7 August 2023

Priority Targets Identified and Additional Ground Staked at Ross and Cancet West Lithium Projects

ASX: FIN

Highlights

  • Prospectivity analysis completed by Mercartor Geological Services has generated 9 target areas across the Ross Lithium Project and 7 target areas across the Cancet West Lithium Project.

  • The most prospective target areas within the two Projects have been named the ‘R01’ target area on the Ross project and the ‘WC01’ target area on the Cancet West project area.

  • The ‘ R01’ target area at Ross, is associated with multiple granitic intrusions that occur in the vicinity of amphibolite, a mapped tourmaline occurrence and low-level geochemical anomalies associated with interpreted LCT pegmatites.

  • The ‘ WC01’ target area at Cancet West, is associated with elevated lithium and caesium geochemistry in stream sediment samples and occurs within a mapped amphibolite unit proximal to a monzonite intrusion.

Corporate Directory

Technical Director Brian Talbot

Non-Executive Director Jason Bontempo

Director and Company Secretary Aaron Bertolatti

  • Due to the exceptional results achieved from this prospectivity analysis, FIN have now staked an additional 28 claims covering an area of open ground immediately west of Cancet West and staked an additional 16 claims covering an area of open ground northeast of Ross. Both areas appear to be highly prospective for LCT pegmatites as highlighted by the Prospectivity analysis.

  • Planning is now under way for the upcoming field programme which will include field mapping, outcrop sampling and geochemical sampling over the most prospective target areas and is expected to commence in Q3 2023.

LCT PEGMATITE TARGETS REFINED AT ROSS AND CANCET WEST LITHIUM PROJECTS

Fin Resources (‘Fin’) retained Mercator Geological Services Limited (‘Mercator’) to complete a target generation exercise using their proprietary prospectivity analysis method on the Ross and Cancet West Lithium Projects within the James Bay area, Quebec, Canada.

The Cancet West Project (52km[2] ) sits approximately 45 kms west of Winsome Resources (WR1:ASX) Cancet lithium deposit (Cancet) and 100 kms west of Patriot Battery Metal’s (PMT.ASX) Corvette Lithium Deposit (Corvette). The Cancet West Project Cancet deposit and Corvette deposit all occur within the La Grande sub province and within 25 km’s of the boundary with the Opinaca sub province.

The closest lithium deposits to the Ross Project (98km[2] ), are the Critical Elements Lithium Corporation’s (TSXV: CRE) Graab prospect and Nemaska’s Lithium’s Whabouchi Mine that occur 65km’s and 100 km’s to the southwest, respectively. Both the Graab and Whabouchi deposits occur in the La Grande sub province, within 15 km’s north of the boundary with the Opatica sub province. The Ross Project also occurs within the La Grande sub province, approximately 20 km’s north of the boundary with the Opatica sub province.

Registered Office 35 Richardson Street West Perth WA 6005

[email protected] www.finresources.com.au

ABN: 25 009 121 644

==> picture [65 x 52] intentionally omitted <==

==> picture [437 x 230] intentionally omitted <==

Figure 1 Location of Ross and Cancet West Lithium Project’s in Quebec, Canada

The primary purpose of the Prospectivity analysis was to further identify and delineate priority lithium targets within Ross and Cancet West prior to the commencement of the planned field programme. The prospectivity model used was designed on the LCT (lithium-cesium-tantalum) pegmatite deposit model of Černy & Ercit (2005)[1] , and review of the known lithium deposits within the area of interest. The final version of the prospectivity map consisted of 87 input layers of data that were used to calculate the prospectivity weightings for each Project. The model was designed to highlight the best targets where favourable structure, lithology, mineralization, and LCT pegmatites geochemistry occur.

The prospectivity analysis has generated nine target areas across the Ross Lithium Project and seven target areas across the West Cancet Lithium Project. Within these broader target areas a number of specific LCT pegmatite targets have been defined.

Fin have now staked an additional 28 claims covering an area of open ground immediately west of Cancet West and staked an additional 16 claims covering an area of open ground northeast of Ross. Both areas appear to be highly prospective for LCT pegmatites as highlighted by the Prospectivity Analysis.

ROSS LITHIUM PROJECT

The nine target areas generated at Ross (‘R01’ through ‘R09’) have a general east-northeast orientation that coincides with the local geology (i.e., strike of regional faults and orientation of amphibolite/basalts).

