Management’s Discussion and Analysis For the Six Months Ended June 30, 2022

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

The following is Management’s Discussion and Analysis (“MD&A”) of the unaudited condensed consolidated interim financial statements of operations of Generation Mining Limited and its wholly owned subsidiary company (together “Generation” or the “Company”) for the three and six months ended June 30, 2022. This MD&A should be read in conjunction with the unaudited consolidated financial statements for the three and six months ended June 30, 2022 and 2021 and the December 31, 2021 year end audited consolidated financial statements including the notes thereto, prepared in accordance with the International Financial Reporting Standards or (“IFRS”).

The MD&A is prepared by management and approved by the Board of Directors as of August 11, 2022. All figures are in Canadian dollars unless stated otherwise. Additional information relevant to the Company’s activities can be found on SEDAR at www.sedar.com.

This MD&A contains forward-looking statements. All statements in this discussion, other than statements of historical fact, that address future exploration activities and events or developments that the Company expects, are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements should be read in conjunction with the risk factors described in the “Risk Factors” and “Cautionary Note Regarding Forward Looking Information” sections at the end of this MD&A and as described in the Company’s Annual Information Form ("AIF") for the year ended December 31, 2022.

Scientific and technical information contained in this MD&A relating to mineral reserves, mineral resources and exploration results was reviewed and approved by Drew Anwyll, P.Eng., M.Eng., Chief Operating Officer of the Company, and Rod Thomas, P.Geo., Director of the Company, each a “Qualified Person” under National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”).

Readers are referred to the NI 43-101 technical report for the Marathon Project entitled, “Feasibility Study Marathon Palladium & Copper Project Ontario, Canada” (the “Feasibility Study”) dated March 23, 2021. Readers are encouraged to review the full text of the Feasibility Study, available for review under the Company’s profile on SEDAR at www.sedar.com. The Feasibility Study supports the scientific and technical information set out in this MD&A.

Certain non-IFRS measures are included in this MD&A and are discussed in the Non-IFRS Measures section of this MD&A.

1

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Contents

BUSINESS OVERVIEW .................................................................................................................................. 3 2022 SECOND QUARTER AND FULL YEAR HIGHLIGHTS .............................................................................. 3 OUTLOOK .................................................................................................................................................... 4 CORPORATE, PROJECT AND EXPLORATION UPDATES ................................................................................ 4 Strengthening Management Team ............................................................................................................... 4 Advancing Project Engineering and Early Procurements .............................................................................. 5 Environment, Permitting and Community .................................................................................................... 7 Project Financing ........................................................................................................................................... 9 FEASIBILITY STUDY - MARATHON PROJECT .............................................................................................. 10 Feasibility Study Highlights[(1)] ...................................................................................................................... 11 Feasibility Sensitivities ................................................................................................................................ 12 RESULTS FROM OPERATIONS ................................................................................................................... 13 SUMMARY OF QUARTERLY RESULTS ........................................................................................................ 16 FINANCIAL POSITION ................................................................................................................................ 17 LIQUIDITY AND GOING CONCERN UNCERTAINITY .................................................................................... 18 CAPITAL RESOURCES ................................................................................................................................. 19 MARATHON PROPERTY ACQUISITION ...................................................................................................... 19 SUMMARY OF MINERAL RESERVES AND RESOURCES .............................................................................. 20 Mineral Resources ...................................................................................................................................... 20 Mineral Reserves ........................................................................................................................................ 21 OTHER MINERAL PROPERTIES .................................................................................................................. 21 RELATED PARTY TRANSACTIONS .............................................................................................................. 22 OUTSTANDING SECURITY DATA ................................................................................................................ 22 FINANCIAL RISK MANAGEMENT ............................................................................................................... 24 FEASIBILITY STUDY – ADDITIONAL KEY RESULTS ...................................................................................... 26 OFF-BALANCE SHEET ARRANGEMENTS .................................................................................................... 28 DIVIDENDS ................................................................................................................................................ 28 CRITICAL ACCOUNTING ESTIMATES AND JUDGEMENTS .......................................................................... 28 ACCOUNTING POLICIES AND BASIS OF PRESENTATION ........................................................................... 28 NON-IFRS MEASURES................................................................................................................................ 29 RECENT ACCOUNTING PRONOUNCEMENTS ............................................................................................ 29 INTERNAL CONTROL OVER FINANCIAL REPORTING ................................................................................. 29 DISCLOSURE CONTROLS AND PROCEDURES ............................................................................................. 30 LIMITATIONS OF CONTROLS AND PROCEDURES ...................................................................................... 30 RISKS AND UNCERTAINTIES ...................................................................................................................... 30 CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION ................................................... 31 INFORMATION CONCERNING ESTIMATES OF MINERAL RESERVES AND RESOURCES ............................. 32

2

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

BUSINESS OVERVIEW

The Company was incorporated under the Business Corporations Act (Ontario) on January 11, 2018. Its registered office is located at 100 King Street West, Suite 7010, Toronto, Ontario M5X 1B1. The Company’s common shares trade on the Toronto Stock Exchange (“TSX”) under the symbol GENM and OTCQB Venture Marketplace under the symbol GENMF. The Company is an exploration and development stage company primarily focused on the development and construction of the Marathon Palladium and Copper project located in Marathon, Ontario Canada (the “Marathon Property” or “Marathon Project” or the “Project”), a large undeveloped platinum group metal and copper mineral deposit in Northwestern Ontario, Canada. The Marathon Project is 100% owned by Generation PGM Inc. (“Generation PGM”) a wholly owned subsidiary of Generation. The Company also has a number of other exploration properties located in Canada.

The Company released the results of the Marathon Project Feasibility Study on March 3, 2021 and published the N.I. 43-101 Technical Report dated March 25, 2021 which is available on the Company’s profile on SEDAR.com. The Marathon Property covers a land package of approximately 22,000 hectares, or 220 square kilometers. The Feasibility Study estimated that at US$1,725/oz palladium, and US$3.20/lb copper, the Marathon Project’s net present value (at a 6% discount rate) is approximately $1.07 billion with a payback of 2.3 years and an internal rate of return of 30%. Project capital costs were estimated at $665 million, net of equipment financing, pre-production operating costs and production revenues. The mine would produce an estimated 245,000 palladium equivalent ounces per year over a 13-year mine life at an all-in sustaining cost of US$809 per palladium-equivalent ounce.

2022 SECOND QUARTER AND FULL YEAR HIGHLIGHTS

  • On May 19, 2022 the Public Hearings conducted by the Joint Review Panel ("JRP") on the Environmental Impact Statement ("EIS") of the Company's Marathon Project concluded. On August 2, 2022 the JRP delivered its report (the "Report"). The Report sets out recommendations for the Company, and the federal and provincial governments, to mitigate or minimize any adverse effects of the Marathon Project. The Report has been submitted to the offices of both the Federal Minister of Environment and Climate Change and the Ontario Minister of the Environment. The ministerial decisions are expected to follow within 120 days.

  • On June 8, 2022 the Company provided a Project Finance update, having received significant nonbinding expressions of interest from more than a dozen lenders, including commercial banks, export credit agencies, offtake partners and equipment lessors. The Company’s appointed project finance advisor, Endeavour Financial, estimates that the project can carry approximately US$400 million in senior debt based on the Company’s Feasibility Study dated March 3, 2021. Export Development Canada (EDC) has provided an expression of interest to support the project, subject to the successful completion of its due diligence process, indicating the potential to provide project debt financing of up to US$200 million.

  • The Company has significantly bolstered its management team to support the advancement and development of the Marathon Project. Newly filled roles include VP Finance, VP Investor Relations, VP Geology, VP Sustainability and Technical Services Manager. See Corporate Updates section of this MD&A for further discussion.

3

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

  • Subsequent to quarter end, the Company announced the acquisition of an unused ball and SAG mill, reducing the risk associated with the procurement, logistics and cost-uncertainty associated with these long-lead items for the Project.

  • Following quarter end, the Company announced a lease purchase option agreement of an existing construction camp located near the Town of Marathon, Ontario, which will be used to accommodate up to 263 workers for the initial site preparation phase through the construction phase.

  • On March 31, 2022 the Company closed a Precious Metal Purchase Agreement (“PMPA”) with Wheaton Precious Metals Corp. (“Wheaton”) and concurrently drew the first $20 million under the facility.

  • In January 2022, the Company concluded the acquisition of the remaining interest in the Marathon Property from Sibanye-Stillwater to hold a 100% interest in the Marathon Project. Sibanye-Stillwater is currently the largest shareholder of Generation holding 32,813,127 common shares representing a current ownership position of approximately 18.2% of the Company.

OUTLOOK

The Company intends to continue to aggressively advance the development of the Marathon Project. Key milestones and areas of focus over the next twelve months will include the following:

  • Environmental Assessment (“EA”) decisions by both the Federal Minister of Environment and Climate Change and the Ontario Minister of the Environment are expected by November 30, 2022 (120 days following the issuance of the JRP’s Report dated August 2, 2022);

  • Following the approval of the EA, receive permits critical to allow for construction to commence;

  • Finalize Community Benefit Agreements (“CBA”) with Biigtigong Nishnaabeg First Nations partners;

  • Advancement of detailed engineering, long-lead procurements and project execution plan;

  • Arrange project financing required to develop the Marathon Project; and

  • Commence early-works construction.

CORPORATE, PROJECT AND EXPLORATION UPDATES

Strengthening Management Team

The Company has made significant additions to the management team throughout 2022 to support the advancement and development of the Marathon Project.

In April the Company appointed Christopher Stackhouse as Vice-President of Finance. Mr. Stackhouse spent seven years with Guyana Goldfields Inc. (now part of the Zijin Mining Group) and was instrumental in the preparation of the feasibility study, financing, development and operation of Guyana’s US$250 million Aurora Gold Mine.

In May the Company appointed Mauro Bassotti as Vice President of Geology. Mr. Bassotti brings over 24 years diverse international and domestic experience with open pit and underground mines in gold, copper and other base metals. He has extensive leadership experience in brownfield and capital drilling, all aspects of operational geological site functions, and technical services. Mr. Bassotti has successfully

4

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

delivered projects from exploration drilling to delineation drilling, identifying additional indicated mineral resources and inferred mineral resources at a number of projects. Most recently he was Senior Director Geology of Ma’aden Mining, Gold and Base Metals in Riyadh, KSA, where he was responsible for the corporate guidance and direction of the Geological group. Prior to this role, he worked with Detour Gold, New Gold, Barrick Gold and Placer Dome, across Asia Pacific, Africa, Australia, and Canada. Mauro has been recognized as the Qualified Person under N143-101 and other reporting requirements.

