EVOLUTION MINING LIMITED Regulatory Filings 2024

Feb 13, 2024

64885_rns_2024-02-13_b097229a-3923-4b52-9d6e-039f4f631dbb.pdf

Regulatory Filings

Open in viewer

Opens in your device viewer

==> picture [110 x 78] intentionally omitted <==

ABN 74 084 669 036

ASX Announcement

Sydney Office P +61 2 9696 2900 F +61 2 9696 2901 Level 24 175 Liverpool Street Sydney NSW 2000

www.evolutionmining.com.au

14 February 2024

ANNUAL MINERAL RESOURCES AND ORE RESERVES STATEMENT as at 31 December 2023

Material increase in Group Mineral Resources and Ore Reserves

Evolution Mining Limited (ASX: EVN) is pleased to release its annual Mineral Resources and Ore Reserves (MROR) estimates as at 31 December 2023.

Key Highlights

  • Group Mineral Resources have been estimated to contain 32.7 million ounces of gold and 4.1 million tonnes of copper (including the 80% portion of the Northparkes Mineral Resource which is reported exclusive of the Northparkes Ore Reserve)

  • A substantial increase of 2.3 million ounces of gold (8%) and 2.4 million tonnes of copper (134%) compared with the estimate as at 31 December 2022

  • The Northparkes acquisition is the main driver of Mineral Resource growth. Group Mineral Resources are expected to increase further once the work to report the Northparkes Mineral Resource inclusive of Ore Reserves is completed during the September 2024 quarter.

  • Group Ore Reserves are estimated to contain 11.5 million ounces of gold and 1.3 million tonnes of copper net of mining depletion of 884 thousand ounces of gold and 48 thousand tonnes of copper

  • An increase of 1.5 million ounces of gold (15%) and 659 thousand tonnes of copper (100%) compared with the estimate as at 31 December 2022

  • The acquisition of Northparkes and doubling of the Ore Reserve at Ernest Henry (reported 5 June 2023) drove the sizable growth in the Group Ore Reserve in 2023

  • Drilling success at Ernest Henry, Cowal and Mungari enabled Evolution to replace almost all of the 2023 mined ounces

  • Average mine life of ~15 years[1] in Tier 1 jurisdictions reinforces the quality of Evolution’s portfolio

Commenting on the updated Mineral Resources and Ore Reserves estimate, Evolution’s Managing Director and Chief Executive Officer, Lawrie Conway, said:

“We are extremely pleased with the outcomes of the Mineral Resources and Ore Reserves update. The acquisition of Northparkes brings a reliable, well-established, long-life copper and gold operation into the portfolio. Featuring concentrated mining options with five deposits situated within a two-kilometre radius, Northparkes provides Evolution with additional exposure to copper over the long term.

“Our drilling programmes across the business continue to be successful and have positively impacted the 2023 results. Drilling at Cowal continues to deliver encouraging results, driving the addition of gold metal in underground Mineral Resources. The increase in Ore Reserves at Mungari underlines our confidence in the mill expansion. Ernest Henry’s successful drilling program targeted the Ernie Junior and Bert deposits and returned positive results, reinforcing a long life at the asset,” Mr Conway added.

1 Based on December 2023 Ore Reserves and FY24 Guidance for gold production

Evolution Mining Limited

==> picture [83 x 59] intentionally omitted <==

Group Mineral Resources[2] are estimated to contain 1.1 billion tonnes grading 0.91g/t gold for 32.7 million ounces of contained gold and 640.9 million tonnes grading 0.65% copper for 4.1 million tonnes of copper, excluding the Northparkes Ore Reserve. Gold and copper depletion from the Mineral Resource were estimated to be 934 thousand ounces and 66 thousand tonnes, respectively.

Group Ore Reserves are estimated to contain 404.3 million tonnes grading 0.88g/t gold for 11.5 million ounces of gold and 214.7 million tonnes grading 0.62% copper for 1.3 million tonnes of copper net of mining depletion of 884 thousand ounces of gold and 48 thousand tonnes of copper.

Key changes to the Mineral Resources and Ore Reserve estimates (net of mining depletion)

Northparkes

  • Mineral Resource estimate of 420.8 million tonnes at 0.55% copper and 0.19g/t gold for 2.3 million tonnes of contained copper and 2.6 million ounces of contained gold

  • The Northparkes Mineral Resource is reported at Evolution’s 80% attributable ownership interest and excludes the reported Ore Reserve. The Group Mineral Resource will increase when the Northparkes Mineral Resource is reported to include the Ore Reserve (as per other Evolution assets) which is due to be completed in the September quarter 2024

  • Ore Reserve estimate of 75.0 million tonnes at 0.51% copper and 0.27g/t gold for 386 thousand tonnes of contained copper and 662 thousand ounces of contained gold

Table 1: Summary breakdown showing Evolution’s Group Mineral Resource[2] and Northparkes Ore Reserve as at 31 December, 2023

Gold Copper
Mineral Resources Tonnes (Mt) Grade
(g/t)
Gold metal
(koz)
Tonnes
(Mt)
Grade (%) Copper
metal (kt)
Group (excl. Northparkes) 695.7 1.34 30,073 220.1 0.83 1,823
Northparkes (excl. Ore
Reserve)
420.8 0.19 2,609 420.8 0.55 2,316
Total2 1,116.5 0.91 32,682 640.9 0.65 4,139
Ore Reserves Tonnes (Mt) Grade (g/t) Gold metal
(koz)
Tonnes
(Mt)
Grade (%) Copper
metal (kt)
Northparkes 75.0 0.27 662 75.0 0.51 386
  • The Northparkes Mineral Resource and Ore Reserve are reported in accordance with the JORC code 2012

Cowal

  • Mineral Resource estimate increased to 285.1 million tonnes at 0.98g/t gold for 9.0 million ounces of contained gold, an increase of 158 thousand ounces (2%) net of depletion compared to the December 2022 estimate of 273.3 million tonnes at 1.01g/t gold for 8.8 million ounces of contained gold

  • Increase driven by new drilling data in the Cowal underground as well as expansion of mineralisation in the open pit. Recent drilling results from Edradour reported in the September 2023 and December 2023 exploration updates will be incorporated in the December 2024 Mineral Resources and Ore Reserves update

  • Ore Reserve estimate increased 135 thousand ounces (3%) to 134.6 million tonnes at 1.03g/t gold for 4.5 million ounces of contained gold compared to the December 2022 estimate of 129.5 million tonnes at 1.04g/t gold for 4.3 million ounces of contained gold

  • Increase due to new data including drilling underground and updated modifying factors for the open pit continuation (OPC) Feasibility Study

==> picture [493 x 36] intentionally omitted <==

2 The Group Mineral Resource is reported inclusive of the Northparkes Mineral Resource, which excludes the Northparkes Ore Reserve

Evolution Mining Limited

2

==> picture [83 x 59] intentionally omitted <==

Ernest Henry

  • Mineral Resource estimate increased to 97.1 million tonnes at 1.30% copper and 0.76g/t gold for 1.3 million tonnes of contained copper and 2.4 million ounces of contained gold . This is compared to the December 2022 estimate of 94.8 million tonnes at 1.27% copper and 0.75g/t gold for 1.2 million tonnes of contained copper and 2.3 million ounces of contained gold

  • Increase of 96 thousand ounce (4%) in contained gold ounces and 56 thousand tonne (5%) in contained copper tonnes

  • Increases driven by drilling results confirming extensions to the Ernie Junior and Bert ore bodies

  • Numerous growth targets exist including depth extensions below the main ore body, between the main ore body and Ernie Junior, and along strike of Ernie Junior. Mineralisation at Bert remains open down plunge which will continue to be drilled throughout the year

  • Ore Reserves estimate increased to 74.5 million tonnes at 0.76% copper and 0.44g/t gold for 563 thousand tonnes of contained copper and 1.1 million ounces of contained gold . This is compared to the December 2022 estimate of 34.3 million tonnes at 0.85% copper and 0.45g/t gold for 290 thousand tonnes of contained copper and 495 thousand ounces of contained gold

  • Increase of 569 thousand ounce (115%) in contained gold and 273 thousand tonnes (94%) in contained copper

  • Significant increase driven by conversion of Mineral Resources to Ore Reserves within the mine extension footprint, following completion of the Pre-Feasibility Study (as announced on 5 June 2023)

Mungari

  • Mineral Resources estimate increased to 125.8 million tonnes at 1.45g/t gold for 5.9 million ounces of contained gold, compared to the December 2022 estimate of 97.5 million tonnes at 1.70g/t gold for 5.3 million ounces

  • Increase of 532 thousand ounces (10%) primarily due to design changes in the open pits which are optimised to the new metal price and cost assumptions

  • Ore Reserves estimate increased to 37.4 million tonnes at 1.33g/t gold for 1.6 million ounces of contained gold compared to the December 2022 estimate of 24.3 million tonnes at 1.58g/t gold for 1.24 million ounces of contained gold

