Renewal was approved on 7 May 2013 for a term of 5 years and will expire on 18 June 2017.
As per the conditions of the exploration permit Genesis were required to relinquish 14 sub blocks from EPM 15771. A Partial Relinquishment Report was lodged on the 16 June 2016. 14 of the 21 sub blocks were relinquished, 7 sub-blocks were retained. EPM15771 now covers 42.62sq km.
The 9[th] Annual Technical Report was lodged on 20 June 2016.
A Partial Surrender of an Environmental Authority was lodged on the 27 June 2016.
No field work was carried out. A review of all available data is underway to confirm if more drilling is necessary at the Mt Miller mine and if other prospect areas on the tenement require drill testing during Q3 2016.
PIONEER PROJECT: Gold (GES 100%)
The Pioneer Project consists of one granted Exploration Permit Mineral (EPM15619) covering 6.23 sq km approximately 70 km by road from Bundaberg via the Bruce Highway in Queensland (Figure 5) .
The project lies within the Gaeta Goldfield and has undergone previous exploration for gold, uranium and base metals, with numerous historical gold workings located throughout the area. Historical mining was primarily focused on the Pioneer Reef which was the largest producer, but mining activities also included several other reefs including Gympie, Lord Nelson, West Yorkshire and Happy Jack.
A Licence Renewal Application was lodged on 28 April 2016 requesting another two year period. The licence currently expires on the 2 August 2016.
As per the conditions of the exploration permit Genesis were required to relinquish 2 sub blocks from EPM 15619. Pursuant to section 793 of the Mineral Resources Act 1989 (MRA ), the relinquishment was accepted by the Department of Natural Resources and Mines Queensland on 22 August 2013. The tenement area has been reduced from 12.67 sq km to 6.23 sq km.
No field work was carried out. A review of all available data is underway to compile all geological mapping and define targets for drill testing during Q3 2016.
McARTHUR RIVER PROJECT: Manganese (GES 100%)
The McArthur River project consists of Exploration Licence EL24814 covering 380.88 sq km and is located approximately 850 km south east of Darwin in the Northern Territory and 450 km north-west of Mount Isa in Queensland (Figure 5) .
The project area contains the Masterton No2 manganese occurrence.
A Licence Renewal Application was lodged on 5 April 2016. It was approved on 13 May 2016 for a further term of 2 years and will expire on 17 April 2018. All 116 sub-blocks were retained.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 12
The 10[th] Annual Technical Report was lodged on 18 April 2016 and accepted as satisfactory by the DME on the 9 May 2016.
The Mining Management Plan Update was lodged on the 21 October 2015, it was accepted by DME on 30 October 2015.
No field work was carried out. A full review of all data available is underway to guide further exploration on the tenement.
LAURA RIVER Au-Pt PROJECT: (EMP15242) (GES:100%)
The Laura River project consists of Exploration Licence EPM15242 covering 82.67 sq km is centered on the Cape York Peninsular township of Laura, 210km north-west of Cairns and 88km west of Cooktown in North Queensland (Figure 5) . The area is prospective for gold. Several historical alluvial workings are found in the vicinity of the Laura River and tributaries.
The 8[th] Annual Technical Report was lodged on the 24 August 2015.
A Licence Renewal Application was lodged on the 19 May 2016 requesting another 2 year term. The tenement currently expires on the 23 August 2016.
As per the conditions of the exploration permit Genesis were required to relinquish 25 sub blocks from EPM 15242. A Partial Relinquishment Report was lodged on the 20 June 2016. 25 of the 50 sub blocks were relinquished, 25 sub-blocks were retained. EPM15242 now covers 82.67sq km.
A Partial Surrender of an Environmental Authority was lodged on the 22 June 2016.
No field work was carried out.
FENN GAP Mn-Fe PROJECT: (EMP24839) (GES:100%)
The Fenn Gap project consists of one Exploration Licence EL24839 which covers a total area of 26.93 sq km, is located approximately 25 km south west of Alice Springs in the Northern Territory (Figure 5) . The project is 25 km from major infrastructure such as the Stuart Highway and Alice to Adelaide Railway.
Genesis was issued with a Partial Cancellation Notice (Loss of Block Penalty) for Fenn Gap on 23 June 2014, requesting the relinquishment of 13 sub blocks. EL24839 now comprises of 14 sub blocks covering 26.93 sq km.