In May the Company appointed Ann Wilkinson as Vice President of Investor Relations, a newly created role. Ms. Wilkinson has over 20 years’ experience in the mining industry in both investor relations and other management roles, bringing diverse expertise in investor and stakeholder relations domestically and internationally in Chile, Dominican Republic, Brazil and Honduras. Ann has successfully devised and executed investor relations initiatives on both strategic and tactical levels for existing and prospective investors and raised significant capital for various projects. She is well recognized within the investment community.

In May Daniel Janusauskas was appointed Technical Services Manager for the Company. Mr. Janusauskas’ most recent experience was with Baffinland Iron Mines in Nunavut as Technical Services Superintendent where he supervised Engineering, Geology, Survey and Production Technology teams. Previous mining experience with Detour Gold Inc., as a Strategic Mine Engineer, contributing to the life-of-mine planning, and co-authoring the 2015-2018 NI-43-101 Reports and Mineral Resource and Reserve Estimates.

In July the Company appointed Ruben Wallin as Vice President of Sustainability. Mr. Wallin is an environment and sustainability professional with more than 30 years of experience in the global mining industry. He has broad corporate and operational management experience in the areas of environment, health and safety, community relations, government relations, permitting and tailings management. Mr. Wallin has worked extensively throughout the Americas and Africa during his career and is experienced in current global industry standards and best practices. In Canada, he has been involved in the successful operation of the Detour Lake Mine, the Canadian Malartic Mine and the Victor Mine. Before joining McEwen Mining where he was the Vice President, Sustainability, Mr. Wallin held the position of Vice President of Environment and Sustainability for Detour Gold Corporation.

Advancing Project Engineering and Early Procurements

Engineering

The Company completed value engineering in the first quarter of 2022 and advanced the Project engineering and long-lead procurement (“EP Services”) of the Marathon Project throughout the first and second quarters of 2022. The EP Services work is being completed by the Wood PLC (“Wood”) engineering team (work progressing out of the Oakville Ontario office) with direct interaction with the Generation engineering and project team. The tailings dam designs, water infrastructure, and remaining on-site and off-site infrastructure designs will be advanced in parallel to the plant designs with the goal to advance approximately 75% of engineering to be complete at the commencement of construction. The budgeted costs to accomplish this phase of engineering is approximately $21.5 million, of which $4.2 million has been incurred at June 30, 2022.

5

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Early Procurements

SAG and Ball Mills

On August 8, 2022 the Company announced it had entered into an agreement with Hycroft Mining Holding Corporation (“Hycroft”) for the purchase of an unused, surplus SAG mill and ball mill (the “Mills”) currently stored in Nevada and Texas, USA for US$12,000,000 (the ”Purchase Price”), of which US$500,000 was due on signing, the second payment of US$500,000 due not later than September 30, 2022, and a final payment of US$11,000,000 due not later than March 31, 2023. The Company will also assume certain costs related to the Mills, including storage, insurance and financing charges, if any, until completion of the sale.

Prior to entering into the agreement, the Mills were inspected by FLSmidth (mechanical, structural) and ABB (electrical) and additionally, Orway Mineral Consultants completed a design applicability review. Prior to installation, FLSmidth has recommended cosmetic upgrades and painting of the mill components and ABB has recommended updating of the Mill drives. Overall, the reports have confirmed that the Mills are suitable for use on the Project. In addition, the Mills are slightly larger in size and power than as defined in the March 2021 Feasibility Study, which allows for the grinding circuit to be operated in a SAB configuration (as opposed to SABC), thereby eliminating the need for a pebble crusher in the current design. These Mills have been used in the current detailed engineering design being progressed by Wood.

Construction Camp

On July 12, 2022 the Company announced that it had entered into an agreement with Valard Equipment LP (“Valard”) for the lease of a construction camp (the “Camp”) located in Marathon, Ontario until June 30, 2023 (the “Lease Term”) and an option, exercisable at the Company’s discretion, to purchase the Camp on or before the end of the Lease Term. In connection with this agreement, the Company has also leased the existing serviced camp site from the Town of Marathon.

The Camp will be used to accommodate up to 263 workers for the initial site preparation phase through the construction phase. Additional accommodation capacity will be secured for the Marathon Project as construction ramps up to the maximum peak of approximately 1,000 workers. Previously, the Camp was used to accommodate the workforce for a Transmission Line Project and has all the required infrastructure services, including a commercial kitchen, a recreation facility, a maintenance facility and management offices. The Biigtigong Nishnaabeg First Nation community will operate and service the Camp as part of Gen PGM’s commitments under the Memorandum of Agreement with Biigtigong Nishnaabeg, previously announced on January 27, 2022.

Early Works Construction

Management currently expects that initial site clearing activities can commence as early as the first quarter of 2023. The timing for the start of early works construction is based on achieving the required permits and project financing, as discussed in their respective sections in this MD&A, along with formal Board approval to advance the Project.

6

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Environment, Permitting and Community

Environmental Assessment Updates

The development of a mining project in Ontario requires various approvals from both the Federal and Provincial governments. Project permitting is generally split into two phases, the Environmental Assessment (“EA”) phase followed by the permitting phase.

The Marathon Project is being assessed in accordance with the Canadian Environmental Assessment Act 2012 (“CEAA 2012”) and Ontario’s Environmental Assessment Act, 1990 (“EA Act”) through a JRP pursuant to the Canada-Ontario Agreement on Environmental Assessment Cooperation (2004).

Following approval of the Federal and Provincial Environmental assessments, various permits, approvals, and licenses will be required to construct and operate the Marathon Project.

The initial EA process was commenced by the prior proponent (Stillwater Canada Inc) of the Marathon Project in 2010 and was put on hold in January 2014. In September 2019, the Company received confirmation from the federal and provincial governments that the Marathon Project will remain subject to the requirements of the CEAA 2012 and the EA Act, and the process could be restarted.

In July 2020, the Company officially commenced the process to restart the EA approval process and to complete an Environmental Impact Statement (“EIS”) report addendum. In November 2020, the Government of Canada and the Province of Ontario appointed the JRP members to continue the EA of the Company’s Marathon Project. Updated baseline studies were submitted in November 2020 and the initial volume of the EIS was completed in January 2021 and the second volume in April 2021. The EIS provides an outline and analysis of key elements of the Project design, the environmental, economic, and social components along with the mitigation, controls and benefits that will be present over the life cycle of the Project from construction to post closure. The Project is being assessed in accordance with the CEAA 2012 and EA Act by the JRP. The JRP is an independent single Environmental Assessment process that is harmonized with the Federal and Ontario provincial governments and concludes with a recommendation report from the JRP to the federal and provincial Ministers.

In December 2021, the JRP determined that the EIS and additional information requests was sufficient to proceed to the public hearing and announced that the hearing is scheduled to take place from March 15[th] to May 19[th] , 2022. Over 50 participants, including members of the public, NGOs, government agencies and Indigenous groups participated in the hearing to to share their perspective and raise questions on the potential environmental and socio-economic effects of the project.

Representatives of Generation PGM, along with its expert witnesses, participated in the technical, general and Indigenous community sessions as scheduled throughout the hearing. Generation PGM’s witnesses explained the positive socio-economic aspects of the project as well as their expert predictions that the project is not expected to have significant adverse environmental effects. Throughout the hearing, the Panel members asked for several undertakings for supplemental information to complete their review, and requested that Generation PGM summarize all the mitigation measures, monitoring plans, follow-up programs and associated environmental management plans it had committed to in the EIS and during the EA process in a consolidated document (“Undertaking 31”). During the hearings, Biigtigong Nishnaabeg

7

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

and Pays Plat First Nation requested engagement with Generation PGM to ensure their requirements were captured in Generation PGM’s response to Undertaking 31. As a result, Generation PGM and Biigtigong Nishnaabeg requested a four-week extension to engage on critical commitments specific to Biigtigong Nishnaabeg and the filing of Undertaking 31. The Panel accepted the extension request. Consequently, Undertaking 31 was filed May 11, 2022, with closing remarks from the JRP occurring on May 19, 2022.

On August 2, 2022 the JRP published its Report. The Report sets out recommendations for the Company, and the federal and provincial governments, to mitigate or minimize any adverse effects of the Marathon Project. The completion of the Panel report is a significant milestone in the Environmental Assessment process. This Report has been submitted to the offices of both the Federal Minister of Environment and Climate Change and the Ontario Minister of the Environment. The ministerial decisions are expected to follow within 120 days.

As the proponent, the Generation PGM is responsible for the costs of the JRP and certain other permitting costs. As of the date of this MD&A, the JRP has incurred approximately $2.5 million.

Permitting Updates

The Company has commenced detailed engineering and permitting activities in parallel with the EA process, including preparation of the draft closure plan allowing for Indigenous consultation and review. Environmental committees have been established with Indigenous communities to collaborate on permit development for fisheries, caribou, water management and closure as well as upcoming environmental monitoring field programs.

To assist with the permitting program, the sustainability team is being supported by:

  • Wood Group PLC: closure planning, fisheries compensation planning, caribou mitigation and advance permits to allow for construction to commence,

  • Stantec Inc. : comprehensive air and noise modelling,

  • Knight Piésold Ltd : tailings and water management facility designs,

  • EcoMetrix Inc : geochemistry, aquatics, water quality modelling, and

  • Northern BioScience : monitoring of species at risk and terrestrial studies on the property.

Community Update

The Company and its predecessors have been engaged in consultation and negotiations with several Indigenous communities and regional municipalities with respect to the Project since 2004. The Company along with the identified communities are progressing relationships through regular meetings and interactions to advance towards the development of the Project. The Company is striving to ensure these partnerships have mutually beneficial outcomes and anticipates strong and long-lasting relationships with these groups.

In April 2021, the Company and Biigtigong Nishnaabeg signed an Agreement in Principle which outlines the framework for a Community Benefit Agreement (CBA). In January 2022, a Memorandum of Understanding (MOA) was also signed which commits the Company and Biigtigong Nishnaabeg to:

8

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

  • Collaborate on sustainable community-based business opportunities that will last beyond the life of the Marathon Project,

  • Target and support businesses that include training, development and growth of Biigtigong Nishnaabeg community members in their professional development and long-term employment,

  • Support strategic partnerships and initiatives that help Biigtigong Nishnaabeg participate in opportunities to gain management experience in the mining industry,

  • Support Biigtigong Nishnaabeg with their strategic goals of growing current and aspirational sustainable businesses, and

  • Defining some of the contracting projects that will be sole-sourced to Biigtigong Nishnaabeg to further maximize economic benefits for the Marathon Project’s closest Indigenous partner community.

Biigtigong Nishnaabeg has been an integral part of the environmental assessment process and Marathon Project planning. Formalizing the long-term relationship signals the community leadership’s support, in principle, for the Marathon Project and the Company’s commitment to provide community benefits including training, employment, business opportunities and financial participation. It is anticipated that the CBA will be approved by BN prior to the Ministers’ approval of the EA.