  • Increase of 357 thousand ounces (29%) of contained gold driven primarily by open pit design changes and new data

Red Lake

  • Mineral Resource estimate decreased to 55.1 million tonnes at 6.56g/t gold for 11.6 million ounces of contained gold , compared to December 2022 estimate of 60.4 million tonnes at 6.35g/t gold for 12.3 million ounces of contained gold

  • Decrease of 711 thousand ounces (-6%) driven by mining depletion, reclassification and higher cost assumptions that increased cut-off grades at Lower Red Lake, Lower Campbell and Cochenour

  • Ore Reserves decreased to 12.4 million tonnes at 6.87g/t gold for 2.7 million ounces of contained gold compared to the December 2022 estimate of 13.0 million tonnes at 6.90g/t gold for 2.9 million ounces of contained gold

  • Decrease resulting from a model change at Aviation and mining depletion

Mt Rawdon

  • Mineral Resource estimate decreased to 9.5 million tonnes at 0.44g/t gold for 134 thousand ounces of contained gold , compared to the December 2022 estimate of 28.8 million tonnes at 0.52g/t gold for 478 thousand ounces of contained gold

  • Decrease of 344 thousand ounces (-72%) was driven primarily by changes in reporting process to the final pit design (instead of $2500/oz optimised shell). Depletion accounted for 67 thousand ounces

Evolution Mining Limited

3

==> picture [83 x 59] intentionally omitted <==

  • Ore Reserve estimate decreased to 5.2 million tonnes at 0.59g/t gold for 100 thousand ounces of contained gold , compared to the December 2022 estimate of 10.9 million tonnes at 0.61g/t gold for 216 thousand ounces of contained gold

  • Decrease driven by revised final pit design, ahead of mining completion in the September quarter 2024. Processing of stockpiles is expected to continue until the end of FY25

Evolution’s Group Mineral Resource tables summarising the contained gold and contained copper content in the reported Mineral Resource as at 31 December 2023 are provided in Table 3 and Table 5 respectively. Mineral Resources are reported inclusive of Ore Reserves for all assets except for Northparkes which reports its Mineral Resource exclusive of its reported Ore Reserve. The reported Mineral Resource excludes mined areas and remnant resource areas sterilised by mining activities. Changes in the reported Mineral Resource between 31 December 2022 and the updated 31 December 2023 estimate are illustrated in waterfall graphs in Figure 1 and Figure 3.

Evolution’s Group Ore Reserve tables summarising the contained gold and contained copper content of the reported Ore Reserve as at 31 December 2023 are provided in Table 4 and Table 6. Changes in the reported Ore Reserve between 31 December 2022 and the updated 31 December 2023 estimate are illustrated in waterfall graphs in Figure 2 and Figure 4.

Evolution Mining Limited

4

==> picture [83 x 59] intentionally omitted <==

==> picture [500 x 246] intentionally omitted <==

----- Start of picture text -----

Exclusive of
Ore Reserve
Inclusive of
Ore Reserve
----- End of picture text -----

Figure 1: Group Mineral Resource changes: contained gold ounces by asset December 2022 to December 2023

==> picture [500 x 251] intentionally omitted <==

Figure 2: Group Ore Reserve changes: contained gold ounces by asset December 2022 to December 2023

Evolution Mining Limited

5

==> picture [83 x 59] intentionally omitted <==

==> picture [500 x 253] intentionally omitted <==

  • Figure 3: Group Mineral Resource changes: contained copper tonnes by asset December 2022 to December 2023

==> picture [501 x 258] intentionally omitted <==

Figure 4: Group Ore Reserve changes: contained copper tonnes by asset December 2022 to December 2023

Evolution Mining Limited

6

==> picture [83 x 59] intentionally omitted <==

Mineral Resources and Ore Reserve Growth since Evolution’s inception

The contained gold content within Evolution’s reported Mineral Resources and Ore Reserves inclusive of mining depletion has grown by 369% (from 6.97Moz) and 228% (from 3.49Moz) respectively since Evolution’s formation in November 2011.

In total, Evolution has added 12.8 million ounces of gold to the reported Mineral Resource predominantly by drilling, along with modelling and optimisation updates. This growth is in addition to 24.4 million ounces from acquisitions, reinforcing the Company’s strategy of identifying and acquiring assets with strong mineral endowment where value can be unlocked.

==> picture [491 x 228] intentionally omitted <==

----- Start of picture text -----

Divestments
Growth
Depletion
Acquisitions
Evolution
Evolution
Dec 2023
Nov 2011
----- End of picture text -----

Figure 5: Evolution Mineral Resources growth since inception – contained gold (koz)

==> picture [491 x 229] intentionally omitted <==

----- Start of picture text -----

Divestments
Acquisitions
Growth
Depletion
Evolution
Evolution
Dec 2023
Nov 2011
----- End of picture text -----

Figure 6: Evolution Group Ore Reserves growth since inception – contained gold (koz)

Evolution Mining Limited

7

==> picture [83 x 59] intentionally omitted <==

Since the Company’s formation in November 2011, Evolution’s Group Mineral Resources and Ore Reserves have grown by 4.1 million tonnes of copper (Figure 7) and 1.3 million tonnes (Figure 8) of copper respectively, including mining depletion from in situ Mineral Resources and Ore Reserves of 206 thousand tonnes and 139 thousand tonnes respectively. In addition to the acquisitions of Ernest Henry and Northparkes, the Company has added 525 thousand tonnes of copper to the estimated Ore Reserve predominantly from drilling at Ernest Henry, along with modelling and optimisation updates.

==> picture [497 x 242] intentionally omitted <==

----- Start of picture text -----

Divestments Growth
Depletion
Acquisitions
Evolution Evolution
Nov 2011 Dec 2023
----- End of picture text -----

Figure 7: Evolution Group Mineral Resources growth since inception – contained copper (kt)

==> picture [490 x 239] intentionally omitted <==

----- Start of picture text -----

Growth
Divestments
Depletion
Acquisitions
Evolution
Evolution
Nov 2011
Dec 2023
----- End of picture text -----

Figure 8: Evolution Group Ore Reserves growth since inception – contained copper (kt)

Evolution Mining Limited

8

==> picture [83 x 59] intentionally omitted <==

Northparkes – significant addition to the Evolution portfolio

The extensive Mineral Resource and Ore Reserve footprint contained within the mining lease at Northparkes is illustrated in Figure 9. Underground operations are currently focussed on the block and sub-level caves at E26, and open pit mining at E31 and E31N. The large Mineral Resource base at Northparkes provides optionality for future mine plans.

Drilling in the immediate future will target shallow high-grade copper-gold prospects located on or close to the mining lease in proximity to existing infrastructure, as well as deeper portions of E48 to support underground mine planning.

==> picture [490 x 311] intentionally omitted <==

Figure 9: Oblique section of Northparkes looking ESE

Evolution Mining Limited

9

==> picture [83 x 59] intentionally omitted <==

Waterfall chart definitions

Additions

This is material above the reported cutoff criteria that was mined during the year which was situated outside the previously reported Mineral Resource or Ore Reserve. This is additional material which was defined by drilling and grade control activities which was not reported within the previous public Mineral Resource and/or Ore Reserve estimate. An example might be that planned underground development intersected a new zone of mineralisation or that drilling activities within the year identified new zones of mineralisation which were subsequently mined within the calendar year and were not previously reported to the market.

Subtractions

This relates to material which was reported within the Mineral Resource and/or Ore Reserve that was planned to be mined but subsequently was not recovered from mining activities. From an Ore Reserve perspective this may relate to the loss of planned mining inventory due to poor ground conditions and/or geotechnical or other hazards. From a Mineral Resource perspective mining activities may have resulted in the sterilization of some remnant Mineral Resource and subsequently the reported Mineral Resource within this region no longer has reasonable prospects of economic extraction.

New Data

This occurs where a change in the Resource and Reserve base is driven by a change in either the methodology or interpretation of the resource estimate and incorporates the impact of new resource definition drilling and/or grade control activities data on the model. Localised changes in tonnes and grade which occur due to infill drilling, grade control activities which have been used in the updated resource estimate and PreFeasibility study inventory are also included in this category.

Design change

This occurs where a change in the input parameters used to generate the estimate are modified from the previous year and this impacts on the generation of either the A$2,500/oz optimised shells used to constrain Mineral Resources for reporting, or the engineered pit or stope design used to constrain Ore Reserves for reporting. This category also includes impacts on design associated with changes in costs and/or changes in associated reporting cutoff grades.

Stockpile

This captures the net change to stockpiled material at each site in the twelve-month reporting period.

Depletion

This is the component of Mineral Resource and Ore Reserve which has been mined. It also includes any remnant material which is now considered to be not economically viable; any additional material outside the reported Mineral Resource which has been defined by grade control activities and has been mined (refer 'Additions’) and any additions to stockpiles. This is not the total production figure of ore mined for the year which would include mining dilution.