A Licence Renewal Application requesting another two year period was lodged on the 26 April 2016. The current expiry date was 5 May 2016. This application is still PENDING.
The 8[th] Annual Technical Report was lodged on 9 May 2016 and accepted as satisfactory by the DME on the 1 June 2016.
A Mining Management Plan Update was lodged on 7 September 2015. This was approved on 16 September 2015.
No field work was carried out. A full review of existing data has been completed. A further, more detailed review of drilling data is underway to determine if drilling has adequately tested the known manganese mineralisation.
TENEMENTS AS AT 30 JUNE 2016
| PROJECT TENEMENT NUMBER COMMODITY COMPANY’S BENEFICIAL INTEREST CURRENT AREA (KM2) CURRENT HOLDER COUNTRY/ STATE |
PROJECT TENEMENT NUMBER COMMODITY COMPANY’S BENEFICIAL INTEREST CURRENT AREA (KM2) CURRENT HOLDER COUNTRY/ STATE |
|---|---|
| Alice Springs | EL24817 Copper-Iron- Gold 100% 372.59 Genesis NT |
| Arltunga | EL25238 Gold-PGE 100% 95.2 Genesis NT |
| Fenn Gap | EL24839 Iron- Manganese 100% 26.93 Genesis NT |
| Laura River | EMP15242 Gold-PGE 100% 82.67 Genesis QLD |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 13
| Pioneer | EPM15619 Gold 100% 6.23 Genesis QLD |
|---|---|
| McArthur River | EL24814 Manganese- Base Metals 100% 380.88 Genesis NT |
| Gladstone | EPM15771 Manganese 100% 42.62 Genesis QLD |
| Mt Miller | MLA80166 Manganese 100% 32.24 Ha Genesis QLD |
| Plavica & Crn Vrv |
19-6648/1 Gold-Silver- Copper 62% 16.85 Silgen Resources Macedonia |
All tenements noted above are Exploration Licences except Plavica in Macedonia which is an Exploitation Licence.
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 14
CORPORATE UPDATES
Events during the Quarter
Extraordinary General Meeting
On 22 April 2016 Genesis held an Extraordinary General Meeting. All resolutions proposed by the Company to shareholders at the Extraordinary General Meeting were unanimously carried on a show of hands.
Issue of Shares
On 6 May 2016, Genesis issued 27,139,541 fully paid ordinary shares to a professional and sophisticated investor under a capital raising placement at $0.04 per share.
Appointment of Non-Executive Directors
On 31 May 2016, two new Non-Executive Directors were appointed to the Board of the Company: Mr Kim Heng Lim and Mr Chin Niap Mah.
Events subsequent
None.
Securities on issue as at 30 June 2016:
| CLASS OF SECURITIES | NO. OF SECURITIES ON ISSUE |
|---|---|
| Fully paid ordinary shares 384,885,386 |
|
| Board and Management as at 30 June 2016 Mr Eddie Pang Managing Director Mr Deric Wee Non-Executive Director Ms Alyn Tai Non-Executive Director Mr Kim Heng Lim Non-Executive Director Mr Chin Niap Mah Non-Executive Director Ms Sophie Karzis Company Secretary Ms Patricia Wong Chief Financial Officer Mr James Patterson Exploration Manager |
COMPETENT PERSON
The information in this report that relates to Exploration Targets, Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by James Patterson, a Competent Person who is a Member of the Australian Institute of Geoscientists. James Patterson is a full-time employee of Genesis. James Patterson has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. James Patterson consents to the inclusion in the report of the matters based on his information in the form and context of which it appears.
-ENDS
About Genesis Resources Limited
Genesis Resources Limited is an Australian company with a portfolio of quality gold, iron, manganese, uranium and base metal (copper-zinc-silver) in the highly prospective Proterozoic and Phanerozoic metallogenic provinces of northern and central Australia. Genesis has signed a Joint Venture over an advanced copper-gold project (Plavica) within the Former Yugoslav Republic of Macedonia. The Plavica Project lies within Carpathian Volcanic Arc, a major epithermal province running through Eastern Europe, which is highly prospective for gold, copper and silver mineralisation. Genesis’ projects are close to established infrastructure including railways, shipping ports, highways, power stations and populated areas. The Company’s objective is to provide rapid capital growth through mineral discoveries and development of economic deposits in Australia and overseas.