Project Financing

In August 2021, the Company appointed Endeavour Financial as its Financial Advisor to provide financial advisory services with respect to the development of the Marathon Project. Endeavour Financial, with offices in London, UK, George Town, Cayman Islands, and Vancouver, British Columbia, is a top mining financial advisory firm, with a record of success in the mining industry, specializing in arranging multisourced funding solutions for development-stage companies. The Endeavour Financial team has diverse experience in both natural resources and finance, including investment bankers, geologists, mining engineers, cash flow modelers and financiers.

Phase I – Stream Financing

Phase I of the project financing consisted of the marketing, due diligence and site visits with several financiers who expressed interest in all forms of financing including debt, equity, metal streams and royalties. The Company’s focus was to put in place the first tranche of the project financing without excessive dilution for shareholders, while ensuring the financing was sufficient and complementary to the ultimate financing package. The interest was significant, and the Company received multiple proposals. The most attractive proposal was from Wheaton Precious Metals.

In December 2021, the Company entered into a definitive Precious Metal Purchase Agreement (the “PMPA”) with Wheaton Precious Metals Corp. (“Wheaton”). The PMPA became effective in January 2022 upon closing of the acquisition of the remaining interest in the Marathon Property from Sibanye-Stillwater to hold a 100% interest in the Marathon Project. Pursuant to the PMPA, Wheaton will pay Generation total cash consideration of $240 million, $40 million of which will be paid on an early deposit basis prior to construction to be used for development of the Marathon Project, with the remainder payable in four staged installments during construction, subject to various customary conditions being satisfied. The details of the transaction are as follows:

9

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

  • Under the Marathon PMPA, Wheaton will purchase 100% of the payable gold production until 150 thousand ounces (“koz”) have been delivered, thereafter dropping to 67% of payable gold production for the life of the mine; and 22% of the payable platinum production until 120 koz have been delivered, thereafter dropping to 15% for the life of mine.

  • Wheaton will pay Generation total cash consideration of C$240 million, C$40 million of which will be paid on an early deposit basis prior to construction to be used for development of the Marathon Project, with the remainder payable in four staged installments during construction, subject to various customary conditions being satisfied and pre-determined completion tests.

  • Wheaton will make ongoing payments for the gold and platinum ounces delivered equal to 18% of the spot prices (“Production Payment”) until the value of gold and platinum delivered less the Production Payment is equal to the consideration of C$240 million, at which point the Production Payment will increase to 22% of the spot prices.

  • Generation Mining and its subsidiary Generation PGM will provide Wheaton with corporate guarantees and other security over their assets and various time sensitive performance guarantees relating to the development of the Project.

On March 31, 2022, Generation received, through its wholly-owned subsidiary Generation PGM, the first $20,000,000 payment pursuant to the PMPA with Wheaton.

Phase II – Balance of Project Financing

Phase II involves the access to medium term financing with the initial stage being a request for proposal process (“RFP”) for the balance of the project financing. The RFP process has resulted in strong initial nonbinding expressions of interest from more than a dozen lenders including commercial bank lenders, export credit financiers, private equity companies, potential offtake partners and equipment lessors. The interest has been significant with the total potential committed capital being well in excess of US$1 billion among several interested parties. The Company has been analyzing the proposals, advancing diligence and definitive documentation with a select group of lenders. The Company continues to focus on maximizing capital from non-equity sources while minimizing the cost of capital and maximizing equity returns. Endeavour estimates that the project can carry approximately US$400 million in senior debt based on the Company’s Feasibility Study dated March 3, 2021.

The Company also reported that Export Development Canada (“EDC”) had provided an expression of interest to support the project, subject to the successful completion of its due diligence process. EDC has indicated the ability to provide potential project financing of up to US$200 million. EDC is a financial Crown corporation dedicated to helping Canadian companies of all sizes succeed on the world stage.

The project finance process is expected to take several months and is being run in parallel with the Environmental Assessment and permitting approvals.

FEASIBILITY STUDY - MARATHON PROJECT

On March 3, 2021, the Company announced the results of a Feasibility Study for the Marathon Palladium and Copper Project. On March 25, 2021, the Company filed the N.I. 43-101 titled Feasibility Study Marathon Palladium & Copper Project Ontario, Canada on SEDAR. All dollar amounts are in Canadian

10

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

dollars, stated on a 100% project ownership basis, unlevered other than equipment leasing and based on the base case analysis unless otherwise noted (See notes below).

The Feasibility Study was prepared by G Mining Services Inc. (“GMS”), along with contributions from Ausenco Engineering Canada Inc. (“Ausenco”), Haggarty Technical Services (“HTS”), Knight Piésold Ltd. (“KP”), WESC Inc. and P&E Mining Consultants Inc. (“P&E”).

Feasibility Study Highlights[(1) ]

The Marathon Palladium Copper Project is located along the Trans-Canada Highway in Northwestern Ontario. A March, 2021 Feasibility Study has indicated the Marathon Palladium Copper Project has a net present value of C$1.07 billion (using a 6% discount rate)[2] with a payback of 2.3 years[2] and a robust internal rate of return of 30%[2] based on US$1,725/oz and US$3.20/lb for palladium and copper respectively. The Marathon Palladium Copper Project is projected to produce an average of 245,000 ounces of Palladium Equivalent (PdEq[4] ) annually over a minimum 13-year mine life. Initial capital costs are estimated at C$665 million (US$520 million)[3] , net of equipment financing and pre-completion operating costs and revenues. At US$1725/oz Pd and US$3.20/lb Cu approximately 58% of the revenue will come from palladium, with 26% coming from copper. The remaining revenue will come from platinum, gold and silver. Operating costs are estimated at US$687 per ounce PdEq[4] , while All-In-Sustaining-Costs are estimated at US$809 per ounce PdEq[4] .

Select key results from the study and various sensitivities are presented in the tables below. For further detail the reader should refer to the full Feasibility Study, which can be found on the Company’s website and filed under the Company’s profile on SEDAR (www.sedar.com). Select key results are displayed below, with further detail in the section of this MD&A titled Feasibility – Additional Key Results .

Key Results

Key Result Unit Value
After tax NPV6/IRR2 $billion 1.07
After tax IRR2 % 29.7
Initial capital cost3 $million 665
Paybackperiod Years 2.3
Life of mine Years 12.6
First 3years free cash flow $millions $979
LOM operatingcost $/tonne-milled $23.63
LOM all-in sustainingcost $/oz PdEq4 $809
LOM stripratio (waste:ore) 2.8
LOMpayablepalladium k ounces 2,078
LOMpayable copper million lbs 493
LOMpayableplatinum k ounces 537
LOMpayablegold k ounces 151
LOMpayable silver k ounces 2,823
  1. See “Feasibility Study Marathon Palladium & Copper Project Ontario, Canada” filed on SEDAR and the Company’s website. Also see Non-IFRS measures as set out in the section Non-IFRS Measures of this MD&A

  2. Using flat, real long-term prices of US$1,725/oz for palladium and US$3.20/lb for copper and USD:CAD FX rate of 1.28

  3. Capex net of equipment financing, pre-production operating costs and production revenues

  4. PdEq grade is calculated based on: (Pd US$1,725/31.10348 x Pd grade g/t) + (Cu US$3.20/2204.6x Cu grade %/100) + (Au US$1,400/31.10348 x Au grade g/t) +(Pt US$1,000/31.10348 x Pt grade g/t) + (Ag US$20/31.10348 x Ag grade g/t).

11

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Feasibility Sensitivities

The Project has significant leverage to the palladium and copper prices. The after-tax valuation sensitivities for the key metrics are shown below.

Palladium Price
US$/oz
1,000
1,250
1,500
1,725(1)
1,850
2,000
2,500
NPV6% ($M)
Payback (yrs)
IRR(%)
356
601
847
1,068
1,190
1,337
1,831
4.3
3.2
2.6
2.3
2.1
2.0
1.6
14.8%
20.2%
25.3%
29.7%
32.1%
34.8%
43.7%
Copper Price
US$/lb
2.00
2.50
3.00
3.20(1)
3.50
4.00
4.50
NPV6% ($M)
Payback (yrs)
IRR(%)
792
907
1,022
1,068
1,137
1,251
1,365
2.7
2.5
2.3
2.3
2.2
2.1
2.0
24.7%
26.8%
28.9%
29.7%
30.9%
32.9%
34.8%
-20%
-15%
0%(1)
15%
20%
1,270
1,220
1,068
916
866
2.1
2.1
2.3
2.4
2.5
33.0%
32.2%
29.7%
27.1%
26.2%
-20%
-15%
0%(1)
15%
20%
1,195
1,163
1,068
972
940
1.9
2.0
2.3
2.6
2.7
37.7%
35.4%
29.7%
25.3%
24.1%
OPEX Sensitivity
After-Tax Results
NPV 6% ($M)
Payback (yrs)
IRR(%)
CAPEX Sensitivity
After-Tax Results
NPV 6% ($M)
Payback (yrs)
IRR (%)
  1. Feasibility Study base case.

12

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

RESULTS FROM OPERATIONS

The following tables set forth financial information for the Company which has been summarized from and should be read in conjunction with the Company’s audited consolidated financial statements for the three and six months ended June 30, 2022, and 2021, including the notes thereto.

Three months ended June 30, Three months ended June 30, Six months ended June 30, Six months ended June 30,
Statements of Loss 2022 2021 2022 2021
Expenses
Property acquisition $ 8,795 $ - $ 18,856,376 $ -
Environmental assessment and 1,627,302
829,208

4,143,834

2,090,689
community consultation
Project feasibility and engineering 3,413,135
406,631

6,036,089

1,103,472
Exploration and site costs 999,167
1,520,808

1,548,088

2,270,785
Other 1,589
220,138

260,039

380,849
Acquisition, evaluation and exploration 6,049,988
2,976,786

30,844,426

5,845,795
expenditures
Share-based compensation 391,518
1,448,594

746,271

1,673,182
Audit, legal and advisory fees 206,556
39,388

1,017,425

69,863
Management and corporate 1,303,138
561,411

1,889,855

702,726
administration services
Shareholder and investor 222,921
341,630

441,761

599,997
communications costs
Occupancy cost 28,129
33,440

58,439

71,298
Interest(recovery)expense 14,329
7,998

21,390

16,276
Operatingloss (8,216,579) (5,409,247) (35,019,567) (8,979,137)
Realized and unrealized gain (loss) on (297,000)
(441,510)

(864,000)

888,765
marketable securities
Fair value gain on financial liability 838,238
-

838,238

-
Foreign exchange loss (791)
-

(791)

-
Interest income 66,839
2,500

76,080

6,080
Net Loss and Comprehensive Loss $(7,609,293)
$(5,848,257)

$(34,970,040)

$ (8,084,292)
Net Lossper Share – Basic and diluted $ (0.04) $ (0.04) $ (0.20) $(0.06)

Three Months Ended June 30, 2022, compared to 2021

The Company incurred a net loss of $7,609,293 or $0.04 per share for the three months ended June 30, 2022, compared to a net loss of $5,848,257 or $0.04 per share for the three months ended June 30, 2021. The significant differences are outlined below.