Evolution Mining Limited

10

==> picture [83 x 59] intentionally omitted <==

Commodity price assumptions

Evolution annually reviews commodity price assumptions used to estimate the reported Group Mineral Resource and Ore Reserve. This review includes historic and forward looking analysis of gold and copper pricing and a review of pricing used by peer companies. Evolution’s Group recommended guidance for price assumptions for the cut-off grade and optimisation of the December 2023 Mineral Resource and Ore Reserve are provided below. An AUD:CAD exchange rate assumption of 0.9 has been used for Red Lake.

  • Gold: $1,800/oz for Ore Reserves, $2,500/oz for Mineral Resources

  • Silver: $25.00/oz for Ore Reserves, $27.50/oz for Mineral Resources

  • Copper: $9,000/t for Ore Reserves, $12,000/t for Mineral Resources

This year’s price assumptions for Mineral Resource reporting have increased by ~14% for gold from $2200/oz to $2500/oz gold and by 20% for copper from $10,000/t copper to $12,000/t copper.

This year’s price assumptions for gold and copper for Ore Reserve cut-off grade and optimisation have increased from $1650/oz to $1,800/oz gold and from $7,000/t copper to $9,000/t copper.

Mineral Resources

All open pit Mineral Resource estimates (except for Northparkes and Marsden) are reported within optimised pit shells which have been developed using a $2,500/oz price assumption and take into account forecast mining costs and metallurgical recoveries. Northparkes Open Pit Mineral Resource includes all material within designed pit shells above an economic cutoff grade; cut-off grades are 0.65g/t Au for E44 and 0.34% CuEq for E31 and have been calculated based on a US$3.30/lb copper price, US$1,350/oz gold price and 0.73 $AUD:$USD conversion rate. The Marsden Mineral Resource is reported based on a net smelter return (NSR) value calculation that considers mining and processing costs, metallurgical recoveries, royalties, transport and refining costs. The NSR produces a value cut-off (by block) that is approximately equivalent to a 0.2g/t gold cut-off which has been calculated using a $1,800 per ounce price assumption for gold and a $9000/t price assumption for copper.

All underground Mineral Resources (except Ernest Henry) are reported within underground mining shapes (MSOs) using a $2,500/oz price assumption and take into account forecast mining costs and metallurgical recoveries. The Ernest Henry Mineral Resource estimate is reported within an interpreted 0.7% copper envelope. All material inside this interpreted 0.7% copper envelope inclusive of low grade or waste material is contained within the reported Mineral Resource.

Ore Reserves

Evolution’s reported Ore Reserves are supported by Pre-Feasibility and/or Feasibility studies.

All open pit Ore Reserve estimates are reported within detailed pit designs and all underground Ore Reserves are reported within mineable underground shapes, inclusive of dilution. Pit designs and underground mining inventories have taken into account all applicable modifying factors, forecast mining costs and metallurgical recoveries and have been developed subject to an economic test to verify that economic extraction is justified. The economic test includes all applicable capital costs and is performed via a sensitivity analysis using a range of assumed gold prices from $1,800 to $2,650 per ounce and/or copper prices from $9,000 to $12,000 per tonne and considers a range of financial metrics including AISC, NPV and FCF. Assets may use different assumptions within this range during optimisation or financial modelling stages, taking into account short-term gold price forecasts and other factors. Details of the optimisation and financial parameters used for each asset are summarized below:

  • Cowal Ore Reserve cut-off grade and the optimisation of the E46, GR & underground deposits used a $1,800/oz gold price assumption. Optimisation of E41 and E42 Stage I was conducted at gold price assumptions of $1,584/oz and $1,944/oz respectively to ensure minimum mining width was exceeded and to maximise operating margin.

  • The Marsden Ore Reserve has been reported using a ‘Net Smelter Return’ (NSR) cut-off which takes into account ore haulage, ore processing and administration costs, concentrate costs, metallurgical recoveries, metal prices, and royalties. The breakeven NSR value equates approximately to a 0.3g/t Au cutoff. The Ore Reserve estimate was developed using a $1,350/oz gold price and a $6000/t copper price

  • Northparkes' Ore Reserve is based on a variety of different studies (Pre-Feasibility and Feasibility) over a ten-year period. Price assumptions for copper and gold range from US$2.75/lb to US$3.77/lb

Evolution Mining Limited

11

==> picture [83 x 59] intentionally omitted <==

  • and US$1250/oz to US$1750/oz respectively. Exchange rate assumptions AUD:USD ranged between 0.72 and 0.78. For further details refer Northparkes material information summary in this release

  • The Ernest Henry Ore Reserve estimate uses a ‘Net Smelter Return’ (NSR) calculation to assess revenue. The NSR accounts for processing costs, concentrate specification, transport costs, royalty payments, treatment and refining charges. Revenue generation for the Ore Reserve was assessed using price assumptions between $7,000/t and $12,000/t for copper and between $1,600/oz and $2,400/oz gold. For further details refer to the Ernest Henry material information summary in this release

  • The Mungari Ore Reserve estimate was evaluated at a revenue gold price of $2,500/oz. The Open Pit Reserve estimates were optimised at a gold price of between $1,800 and $2,400/oz. The Underground Ore Reserve estimate was optimised with a cut-off grade based on $1,800/oz gold price with incrementally profitable material included at $2,500/oz revenue gold price. For further details refer to Mungari’s material information summary in this release

  • Red Lake Ore Reserve stoping cut-off grades have been updated for Lower Red Lake, Cochenour, HG Young and McFinley using a $1800/oz price assumption taking into account mining, processing general & administrative costs. The Ore Reserve stoping cut-off grade for Upper Campbell and Upper Red Lake has remained unchanged from last year and were developed using a gold price of $1,450/oz. A foreign exchange rate of 0.9 AUD:CAD has been used at Red Lake. For further details on price assumptions and applied cutoff criteria refer to Red Lake’s material information summary in this release

  • Mt Rawdon Ore Reserve estimate is reported within a final pit design which has been developed using an $1800/oz gold price assumption

All prices are in AUD unless otherwise stated.

Evolution Mining Limited

12

==> picture [83 x 59] intentionally omitted <==

JORC 2012 and ASX Listing Rules Requirements

This annual statement of Mineral Resources and Ore Reserves has been prepared in accordance with the 2012 Edition of the ‘Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves’ (the JORC Code 2012).

The Mineral Resource and Ore Reserve summaries are tabulated on the following pages. Material information summaries are provided for the Ernest Henry, Northparkes, Mungari and Red Lake Mineral Resources and Ore Reserves pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements.

Approval

This release has been approved by the Evolution Board of Directors.

Forward looking statements

This report prepared by Evolution Mining Limited (or ‘the Company’) include forward looking statements. Often, but not always, forward looking statements can generally be identified by the use of forward looking words such as ‘may’, ‘will’, ‘expect’, ‘intend’, ‘plan’, ‘estimate’, ‘anticipate’, ‘continue’, and ‘guidance’, or other similar words and may include, without limitation, statements regarding plans, strategies and objectives of management, anticipated production or construction commencement dates and expected costs or production outputs. Forward looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause the Company’s actual results, performance and achievements to differ materially from any future results, performance or achievements. Relevant factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and project development, including the risks of obtaining necessary licenses and permits and diminishing quantities or grades of reserves, political and social risks, changes to the regulatory framework within which the Company operates or may in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel, industrial relations issues and litigation. Forward looking statements are based on the Company and its management’s good faith assumptions relating to the financial, market, regulatory and other relevant environments that will exist and affect the Company’s business and operations in the future. The Company does not give any assurance that the assumptions on which forward looking statements are based will prove to be correct, or that the Company’s business or operations will not be affected in any material manner by these or other factors not foreseen or foreseeable by the Company or management or beyond the Company’s control. Although the Company attempts and has attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in forward looking statements, there may be other factors that could cause actual results, performance, achievements or events not to be as anticipated, estimated or intended, and many events are beyond the reasonable control of the Company. Accordingly, readers are cautioned not to place undue reliance on forward looking statements. Forward looking statements in these materials speak only at the date of issue. Subject to any continuing obligations under applicable law or any relevant stock exchange listing rules, in providing this information the Company does not undertake any obligation to publicly update or revise any of the forward-looking statements or to advise of any change in events, conditions or circumstances on which any such statement is based.

For further information please contact:

Investor Enquiries

Media Contact

Peter O’Connor Michael Vaughan General Manager Investor Relations Media Relations Evolution Mining Limited Fivemark Partners Tel: +61 (0)2 9696 2900 Tel: +61 (0)422 602 720

About Evolution Mining

Evolution Mining is a leading, globally relevant gold miner. Evolution currently operates six mines, with five wholly-owned mines – Cowal in New South Wales, Ernest Henry and Mt Rawdon in Queensland, Mungari in Western Australia, and Red Lake in Ontario, Canada - and an 80% share of Northparkes in New South Wales. Financial Year 2024 gold production guidance is 789,000 ounces (±5%) and copper production of 62,500 tonnes (±5%) at a sector leading All-in Sustaining Cost of $1,340 per ounce (±5%).