For more information please visit the Company’s website at: www.genesisresourcesltd.com.au
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 15
Appendix 1 Reporting of Exploration Results – Plavica Project JORC Code, 2012 Edition – Table 1 Report
The following section is provided to ensure compliance with the JORC (2012) requirements for the reporting of Exploration Results for the Plavica project.
Section 1 - Sampling Techniques and Data
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Sampling | Nature and quality of sampling (eg cut channels, random chips, or | N/A |
| techniques | specific specialised industry standard measurement tools appropriate | |
| to the minerals under investigation, such as down hole gamma | ||
| sondes, or handheld XRF instruments, etc). These examples should | ||
| not be taken as limiting the broad meaning of sampling. | ||
| Include reference to measures taken to ensure sample representivity | N/A | |
| and the appropriate calibration of any measurement tools or systems | ||
| used. | ||
| Aspects of the determination of mineralisation that are Material to the | Holes were generally drilled towards grid north with dips of | |
| Public Report. | approximately 60 degrees to optimally intersect the steeply dipping | |
| east-west striking mineralised zones of high sulphidation style | ||
| epithermal mineralization. | ||
| In cases where ‘industry standard’ work has been done this would be | The drill hole locations are to be picked up by local survey contractors | |
| relatively simple (eg ‘reverse circulation drilling was used to obtain 1 | using a DGPS (Differential Global Positioning System). | |
| m samples from which 3 kg was pulverised to produce a 30 g charge | ||
| for fire assay’). In other cases more explanation may be required, such as where there is coarse gold that has inherent sampling problems. Unusual commodities or mineralisation types (eg |
Down hole surveys have been undertaken using a Reflex EZ-Trac tool. Down hole surveys were conducted at intervals of 25m. |
|
| submarine nodules) may warrant disclosure of detailed information. | All DD holes completed by the Genesis were sampled by cutting the | |
| core longitudinally in half using diamond saws. Sampling of diamond | ||
| core was also undertaken on 1m intervals. | ||
| Diamond core was drilled to obtain high quality samples that were | ||
| logged for lithological, structural, geotechnical, density and other | ||
| attributes. Sampling of diamond core was also on one meter intervals | ||
| with the core being cut in half using a diamond core saw | ||
| Sub-samples of ~3 kg were sent to the laboratory for assaying. | ||
| Analysis has been performed by commercial laboratories with | ||
| samples sent to SGS Ankara. The samples sent to SGS follow | ||
| standard SGS crushing and pulverization procedures and a | ||
| conventional fire assay procedure with either atomic absorption or | ||
| gravimetric finish on a 30 gram sub-sample. Fire Assay is considered | ||
| a total recoverymethod forgold. |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 16
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| QC samples have been inserted into the routine sample stream to | ||
| monitor sample quality as per industry best practice. These include | ||
| standards, blanks and duplicates at regular (25m intervals) | ||
| RC Samples were split every 1m at the rig using a rifle splitter and the | ||
| sub-samples ofapproximately 3kg sent to SGSAnkara. | ||
| Drilling | Drill type (eg core, reverse circulation, open-hole hammer, rotary air | The core drill rigs used 3m drill rods. Diamond drilling has employed a |
| techniques | blast, auger, Bangka, sonic, etc) and details (eg core diameter, triple | 63.5mm diameter HQ ‘standard tube’ core drilling methods. |
| or standard tube, depth of diamond tails, face-sampling bit or other | RC drilling has been completed with 6m rods using a 4.5” or 121 mm | |
| type, whether core is oriented and if so, by what method, etc). | face sampling hammer bit. | |
| Orientation are completed every run (maximum 3m) using a spear | ||
| technique. Diamond drill core is typically orientated where possible | ||
| though often the core is highly fractured and cannot be reliably | ||
| orientated usingstandard techniques. | ||
| Drill sample | Method of recording and assessing core and chip sample recoveries | Diamond drill core is assessed by measuring the recovered drill |
| recovery | and results assessed. | length against the actual drilled. Diamond drill recovery is generally |
| Measures taken to maximise sample recovery and ensure | above 95%.Recoveries drop to less than this in minor (1-2m) zones of | |
| representative nature of the samples. | vuggy silica and clay. | |
| Whether a relationship exists between sample recovery and grade and whether sample bias may have occurred due to preferential loss/gain of fine/coarse material. |
RC sample weights have been taken on all primary samples. Theoretical sample weights are then compared to the actual sample to identify any intervals that have had poor recovery. Average recoveries |
|
| for RC holes are >95% but can vary significantly between holes. | ||