  • Acquisition, evaluation, and exploration expenses were $6,049,988 for the three months ended June 30, 2022, compared to $2,976,786 for the three months ended June 30, 2021.The increase of $3,073,202 is primarily related to the following:

  • an increase of $798,094 in costs associated with the Joint Review Panel, environmental assessment and community consultation which relate primarily to the costs of the Joint Review Panel. For the three months ended June 30, 2022, environmental assessment and community consultation expenditures included $584,638 related to costs associated with the Joint Review Panel.

  • an increase of $3,006,504 in project feasibility and engineering costs as the Company advances the design engineering of the plant, and

  • a decrease in exploration and site costs of $521,641 due to a reduced exploration program.

13

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

  • Share-based compensation was $391,518 for the three months ended June 30, 2022, compared to $1,448,594 for the three months ended June 30, 2021. Share-based compensation is a noncash item calculated using the Black Scholes valuation model and fluctuates period to period depending on the number of options vested.

  • Audit, legal and advisory fees were $206,556 for the three months ended June 30, 2022, compared to $39,388 for the three months ended June 30, 2021. The increase of $167,168 in 2022 is primarily related to an increase of legal fees and financing fees associated with the advancement of the Marathon Project.

  • Management and corporate administration services expenses were $1,303,138 in the three months ended June 30, 2022, compared to $561,411 for the three months ended June 30, 2021. The increase of approximately $741,727 is the result of an increase in administration activities, executive compensation and bonuses resulting for the growth of the development team.

  • Shareholder and investor communications costs were $222,921 in the three months ended June 30, 2022, compared to $341,630 in the three months ended June 30, 2021. The decrease of approximately $118,709 is primarily related to a decrease in marketing fees.

  • Occupancy costs were $28,129 in the three months ended June 30, 2022, compared to $33,440 in the three months ended June 30, 2021. The expenditures are consistent for the comparable quarters.

  • Interest expense was $14,329 in the three months ended June 30, 2022, compared to interest recovery of $7,998 in the three months ended June 30, 2021. Interest expense results from the recognition and depreciation of the company’s leases as a right-of-use asset.

  • Realized and unrealized gains and losses on marketable securities relate to the sale and/or period end fair value adjustments of marketable securities or marketable securities receivable during the period. Transactions during the quarter are outlined above under the section heading Marketable Securities.

  • Fair value gains on the financial liability relate to the fair value adjustments associated with the financial liability associated with the stream arrangement. See Project Financing – Phase 1 Stream Financing section of this MD&A for further detail.

  • Interest income results from interest earned on short term guaranteed investment certificates.

Six Months Ended June 30, 2022, compared to 2021

The Company incurred a net loss of $34,970,040 or $0.20 per share for the six months ended June 30, 2022, compared to a net loss of $8,084,292 or $0.06 per share for the six months ended June 30, 2021.The significant differences are outlined below.

  • Acquisition, evaluation, and exploration expenses were $30,844,426 for the six months ended June 30, 2022, compared to $5,845,795 for the six months ended June 30, 2021.The increase of $24,998,631 is primarily related to the following:

  • an increase of $18,856,376 associated with the acquisition of the remaining interest in the Marathon Project from Stillwater,

  • an increase of $2,053,145 in costs associated with the Joint Review Panel, environmental assessment and community consultation which relate primarily to the costs of the Joint Review Panel. For the six months ended June 30, 2022, environmental assessment and

14

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

community consultation expenditures included $1,433,957 paid to the federal government to reimburse it for costs associated with the Joint Review Panel.

  • an increase of $4,932,617 in project feasibility and engineering costs as the Company advances the design engineering of the plant, and

  • a decrease in exploration and site costs of $722,697 due to a reduced exploration program.

  • Share-based compensation was $746,271 for the six months ended June 30, 2022, compared to $1,673,182 for the six months ended June 30, 2021.Share-based compensation is a non-cash item calculated using the Black Scholes valuation model and fluctuates period to period depending on the number of options vested.

  • Audit, legal and advisory fees were $1,017,425 for the six months ended June 30, 2022, compared to $69,863 for the six months ended June 30, 2021. The increase of $947,562 in 2022 is primarily related to an increase of legal fees and financing fees. The increase in fees is directly attributable to the acquisition of the remaining interest in the Marathon Project from Stillwater and the Precious Metal Purchase Agreement with Wheaton Precious Metals Corp.

  • Management and corporate administration services expenses were $1,889,855 in the six months ended June 30, 2022, compared to $702,726 for the six months ended June 30, 2021.The increase of approximately $1,187,129 is the result of an increase in administration activities, executive compensation and bonuses resulting for the growth of the development team.

  • Shareholder and investor communications costs were $441,761 in the six months ended June 30, 2022, compared to $599,997 in the six months ended June 30, 2021.The decrease of approximately $158,236 is primarily related to a decrease in marketing fees.

  • Occupancy costs were $58,439 in the six months ended June 30, 2022, compared to $71,298 in the six months ended June 30, 2021.The expenditures are consistent for the comparable quarters.

  • Interest expense was $21,390 in the six months ended June 30, 2022, compared to interest recovery of $16,276 in the six months ended June 30, 2021.Interest expense results from the recognition and depreciation of the company’s leases as a right-of-use asset.

  • Realized and unrealized gains and losses on marketable securities relate to the sale and/or period end fair value adjustments of marketable securities or marketable securities receivable during the period. Transactions during the quarter are outlined above under the section heading Marketable Securities.

  • Fair value gains on the financial liability relate to the fair value adjustments associated with the financial liability associated with the stream arrangement. See Project Financing – Phase 1 Stream Financing section of this MD&A for further detail.

  • Interest income results from interest earned on short term guaranteed investment certificates.

15

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Acquisition, Evaluation and Exploration Expenditures

Below are the acquisition, evaluation and exploration expenditures for the three and six months ended June 30, 2022, compared with the equivalent period in 2021.

3 months ended June 30, 3 months ended June 30, 6 months ended June 30, 6 months ended June 30,
2022 2021 2022 2021
Davidson $6,520 $104,281
$135,266
$128,765
Marathon 6,043,468 2,872,505
30,709,160
5,717,030
Total mineral property expenditures
$ 6,049,988
$2,976,786
$ 30,844,426
$5,845,795

The following table displays the cumulative mineral property expenditures by project as at June 30, 2022.

Cumulative Evaluation Cumulative
December 31, Acquisition and June
30,
2021 exploration 2022
Darnley Bay $576,941 $ -
$ -

$576,941
Davidson 579,752 135,266
-

715,018
Marathon 29,718,094 18,949,720
11,759,440

60,427,254
Total expenditures in theyear $30,874,787 $19,084,986
$11,759,440

$61,719,213

Marketable Securities

As of June 30, 2022, the Company held 5,400,000 Major Precious Metals Shares (December 31, 2021 - 5,400,000) valued at $378,000 (December 31, 2021 - $1,242,000). The fair value was determined using the traded market value on June 30, 2022, and December 31, 2021. The fair value adjustments resulted in an unrealized loss of $297,000 for the three months ended June 30, 2022 (June 30, 2021 - unrealized loss $1,609,200) and an unrealized loss of $864,000 for six months ended June 30, 2022 (June 30, 2021 - unrealized loss of $404,425).

During the three months ended June 30, 2022, the Company sold nil shares (June 30, 2021 - 2,403,000) for total proceeds of nil (June 30, 2021 - $1,359,930), and a realized gain of nil (June 30, 2021 - $1,167,690). During the six months ended June 30, 2022, the Company sold nil shares (June 30, 2021 - 2,755,000) for total proceeds of nil (June 30, 2021 - $1,513,590), and a realized gain of nil (June 30, 2021 - $1,293,190).

SUMMARY OF QUARTERLY RESULTS

Three Months Ended Jun 30 2022 Mar 31 2022
Dec 31 2021
Sep 30 2021
June 30 2021
Mar 31 2021
Dec 31, 2020
Sep 30, 2020
Acquisition, evaluation and exploration $6,049,988
$24,794,438

$3,816,514
$2,914,161
$ 2,976,786
$2,869,009
$3,359,924
$2,648,228
General and administration 1,775,073
1,653,797

631,179
354,655
983,869
476,293
388,326
448,193
Share-basedpayments 391,518
354,753

227,734
372,942
1,448,594
224,588
155,276
139,986
Operating loss (8,216,579)
(26,802,988)

(4,675,427)
(3,641,758)
(5,409,249)
(3,569,888)
(3,903,526)
(3,272,407)
Realized and unrealized gain (loss) on (297,000)
(567,000)

(648,000)
(54,000)
(441,510)
1,330,275
547,075
(2,939,435)
marketable securities
Gain on debt write-off -
-

-
-
-
-
180,516
-
Fair value on financial liability 838,238
-

-
-
-
- -
Foreign exchange loss 791
-

-
-
-
-
-
-
Interest income 66,839
9,241

5,119
14,946
2,500
3,580
5,611
7,099
Net and comprehensive loss (7,609,293)
(27,360,747)

(5,318,308)
(3,680,812)
(5,848,259)
(2,236,033)
(3,170,324)
(6,204,743)
Basic and diluted(loss)earningsper share $(0.04)
$(0.16)

$(0.04)
$(0.02)
$(0.04)
$(0.02)
$(0.02)
$(0.05)
Weighted average number of common shares
179,917,408

171,462,569

150,281,914
150,025,839
143,035,426
139,038,358
131,367,147
130,527,507
outstanding

16

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

The Company’s operating losses are driven mainly by the extent and cost of the company’s acquisition, evaluation and exploration activities. The significant changes over the most recent eight completed quarters are outlined below.

  • Acquisition and evaluation expenditures have been steadily increasing over the last several quarters as the Company advances the Marathon Property on several initiatives from feasibility through permitting and detailed engineering. In the first quarter of 2022, an increase of $18,942,584 is associated with the acquisition of the remaining interest in the Marathon Project from Stillwater.

  • General and administrative expenses have remained consistent with comparable quarters other than the second quarter of 2021 when employee bonuses were incurred and the first quarter of 2022 when there was an increase in fees associated with the acquisition of the remaining interest in the Marathon Project from Stillwater and the Precious Metal Purchase Agreement with Wheaton Precious Metals Corp. Current quarter general and administrative expenses are a result of increased management team and administrative work streams to support the advancement of the Marathon Project.

  • Share-based payments is a non-cash item calculated using the Black Scholes valuation model and fluctuates period to period depending on the number of options granted and vesting.