Evolution Mining Limited

13

==> picture [83 x 59] intentionally omitted <==

Competent Persons’ Statement

The information in this statement that relates to the Mineral Resources and Ore Reserves listed in the table below is based on, and fairly represents, information and supporting documentation prepared by the Competent Person whose name appears in the same row, who is employed on a full-time basis by Evolution Mining Limited (except for Dean Basile who is employed by Mining One Pty Ltd and Glen Williamson who is employed by AMC Consultants Pty Ltd) and is a Member or Fellow of the Australasian Institute of Mining and Metallurgy (AusIMM), Australian Institute of Geoscientists (AIG) or Recognised Professional Organisation (RPO) and consents to the inclusion in this report of the matters based on their information in the form and context in which it appears. Each person named in the table below has sufficient experience which is relevant to the style of mineralisation and types of deposits under consideration and to the activity which he has undertaken to qualify as a Competent Person as defined in the in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’.

Evolution employees acting as a Competent Person may hold equity in Evolution Mining Limited and may be entitled to participate in Evolution’s executive equity long-term incentive plan, details of which are included in Evolution’s annual Remuneration Report. Annual replacement of depleted Ore Reserves is one of the performance measures of Evolution’s long-term incentive plans.

Table 2: Competent Persons

Deposit Competent Person Membership Status Member
number
Cowal Mineral Resource Ben Reid AusImm Member 991804
Cowal Open Pit Ore Reserve Dean Basile AusIMM Chartered
Professional
(Mining)
301633
Cowal Underground Ore Reserve Ryan Bettcher AusIMM Member 310517
Northparkes Open Pit Mineral
Resource
Geoff Smart AusIMM Member 106459
Northparkes Open Pit Ore
Reserve
Sam Ervin AusIMM Member 335108
Northparkes Underground
Mineral Resource
David Richards AusIMM Member 203408
Northparkes Underground Ore
Reserve
Sarah Webster AusIMM Chartered
Professional
(Geotechnical
Engineering)
228953
Northparkes Underground Ore
Reserve
Mark Flynn AusIMM Member 326289
Red Lake Mineral Resource Alain Mouton Professional
Geoscientists of
Ontario
Member 3782
Red Lake Ore Reserve Brad Armstrong Professional
Engineers-Ontario
Member 100152392
Mungari Mineral Resource Brad Daddow AIG Member 7736
Mungari Open Pit Ore Reserve Blake Callinan AusIMM Member 992387
Mungari Underground Ore
Reserve
Blake Callinan AusIMM Member 992387
Ernest Henry Mineral Resource Phillip Micale AusIMM Member 301942
Ernest Henry Ore Reserve Michael Corbett AusIMM Member 307897
Mt Rawdon Mineral Resource Matthew Graham-Ellison AusIMM Member 337100
Mt Rawdon Ore Reserve Ben Young AusIMM Member 309295
Marsden Mineral Resources James Biggam AusIMM Member 112082
Marsden Ore Reserve Glen Williamson AusIMM Fellow 106019

Evolution Mining Limited

14

==> picture [73 x 52] intentionally omitted <==

Table 3: Group Mineral Resource Statement for contained Gold as at 31 December 2023

Gold Gold Gold Measured Measured Total Resource Total Resource Total Resource CP9 December
22
Resources
Indicated Inferred
Project Type Cut-off Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)


Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Gold Metal
(koz)
Cowal1 Stockpiles 0.35g/t Au 46.4 0.51 763 2.0 0.65 42 -
-

-

48.4
0.52 805 1 645
Cowal2 Openpit 0.35g/t Au -
-

-

172.0
0.85 4,691 30.0 0.79 763 202.0 0.84 5,455 1 5,510
Cowal3 UG 1.5g/t Au -
-

-

21.7
2.50 1,741 13.1 2.37 998 34.8 2.45 2,738 1 2,685
Cowal1 Total 46.4 0.51 763 195.6 1.03 6,474 43.1 1.27 1,761 285.1 0.98 8,998 1 8,840
Ernest Henry4 Total 0.7% Cu 30.3 0.82 798 36.7 0.78 920 30.1 0.69 670 97.1 0.76 2,388 2 2,292
Mungari1 Stockpiles -
-

-

3.0
0.60 58 0.0 1.14 2 3.1 0.60 59
Mungari2 Openpit 0.29 – 0.33g/t Au -
-

-

75.6
0.97 2,347 28.3 1.02 926 103.9 0.98 3,273 3 2,758
Mungari3 UG 1.46 – 2.47g/t Au 1.5 4.63 219 8.6 4.34 1,199 8.7 3.98 1,120 18.8 4.20 2,538 3 2,580
Mungari1 Total 1.5 4.63 219 87.2 1.29 3,603 37.1 1.72 2,048 125.8 1.45 5,870 3 5,338
Red Lake1, 3 Total 2.5 – 3.3g/t Au -
-

-

32.4
6.89 7,174 22.7 6.10 4,456 55.1 6.56 11,631 4 12,342
Mt Rawdon1 Total 0.23g/t Au 5.9 0.30 57 3.7 0.65 77 - - - 9.5 0.44 134 5 478
Marsden5 Total ~0.2g/t Au -
-

-

119.8
0.27 1,031 3.1 0.22 22 123.0 0.27 1,053 6 1,053
Subtotal 84.0 0.68 1,837 475.4 1.26 19,279 136.2 2.05 8,957 695.7 1.34 30,073 30,343
Northparkes6 Openpit Various 7.3 1.05 246 2.4 1.2 93 0.1 1.16 6 9.8 1.09 345 7 -
Northparkes7 UG Various 192 0.19 1,153 172.5 0.15 832 46.5 0.19 280 410.9 0.17 2,264 8 -
Northparkes8 Total 199.3 0.22 1,398 174.9 0.16 925 46.6 0.19 285 420.8 0.19 2,609 -
Total 283.3 0.36 3,235 650.3 0.97 20,205 182.8 1.57 9,242 1116.4 0.91 32,682 30,343

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding.

“UG” denotes underground

  1. Includes stockpiles

  2. Open Pit Mineral Resource reporting shells were optimised using a gold price of $AU 2,500/oz. All material which meets or exceeds the cut-off grade within the developed pit shells is included in the reported Mineral Resource

  3. Underground Mineral Resource reporting shapes were developed using a gold price of $AU 2,500/oz; all material which falls within optimized mining shapes inclusive of internal waste or low grade is included in the reported Mineral Resource

  4. Ernest Henry Operations reported Mineral Resources are reported within an interpreted 0.7% Cu mineralised envelope which includes internal waste and low-grade material

  5. Marsden Mineral Resource is reported based on an NSR value calculation that considers mining and processing costs, metallurgical recoveries, royalties, transport and refining costs into account. The NSR produces a value cut-off (by block) that is approximately equivalent to a 0.2g/t gold cut-off

  6. Northparkes Open Pit Mineral Resource includes all material within designed pit shells above an economic cutoff grade; cut-off grades are 0.65g/t Au for E44 and 0.34% CuEq for E31 and have been calculated based on US$3.30/lb copper, US$1,350/oz gold and 0.73 AUD:USD conversion rate

  7. Northparkes Underground Mineral Resource metal price and exchange rate assumptions vary by project, reporting shapes were developed using price assumptions between US $1.69 - US$3/lb copper, US$660 - US$1350/oz gold and an $AUD:$USD conversion rate of 0.73 - 0.75. Northparkes underground cut-off grades are reported within 0.4% Cu grade shells with the exception of E22 using A$18NSR, E26 L2 using A$40NSR and MJH using A$25NSR

  8. The reported Mineral Resource shown for Northparkes is exclusive of Ore Reserves. The values reported reflect the 80% portion attributable to Evolution Mining

  9. Mineral Resources Competent Persons (CP’s) are: 1. Ben Reid; 2. Phil Micale; 3. Brad Daddow; 4. Alain Mouton; 5. Mathew Graham-Ellison; 6. James Biggam; 7. Geoff Smart; 8. David Richards