| No detailed analysis of grade versus recovery has been undertaken | ||
| at this stage however comparison of RC against DD gold results | ||
| indicates a slight positive bias for RC drilling. This may indicate some | ||
| loss of fines when using DD methods. | ||
| No coarse gold has been observed through Photo-micrographic | ||
| studies. |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 17
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Logging | Whether core and chip samples have been geologically and | All drill holes have been logged in full and record standard criteria |
| geotechnically logged to a level of detail to support appropriate | such as lithology, alteration, mineralisation, structural, weathering and | |
| Mineral Resource estimation, mining studies and metallurgical | oxidation. Geotechnical data such as drill recovery, RQD, hardness, | |
| studies. | fracture type and frequency are also recorded for input into future | |
| Whether logging is qualitative or quantitative in nature. Core (or | scoping level mining studies. | |
| costean, channel, etc) photography. | ||
| The total length and percentage of the relevant intersections logged. | All logging is entered into excel spreadsheet templates or onto hard | |
| copy forms which are transferred to excel spreadsheets. These | ||
| spreadsheets are then routinely imported into Micromine. | ||
| All diamond core is photographed in a wet and dry state. | ||
| Sub- | If core, whether cut or sawn and whether quarter, half or all core | Refer to the above sampling techniques |
| sampling | taken. | Quarter core duplicates are submitted every 50m. |
| techniques | If non-core, whether riffled, tube sampled, rotary split, etc and | |
| and sample | whether sampled wet or dry. | |
| preparation | For all sample types, the nature, quality and appropriateness of the | |
| sample preparation technique. | ||
| Quality control procedures adopted for all sub-sampling stages to | ||
| maximise representivity of samples. | ||
| Measures taken to ensure that the sampling is representative of the in | ||
| situ material collected, including for instance results for field | ||
| duplicate/second-half sampling. | ||
| Whether sample sizes are appropriate to the grain size of the material | ||
| being sampled. | ||
| Quality of | The nature, quality and appropriateness of the assaying and | Refer to the above analysis methods |
| assay data | laboratory procedures used and whether the technique is considered | |
| and | partial or total. | Industry standard QC sample insertion procedures have been |
| laboratory | For geophysical tools, spectrometers, handheld XRF instruments, etc, | adopted. QC insertion rates are: |
| tests | the parameters used in determining the analysis including instrument | - every 50m is a field duplicate, |
| make and model, reading times, calibrations factors applied and their | - every 25m is a Standard, |
|
| derivation, etc. Nature of quality control procedures adopted (eg standards, blanks, |
- every 50m is a coarse blank |
|
| duplicates, external laboratory checks) and whether acceptable levels of accuracy (ie lack of bias) and precision have been established. |
The QAQC results indicate acceptable levels of precision and accuracy |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 18
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Verification | The verification of significant intersections by either independent or | Samples are currently submitted to an umpire laboratory however the |
| of sampling | alternative company personnel. | results are yet to be reviewed |
| and | The use of twinned holes. | |
| assaying | Documentation of primary data, data entry procedures, data | Data is imported into Micromine. There is no adjustment of assay |
| verification, data storage (physical and electronic) protocols. | data. | |
| Discuss any adjustment to assay data. | ||
| Location of | Accuracy and quality of surveys used to locate drill holes (collar and | A local control station near the project is utilised by the local |
| data points | down-hole surveys), trenches, mine workings and other locations | surveying contractor. Holes are routinely surveyed using Surveyors |
| used in Mineral Resource estimation. | with DGPS equipment. | |
| Specification of the grid system used. | ||
| Quality and adequacy of topographic control. | All surveys are taken using the Gauss–Krüger (GK) coordinate | |
| system which has been the system used for survey by Genesis at | ||
| Plavica since 2012. | ||
| Data spacing | Data spacing for reporting of Exploration Results. |
The nominal drill hole spacing is 100m (easting) x 50m (northing) |
| and | Whether the data spacing and distribution is sufficient to establish the | |
| distribution | degree of geological and grade continuity appropriate for the Mineral | Samples are collected at one meter lengths and are not composited |
| Resource and Ore Reserve estimation procedure(s) and | in the field / core-shed. | |
| classifications applied. | ||
| Whether sample compositing has been applied. | ||