  • Realized and unrealized gains and losses on marketable securities and receivable marketable securities relate to the sale and/or period end fair value adjustments of marketable securities or marketable securities receivable during the period. Transactions during the period are outlined above under the section headings Marketable Securities.

  • Gain on debt write-off is a non-recurring item.

FINANCIAL POSITION

Assets

As at June 30, 2022, the Company had total assets of $20,027,783 (December 31, 2021 - $8,173,106) which consisted of current assets of $18,828,775 (December 31, 2021 - $7,467,448) and non-current assets of $1,199,008 (December 31, 2021 - $705,658).

Current assets as at June 30, 2022, consist primarily of cash and cash equivalents of $17,569,640 (December 31, 2021 - $5,397,171), marketable securities of $378,000 (December 31, 2021 - $1,242,000) and accounts receivable of $768,068 (December 31, 2021 - $727,966). Cash is held in Canadian dollar denominated accounts and short term guaranteed investment certificates, marketable securities consist of 5,400,000 shares of Major Precious Metals at fair value and accounts receivable is mainly comprised of HST receivable.

Non-current assets as at June 30, 2022, consist of restricted cash and cash equivalents pursuant to guaranteed investment certificates held as security for the corporate office lease, land and building acquired pursuant to the acquisition of the Marathon Property and the corporate office and other right of use assets.

17

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Liabilities

As at June 30, 2022, the Company had total liabilities of $23,625,554 (December 31, 2021 - $2,499,598) which consisted of current liabilities of $4,239,026 (December 31, 2021 - $2,348,103) and long-term liabilities of $19,386,528 (December 31, 2021 - $151,495).

Current liabilities as at June 30, 2022, primarily consist of accounts payable and accrued liabilities of $4,182,144 (December 31, 2021 - $2,308,183) and short-term lease liability of $56,882 (December 31, 2021 - $39,920). The increase in accounts payable is due mainly to the increased expenditures relating to the advancement of the Marathon Property.

Long-term liabilities as at June 30, 2022, primarily consist of a $19,161,762 liability related to the Precious Metal Purchase Agreement with Wheaton Precious Metals Corp. As a result of applying IFRS 16, the Company recognized a right-of-use asset for its corporate office lease and other equipment. As at June 30, 2022, the balance of the current lease liability is $56,882 and the long-term lease liability is $224,766.

LIQUIDITY AND GOING CONCERN UNCERTAINITY

The Company relies on equity and potentially debt or other structured financings to fund its acquisition, evaluation and exploration activities, cover administrative expenses and to meet its obligations as they become due.

The Company is at an early stage of development and, as is common with many exploration companies, it relies on financings to fund its exploration and acquisition activities. The Company had a surplus of current assets over current liabilities of $14,589,749 at June 30, 2022; had not yet achieved profitable operations; had accumulated losses of $75,561,673 at June 30, 2022; and expects to incur further losses in the development of its business. Generation Mining does not have adequate cash resources to fund its operations over the next twelve months and will require additional financing in order to conduct its planned work programs on its mineral properties, meet its ongoing levels of corporate overhead and discharge its liabilities as they come due. There can be no certainty as to the ability of the Company to raise sufficient additional financing in order to continue to operate, and accordingly, there is a material uncertainty that may cast significant doubt about the Company’s ability to continue as a going concern.

The Company's main source of liquidity is its cash. These funds are primarily used to finance working capital, exploration and evaluation expenditures, capital expenditures, and acquisitions. The Company manages its liquidity risk by regularly monitoring its cash flows from operating activities and holding adequate amounts of cash. Cash is held on deposit in guaranteed investment certificates with a major Canadian chartered bank.

Cash used in operating activities during the six months ended June 30, 2022, was $12,158,564 compared with $6,530,848 in the same period of the prior period. The cash used in operations in both periods relate mainly to the acquisition, exploration and evaluation of the Marathon Property, and corresponding increases in audit, legal and advisory fees, investor communications expenses and general and administrative expenses.

Cash used in investing activities was $584,026 during the six months ended June 30, 2022, compared to cash provided by investing activities of $1,513,590 in the same period in 2021.Cash used in investing

18

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

activities in the current period consists of the acquisition of the remaining interest in the Marathon property and a right of use asset addition.

Cash generated from financing activities during the six months ended June 30, 2022, amounted to $24,915,059, compared to $5,480,227 in the prior period. Financing activities during both periods consisted of proceeds from the exercise of common share purchase warrants and the exercise of stock options (See Outstanding Security Data section below for further details). Financing activities also consisted of proceeds from the Precious Metals Purchase Agreement.

Subsequent to quarter end, the Company announced it had entered into an option agreement to purchase a construction camp as well as unused ball and SAG mills. See section Advancing Project Engineering and Early Procurements for additional information on these commitments.

CAPITAL RESOURCES

The Company does not have any debt or credit facilities with financial institutions.

At present, the Company’s operations do not generate cash in-flows and its financial success is dependent on management’s ability to discover economically viable mineral deposits. The mineral exploration process can take many years and is subject to factors that are beyond the Company’s control. To finance the Company’s exploration programs, detailed engineering, environmental assessment and to cover administrative and overhead expenses, the Company raises money through equity, debt and metal streaming financings. Many factors influence the Company’s ability to raise funds, including the health of the resource market, the climate for mineral exploration investment, the Company’s track record, and the experience and caliber of its management. Actual funding requirements may vary from those planned due to a number of factors, including the progress of exploration and development activities.

Management believes it will be able to raise capital as required in the long term but recognizes there will be risks involved that may be beyond their control. If the Company is unable to raise sufficient financing, it may need to scale back its intended operational programs and its other expenses. Other than as discussed herein, the Company is not aware of any trends, demands, commitments, events or uncertainties that may result in its liquidity either materially increasing or decreasing at present or in the foreseeable future, other than general market conditions, which are uncertain for junior exploration companies. Material increases or decreases in the Company’s liquidity will be substantially determined by the success or failure of its exploration and development programs, as well as its continued ability to raise capital.

MARATHON PROPERTY ACQUISITION

On July 10, 2019, the Company, through Generation PGM, completed the acquisition of a 51% initial interest in the Marathon Property and entered into a joint venture agreement with Stillwater Canada Inc. (“Stillwater”). The Company paid $3,000,000 in cash and issued 11,053,795 common shares of the Company at a deemed price of $0.2714 per common share (totaling $3,000,000), for total consideration of $6,000,000.

Pursuant to the joint venture agreement Generation Mining had the right to increase its interest in the Marathon Property to 80% by sole funding $10,000,000 in exploration, evaluation and development

19

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

expenditures and preparing a preliminary economic assessment (“PEA”) within four years (“Ownership Increase Right”). On February 19, 2020, the Company filed a PEA and in November 2020 incurred $10,000,000 in exploration and evaluation expenditures fulfilling the Ownership Increase Right. On November 27, 2020, the Company increased its ownership interest to hold an 80% interest in the Marathon Property. On December 14, 2020 Stillwater elected to forgo its proportionate share of joint venture funding and dilute pursuant to the provisions of the joint venture agreement (“Dilution Provisions”). On July 21, 2021, Stillwater elected to not exercise its ownership increase right to expand its ownership in the Marathon Property to 51%. Pursuant to the Dilution Provisions Generation Mining held an 83.5% and Stillwater a 16.5% interest in the joint venture as at September 30, 2021.

On December 8, 2021, Generation entered into a binding acquisition agreement (the “Acquisition Agreement”) with Stillwater, pursuant to which Generation would acquire Stillwater’s remaining 16.5% interest in the Marathon Project for total consideration of 21,759,332 common shares of Generation. On January 26, 2022, the Company completed the acquisition of Stillwater’s interest and currently owns a 100% interest in the Marathon Project. As a result of this transaction, Sibanye, a leading international precious metals mining company, with a diverse portfolio of operations in the United States and Southern Africa, now holds 32,813,127 common shares of the Company, representing approximately 18.2% of the Company’s issued and outstanding common shares as at May 12, 2022.

SUMMARY OF MINERAL RESERVES AND RESOURCES

Mineral Resources

The Mineral Resource Estimate below is for the combined Marathon, Geordie and Sally deposits. The Mineral Resource Estimates were prepared by P&E Mining Consultants Inc.

Pit Constrained Combined Mineral Resource Estimate[1-8 ] for the Marathon, Geordie and Sally Deposits (Effective date June 30, 2020)

Pit Constrained Combined Mineral Resource Estimate1-8for the Marathon, Geordie and Sally Deposits
(Effective date June 30, 2020)
Pit Constrained Combined Mineral Resource Estimate1-8for the Marathon, Geordie and Sally Deposits
(Effective date June 30, 2020)
Pit Constrained Combined Mineral Resource Estimate1-8for the Marathon, Geordie and Sally Deposits
(Effective date June 30, 2020)
Pit Constrained Combined Mineral Resource Estimate1-8for the Marathon, Geordie and Sally Deposits
(Effective date June 30, 2020)
Pit Constrained Combined Mineral Resource Estimate1-8for the Marathon, Geordie and Sally Deposits
(Effective date June 30, 2020)
Pit Constrained Combined Mineral Resource Estimate1-8for the Marathon, Geordie and Sally Deposits
(Effective date June 30, 2020)
Mineral
Tonnage
Pd
Cu
Au
Pt
Ag
Resource
Category
kt
g/t
koz
%
M lbs
g/t
koz
g/t
Koz
g/t
koz
Marathon Deposit
Measured
113,793
Indicated
89,012
M+I
202,806
Inferred
6,931
0.63
2,304
0.45
1,296
0.55
3,599
0.43
95
0.20
502
0.19
373
0.20
875
0.17
26
0.07
262
0.06
182
0.07
444
0.08
17
0.21
762
0.16
449
0.19
1,211
0.14
32
1.49
5,466
1.77
5,078
1.62
10,544
1.55
345
Geordie Deposit
Indicated
17,268
Inferred
12,899
0.56
312
0.51
212
0.35
133
0.28
80
0.05
25
0.03
14
0.04
20
0.03
12
2.4
1,351
2.4
982
Sally Deposit
Indicated
24,801
Inferred
14,019
0.35
278
0.28
124
0.17
93
0.19
57
0.07
56
0.05
24
0.2
160
0.15
70
0.7
567
0.6
280
Total Project
Measured
113,793
Indicated
131,081
M+I
244,874
Inferred
33,849
0.63
2,304
0.45
1,886
0.53
4,190
0.40
431
0.20
502
0.21
599
0.20
1,101
0.22
163
0.07
262
0.06
263
0.07
525
0.05
55
0.21
762
0.15
629
0.18
1,391
0.10
114
1.49
5,466
1.66
6,996
1.58
12,462
1.48
1,607

20

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Notes:

1. Mineral Resources were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, (2014) and Best Practices Guidelines (2019) prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council.

2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.