Within the broader target areas. 21 specific targets have been defined by the ‘structure’ sub-scores and to a lesser extent the three ‘geochemical’ sub-scores (LCT, primary pathfinders and secondary pathfinders). The target areas, specific targets and prospectivity score across the Ross Project are shown in Figure 2.

The ‘R1’ target area is associated with two pegmatitic granite units associated with tourmaline occurrences and ‘R3’ includes multiple mapped pegmatite occurrences. The ‘R4’, ‘R5’, ‘R6’ and ‘R8’ target areas all follow mapped amphibolite units within the Ross Project. Significantly, the ‘R4’ target area also includes a mapped tourmaline occurrence. The ‘R7’ target area covers a cluster of pegmatite outcrop occurrences that have additionally been mapped by Ministry of Natural Resources and Forestry Quebec.

1 Černý, Petr & Ercit, T. Scott. (2005). The classification of granitic pegmatites revisited. The Canadian Mineralogist. 43. 2005-2026. 10.2113/gscanmin.43.6.2005.

==> picture [65 x 52] intentionally omitted <==

The highest priority target areas identified at Ross by the prospectivity mapping and previous work reported by Fin[2] will be targeted during the upcoming field work programme.

==> picture [453 x 296] intentionally omitted <==

Figure 2: Prospectivity grid for the Ross Project with identified Lithium target areas

CANCET WEST LITHUM PROJECT

The seven target areas generated at Cancet West (‘WC01’ through ‘WC07’) have a general east-northeast orientation that again coincides with the local geology (i.e., strike of regional faults and orientation of amphibolite/basalts).

The nine specific targets that occur within the broader target areas are defined by the ‘structure’ sub-scores and to a lesser extent the three ‘geochemical’ sub-scores (LCT, primary pathfinders and secondary pathfinders). The target areas, specific targets and prospectivity score across the Cancet West Project are shown in Figure 3.

The ‘WC01’ target area in the western block of Cancet West is associated with elevated lithium and cesium geochemistry in stream sediment samples and occurs within a mapped amphibolite unit proximal to a monzonite intrusion. Further to the west of WC01 in an area covered by the newly pegged claim there is an area outlined by the Ministry of Natural Resources and Forestry Quebec as being highly favourable for porphyry cu-au+/-mo. Both of these target areas identified during the prospectivity mapping and previous work report by Fin[3] will be targeted during the upcoming field work programme.

2 See Fin Resources (ASX:FIN) ASX Release May 29th 2023

3 See Fin Resource (ASX:FIN) ASX announcement released 18th May 2023

==> picture [65 x 52] intentionally omitted <==

==> picture [481 x 263] intentionally omitted <==

Figure 3: Prospectivity grid for the Cancet West Project with identified Lithium target areas

Upcoming Works Programmes across the Mt Tremblant Lithium Projects

Near-term works programme for the three project areas will include;

  • Continued In-depth review of historical datasets and mapped outcrops across the Projects.

  • Remote sensing and geophysics as required, with interpretation in conjunction with the historic datasets and satellite imagery to highlight areas for ground-proofing and sampling during the upcoming summer season.

  • Preparations and planning for the upcoming field season are underway with commencement planned during Q3 2023.

Authorised for release by: Jason Bontempo - Non-Executive Director

For further information contact: Jason Bontempo - [email protected]

==> picture [66 x 52] intentionally omitted <==

Cautionary Note

The interpreted presence of pegmatite, pegmatite granite or visual spodumene does not equate to lithium mineralisation. The Company is encouraged by the geology identified by the initial work programmes within Cancet West, but no quantitative or qualitative assessment of mineralisation is possible at this stage. The Company plans to undertake field work to test for potential lithium mineralisation and laboratory analysis of rock chip samples is required to determine if the remote-sensing has mapped pegmatites and pegmatite granites that have the potential to host mineralisation

Competent Persons Statement

The information in this report that relates to Exploration Results is based on information compiled by FIN and reviewed by Mr. Thomas Ridges who is a member of the Australian Institute of Mining and Metallurgy. Mr. Thomas Ridges is an employee of Sustainable Resources Pty Ltd consulting to FIN and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr. Ridges consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Forward looking statements