| Orientation | Whether the orientation of sampling achieves unbiased sampling of | Holes were generally drilled towards grid north with dips of |
| of data in | possible structures and the extent to which this is known, considering | approximately 45 to 60 degrees to optimally intersect the steeply |
| relation to | the deposit type. | dipping east-west striking mineralised zones |
| geological | If the relationship between the drilling orientation and the orientation | |
| structure | of key mineralised structures is considered to have introduced a | No orientation based sampling bias has been identified in the data at |
| sampling bias, this should be assessed and reported if material. | this stage | |
| Sample | The measures taken to ensure sample security. | Chain of Custody is managed by Genesis Staff. All drilling assay |
| security | samples were collected from the field by Genesis personnel. Core | |
| samples were stored at the secure sample processing and storage | ||
| facility where they were subsequently processed and prepared for | ||
| pickup. This facility has CCTV. Assay samples were collected by | ||
| appropriately qualified staff at the laboratories. |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 19
| Criteria | JORC Code explanation | Commentary |
|---|---|---|
| Audits or | The results of any audits or reviews of sampling techniques and data. | An audit of drilling and sampling procedures was undertaken by |
| reviews | Golder Associates in 2012 at the commencement of that years drilling | |
| program. A number of priority based recommendations were provided | ||
| to Genesis. All priority 1 recommendations were implemented and | ||
| many of the lower priority actions have also been completed. The | ||
| implementation of these recommendations has provided increased | ||
| confidence in the quality of the data used in the resource estimate |
Section 2 – Reporting of Exploration Results.
| Criteria | JORC | Code explanation | Commentary |
|---|---|---|---|
| Mineral tenement and land tenure status |
| Type, reference name/number, location and ownership including agreements or material issues with third parties such as joint ventures, partnerships, overriding royalties, native title interests, historical sites, wilderness or national park and environmental |
A 30 year Exploitation Licence and Concession Agreement were granted to Silgen Resources International Ltd, an incorporated joint venture entity owned by Genesis and its Macedonian-based joint venture partner RIK Sileks AD Kratovo. Silgen is 62% owned by |
| settings. | Genesis. The JV Company has been formally granted the Licence for | ||
| | The security of the tenure held at the time of reporting along with | a term of 30 years. The area covered by the Licence totals 16.85 km2. |
|
| any known impediments to obtaining a licence to operate in the | Genesis has pledged its 62% share of Silgen to completing a Feasibility | ||
| area. | Study to mine Plavica and has agreed to spend USD $7.5M for this | ||
| work. | |||
| All Australian Tenements are Exploration Licences except Mt Millar | |||
| which is a Mining Lease Application and are 100% owned by Genesis. | |||
| Exploration done by other parties |
Acknowledgement and appraisal of exploration by other parties. | At Plavica previous small scale mining was undertaken by Romans and Ottoman Turks. 2 adits were completed by British Mines Selection in the 1930’s targeting enargite veins. |
|
| Previous exploration has been conducted by the Yugoslav | |||
| Government, Cyprus Amax, Rio Tinto and European Minerals. |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 20
| Criteria | JORC | Code explanation | Commentary |
|---|---|---|---|
| Geology | Deposit type, geological setting and style of mineralisation | Both Plavica and Maricanski Rid host oxide gold mineralization in | |
| vuggy silica and clay zones within silica caps of a high sulphidation | |||
| epithermal style setting. Alunite alteration is widespread. | |||
| Beneath this oxide zone is a series of steeply dipping E-W striking | |||
| structures comprising enargite-pyrite veins and vuggy silica zones. | |||
| These zones are rich in Au, Cu, Ag and occasionally Pb and Zn. | |||
| The prospects lie within the Western Tethyan Arc and are Tertiary in | |||
| age. | |||
| Drill hole Information |
| A summary of all information material to the understanding of the exploration results including a tabulation of the following information for all Material drill holes: |
All drill hole collars with location, elevation, depth, dip and azimuth are tabulated in the body of the report. |
| o easting and northing of the drill hole collar | |||
| o elevation or RL (Reduced Level – elevation above sea level in metres) | |||
| of the drill hole collar | |||
| o dip and azimuth of the hole | |||
| o down hole length and interception depth | |||
| o hole length. | |||
| | If the exclusion of this information is justified on the basis that the | ||
| information is not Material and this exclusion does not detract from the | |||
| understanding of the report, the Competent Person should clearly | |||
| explain why this is the case. | |||
| Data aggregation methods |
|