Evolution Mining Limited

15

==> picture [83 x 60] intentionally omitted <==

Table 4: Group Ore Reserve Statement for contained Gold as at 31 December 2023

Gold Gold Gold Total Reserve Total Reserve CP10 December
22
Reserves
Proved Probable
Project Type Cut-off Tonnes
(Mt)
Gold
Grade
(g/t)
Gold Gold Gold Gold
Metal
(koz)
Metal
(koz)
Tonnes
(Mt)
Grade
(g/t)
Gold Metal
(koz)
Tonnes
(Mt)
Grade
(g/t)
Gold Metal
(koz)
Cowal1 Stockpile 0.45g/t Au 40.4 0.52 681 2.0 0.65 42 42.4 0.53 723 1 575
Cowal2 Openpit 0.45g/t Au 73.6 1.00 2,376 73.6 1.00 2,376 1 2,585
Cowal3 UG 0.6 – 1.8g/t Au 18.7 2.27 1,364 18.7 2.27 1,364 2 1,169
Cowal1 Total 40.4 0.52 681 94.3 1.25 3,783 134.6 1.03 4,463 4,329
Ernest Henry4 UG 0.50 – 0.75% CuEq 24.6 0.62 491 49.9 0.36 573 74.5 0.44 1,064 3 495
Mungari1 Stockpile 0.45g/t Au 1.1 0.83 28 1.1 0.83 28 4
Mungari5 Openpit 0.39 – 0.56g/t Au 33.2 1.05 1,121 33.2 1.05 1,121 4 703
Mungari6 UG 2.18 – 3.63g/t Au 0.4 4.42 60 2.7 4.39 385 3.1 4.40 445 4 535
Mungari1 Total 0.4 4.42 60 36.9 1.29 1,534 37.4 1.33 1,595 1,238
Red Lake1,7 Total 2.5 – 4.1g/t Au 12.4 6.87 2,748 12.4 6.87 2,748 5 2,878
Mt Rawdon1 Openpit 0.32g/t Au 1.9 0.41 25 3.3 0.70 75 5.2 0.59 100 6 216
Marsden8 Openpit 0.3g/t Au 65.2 0.39 817 65.2 0.39 817 7 817
Subtotal 67.3 0.58 1,258 262.2 1.13 9,530 329.4 1.02 10,787 9,973
Northparkes1 Stockpile 0.38 – 0.58% CuEq 3.1 0.32 32 3.1 0.32 32 8 -
Northparkes9 Openpit 0.33 – 0.50% CuEq 8.4 0.50 134 1.3 0.30 12 9.7 0.47 147 8 -
Northparkes9 UG 0.38 – 0.58% CuEq 0.6 0.37 7 61.6 0.24 477 62.2 0.24 484 9,10 -
Northparkes1 Total 12.1 0.44 173 62.9 0.24 489 75.0 0.27 662 -
Total 79.4 0.56 1,430 324.9 0.96 10,019 404.3 0.88 11,449 9,973

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding

  1. Includes stockpiles

  2. Cowal Open Pit Ore Reserves are reported with respect to the declared Mineral Resource from December 2023. E42, E41, E46 and GRE Open Pit Ore Reserves are supported by the OPC Feasibility Study completed in June 2023 that demonstrates the proposed mine plans and schedules are economically viable. E46 and GR were optimised using a A$1,800/oz gold price assumption. E41 and E42 Stage I were optimised using gold price assumptions of $1,584/oz and $1,944/oz respectively. The Cowal Open Pit Ore Reserves are economically tested at up to A$2,650/oz and considers updated modifying factors and depletion.

  3. Cowal Underground Ore Reserve has been optimised using a A$1,800/oz price assumption, economically tested at up to A$2,650/oz and considers updated modifying factors and depletion. The Cowal Underground Ore Reserve includes development material at an incremental cut-off grade of 0.6g/t Au

  4. Ernest Henry reported Ore Reserve estimate is based on the December 2022 Mineral Resource detailed in the ASX Release titled “Annual Mineral Resources and Ore Reserves Statement” dated 16 Feb 2023 and available to view at www.evolutionmining.com.au . The applied flow model cut-off grades of 0.50% and 0.75% copper equivalent ('CuEq’) are determined through an economic evaluation process which considers the Net Smelter Return (NSR) and operating costs. The utilised copper equivalent equation is: CuEq = Cu + Au NSR/56.4 where; Au NSR = 38.5 * Au - 0.047

  5. Mungari Open Pit Ore Reserve cut-off varies from 0.39g/t Au to 0.65g/t Au; the weighted average cut-off is 0.50g/t Au. Gold prices between A$1,800 and A$2,400/ounce were used to calculate cut-off grades for the Open Pit Ore Reserve estimate

  6. Mungari Underground Ore Reserve cut-off varies from 2.80g/t Au to 3.63g/t Au; the weighted average cut-off is 3.19g/t Au. Gold price of A$1,800 was used to calculate cut-off grades for the Underground Ore Reserve estimate

  7. Red Lake Ore Reserve has been evaluated using an A$1800/oz price, except for the Upper Campbell and Upper Red Lake regions which have been re-reported this year using previous price assumptions of A$1600/oz. In 2024 a ‘Hill of Value’ study is scheduled to optimize the mine plan and cutoff criteria throughout the operation

  8. The Marsden Ore Reserve has been reported using a ‘Net Smelter Return’ (NSR) cut-off which takes into account ore haulage from Marsden to Cowal, ore processing costs at Cowal, general and administration costs, treatment and refining costs, concentrate costs, metallurgical recoveries, metal payabilities, metal prices, and royalties.The breakeven NSR value equates approximately to a 0.3g/t Au cutoff. The Ore Reserve estimate was developed using a A$1,350 per ounce gold price and a A$6000/t copper price

  9. Northparkes Ore Reserve is based on Pre-Feasibility & Feasibility studies completed at different times using differing price assumptions. Copper price assumptions vary between US$ 2.75-3.77/lb, Gold price assumptions vary between US$ 12501750/oz and $AUD:$USD exchange rates used were between 0.73-0.78. The values reported reflect the 80% portion attributable to Evolution Mining.

  10. Group Gold Ore Reserve Competent Person (CP) Notes refer to 1. Dean Basile (Mining One); 2. Ryan Bettcher; 3. Michael Corbett; 4. Blake Callinan; 5. Brad Armstrong; 6. Ben Young; 7. Glen Williamson; 8. Sam Ervin; 9. Mark Flynn; 10. Sarah Webster

Evolution Mining Limited

16

==> picture [83 x 60] intentionally omitted <==

Table 5: Group Mineral Resource Statement for contained Copper as at 31 December 2023

Copper Copper Copper Total Resource Total Resource Total Resource CP6

December 22
Resources
Measured Indicated Inferred
Project Type Cut-off Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)


Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)


Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)


Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Copper
Metal (kt)
Ernest Henry1 Total 0.7% Cu 30.3 1.39 422 36.7 1.33 487 30.1 1.18 354 97.1 1.30 1,263 1 1,207
Marsden2 Total ~0.2g/t Au -
-

-

119.8
0.46 553 3.1 0.24 7 123.0 0.46 560 2 560
Subtotal 30.3 1.39 422 156.5 0.66 1,040 33.2 1.09 362 220.1 0.83 1,823 1,767
Northparkes3 Openpit Various 7.3 0.16 12 2.4 0.03 1 0.1 0.03 0 9.8 0.12 12 3 -
Northparkes4 UG Various 192.0 0.58 1,116 172.5 0.54 923 46.5 0.57 265 410.9 0.56 2,304 4 -
Northparkes5 Total 199.3 0.57 1,128 174.9 0.53 924 46.6 0.57 265 420.8 0.55 2,316 -
Total 229.6 0.68 1,550 331.4 0.59 1,963 79.8 0.78 626 640.9 0.65 4,139 1,767

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding.

  1. Ernest Henry Operations reported Mineral Resources are reported within an interpreted 0.7% Cu mineralised envelope which includes internal waste and low-grade material

  2. Marsden Mineral Resource is reported based on an NSR value calculation that considers mining and processing costs, metallurgical recoveries, royalties, transport and refining costs into account. The NSR produces a value cut-off (by block) that is approximately equivalent to a 0.2g/t gold cut-off

  3. Northparkes Open Pit Mineral Resource includes all material within designed pit shells above an economic cutoff grade; cut-off grades are 0.65g/t Au for E44 and 0.34% CuEq for E31 based on US$3.30/lb copper, US$1,32/oz gold and 0.73 AUD:USD conversion rate

  4. Northparkes Underground Mineral Resource metal price and exchange rate assumptions vary by project, reporting shapes were developed using price assumptions of US $1.69 - US$3/lb copper, US$660 - US$1350/oz gold and an AUD:USD conversion rate of 0.73 -0.75. Northparkes underground cut-off grades are reported within 0.4% Cu grade shells with the exception of E22 using A$18NSR, E26 L2 using A$40NSR and MJH using A$25NSR

  5. The reported Mineral Resource shown for Northparkes is exclusive of Ore Reserves. The values reported reflect the 80% portion attributable to Evolution Mining

  6. Group Copper Mineral Resource Competent Person (CP) Notes refer to 1. Phil Micale; 2. James Biggam; 3. Geoff Smart; 4. David Richards

Evolution Mining Limited

17

==> picture [83 x 60] intentionally omitted <==

Table 6: Group Copper Ore Reserve Statement for contained Copper as at 31 December 2023

Copper Copper Copper Total Reserve Total Reserve CP5 December 22
Reserves
Proved Probable
Project Type Cut-off Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Tonnes
(Mt)
Copper
Grade (%)
Copper
Metal
(kt)
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Copper Metal
(kt)
Ernest Henry1 UG 0.50 – 0.75% CuEq 24.6 1.08 267 49.9 0.59 297 74.5 0.76 563 1 290
Marsden2 Openpit 0.3g/t Au -
-