This release may include forward-looking statements. These forward-looking statements are not historical facts but rather are based on FIN’s current expectations, estimates and assumptions about the industry in which FIN operates, and beliefs and assumptions regarding FIN‘s future performance. Words such as “anticipates”, “expects”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “potential” and similar expressions are intended to identify forward-looking statements. Forward-looking statements are only predictions and not guaranteed, and they are subject to known and unknown risks, uncertainties and assumptions, some of which are outside the control of FIN. Actual values, results or events may be materially different to those expressed or implied in this release. Past performance is not necessarily a guide to future performance and no representation or warranty is made as to the likelihood of achievement or reasonableness of any forward-looking statements or other forecast. Given these uncertainties, recipients are cautioned not to place reliance on forward looking statements. Any forward-looking statements in this release speak only at the date of issue of this release. Subject to any continuing obligations under applicable law and the ASX Listing Rules, FIN does not undertake any obligation to update or revise any information or any of the forward-looking statements in this release or any changes in events, conditions or circumstances on which any such forward looking statement is based. Actual values, results, interpretations or events may be materially different to those expressed or implied in this announcement.

Historical Reporting of Results

COMMENTS REGARDING THE REPORTING OF OTHER ENTITIES EXPLORATION RESULTS

  • The historical exploration results reported here in have been sourced from public reports as listed in the References.

  • The information in this announcement is an accurate representation of the available data for project that has been sourced to date.

  • The historical exploration results were not reported in accordance with the JORC Code

==> picture [66 x 52] intentionally omitted <==

Appendix 1:

Additional Cancet West and Ross Mineral Claims

Project Title No Seq. No Status Expiry Date Area(Ha)
Cancet West(W) NA 401680590 Pending NA 51,2
Cancet West(W) NA 401680591 Pending NA 51,2
Cancet West(W) NA 401680220 Pending NA 51,2
Cancet West(W) NA 401680221 Pending NA 51,2
Cancet West(W) NA 401680616 Pending NA 51,2
Cancet West(W) NA 401680617 Pending NA 51,2
Cancet West(W) NA 401680618 Pending NA 51,2
Cancet West(W) NA 401680619 Pending NA 51,2
Cancet West(W) NA 401680620 Pending NA 51,2
Cancet West(W) NA 401680621 Pending NA 51,2
Cancet West(W) NA 401680622 Pending NA 51,2
Cancet West(W) NA 401680243 Pending NA 51,2
Cancet West(W) NA 401680244 Pending NA 51,2
Cancet West(W) NA 401680245 Pending NA 51,2
Cancet West(W) NA 401680246 Pending NA 51,2
Cancet West(W) NA 401680247 Pending NA 51,2
Cancet West(W) NA 401680268 Pending NA 51,2
Cancet West(W) NA 401680269 Pending NA 51,2
Cancet West(W) NA 401680270 Pending NA 51,2
Cancet West(W) NA 401680271 Pending NA 51,2
Cancet West(W) NA 401680272 Pending NA 51,2
Cancet West(W) NA 401680673 Pending NA 51,2
Cancet West(W) NA 401680296 Pending NA 51,2
Cancet West(W) NA 401680297 Pending NA 51,2
Cancet West(W) NA 401680298 Pending NA 51,2
Cancet West(W) NA 402981810 Pending NA 51,2
Cancet West(W) NA 401680698 Pending NA 51,2
Ross NA 401713811 Pending NA 52,9
Ross NA 401713812 Pending NA 52,9
Ross NA 401713781 Pending NA 52,9
Ross NA 401713782 Pending NA 52,9
Ross NA 401713783 Pending NA 52,9
Ross NA 401715922 Pending NA 52,9
Ross NA 401713751 Pending NA 52,9
Ross NA 401713752 Pending NA 52,9
Ross NA 401713753 Pending NA 52,9
Ross NA 401713754 Pending NA 52,9
Ross NA 402563804 Pending NA 52,9
Ross NA 401713723 Pending NA 52,9
Ross NA 401713724 Pending NA 52,9
Ross NA 401713725 Pending NA 52,9
Ross NA 401713726 Pending NA 52,9

==> picture [65 x 53] intentionally omitted <==

Appendix 2:

JORC Code, 2012 Edition (Table 1) – Ross and Cancet West Prospectivity Analysis Secton 1 Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections.)

Criteria
JORC Code explanation
Commentary
Sampling
techniques

Nature and quality of sampling (eg cut
channels, random chips, or specific specialised
industry standard measurement tools
appropriate to the minerals under investigation,
such as down hole gamma sondes, or handheld
XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of
sampling.