3. The Inferred Mineral Resource in this estimate has a lower level of confidence that that applied to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration.

4. Mineral Resources are reported within a constraining pit shell at a NSR cut-off value of $13/t.

5. NSR (C$/t) = (Ag x 0.48) + (Au x 42.14) + (Cu x 73.27) + (Pd x 50.50) + (Pt x 25.07) – 2.62.

6. The Mineral Resource Estimate was based on metal prices of US$3.00/lb copper, US$1,500/oz gold, US$18/oz silver, US$1,600/oz palladium, and US$900/oz platinum.

7. Mineral Resources are inclusive of Mineral Reserves.

8. Contained metal totals may differ due to rounding.

Mineral Reserves

The Mineral Reserve Estimate for the Marathon Project includes only the Marathon deposit. The Mineral Reserve Estimate was prepared by GMS.

Marathon Project Open Pit Mineral Marathon Project Open Pit Mineral Marathon Project Open Pit Mineral Reserve Estimates1-8 Estimates1-8 (Effective date September 15, 2020) (Effective date September 15, 2020) (Effective date September 15, 2020) (Effective date September 15, 2020)
Mineral Tonnage Pd Cu Au Pt Ag
Reserves
Category
Kt % g/t koz % M lbs g/t koz g/t koz g/t koz
Proven 85,091 72 0.660 1,805 0.202
379
0.070 191 0.212 581 1.359 3,719
Probable 32,610 28 0.512 537 0.213
153
0.061 64 0.168 176 1.541 1,616
P+P 117,701 100% 0.619 2,342 0.205
532
0.067 255 0.200 756 1.410 5,334

1. CIM definitions were followed for Mineral Reserves (see above Note 1).

2. Mineral Reserves are estimated at a cut-off grade varying from $18.00 to $21.33 NSR/t of ore.

3. Mineral Reserves are estimated using the following long-term metal prices (Pd = US$1,500/oz, Pt = US$900/oz, Cu = US$2.75/lb, Au = US$1,300/oz and Ag = US$16/oz) and an exchange rate of C$/US$ of 1.33).

4. A minimum mining width of 5 m was used.

5. Bulk density of ore is variable and averages 3.07 t/m3.

6. The average strip ratio is 2.8:1.

7. The average mining dilution factor is 9%.

8. Numbers may not add due to rounding.

OTHER MINERAL PROPERTIES

In addition to the Marathon Property, the Company holds options, rights and/or ownership interest in the following material mineral properties as of June 30, 2022:

Darnley Bay, Northwest Territories: The Company held the exclusive rights to a mineral concession covering the Inuvialuit Settlement Region’s lands where the Inuvialuit hold the mineral and surface rights and an exploration and development agreement with the Inuvialuit Regional Corporation (the “IRC”). The Company was in default under the various agreements with the IRC. In October 2021, the IRC agreed in principle that the exclusive rights to the mineral rights will be reinstated and an amended exploration agreement will be negotiated. Pursuant to the agreement in principle, the Company will pay $150,000 per year to the IRC upon finalization of the amended agreements.

21

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Davidson, British Columbia : The Company has an option to acquire a 100% interest in a property hosting a molybdenum-tungsten deposit. The option agreement was signed on April 1, 2016, and cumulative payments totalling $714,266 were made as at June 30, 2022, meeting all spending requirements. There is an ongoing commitment of $100,000 payable on each anniversary of the agreement until commercial production is achieved or the agreement is terminated. Upon commercial production, the vendor will be entitled to a net smelter return royalty of 3%.

RELATED PARTY TRANSACTIONS

Key management includes the Company’s directors, officers and any employees with authority and responsibility for planning, directing, and controlling the activities of an entity, directly or indirectly. Compensation awarded to key management includes the following:

3 months ended June 30, 3 months ended June 30, 6 months ended June 30, 6 months ended June 30,
2022 2021 2022 2021
Salaries and bonuses $ 1,643,108 $ 1,072,625 $1,947,483 $ 1,323,500
Share-basedpayments - options 206,970 1,273,454 279,327 1,467,181
Total compensation to key $ 1,850,078 $ 2,346,079 $2,226,810 $ 2,790,681
management

As at June 30, 2022, accounts payable includes $205,299 (June 30, 2021 - $488,640) due to key management of the Company.

OUTSTANDING SECURITY DATA

Common Shares

The following table summarizes the continuity of common shares for the six months ended June 30, 2022, and as at August 11, 2022:

Number of shares $
Balance as at December 31, 2020 136,315,292 28,372,920
Shares issued for exercise of warrants(1) 13,799,307 10,358,502
Shares issued for exercise of options 300,000 201,000
Balance as at December 31, 2021 150,414,599 38,932,422
Issued for property acquisition(2) 21,759,332 19,289,426
Shares issued for exercise of warrants(1) 7,743,477 8,078,059
Balance at June 30, 2022 179,917,408 66,299,907
Shares issued for exercise of options 250,000 130,000
Balance at August 11, 2022 180,167,408 66,429,907

22

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Warrants

The following table summarizes the continuity of warrants for the six months ended June 30, 2022, and as at August 11, 2022:

Number of warrants
Outstanding, December 31, 2020 22,068,284
Warrants issued(1) 639,711
Warrants exercised(1) (13,799,307)
Warrants expired(1) (38,437)
Outstanding, December 31, 2021 8,870,251
Warrants issued(1) (7,743,477)
Warrants exercised(1) (1,126,774)
Outstanding, June 30, 2022 and August 11, 2022 -

(1) The exercise and share issuance or expiry of warrants relate to financings completed on June 5, 2019, August 29, 2019, and February 13, 2020.

(2) On January 26, 2022, the Company completed the acquisition of the remaining interest in the Marathon Project from Stillwater whereby the Company issued 21,759,332 common shares of the Company to Stillwater at a price of $0.89 per common share, or total consideration $19,289,426. The Company now holds 100% of the Marathon Project, and the joint venture agreement dated July 10, 2019, between Stillwater and Generation PGM has been terminated in accordance with its terms.

Stock Options

On May 9, 2018, the Company adopted an incentive Stock Option Plan (the “Plan”). The Plan was amended in July 2020.Under the Plan, options are non-assignable and may be granted for a term not exceeding ten years. The total number of common shares that may be reserved for issuance may not exceed ten percent of outstanding common shares at the grant date and may not exceed five percent for any one person in any 12-month period. The exercise price of an option may not be lower than the market price of the common shares on the Toronto Stock Exchange. The options are non-transferable. Outstanding options may be adjusted by the Board in certain events, as to exercise price and number of common shares, to prevent dilution or enlargement.

The following table sets forth the continuity of outstanding stock options for the six months ended June 30, 2022 and as at August 11, 2022:

Number of options
Outstanding, December 31, 2020 11,225,000
Options granted 3,875,000
Options exercised (300,000)
Options forfeited (50,000)
Outstanding, December 31, 2021 14,750,000
Optionsgranted 2,075,000
Outstanding, June 30, 2022 16,825,000
Options granted 550,000
Options expired (350,000)
Options exercised (250,000)
Outstanding, August 11, 2022 16,775,000

23

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

The fair value of options granted under the Plan is measured on the date of grant using the Black-Scholes pricing model and expensed to net income (loss) using the following inputs and assumptions at the measurement date:

Date Number Exercise Market
Expected
Risk-free Expected Fair Vesting
of Options Price Price Volatility Interest Life Value of
($) ($) (%)(1) Rate (%) (years)/ Options
Dividend ($)
Yield %
08-Mar-21 500,000 1.00 0.95 132 0.92 2.5 - 3/0% 343,333 1/3rdvesting
12-May-21 1,550,000 1.06 1.02 129 0.53 3/0% 1,162,500 Immediate
12-May-21 575,000 1.06 1.02 129 0.53 1.5 - 2/0% 419,750 1/3rd vesting
21-Sept-21 1,250,000 0.80 0.67 108 0.55 3/0% 525,000 1/3rd vesting
18-Feb-22 900,000 0.85 0.85 97 1.57 3/0% 468,000 1/3rd vesting
12-Apr-22 975,000 0.99 0.99 92 2.39 3/0% 575,250 1/3rd vesting
21-Jun-22 200,000 0.80 0.61 86 3.34 3/0% 62,000 1/3rd vesting

(1) Based on the Company’s historical volatility.

As at June 30, 2022, stock options carry exercise prices and terms to maturity as follows:

Exercise price $ Options Options Exercisable Expiry date Remaining contractual
Outstanding life(years)
0.52 600,000 600,000 July 31, 2022 0.1
0.52 75,000 75,000 September 11, 2022 0.2
0.52 100,000 100,000 November 6, 2022 0.4
0.10 2,400,000 2,400,000 May 11, 2023 0.9
1.06 2,075,000 2,075,000 May 12, 2024 1.9
0.30 3,100,000 3,100,000 July 16, 2024 2.0
0.30 200,000 200,000 August 7, 2024 2.1
0.80 1,250,000 833,000 September 21, 2024 2.2
0.65 500,000 500,000 February 5, 2025 2.6
0.85 900,000 300,000 February 18, 2025 2.6
0.45 750,000 750,000 March 18, 2025 2.7
0.99 975,000 325,000 April 13, 2025 2.8
0.52 2,750,000 2,750,000 April 20, 2025 2.8
0.80 200,000 67,000 June 21, 2025 3.0
0.52 450,000 450,000 November 6, 2025 3.4
1.00 500,000 500,000 March 8,2026 3.7
0.57(1) 16,825,000 15,025,000 2.1(1)

(1) Weighted average

FINANCIAL RISK MANAGEMENT

The Company examines the various financial risks to which it is exposed and assesses the impact and likelihood of those risks. These risks include credit risk, liquidity risk, foreign currency risk, interest rate risk, other price risk and fair valuation risk, and are detailed in Note 4 of the Company’s audited consolidated financial statements for the year ended December 31, 2021.

Credit Risk

Credit risk is the financial risk of non-performance of a contracted counter party. The Company's credit risk is primarily attributable to cash and receivables. The Company reduces its credit risk by maintaining its cash with a Canadian chartered bank. The Company’s maximum exposure to credit risk as at June 30,

24

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

2022, is the carrying value of cash and receivables. The credit risk on receivables is deemed low as the majority is related to federal government refunds.

Liquidity Risk

Liquidity risk encompasses the risk that the Company cannot meet its financial obligations in full. The Company's main source of liquidity is its cash and marketable securities. These funds are primarily used to finance working capital, exploration and evaluation expenditures, capital expenditures, and acquisitions. The Company manages its liquidity risk by regularly monitoring its cash flows from operating activities and holding adequate amounts of cash. As at June 30, 2022, the Company has current assets of $18,828,775 (December 31, 2021 - $7,467,448) to cover current liabilities of $4,239,026 (December 31, 2021 - $2,348,103). The current assets include restricted cash, marketable securities, receivables and prepaid expenses. The Company also manages liquidity risk on the basis of expected maturity dates. The following table analyzes financial liabilities by remaining contractual maturity (contractual and undiscounted cash flows).