In reporting Exploration Results, weighting averaging techniques, maximum and/or minimum grade truncations (e.g. cutting of high grades) and cut-off grades are usually Material and should be stated. Where aggregate intercepts incorporate short lengths of high grade results and longer lengths of low grade results, the procedure used for such aggregation should be stated and some typical examples of such aggregations should be shown in detail. |
A 0.4 g/t Au cut-off is used for reporting of Au grades and a 0.3 % for Cu grades. No top cuts are used. A minimum of 3m length is used for compositing and a maximum of 3m of internal waste is used. These parameters are considered adequate for this deposit style. No metal equivalents used |
| | The assumptions used for any reporting of metal equivalent values | ||
| should be clearly stated. | |||
| Relationship between |
| These relationships are particularly important in the reporting of Exploration Results. |
Core orientation and sectional interpretation suggest the mineralised zones are sub-vertical. |
| mineralisation | |
If the geometry of the mineralisation with respect to the drill hole angle | |
| widths and intercept lengths |
| is known, its nature should be reported. If it is not known and only the down hole lengths are reported, there should be a clear statement to this effect (e.g. ‘down hole length, true width not known’). |
Holes are drilled on 45 to 60 degree angles to intersect the zones at the highest angle possible but also taking into account the steep topography of the area and the difficulty of locating drill pads. As a result the mineralized zones are intersected at an oblique angle and |
| therefore down-hole lengths are not true widths. |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 21
| Criteria | JORC | Code explanation | Commentary | Commentary |
|---|---|---|---|---|
| Diagrams | | Appropriate maps and sections (with scales) and tabulations of | | A plan and section are included. |
| intercepts should be included for any significant discovery being | . | |||
| reported. These should include, but not be limited to a plan view of drill | ||||
| hole collar locations and appropriate sectional views. | ||||
| Balanced | | Where comprehensive reporting of all Exploration Results is not | | Of the holes reported this Quarter, some had significant results whilst |
| reporting | practicable, representative reporting of both low and high grades and/or | others had ‘No Significant Assays’ (NSA). | ||
| widths should be practiced to avoid misleading reporting of Exploration | ||||
| Results. | ||||
| Other | | Other exploration data, if meaningful and material, should be reported | | N/A. |
| substantive | including (but not limited to): geological observations; geophysical | |||
| exploration | survey results; geochemical survey results; bulk samples – size and | |||
| data | method of treatment; metallurgical test results; bulk density, | |||
| groundwater, geotechnical and rock characteristics; potential | ||||
| deleterious or contaminating substances. | ||||
| Further work | | The nature and scale of planned further work (e.g. tests for lateral | | Further step-out drilling will depend on the next set of results that are |
| extensions or depth extensions or large-scale step-out drilling). | currently pending. | |||
| | Diagrams clearly highlighting the areas of possible extensions, including | |||
| the main geological interpretations and future drilling areas, provided | ||||
| this information is not commercially sensitive. |
Genesis Resources Limited | Quarterly Activities Report | April 2016 – June 2016
Page 22
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Rule 5.5
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Introduced 01/07/96 Origin Appendix 8 Amended 01/07/97, 01/07/98, 30/09/01, 01/06/10, 17/12/10, 01/05/2013
Name of entity
| Name of entity | |
|---|---|
| GENESIS RESOURCES LIMITED | |
| ABN 22 114 787 469 |
Quarter ended (“current quarter”) |
| 22 114 787 469 | 30 June 2016 |
Consolidated statement of cash flows
| Cash flows related to operating activities 1.1 Receipts from product sales and related debtors 1.2 Payments for (a) exploration & evaluation (b) development (c) production (d) administration 1.3 Dividends received 1.4 Interest and other items of a similar nature received 1.5 Interest and other costs of finance paid 1.6 Income taxes paid 1.7 Other (provide details if material) Net Operating Cash Flows |
Current quarter $A’000 |
Year to date (12 months) $A’000 |
|---|---|---|
| (533) - - (425) - - 2 (7) - |
(2,482) - - (1,809) - - 10 (25) - |
|
| (963) | (4,306) | |
| Cash flows related to investing activities 1.8 Payment for purchases of: (a) prospects (b) equity in subsidiary (c) other fixed assets (d) other non current assets 1.9 Proceeds from sale of: (a) prospects (b) equity investments (c) other fixed assets (d) other non current assets 1.10 Loans to other entities 1.11 Loans repaid by other entities 1.12 Other (provide details if material) Net investing cash flows 1.13 Total operating and investing cash flows (carriedforward) |
- - - - - - - - - - - |
- (5) (7) - - - - - - - - |
| - | (12) | |
| (963) | (4,318) |
- See chapter 19 for defined terms.