Include reference to measures taken to ensure
sample representivity and the appropriate
calibration of any measurement tools or
systems used.
Aspects of the determination of mineralisation
that are Material to the Public Report. In cases
where ‘industry standard’ work has been done
this would be relatively simple (eg ‘reverse
circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to
produce a 30 g charge for fire assay’). In other
cases more explanation may be required, such
as where there is coarse gold that has inherent
sampling problems. Unusual commodities or
mineralisation types (eg submarine nodules)
may warrant disclosure of detailed information.
Prospectivity Analysis

Not applicable, no sample results or drilling reported.
Drilling techniques

Drill type (eg core, reverse circulation, open-
hole hammer, rotary air blast, auger, Bangka,

Not Applicable no drilling reported

==> picture [65 x 53] intentionally omitted <==

Criteria JORC Code explanation Commentary
sonic, etc) and details (eg core diameter, triple
or standard tube, depth of diamond tails, face-
sampling bit or other type, whether core is
_oriented and if so, by what method, etc). _
Drill sample Method of recording and assessing core and Not Applicable no drilling reported
chip sample recoveries and results assessed.
recovery Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential loss/gain
of fine/coarse material.
Logging Whether core and chip samples have been Not applicable no drilling reported
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
Whether logging is qualitative or quantitative in
nature. Core (or costean, channel, etc)
photography.
The total length and percentage of the relevant
intersections logged.
Sub-sampling If core, whether cut or sawn and whether Not applicable no drilling reported
techniques and quarter, half or all core taken.
If non-core, whether riffled, tube sampled,
sample preparation rotary split, etc and whether sampled wet or
dry.
For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
Quality control procedures adopted for all sub-
sampling stages to maximise representativity of
samples.
Measures taken to ensure that the sampling is

==> picture [65 x 53] intentionally omitted <==

Criteria
JORC Code explanation
Commentary
representative of the in situ material collected,
including for instance results for field
duplicate/second-half sampling.

Whether sample sizes are appropriate to the
grain size of the material being sampled.
Quality of assay
data and laboratory
tests

The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.

For geophysical tools, spectrometers, handheld
XRF instruments, etc, the parameters used in
determining the analysis including instrument
make and model, reading times, calibrations
factors applied and their derivation, etc.

Nature of quality control procedures adopted
(eg standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (i.e. lack of bias) and
precision have been established.
Prospectivity Analysis

Not applicable no drilling or sampling reported
Verification of
sampling and
assaying

The verification of significant intersections by
either independent or alternative company
personnel.

The use of twinned holes.

Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.

Discuss any adjustment to assay data.

Not applicable no drilling or sampling reported
Location of data
points

Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.

Not applicable no drilling or sampling reported

==> picture [65 x 53] intentionally omitted <==

Criteria JORC Code explanation Commentary
Data spacing and Data spacing for reporting of Exploration The data is not appropriate for use in estimating Mineral Resources and is not
distribution Results.
Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the
intended for such use. There has been insufficient exploration to define a Mineral
Resource and it is uncertain if further exploration will results in the determination of
a Mineral Resource at this stage.
Mineral Resource and Ore Reserve estimation No sample compositing was applied.
procedure(s) and classifications applied.
Whether sample compositing has been applied.
Orientation of data Whether the orientation of sampling achieves The data is early stage high level broad data to be used for initial interpretation of
in relation to unbiased sampling of possible structures and
the extent to which this is known, considering
the Li prospectivity within the Ross and Cancet West Projects.
geological structure the deposit type.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
Sample security The measures taken to ensure sample security. Not applicable no drilling or sampling reported
Audits or reviews The results of any audits or reviews of sampling No specific external audits or reviews have been undertaken on the data by the
techniques and data. Company.

==> picture [65 x 53] intentionally omitted <==

Secton 2 Reportng of Exploraton Results

(Criteria listed in the preceding section also apply to this section.)

Criteria JORC Code explanation JORC Code explanation Commentary
Mineral tenement and land tenure status Type, reference name/number, location and ownership See FIN ASX announcement June 2023 Quarterly
including agreements or material issues with third Report for a list of Mineral Claims related to Ross
parties such as joint ventures, partnerships, overriding
royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
and Cancet West, additional claims added can be
found in Appendix 1.
The security of the tenure held at the time of reporting The mineral claims are 100% owned by Fin
along with any known impediments to obtaining a Resources Ltd and its subsidiaries.
licence to operate in the area.
The minerals claims have no underlying royalties.
Cancet West and a portion of the Ross Project
are cover by Hydroelectric Reserves to the State
of Quebec. Exploration is allowed under specific
conditions outlines by the state.
The mineral claims are in good standing.
Exploration done by other parties Acknowledgment and appraisal of exploration by other Limited previous exploration for Lithium within
parties. the region.
See previous announcements by fin resources for
a summary of historical exploration.
Geology Deposit type, geological setting and style of The Ross Project is located in the northeast part
mineralisation. of the Superior Province of the Canadian Shield
craton. The Superior Province extends from
Manitoba to Quebec, and is mainly composed of
Archean-age rocks. The general metamorphism is
of greenschist facies, except in the vicinity of
intrusive bodies, where it reaches the
amphibolite-to granulite facies.