-

65.2
0.57 371 65.2 0.57 371 2 371
Subtotal 24.6 1.08 267 115.1 0.58 668 139.7 0.67 934 661
Northparkes3 Stockpiles 0.33 – 0.55% CuEq 3.1 0.31 10 -
-

-

3.1
0.31 10 -
Northparkes4 Open pit 0.34 – 0.50% CuEq 8.4 0.35 30 1.3 0.31 4 9.7 0.35 33 3 -
Northparkes4 UG 0.38 – 0.58% CuEq 0.6 0.49 3 61.6 0.55 340 62.2 0.55 343 4,5 -
Northparkes Total 12.1 0.35 42 62.9 0.55 344 75 0.51 386 -
Total 36.7 0.84 309 177.9 0.57 1,011 214.7 0.62 1,320 661

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding

  1. Ernest Henry reported Ore Reserve estimate is based on the December 2022 Mineral Resource detailed in the ASX Release titled “Annual Mineral Resources and Ore Reserves Statement” dated 16 Feb 2023 and available to view at www.evolutionmining.com.au. The applied flow model cut-off grades of 0.50% and 0.75% copper equivalent ('CuEq’) are determined through an economic evaluation process which considers the Net Smelter Return (NSR) and operating costs. The utlised copper equivalent equation is: CuEq = Cu + Au NSR/56.4 where; Au NSR = 38.5 * Au - 0.047

  2. Marsden Ore Reserve is reported based on an NSR value calculation that considers ore haulage from Marsden to Cowal, ore processing costs at Cowal, general and administration costs, treatment and refining costs, concentrate costs, metallurgical recoveries, metal payabilities, metal prices, and royalties. The breakeven NSR value equates approximately to a 0.3g/t Au cutoff. The Ore Reserve estimate was developed using a $1,350 per ounce gold price and a $6000/t copper price

  3. Includes stockpiles

  4. Northparkes Ore Reserve is based on Pre-Feasibility & Feasibility studies completed at different times using differing price assumptions. Copper price assumptions vary between US$ 2.75-3.77/lb, Gold price assumptions vary between US$ 1250-1750/oz and $AUD:$USD exchange rates used were between 0.73-0.78. The values reported reflect the 80% portion attributable to Evolution Mining

  5. Group Copper Ore Reserve Competent Person (CP) Notes refer to 1. Michael Corbett; 2. Glen Williamson; 3. Sam Ervin; 4. Mark Flynn; 5. Sarah Webster

Evolution Mining Limited

18

==> picture [83 x 59] intentionally omitted <==

MATERIAL INFORMATION SUMMARIES

The Cowal, Ernest Henry, Mungari, Red Lake, Mt Rawdon, Marsden and Northparkes Mineral Resource and Ore Reserve estimates have been reported in accordance with the 2012 Edition of the ‘Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves’ (the JORC Code 2012) and the ASX Listing Rules.

Material Information Summaries are provided for the Ernest Henry, Mungari, Red Lake and Northparkes Mineral Resource and Ore Reserve estimates pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 is presented in Appendix 1.

Overview - Ernest Henry Mineral Resource Statement

The Ernest Henry December 31, 2023 Mineral Resource is estimated at 97.1 million tonnes at 1.30% copper and 0.76g/t gold (inclusive of Ore Reserves but excludes mined areas and areas sterilised by mining activities) (Table 7). The Mineral Resource has been reported within an interpreted 0.7% copper grade shell and includes any zones of internal waste or low-grade material which cannot be selectively mined by the chosen sub-level caving mining method used at the Ernest Henry mine. All material reported within the Mineral Resource is considered by the Competent Person (CP) to meet reasonable prospects for eventual economic extraction, taking into account the proposed mining technique and historical metallurgical recoveries. The Mineral Resource update is current as of 31 December 2023 and takes into account all mining activities undertaken to this date.

Table 7: Ernest Henry Mineral Resource as at 31 December 2023

Dec 2023 Total Dec 2022
Measured Indicated Inferred
Resource Resource
Tonnes (Mt) 30.3 36.7 30.1 97.1 94.8
Copper grade (%) 1.39 1.33 1.18 1.30 1.27
Copper tonnes (kt) 422 487 354 1,263 1,207
Gold grade (g/t) 0.82 0.78 0.69 0.76 0.75
Gold ounces (koz) 798 920 670 2,388 2,292

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding The Mineral Resource estimate is reported within an interpreted 0.7% Cu mineralised envelope. Ernest Henry Mineral Resource Competent Person is Phillip Micale.

The December 31, 2023 reported Mineral Resource represents a net increase of 2.3Mt (Figure 10). Complimentary to this is an increase in estimated copper grade (from 1.27% to 1.30%) and estimated gold grade 0.75g/t to 0.76g/t. The increase in tonnes and grade has resulted in a net increase in the reported contained copper content by 5% or 56kt to 1,263kt (Figure 11) and an increase in the reported contained gold ounces by ~4% or 96koz to 2,388koz (Figure 12).

Changes in the reported Mineral Resource are due to new drilling at depth and laterally. Deeper drilling has improved the confidence in Mineral Resource classification and drilling laterally to the north has resulted in an increase in mineralisation volume through refined geological interpretation. Infill drilling into the Bert orebody has also improved confidence in Mineral Resource classification. Including sterilisation, a total of 6.9 million tonnes were depleted from the Mineral Resource through mining activities since December 2022 which resulted in depleting 132koz of gold and 77kt of copper.

Evolution Mining Limited

19

==> picture [83 x 59] intentionally omitted <==

==> picture [488 x 190] intentionally omitted <==

Figure 10: EHOWaterfall chart illustrating the change in Mineral Resource tonnes from December 2022 to December 2023

==> picture [488 x 197] intentionally omitted <==

Figure 11: Waterfall chart demonstrating the change in Mineral Resource contained copper by category from December 2022 to December 2023

==> picture [488 x 197] intentionally omitted <==

Figure 12: Waterfall chart demonstrating the change in Mineral Resource contained gold by category from December 2022 to December 2023

Evolution Mining Limited

20

==> picture [83 x 59] intentionally omitted <==

Overview - Ernest Henry Ore Reserve Statement

The December 2023 Ernest Henry Ore Reserve estimate is 74.5Mt at 0.76% copper and 0.45g/t gold, for 563kt and 1,064koz. This represents increases of 273 kt copper and 569koz gold compared to the December 2022 Ore Reserve estimate of 34.3Mt at 0.85% copper 0.45g/t gold and, for 290kt and 495koz.

The largest increase is due to the inclusion of the Mine Extension below the 1125 Level, following completion of a supporting Pre-feasibility Study (PFS) in June 2023. Table 9 and Figure 13 – Figure 15 demonstrate the changes from December 2022 to December 2023.

Table 8: Ernest Henry Ore Reserve as at 31 December 2023

December 2023
Proved
December 2023
Probable
December 2023
Total
December 2022
Total
Tonnes (Mt) 24.6 49.9 74.5 34.3
Copper grade (%) 1.08 0.59 0.76 0.85
Copper metal (kt) 267 297 563 290
Gold grade (g/t) 0.62 0.36 0.44 0.45
Gold metal (koz) 491 573 1,064 495

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding. The Ore Reserve estimate is based on the December 2022 Mineral Resource detailed in the ASX release titled “Annual Mineral Resources and Ore Reserves Statement” dated 16 Feb 2023 and available to view at www.evolutionmining.com.au. Level footprints are designed to align with Domain 7 (0.70% Cu), which defines the Mineral Resource, while also maintaining a geometry amendable to caving. The cut-off (shut-off) grades of 0.75% CuEq and 0.50% CuEq, as applied in the cave flow model software, are determined through an economic evaluation process.