Undiscounted Undiscounted Accounts payable and Total
lease liability – lease liability – accrued liabilities
base contract operating costs
Less than 1 year $104,463 $25,581 $4,182,144
$4,312,188
1-5years 153,551 172,237 -
325,788
Balance at June 30, 2022
$258,014
$ 197, 818 $4,182,144
$4,637,976

Foreign Currency Risk

Foreign currency risk is the risk that the fair value of future cash flows of a financial instrument will fluctuate because of change in foreign exchange rates. The Company has no significant exposure to foreign currency exchange risk as it has no significant transaction balances denominated in a foreign currency.

Interest Rate Risk

Interest rate risk is the risk borne by an interest-bearing asset or liability as a result of fluctuations in interest rates.

Other Price Risk

Other price risk is the risk that the value of financial instruments will fluctuate as a result of changes in market prices, whether caused by factors specific to an individual investment, its issuer, or all factors affecting all instruments traded in a market or market segment. The Company is exposed to fluctuations in market prices of its marketable securities in a quoted mining exploration company. The fair value of these financial instruments represents the maximum exposure to price risk.

If the quoted price of these instruments had changed by 10% as at June 30, 2022, comprehensive income would have changed by approximately $37,800.

Fair Value

The carrying value of cash, accounts payable and accrued liabilities are considered to be representative of their fair value due to their short-term nature. Marketable securities are recorded at fair value as of

25

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

June 30, 2022 and classified as Level 1 in the fair value hierarchy as they are recorded at fair value by reference to market quoted prices.

Financial liability associated with the Company’s Precious Metal Purchase Agreement is recorded at fair value and classified as Level 3 in the fair value hierarchy as some of the inputs do not have an observable or corroborated market data. The fair value of the stream obligation is calculated using the risk-free interest rate derived from the Bank of Canada long term treasury rate, consensus metal prices, company specific credit spread based on various debt term sheets received and expected gold and platinum ounces to be delivered from the current life of mine plan for the Marathon Project.

FEASIBILITY STUDY – ADDITIONAL KEY RESULTS

On March 3, 2021, the Company announced the results of a Feasibility Study for the Marathon Palladium and Copper Project. On March 25, 2021, the Company filed the NI 43-101 titled Feasibility Study Marathon Palladium & Copper Project Ontario, Canada on SEDAR. All dollar amounts are in Canadian dollars, stated on a 100% project ownership basis, unlevered other than equipment leasing and based on the base case analysis unless otherwise noted (See notes below).

The Feasibility Study was prepared by G Mining Services Inc. (“GMS”), along with contributions from Ausenco Engineering Canada Inc. (“Ausenco”), Haggarty Technical Services (“HTS”), Knight Piésold Ltd. (“KP”), WESC Inc. and P&E Mining Consultants Inc. (“P&E”).

Key results and assumptions used in the Feasibility Study are summarized below.

Production Data(1) Values Units
Life of Mine – Pre-Production 2 Years
Life of Mine – Operations 12.6 Years
Total Milled Tonnes - Pre-Production 1.9 Mt
Total Milled Tonnes – Operations 115.8 Mt
Total Mined Tonnes - Pre-Production 25.4 Mt
Total Mined Tonnes – Operations 421.8 Mt
Strip Ratio – Pre-Production 3.33 Waste:ore
Strip Ration – Operations 2.77 Waste:ore
Recovered Metal(3)– Palladium 2,028 k oz
Recovered Metal – Copper 493 M lbs
Recovered Metal – Platinum 634 k oz
Recovered Metal – Gold 183 k oz
Recovered Metal – Silver 3,796 k oz
Payable Metal(3)– Palladium 1,905 k oz
Payable Metal – Copper 467 M lbs
Payable Metal – Platinum 537 k oz
Payable Metal – Gold 151 k oz
Payable Metal – Silver 2,823 k oz
Recovery – Palladium 86.9 %
Recovery – Copper 93.0 %
Recovery – Platinum 84.2 %
Recovery – Gold 72.4 %
Recovery – Silver 71.5 %
Capital Costs(1) Values Units
Initial Capital(4) 665 $M
LOM Sustaining Capital 423 $M
LOM Total Capital 1,087 $M
Closure Costs 66 $M

26

==> picture [192 x 16] intentionally omitted <==

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

LOM Operating Coats(1) Values Units
Mining – Mined 2.53 $/t mined
Mining – Milled 9.23 $/t milled
Processing 9.08 $/t milled
General & Administration 2.48 $/t milled
Transport & Refining Charges 2.80 $/t milled
Royalties 0.03 $/t milled
Total Operating Costs 23.63 $/t milled
LOM Average Operating Cost 687 US$/oz PdEq
LOM Average AISC 809 US$/oz PdEq
Financial Assumptions(1) Values Units
Palladium 1,725 US$/oz
Copper 3.20 US$/lb
Platinum 1,000 US$/oz
Gold 1,400 US$/oz
Silver 20.00 US$/oz
Exchange Rate 1.28 C$/US$
Diesel Fuel 0.77 $/L
Electricity 0.08 $/kWhr
Financial Analysis(1) Values Units
Pre-tax Undiscounted Cash Flow 3,004 $M
Pre-tax NPV6% 1,636 $M
Pre-tax IRR 38.6 %
Pre-tax Payback 1.9 Years
After-tax Undiscounted Cash Flow 2,060 $M
After-tax NPV6% 1,068 $M
After-tax IRR 29.7 %
After-tax Payback 2.3 Years
Capital Costs(1) Initial Sustaining Total
($ M) ($ M) ($ M)
Mining 127.8 184.1 311.9
Process Plant 269.2 38.5 307.7
Infrastructure 107.7 29.3 137.0
Tailings Storage and Water Management 61.2 170.8 232.0
Construction Indirect 113.5 - 113.5
General and Owner's Cost 14.9 - 14.9
Preproduction,Startup,Commissioning (5) (52.9) - (52.9)
Subtotal (before equipment financing) 641.4 422.7 1,064.1
Contingency 74.8 - 74.8
Subtotal (including contingency) 716.2 422.7 1,138.9
Less: Equipment Financing Drawdowns (72.4) - (72.4)
Add: Equipment Lease Payment & Fees 21.0 - 21.0
Total Initial Capital (after equipment financing) 664.8 422.7 1087.5
Closure & Reclamation 65.9 65.9
Total Capital Costs 664.8 488.6 1,153

27

==> picture [192 x 16] intentionally omitted <==

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

Operating Costs(1) $ M $/tonne milled US$/oz PdEq(2)
Mining 1,069 9.23 268
Processing 1,051 9.08 264
General & Administration and Others 287 2.48 72
Concentrate Transport Costs 146 1.26 37
Treatment & Refining Charges 178 1.54 45
Royalties 4 0.03 1
LOM Operating Costs 2,736 23.61 687
Closure & Reclamation 66 0.57 17
SustainingCapital 423 3.65 106
LOM AISC 3,224 27.78 809

Notes:

1. See "Feasibility Study Marathon Palladium & Copper Project Ontario, Canada" filed on SEDAR and the Company's website. Also see NonIFRS measures as set out in the section Non-IFRS Measures of this MD&A

2. PdEq grade is calculated based on: (Pd US$1,725/31.10348 x Pd grade g/t) + (Cu US$3.20/2204.6 x Cu grade %/100) + (Au US$1,400/31.10348 x Au grade g/t) +(Pt US$1,000/31.10348 x Pt grade g/t) + (Ag US$20/31.10348 x Ag grade g/t ).

3. Recovered metal and payable metal is presented life of mine including pre-production.

4. Initial Capital shown after equipment financing and pre-production operating costs and production revenues.

5. Including pre-production operating costs and revenues.

OFF-BALANCE SHEET ARRANGEMENTS

As at June 30, 2022, the Company did not have any off-balance sheet items.

DIVIDENDS

The Company has neither declared nor paid any dividends on its common shares. The Company intends to retain its earnings, if any, to finance growth and expand its operation and therefore does not anticipate paying any dividends on its common shares in the foreseeable future.

CRITICAL ACCOUNTING ESTIMATES AND JUDGEMENTS

The preparation of the financial statements requires management to make judgments, estimates and assumptions that affect the application of accounting policies and the reported amounts of assets, liabilities and contingent liabilities at the date of the financial statements and reporting amounts of revenues and expenses during the reporting period. Estimates and assumptions are continually evaluated and are based on management’s experience and other factors, including expectations of future events that are believed to be reasonable under the circumstances. However, actual outcomes may differ materially from these estimates.

The estimates and underlying assumptions are reviewed on an ongoing basis. Revisions to accounting estimates are generally recognized in the period in which the estimates are revised.

Our significant judgments, estimates and assumptions are disclosed in note 2 of the audited consolidated financial statements for the year ended December 31, 2021.

ACCOUNTING POLICIES AND BASIS OF PRESENTATION

The Company’s accounting policies are disclosed in note 3 of the Company’s audited consolidated financial statements for the year ended December 31, 2021.

28

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

NON-IFRS MEASURES

The Company has included certain terms or performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards (“IFRS”) in this MD&A. These include operating costs, AISC, LOM average AISC, LOM average operating cost, and Free Cash Flow. NonIFRS measures do not have any standardized meaning prescribed under IFRS, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS. These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.

  • Operating Costs include mining, processing, general and administrative and other, concentrate transportation costs, treatment and refining charges, and royalties.

  • AISC include Operating Costs, closure, and reclamation, and sustaining capital.

  • LOM Average AISC includes LOM AISC divided by LOM PdEq.

  • LOM Average Operating Cost includes LOM Operating Costs divided by LOM PdEq.

  • Free Cash Flow includes total revenue less Operating Costs, working capital adjustments, equipment financing, initial capital, sustaining capital and closure costs.

RECENT ACCOUNTING PRONOUNCEMENTS

Future Accounting Changes

Certain new standards, interpretations, amendments and improvements to existing standards were issued by the IASB or IFRS Interpretation Committee that are not yet effective for the relevant reporting periods. Updates that are not applicable or are not consequential to the Company have been excluded there from. The Company is in the process of evaluating the impact on its financial statements.

New Accounting Pronouncement

Classification of Liabilities as Current or Non-current (Amendments to IAS 1)

In January 2020, the IASB issued amendments to IAS 1, "Presentation of Financial Statements" to clarify that the classification of liabilities as current or non-current should be based on rights that are in existence at the end of the reporting period and is unaffected by expectations about whether or not an entity will exercise their right to defer settlement of a liability. The amendments further clarify requirements for classifying liabilities an entity will or may settle by issuing its own equity instruments. These amendments are effective for annual reporting periods beginning on or after January 1, 2023, with earlier application permitted. The adoption of these amendments is not expected to have a significant impact on the consolidated financial statements.