==> picture [65 x 53] intentionally omitted <==

Criteria JORC Code explanation Commentary
The Project’s claims are centred on 30 km of
prospective greenstone strike length of the Natel
Formation within the La Grande Sub province of
the Archean Superior Province in Quebec
Canada. The Natel Formation consists of massive
or pillowed flows of amphibolitized basalt,
andesite, komatiite and rhyolite, as well as
volcaniclastic units (block and lapilli tuff, lapilli
tuff and tuff).
The Le Grande Sub Province is host to a number
of major lithium projects, including the
Whabouchi Lithium Mine which along strike to
the south west of the Ross Project Project.
The Cancet West Project’s claims are centred on
14 km of prospective greenstone strike length of
the Lac Guyer Greenstone Belt located within the
La Grande Sub province of the Archean Superior
Province in Quebec Canada. The Lac Guyer
Greenstone Belt is an east-west trending
greenstone belt which is host to multiple gold,
base-metal and lithium occurrences and deposits.
Lithium mineralisation is in the form of
spodumene-bearing pegmatites.
The Lac Guyer Greenstone Belt is host to two
major lithium projects, both of which are along
strike to the east of the Cancet West Project;
Patriot Battery Metals (ASX: PMT) Corvette
Project and Winsome Resources Limited
(ASX:WR1) Cancet Project

==> picture [65 x 53] intentionally omitted <==

Criteria JORC Code explanation JORC Code explanation Commentary
Drill hole Information A summary of all information material to the Not Applicable, no drilling being reported.
understanding of the exploration results including a
tabulation of the following information for all Material
drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above
sea level in metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified on the
basis that the information is not Material and this
exclusion does not detract from the understanding of
the report, the Competent Person should clearly explain
why this is the case.
Data aggregation methods In reporting Exploration Results, weighting averaging Not Applicable, no drilling being reported.
techniques, maximum and/or minimum grade
truncations (eg cutting of high grades) and cut-off
grades are usually Material and should be stated.
Where aggregate intercepts incorporate short lengths
of high grade results and longer lengths of low grade
results, the procedure used for such aggregation should
be stated and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of metal
equivalent values should be clearly stated.
Relationship between mineralisation These relationships are particularly important in the Not Applicable, no drilling being reported.
widths and intercept lengths reporting of Exploration Results.
If the geometry of the mineralisation with respect to
the drill hole angle is known, its nature should be
reported.
If it is not known and only the down hole lengths are
reported, there should be a clear statement to this
effect (eg ‘down hole length, true width not known’).

==> picture [65 x 53] intentionally omitted <==

Criteria JORC Code explanation JORC Code explanation Commentary
Diagrams Appropriate maps and sections (with scales) and Diagrams are included in the body of the
tabulations of intercepts should be included for any document.
significant discovery being reported These should
include, but not be limited to a plan view of drill hole
collar locations and appropriate sectional views.
Balanced reporting Where comprehensive reporting of all Exploration All results reported are exploration results in
Results is not practicable, representative reporting of nature. No representative significance were
both low and high grades and/or widths should be
practiced to avoid misleading reporting of Exploration
applied to the results.
Results.
Other substantive exploration data Other exploration data, if meaningful and material, Assessment of other substantive exploration data
should be reported including (but not limited to): is currently underway yet complete however
geological observations; geophysical survey results;
geochemical survey results; bulk samples – size and
considered immaterial at this stage.
method of treatment; metallurgical test results; bulk
density, groundwater, geotechnical and rock
characteristics; potential deleterious or contaminating
substances.
Further work The nature and scale of planned further work (eg tests Continued In-depth review of historical datasets
for lateral extensions or depth extensions or large-scale and mapped outcrops across the Projects.
step-out drilling).
Diagrams clearly highlighting the areas of possible Remote sensing and geophysics as required, with
extensions, including the main geological interpretation.
interpretations and future drilling areas, provided this
information is not commercially sensitive.
Preparations and planning for the upcoming field
season are underway with commencement
planned during Q3 2023.