The utlised copper equivalent equation is: CuEq = Cu + Au NSR/56.4 where; Au NSR = 38.5 * Au - 0.04 Ernest Henry Ore Reserve Competent Person is Michael Corbett

Table 9: Comparison of December 2022 and December 2023 Ernest Henry Ore Reserve estimates

Estimate Proved Probable Total Ore Reserves Total Ore Reserves Total Ore Reserves
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal (kt)
18.2 1.07 196 16.1 0.59 94 34.3 0.85 290
24.6 1.08 267 49.9 0.59 297 74.5 0.76 563
Absolute Change 6.4 0.01 71 33.8 0.01 202 40.3 -0.09 273
Relative Change 35% 1% 36% 211% 1% 215% 117% -11% 94%
Estimate Proved Probable Total Ore Reserves
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
18.2 0.57 336 16.1 0.31 159 34.3 0.45 495
24.6 0.62 491 49.9 0.36 573 74.5 0.44 1,064
Absolute Change 6.4 0.05 156 33.8 0.05 414 40.3 -0.01 569
Relative Change 35% 9% 46% 211% 16% 260% 117% -2% 115%

Evolution Mining Limited

21

==> picture [83 x 59] intentionally omitted <==

Table 10: Ernest Henry Ore Reserve as at 31 December 2023 – breakdown by region

Copper Copper Proved Probable Total Ore Reserve Total Ore Reserve Total Ore Reserve
Project Cut-off
(flow
model)
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Tonnes
(Mt)
Copper
Grade
(%)
Copper
Metal
(kt)
Ernest Henry
(Base)
0.75
CuEq
15.7 1.07 168 14.2 0.58 82 29.9 0.84 250
Ernest Henry
(Extension)
0.50
CuEq
9.0 1.10 99 35.7 0.60 214 44.6 0.70 313
Total 24.6 1.08 267 49.9 0.59 297 74.5 0.76 563
Gold Proved Probable Total Ore Reserve
Project Cut-off
(flow
model)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Ernest
Henry
(Base)
0.75
CuEq
15.7 0.57 288 14.2 0.30 139 29.9 0.44 427
Ernest
Henry
(Extension)
0.50
CuEq
9.0 0.70 203 35.7 0.38 434 44.6 0.44 637
Total 24.6 0.62 491 49.9 0.36 573 74.5 0.44 1,064

==> picture [488 x 271] intentionally omitted <==

Figure 13: Waterfall chart illustrating the change in Ernest Henry Ore Reserve tonnage from December 2022 to December 2023

Evolution Mining Limited

22

==> picture [83 x 59] intentionally omitted <==

==> picture [488 x 240] intentionally omitted <==

Figure 14: Waterfall chart illustrating the change in Ernest Henry Ore Reserve – contained copper from December 2022 to December 2023

==> picture [488 x 272] intentionally omitted <==

Figure 15: Waterfall chart illustrating the change in Ernest Henry Ore Reserve – contained gold from December 2022 to December 2023

Evolution Mining Limited

23

==> picture [83 x 59] intentionally omitted <==

Ernest Henry Mineral Resource Material Information Summary

A Material Information Summary is provided for the Mineral Resource at Ernest Henry Operation (EHO) pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 is presented in Appendix A1.

Material Assumptions for Mineral Resources

The Ernest Henry Mineral Resource estimate is defined within an interpreted 0.7% Cu grade shell. Assigned mining and processing costs and metallurgical recoveries used in the development of underground Mineral Resource reporting shapes are supported by current mining data and metallurgical recoveries. The EHO underground mine uses a sub-level caving (SLC) mining technique.

Property Description, Location and Tenement holding

Ernest Henry operation (EHO), owned and operated by Evolution, is located 38km north-east of Cloncurry (Figure 16), 150km east of Mount Isa and 750km west of Townsville, in north-west Queensland, Australia.

==> picture [319 x 165] intentionally omitted <==

Figure 16: Location map of Ernest Henry mine

The Ernest Henry operations extend across eight (8) current mining leases (Table 11 and Figure 17) all owned by Ernest Henry Mining Pty Ltd. The details of these leases are summarised and illustrated below.

Table 11: Summary table of Ernest Henry mining leases


Lease

Ownership
Expiry Date
ML2671 Ernest HenryMiningPtyLtd 100% 30/11/2025
ML90041 Ernest HenryMiningPtyLtd 100% 30/11/2037
ML90072 Ernest HenryMiningPtyLtd 100% 30/11/2025
ML90085 Ernest HenryMiningPtyLtd 100% 31/03/2026
ML90100 Ernest HenryMiningPtyLtd 100% 31/05/2026
ML90107 Ernest HenryMiningPtyLtd 100% 31/08/2026
ML90116 Ernest HenryMiningPtyLtd 100% 30/09/2026
ML90075 Ernest HenryMiningPtyLtd 100% 30/11/2025

Evolution Mining Limited

24

==> picture [83 x 59] intentionally omitted <==

==> picture [449 x 300] intentionally omitted <==

Figure 17: Aerial photo with Mining Lease boundaries overlain

Geology and Geological Interpretation

The Ernest Henry copper-gold deposit is hosted in a hydrothermal breccia pipe plunging at roughly 45 degrees to the south, bounded between two shear zones. At depth, the orientation of shearing appears to be having a greater effect on the orebody and the primary mineralised lenses are becoming more elongate northsouth, separating into discrete pods and lenses.

The Ernest Henry deposit is hosted entirely in felsic intermediate metavolcanic rocks, within a unit of the Mount Fort Constantine Volcanics, circa 1800 to 1750 million years. Regionally these lithologies lie adjacent to a large meta-diorite body which traverses the deposit from the south-west to the north-east. Timing of mineralisation at the Ernest Henry deposit is commonly accepted by many workers as occurring between regional D3 through to D4 deformation events circa 1530 to 1500 million years.

Mineralisation is associated with a matrix supported hydrothermal breccia that is enveloped by crackle veined potassium feldspar altered meta-volcanic rocks. The matrix is largely composed of magnetite, quartz, biotite, chalcopyrite, pyrite, fluorite, gold, molybdenite, uraniferous minerals and potassic feldspar. Other gangue minerals in the matrix consist of chlorite, calcite, dolomite, barite, apatite, muscovite, garnet, scapolite, sphene, rutile and tourmaline.

Chalcopyrite, the only copper mineral observed within the primary orebody, and pyrite are the only significant sulphide minerals within the orebody. Chalcopyrite is fine to medium grained, anhedral and commonly occurs as disseminated grains attached to magnetite and/or pyrite. Chalcopyrite and pyrite are contained mostly within the breccia matrix, comprising 1% to 20% of the matrix volume.

Gold occurs about 98% of the time in the form of native gold-electrum (65-95wt% Au), other minor contributions come from sylvanite, auriferous cobaltite, pyrite and chalcopyrite. It is believed that gold precipitation was closely associated with, but preceded some of the chalcopyrite deposition, as indicated by the lower gold and copper ratios of late-stage chalcopyrite rich veins. Although the Ernest Henry orebody contains arsenic, fluorine and uranium minerals, they typically fall below product thresholds, and aren’t considered deleterious.

Both clast and matrix supported breccias typically coincide with copper grades above 0.7% Cu. Felsic altered, clast supported hydrothermal breccia exists as a halo around the main +0.7% Cu zone which also typically hosts gold grades >0.5g/t Au. Zones of elevated gold grades (>1g/t, Au) are coincident with a magnetite /

Evolution Mining Limited

25

==> picture [83 x 59] intentionally omitted <==

carbonate rich structure or structural zone logged as secondary generation breccia which are constrained within the interpreted 0.7% Cu zone.

A total of five copper mineralisation domains and six gold mineralisation domains were developed for the Ernest Henry deposit.

Drilling and Survey Techniques

Drilling at Ernest Henry has been completed between 1980 and 2023. Diamond drill holes (HQ, NQ2 and NQ size) are the primary source of geological and grade data informing the grade estimate. Reverse Circulation (RC) and Air Core (AC) drilling was also used to delineate oxide areas of the resource which are now depleted. Core has been oriented using a variety of techniques in line with standard industry practice of the time. Core recovery through the deposit is excellent (>99.5%).

Collar coordinates were picked up by site surveyors using a Leica total station survey instrument and reported in MGA94 Zone 54 grid. A variety of downhole survey methods have been utilised in the underground resource, however 95% of the diamond drill holes have been surveyed using a recognised high quality gyroscopic instrument recording down hole survey data in 3m intervals.

Data, Data spacing and distribution

A total of 1,239 drill holes with 122,281 intervals containing assays were extracted from acQuire for the December 2023 Mineral Resource estimate. Of these, 969 drill holes contain copper and gold assays. This is an increase of 70 new drill holes used for geological interpretation and grade estimation in the December 2023 model compared to the December 2022 model. A total of 20 drill holes have been excluded from use in both domain generation and grade estimation in the December 2023 resource model update due to issues associated with the quality of either assay or survey data.

An additional 21,002 samples are included in the updated 31 December 2023 Mineral Resource estimate compared to the 31 December 2022 Mineral Resource estimate. Of the 70 new drillholes, 16 were drilled inside the FS area (below 1125 mRL) and the remaining 54 holes were targeting the current ‘Life of Mine’ (LOM) area above 1125mRL and Bert.

Initial resource definition drillhole programs are designed to achieve a nominal mineralisation intersection spacing of 60m centres. Drillholes are designed and drilled to intersect perpendicular to mineralisation and shear zones bounding mineralisation wherever possible. Subsequent to the initial phase of resource definition drilling, infill drilling is completed to nominal mineralisation intersection spacing of between 30m and 40m centres.

Sampling and Sub-sampling

Following logging to a standardised geological legend, each core sample is sawn in half with a diamond saw. One half is placed back in the core tray with the other submitted to ALS laboratory in Brisbane. Samples are delineated using geological boundaries and are typically between 0.3m and 2.0m.

