ASX ANNOUNCEMENT 22[nd] October 2013
==> picture [170 x 52] intentionally omitted <==
ASX RELEASE
Tellus Resources Ltd is an Australian-based oil, gas and mineral exploration company. Tellus holds a 100% interest in PEL 105 in the Cooper Basin as well as ATP 904 in the Surat Basin (subject to Ministerial approval). Tellus also holds the Chillagoe Gold Project which includes Exploration Permits covering a combined area of ~28,878 hectares plus Mining Leases covering a combined area of approx. 480 hectares, including the Wandoo & Empire prospects. In addition Tellus has a large tenement package in regional New South Wales prospective for Intrusive Related Gold Deposits (IRG).
Pirie 1 Weekly Drilling Report
Tellus Resources Limited (TLU or the Company) provides its weekly update on the progress of Pirie 1 below.
Upon reaching a depth of 2351m, some 41m into the Hutton formation, there were concerns that the vertical hole deviation had become much higher than had been recorded – this was confirmed by an alternative method which gave an indication of a deviation of more than 8 degrees. Following this, a decision to pull the string was made but the drill string became stuck with a bit depth of 2,218 m - some 130m off bottom.
All subsequent attempts to free the string including wash treatments have not succeeded and it was decided to attempt to sever the pipe above the stuck point. Several attempts have been made to date with tool equipment failure hampering progress. It is expected that the problems will be resolved today and the tool string above the stuck point retrieved.
There were good hydrocarbon shows in the basal Adori and Birkhead formations and a decision to possibly sidetrack will be made in close consultation with the Company’s Joint Venture partner.
Directors/Officers:
Anthony Wehby Carl Dorsch Richard Willson Ben Salmon Anne Adaley George Yatzis
As a consequence of the problems encountered to date, the well is now approximately 8 days behind schedule.
The weekly summary is tabled below as well as the Time/Depth curve.
Issued Shares:
132,614,942 shares Tellus Resources Ltd Level 5, 70 Pirie Street (GPO Box 93) ADELAIDE SA 5001 T: +61 8 8100 9208 F: +61 8 8223 3235
ASX Code : TLU
TELLUS RESOURCES LTD - ASX Announcement
1
ASX ANNOUNCEMENT 22[nd] October 2013
==> picture [170 x 52] intentionally omitted <==
| ITEM | ITEM | DETAIL | DETAIL | DETAIL | DETAIL | DETAIL | ||
|---|---|---|---|---|---|---|---|---|
| Well name | Pirie -1 | |||||||
| Permit | PEL 105 | |||||||
| Tellus Resources Ltd – 50% (Operator)Senex EnergyLtd(SXY)– 50% | ||||||||
| Participants | Tellus Resources Ltd – 50% (Operator)Senex EnergyLtd(SXY)– 50% | |||||||
| Senex EnergyLtd(SXY)– 50% | ||||||||
| Primary targets | Hutton/BirkheadPatchawarra/Tirrawarra | |||||||
| Spud date | 30 September 2013 | |||||||
| Target depth (prognosed) | 3100m | |||||||
| Total depth @ end of current week | 2351m | |||||||
| Total depth @ end of previous week | 1922m | |||||||
| Metres drilled during week | 429m | |||||||
| Activities during week | Drill ahead in 6 | ¾” production hole | ||||||
| Intersect Birkh | ead and Hutton targets | |||||||
| POOH at 2351Work stuck pip | m to log deviation - stuck at 2218me for 3 days | |||||||
| Attempt to sevTwo more atte | er pipe at 2197m – unsuccessfulmts – one misfire + CCLroblem | |||||||
| p p | ||||||||
| Current activities | Change out CC | L, repair e line | ||||||
| Planned activities | Sever drill string at 2120mPull fish string and run clean outLog hole with directional packagePlug back with cement and sidetrackRe drill 6 ¾” hole | |||||||
| Other comments | Participant interests are subject to Ministerialapproval |
For further information on this announcement or Tellus Resources please contact:
Carl Dorsch Michael Boyle Managing Director Client Advisor – Peloton T : 0400 508 088 T : 0418 769 963 E : [email protected] [email protected]
TELLUS RESOURCES LTD - ASX Announcement
2
==> picture [424 x 529] intentionally omitted <==
----- Start of picture text ----- Pirie- 1 Planned TVD Curve0Actual Pirie # 1Planned Days500 Drill 9 7/8" HoleRun 7-5/8" SC1000NU BOPsDrill 6 3/4"Hole15002000 Wiper TripProposed DSTStuck pipe2500Drill 6 3/4"Hole30000 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30Depth (mRT)----- End of picture text -----
Days from Spud