INTERNAL CONTROL OVER FINANCIAL REPORTING

The President and Chief Executive Officer and Chief Financial Officer of the Company are responsible for designing internal controls over financial reporting or causing them to be designed under their supervision in order to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with IFRS. The Company’s internal

29

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

control framework was designed based on the Internal Control - Integrated Framework (2013) issued by the Committee of Sponsoring Organizations of the Treadway Commission.

There was no change in the Company’s internal controls over financial reporting that occurred during the six months ended June 30, 2022, that has materially affected, or is reasonably likely to materially affect, the Company’s internal controls over financial reporting.

DISCLOSURE CONTROLS AND PROCEDURES

Disclosure controls and procedures have been designed to provide reasonable assurance that all relevant information required to be disclosed by the Company is accumulated and communicated to senior management as appropriate to allow timely decisions regarding required disclosure. The Company’s President and Chief Executive Officer and Chief Financial Officer have concluded, based on their evaluation of the design of the disclosure controls and procedures, that as of June 30, 2022, the Company’s disclosure controls and procedures have been designed to provide reasonable assurance that material information is made known to them by others within the Company.

LIMITATIONS OF CONTROLS AND PROCEDURES

The Company’s management, including the Chief Executive Officer and President and Chief Financial Officer, believe that any internal controls over financial reporting and disclosure controls and procedures, no matter how well designed, can have inherent limitations. Therefore, even those systems determined to be effective can provide only reasonable assurance that the objectives of the control system are met.

RISKS AND UNCERTAINTIES

The operations of the Company are speculative due to the high-risk nature of its business, which is the acquisition, financing, exploration and development of mining properties. The risk of financial resources has been further amplified by the recent COVID-19 pandemic which has a significant impact on global economies and financial markets resulting in supply chain delays and inflationary pressures. Should depressed market condition continue in the medium to long term, it may be more difficult for the Company to obtain the required financing to complete its long-term objectives. Failure to obtain financing could result in delay or postponement of further development of the Company’s properties. These risk factors could materially affect the Company’s future operating results and could cause actual events to differ materially from those described in forward–looking information relating to the Company. Accordingly, any investment in securities of the Company is speculative and investors should not invest in securities of the Company unless they can afford to lose their entire investment.

The Company assesses and attempts to minimize the effects of these risks through careful management and planning of its operations and hiring qualified personnel but is subject to a number of limitations in managing risk resulting from its early stage of development. Readers are encouraged to read and consider the risk factors and related uncertainties in the Company’s Annual Information Form and Annual Management Discussion and Analysis for the year ended December 31, 2021.

30

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION

This MD&A contains certain forward-looking information and forward-looking statements, as defined in applicable securities laws (collectively referred to herein as “forward-looking statements”). Forwardlooking statements reflect current expectations or beliefs regarding future events or the Company’s future performance. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as “plans”,

“expects”, “is expected”, “budget”, “scheduled”, “estimates”, “continues”, “forecasts”, “projects”, “predicts”, “intends”, “anticipates”, “targets” or “believes”, or variations of, or the negatives of, such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will” be taken, occur or be achieved, including statements relating to the Company’s Feasibility Study and results therefrom (including NPV, IRR, capital and operating costs and other financial metrics), Mineral Resource and Mineral Reserve potential, exploration and development plans, or the timing of milestones, including public hearings, government approvals and receipt of permits, for advancing construction of the Marathon Project. All forward-looking statements, including those herein are qualified by this cautionary statement.

Although the Company believes that the expectations expressed in such statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the statements. There are certain factors that could cause actual results to differ materially from those in the forward-looking information. These include commodity price volatility, continued availability of capital and financing within the timing required by the Company and on terms acceptable to the Company, uncertainties involved in interpreting geological data, increases in costs, environmental compliance and changes in environmental legislation and regulation, the Company’s relationships with First Nations communities, exploration successes, and general economic, market or business conditions, as well as those risk factors set out in the Company’s AIF for the year ended December 31, 2021, the Technical Report dated March 23, 2021 and in the continuous disclosure documents filed by the Company on SEDAR at www.sedar.com. Readers are cautioned that the risk factors and related uncertainties in the Company’s Annual Information Form and Annual Management Discussion and Analysis for the year ended December 31, 2021, is not exhaustive of the factors that may affect forward-looking statements. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements in this MD&A speak only as of the date of this MD&A or as of the date or dates specified in such statements.

Forward-looking statements are based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions relating to: the availability of financing for the Company’s operations; operating and capital costs; results of operations; the mine development and production schedule and related costs; the supply and demand for, and the level and volatility of commodity prices; timing of the receipt of regulatory and governmental approvals for development projects and other operations; the accuracy of Mineral Reserve and Mineral Resource Estimates, production estimates and capital and operating cost estimates; and general business and economic conditions.

Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking information. For more information on the Company, investors are encouraged to review the Company’s public filings

31

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

on SEDAR at www.sedar.com. The Company disclaims any intention or obligation to update or revise any forward- looking information, whether as a result of new information, future events or otherwise, other than as required by law.

INFORMATION CONCERNING ESTIMATES OF MINERAL RESERVES AND RESOURCES

The Mineral Reserve and Mineral Resource estimates in this MD&A have been disclosed in accordance with NI 43-101, which differs significantly from the requirements of the U.S. Securities and Exchange Commission (the “SEC”), and information with respect to mineralization and Mineral Reserves and Mineral Resources contained herein may not be comparable to similar information disclosed by U.S. companies. The requirements of NI 43-101 for identification of ‘‘reserves’’ are not the same as those of the SEC, and reserves reported by the Company in compliance with NI 43-101 may not qualify as ‘‘reserves’’ under SEC standards. Under U.S. standards, mineralization may not be classified as a ‘‘reserve’’ unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. In addition, and without limiting the generality of the foregoing, this MD&A uses the terms ‘‘Measured Resources’’, ‘‘Indicated Resources’’ and ‘‘Inferred Resources’’. U.S. investors are advised that, while such terms are recognized and required by Canadian securities laws, the SEC has not recognized them in the past. U.S. investors are cautioned not to assume that any part of a ‘‘Measured Resource’’ or ‘‘Indicated Resource’’ will ever be converted into a ‘‘reserve’’. U.S. investors should also understand that ‘‘Inferred Resources’’ have a great amount of uncertainty as to their existence and as to their economic and legal feasibility. It cannot be assumed that all or any part of ‘‘Inferred Resources’’ exist, are economically or legally mineable or will ever be upgraded to a higher category. Under Canadian securities laws, ‘‘Inferred Resources’’ may not form the basis of feasibility or pre-feasibility studies except in certain cases. Disclosure of ‘‘contained ounces’’ in a Mineral Resource is a permitted disclosure under Canadian securities laws, however, the SEC normally only permits issuers to report mineralization that does not constitute ‘‘reserves’’ by SEC standards as in place tonnage and grade, without reference to unit measures. Accordingly, information concerning mineral deposits set forth in this MD&A may not be comparable with information made public by companies that report in accordance with U.S. standards.

The SEC has adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements under the U.S. Securities Exchange Act of 1934, as amended (the “Exchange Act”). These amendments became effective February 25, 2019 (the “SEC Modernization Rules”) with compliance required for the first fiscal year beginning on or after January 1, 2021. Under the SEC Modernization Rules, the historical property disclosure requirements for mining registrants included in Industry Guide 7 under the U.S. Securities Act of 1933, as amended, will be rescinded and replaced with disclosure requirements in subpart 1300 of SEC Regulation S-K. As a result of the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of “Measured Mineral Resources”, “Indicated Mineral Resources” and “Inferred Mineral Resources.” In addition, the SEC has amended its definitions of “Proven Mineral Reserves” and “Probable Mineral Reserves” to be “substantially similar” to the corresponding standards under NI 43101. While the SEC will now recognize “Measured Mineral Resources”, “Indicated Mineral Resources” and “Inferred Mineral Resources”, U.S. investors should not assume that any part or all of the mineralization in these categories will ever be converted into a higher category of Mineral Resources or into Mineral

32

Management’s Discussion and Analysis For the three and six months ended June 30, 2022

==> picture [192 x 16] intentionally omitted <==

Reserves. Mineralization described using these terms has a greater amount of uncertainty as to its existence and feasibility than mineralization that has been characterized as reserves. Accordingly, U.S. investors are cautioned not to assume that any Measured Mineral Resources, Indicated Mineral Resources, or Inferred Mineral Resources that the Company reports are or will be economically or legally mineable. Further, “Inferred Mineral Resources” have a greater amount of uncertainty as to their existence and as to whether they can be mined legally or economically. Therefore, U.S. investors are also cautioned not to assume that all or any part of the “Inferred Mineral Resources” exist. There is no assurance that any Mineral Reserves or Mineral Resources that the Company may report as “Proven Mineral Reserves”, “Probable Mineral Reserves”, “Measured Mineral Resources”, “Indicated Mineral Resources” and “Inferred Mineral Resources” under NI 43-101 would be the same had the Company prepared the reserve or resource estimates under the standards adopted under the SEC Modernization Rules.

Mineral Resources are not Mineral Reserves, and do not have demonstrated economic viability, but do have reasonable prospects for economic extraction. Measured and Indicated Mineral Resources are sufficiently well defined to allow geological and grade continuity to be reasonably assumed and permit the application of technical and economic parameters in assessing the economic viability of the Mineral Resource. Inferred Mineral Resources are estimated on limited information not sufficient to verify geological and grade continuity or to allow technical and economic parameters to be applied. Inferred Mineral Resources are too speculative geologically to have economic considerations applied to them to enable them to be categorized as Mineral Reserves. There is no certainty that Mineral Resources of any classification can be upgraded to Mineral Reserves through continued exploration.

The Company’s Mineral Reserve and Mineral Resource figures are estimates and the Company can provide no assurances that the indicated levels of mineral will be produced or that the Company will receive the price assumed in determining its Mineral Reserves. Such estimates are expressions of judgment based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. While the Company believes that these Mineral Reserve and Mineral Resource Estimates are well established and the best estimates of the Company’s management, by their nature Mineral Reserve and Mineral Resource Estimates are imprecise and depend, to a certain extent, upon analysis of drilling results and statistical inferences which may ultimately prove unreliable. If the Company’s Mineral Reserve or Mineral Reserve Estimates are inaccurate or are reduced in the future, this could have an adverse impact on the Company’s future cash flows, earnings, results or operations and financial condition.

The Company estimates the future mine life of the Marathon Project. The Company can give no assurance that its mine life estimate will be achieved. Failure to achieve this estimate could have an adverse impact on the Company’s future cash flows, earnings, results of operations and financial condition.