01/05/2013 Appendix 5B Page 1
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report
| 1.13 Total operating and investing cash flows (broughtforward) |
(963) | (4,318) |
|---|---|---|
| Cash flows related to financing activities 1.14 Proceeds from issues of shares, options, etc. 1.15 Proceeds from sale of forfeited shares 1.16 Proceeds from borrowings 1.17 Repayment of borrowings 1.18 Dividends paid 1.19 Unallocated shares application fund 1.20 Transaction costs Net financing cash flows |
- - 1,000 (85) - - - |
- - 2,328 (527) - 1,041 - |
| 915 | 2,842 | |
| Net increase (decrease) in cash held 1.20 Cash at beginning of quarter/year to date 1.21 Exchange rate adjustments to item 1.20 1.22 Cash at end ofquarter |
(48) 566 (14) |
(1,476) 2,035 (55) |
| 504 | 504 |
Payments to directors of the entity, associates of the directors, related entities of the entity and associates of the related entities
| 1.23 1.24 |
Aggregate amount of payments to the parties included in item 1.2 Aggregate amount of loans to the parties included in item 1.10 |
Current quarter $A'000 |
|---|---|---|
| - | ||
| - | ||
| 1.25 | Explanation necessaryforanunderstanding ofthe transactions | |
| None |
Non-cash financing and investing activities
| 2.1 2.2 |
Details of financing and investing transactions which have had a material effect on consolidated assets andliabilities but didnotinvolve cash flows |
|---|---|
| None | |
| Details of outlays made by other entities to establish or increase their share in projects in whichthereporting entityhas an interest |
|
| None |
- See chapter 19 for defined terms.
Appendix 5B Page 2
01/05/2013
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
Financing facilities available
Add notes as necessary for an understanding of the position.
| Amount available | Amount used | ||
|---|---|---|---|
| $A’000 | $A’000 | ||
| 3.1 | Loan facilities (refer to (i) and (iii) below) | 7,000 | - |
| 3.2 | Credit standby arrangements | ||
| - | - |
- (i) In September 2013, the Company entered into a loan agreement with an unrelated Malaysian based financing company pursuant to which the financing company made available a loan facility to the Company, with a $3 million facility limit ( First Loan Facility ). In April 2014, the parties reached an agreement to increase the First Loan Facility limit from $3 million to $7 million on the same terms and conditions provided for in the existing loan agreement. Total funds of $7 million remain available for draw down by Genesis under the First Loan Facility.
Estimated cash outflows for next quarter
| Estimated cash outflows for next quarter | |
|---|---|
| 4.1 Exploration and evaluation 4.2 Development 4.3 Production 4.4 Administration |
$A’000 |
| 1,022 | |
| - | |
| - | |
| 260 | |
| Total | 1,282 |
(ii) Whilst the Company expects that its estimated cash flows will exceed its cash currently at hand, the Company has access to the loan facilities as detailed above.
Reconciliation of cash
| Reconciliation of cash | ||
|---|---|---|
| Reconciliation of cash at the end of the quarter (as shown in the consolidated statement of cash flows) to therelateditemsinthe accountsis asfollows. |
Current quarter $A’000 |
Previous quarter $A’000 |
| 5.1 Cash on hand and at bank 5.2 Deposits at call 5.3 Bank overdraft 5.4 Other (Term deposit – bank guarantee) |
504 | 566 |
| - | - | |
| - | - | |
| 98 | 98 | |
| Total: cash at end ofquarter(item 1.22) | 602 | 664 |
- See chapter 19 for defined terms.
01/05/2013 Appendix 5B Page 3
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report
Changes in interests in mining tenements and petroleum tenements
| Tenement reference and location Nature of interest (note (2) Interest at beginning of quarter Interest at end of quarter 6.1 Interests in mining tenements and petroleum tenements relinquished, reduced or lapsed - - - - 6.2 Interests in mining tenements and petroleum tenements acquired or increased - - - - Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. |
Tenement reference and location Nature of interest (note (2) Interest at beginning of quarter Interest at end of quarter 6.1 Interests in mining tenements and petroleum tenements relinquished, reduced or lapsed - - - - 6.2 Interests in mining tenements and petroleum tenements acquired or increased - - - - Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. |
Tenement reference and location Nature of interest (note (2) Interest at beginning of quarter Interest at end of quarter 6.1 Interests in mining tenements and petroleum tenements relinquished, reduced or lapsed - - - - 6.2 Interests in mining tenements and petroleum tenements acquired or increased - - - - Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. |
Tenement reference and location Nature of interest (note (2) Interest at beginning of quarter Interest at end of quarter 6.1 Interests in mining tenements and petroleum tenements relinquished, reduced or lapsed - - - - 6.2 Interests in mining tenements and petroleum tenements acquired or increased - - - - Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. |
Tenement reference and location Nature of interest (note (2) Interest at beginning of quarter Interest at end of quarter 6.1 Interests in mining tenements and petroleum tenements relinquished, reduced or lapsed - - - - 6.2 Interests in mining tenements and petroleum tenements acquired or increased - - - - Issued and quoted securities at end of current quarter Description includes rate of interest and any redemption or conversion rights together with prices and dates. |
|---|---|---|---|---|
| Total number | Number quoted |
Issue price per security (see note 3) (cents) |
Amount paid up per security (see note 3) (cents) |
|
| 7.1 Preference +securities (description) 7.2 Changes during quarter (a) Increases through issues (b) Decreases through returns of capital, buy- backs, redemptions |
- | - | - | - |
| - | - | - | - | |
| 7.3 +Ordinary securities |
384,885,386 | 384,885,386 | Fully paid | Fully paid |
- See chapter 19 for defined terms.
Appendix 5B Page 4
01/05/2013
Appendix 5B
Mining exploration entity and oil and gas exploration entity quarterly report
| 7.4 Changes during quarter (a) Increases through issues (b) Decreases through returns of capital, buy- backs |
Genesis issued a total of 27,139,541 ordinary shares during the quarter under a placement on 6 May 2016. |
27,139,541 | 27,139,541 shares were issued at $0.04 per share under a placement on 6 May 2016. |
The 27,139,541 shares issued on 6 May 2016 are fully paid up at $0.04 per share |
|---|---|---|---|---|
| 7.5 +Convertible debt securities (description) 7.6 Changes during quarter (a) Increases through issues (b) Decreases through securities matured, converted |
- | - | - | - |
| - | - | - | - | |
| 7.7 Options (description and conversion factor) 7.8 Issued during quarter 7.9 Exercised during quarter 7.10 Expired during quarter |
- | - | - | - |
| - | - | - | - | |
| - | - | - | - | |
| - | - | - | - | |
| 7.11 Debentures (totals only) |
- | - | ||
| 7.12 Unsecured notes(totals only) |
- | - |
- See chapter 19 for defined terms.
01/05/2013 Appendix 5B Page 5
Appendix 5B Mining exploration entity and oil and gas exploration entity quarterly report
Compliance statement
-
1 This statement has been prepared under accounting policies which comply with accounting standards as defined in the Corporations Act or other standards acceptable to ASX (see note 5).
-
2 This statement does give a true and fair view of the matters disclosed.
==> picture [75 x 42] intentionally omitted <==
Alyn Tai Non-Executive Director 29 July 2016
Notes
-
1 The quarterly report provides a basis for informing the market how the entity’s activities have been financed for the past quarter and the effect on its cash position. An entity wanting to disclose additional information is encouraged to do so, in a note or notes attached to this report.
-
2 The “Nature of interest” (items 6.1 and 6.2) includes options in respect of interests in mining tenements and petroleum tenements acquired, exercised or lapsed during the reporting period. If the entity is involved in a joint venture agreement and there are conditions precedent which will change its percentage interest in a mining tenement or petroleum tenement, it should disclose the change of percentage interest and conditions precedent in the list required for items 6.1 and 6.2.
-
3 Issued and quoted securities The issue price and amount paid up is not required in items 7.1 and 7.3 for fully paid securities .
-
4 The definitions in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows apply to this report.
-
5 Accounting Standards ASX will accept, for example, the use of International Financial Reporting Standards for foreign entities. If the standards used do not address a topic, the Australian standard on that topic (if any) must be complied with.
== == == == ==
- See chapter 19 for defined terms.
Appendix 5B Page 6
01/05/2013