Samples undergo further preparation and analysis by an external laboratory, involving crushing to 2 mm, riffle splitting and pulverising using an LM5 mill to 85% passing 75 microns. Crushing and grinding equipment are cleaned using compressed air and brushes between each sample and blanks are inserted at a rate of 1:15 samples in mineralised core and 1:30 samples in waste zones to ensure sample contamination is not occurring. Following the pulverisation of the sample a 0.4g sub-sample is prepared for base metal analysis via aqua regia digestion and a 120g sub-sample is taken and sent to ALS Perth, where a 50g sub-sample is taken for analysis via fire assay.

Sample Analysis Methods

Following sample preparation, a 50g sub-sample is analysed for gold (Au) using a fire assay method at ALS Perth. Multi-element analysis for copper (Cu), silver (Ag), cobalt (Co), iron (Fe), molybdenum (Mo), nickel (Ni), phosphorous (P), sulphur (S), uranium (U) and arsenic (As) is completed on a 0.4g sample using aqua regia digestion with an AES finish at ALS Brisbane’s laboratory. Drill core samples are not routinely analysed for fluorite. Concentrate samples however are analysed for all potentially deleterious elements.

Historic quality assurance (QA) procedures include the use of six certified standards as well as field duplicates inserted at 1:25 ratio for all sample batches sent to the ALS laboratory. Pulverised blank samples have been used by Ernest Henry for QA from 2017. A coarse crush blank sample has been used from April 2022.

Evolution Mining Limited

26

==> picture [83 x 59] intentionally omitted <==

Density

The method of density determination in the current model follows the same process outlined in the 2018/19, 2020 and 2021 models. Since the discovery of Ernest Henry, an extensive database of in-situ density measurements has been collected using the Archimedes water displacement principal formula from wet and dry sample weights.

Density measurements are used in conjunction with an elemental assay analysis to generate a stoichiometric regression formula that is applied to every sample and subsequently used in resource estimation.

Quality Assurance and Quality Control

EHO currently uses nine matrix matched CRMs and a pulverised blank and coarse crush blank sample to monitor preparation and assaying processes. CRMs were inserted at a rate of 1 in every 15 samples while blanks were inserted at 1 in every 15 samples within mineralised samples and 1 in every 30 samples in waste zones. Field duplicates inserted at 1 in every 15 samples and crush and pulp duplicates inserted at 1 in every 25 samples were used to monitor the deposit variability and analytical precision. Historic field duplicates were inserted at 1 in every 25 samples. ALS laboratory insert QA samples during the analytical process in line with their internal protocols.

The Competent Person has completed a review of the quality control (QC) results received between December 2022 and December 2023 and considers that the new data utilised to complete the estimate is accurate and precise and has been collected and stored using industry standard practices. The site also has a long history of production and reconciliation against Mineral Resource models which provides further confidence in the quality of analytical data.

Estimation Methodology

Downhole composites are completed in Datamine within each of the interpreted domains. Samples are composited to a 2m sample length, in line with the dominant sample interval (83% of mineralised samples).

Variograms for Cu, Au, Ag and density were completed in Snowden’s Supervisor software and validated in 3D against the sample dataset.

Ordinary kriging (OK) was used to estimate Cu%, Au g/t, Ag g/t and density (t/m3) into 10 mE by 10 mN by 10 mRL parent blocks. The block size was selected based on drillhole spacing, the geometry of the mineralisation and the selective mining method. Results of the Quantitative Kriging Neighbourhood Analysis (QKNA) also substantiated the block size selection and sample neighbourhood for estimation. Parent blocks were reduced (sub-blocked) as low as 2 mE by 2 mN by 2 mRL along domain boundaries to honour interpreted domain volumes.

Estimation Validation

The grade estimates were validated by comparing mean composited grades to mean estimated grades (estimation search pass 1 only), grade trends in easting, northing and elevation slices (swath plots), visual check of estimated grades against composited grades, and debugging the estimation process. Statistical comparisons between mean estimated grades and mean composited grades for each domain are within ±5%. Swath plots of mean estimated grades against mean composite grades within 20m wide easting, northing and elevation slices shows composite grade trends have been closely replicated in the model. Mine to mill reconciliation data gathered over the past 10 years indicates that estimated tonnes and grade fall within a ±5% tolerance against what is produced in practice.

Resource Classification

The classifications have been made in accordance with the JORC 2012 guidelines and are based upon average distance to nearest samples, kriging output metrics (kriging efficiency and slope of regression), confidence in defined mineralisation boundaries, the number of holes used during interpolation, grade variations between holes and hole orientation. Robust Resource classification wireframes were constructed by the Competent Person to delineate the Mineral Resource Classification codes assigned to the block model. Visual checks in section, plan and long section were undertaken to ensure resource classification coding was appropriate and was completed without error.

The Ernest Henry Mineral Resource has been classified using the following general criteria:

Evolution Mining Limited

27

==> picture [83 x 59] intentionally omitted <==

  • Measured: Drill data used for estimation not exceeding 30-40m spacing and including full drill coverage on adjacent sections to the north and south. Estimated with a full complement of composites selected in the kriging process (32)

  • Indicated: Drill data used for estimation between 40–60m, estimated with a full complement of composites selected in the kriging process (32)

  • Inferred: Drill data used for estimation between 60-100m within the 0.1% or 0.7% Cu domains

Other general conditions taken into consideration in the classification are as follows:

  • Kriging Efficiency (KE)

  • Continuity of grades between drill holes

  • Confidence in the geological interpretation of mineralisation boundary

  • Proximity of blocks to the edge of the domain boundaries

The Mineral Resource estimate and Mineral Resource classification categories appropriately reflect the views of the Competent Person and have been reported in accordance with the JORC Code (2012). Mineral Resource classification solids have been developed into the surrounding 0.1% Cu grade shell to appropriately account for the confidence in the grade and tonnage estimate of this material. A component of this material will be mined as part of the sub-level cave and is included within the reported Ore Reserve.

Mineral Resource Reporting and assigned Cut-off criteria

Whilst no cut-off grade has been explicitly applied for reporting the December 2023 Mineral Resource, only blocks within the interpreted 0.7% Cu grade shell (Domain 7 and Domain 77) were reported. The sub-level caving mining method mines all material including any internal waste material within the designed sub-level cave boundary. This mining method does not allow blocks to be selectively mined. Consequently, all material within the interpreted 0.7% Cu grade shell including any zones of internal waste have been included and reported within the Mineral Resource estimate. This reporting process ensures all material reported within the Mineral Resource meets reasonable prospect of economic extraction and international reporting code standards. Prior to the reporting of the Mineral Resource, account was made for mining depletion and sterilisation as detailed below.

Depletion

Previously mined areas are omitted from the reported Mineral Resource. Underground development drives are accurately surveyed, with associated tonnes and grade removed from the reported Mineral Resource. Depletion resulting from production activities is estimated using the calibrated cave flow model. The model includes actual cave extraction to 31 December 2023.

Sterilisation

With respect to Mineral Resource reporting, account is also made for sterilisation (ore loss whereby Mineral Resource material is deemed unrecoverable due to previous mining activities). As sterilisation is not able to be directly calculated, the quantity of ‘external’ material (originating from outside of Domain 7 – interpreted 0.7% Cu shell) recovered through production activities is used as a proxy for sterilisation. The quantity of external material (waste) reporting to draw points is considered to have displaced (sterilised) a comparable quantity of the Mineral Resource from within Domain 7. This sterilised Domain 7 material is classified into Measured, Indicated and Inferred components by interrogating the blasted production volume and subsequently removing the reported percentages to each resource category. This method is appropriate where the total drawn tonnes are comparable to the total blasted tonnes, as is the case for Ernest Henry to date.

The Mineral Resource has been reported within the 0.7% Cu grade shell after exclusion of depletion and accounting for sterilisation as described above. The 0.7% Cu grade is roughly aligned with a $50 net smelter return (NSR) value and meets the reasonable prospects for eventual economic extraction requirement for reporting a Mineral Resource in accordance with the JORC Code.

Audits or reviews

Evolution Mining has a standard validation process which includes internal technical peer review and external audits. Internal peer reviews of the reported Mineral Resource and Ore Reserve are undertaken annually by Evolution’s Transformation & Effectiveness / Technical Services team. Internal corporate governance systems and processes are in place to ensure all required supporting data and documentation is securely stored for future reference.

Evolution Mining Limited

28

==> picture [83 x 59] intentionally omitted <==

In addition to the internal peer review process undertaken by Evolution, an external audit of the reported Mineral Resource & Ore Reserve is undertaken on a 3-year rolling basis across all of Evolution’s assets. The most recent review of the EHO Mineral Resource estimate was completed by SRK in August 2023. This review endorsed the estimate while also recommending minor potential improvements for the next estimate.

Evolution Mining Limited

29

==> picture [83 x 59] intentionally omitted <==

Ernest Henry Underground Ore Reserve Material Information Summary

Material Assumptions for conversion to Ore Reserves

The Ore Reserve estimate is based on the December 2022 Mineral Resource, as detailed in the ASX release titled ‘Annual Mineral Resources and Ore Reserves Statement’ dated 16 February 2023.

The Ernest Henry (Base) Ore Reserve estimate is comparable to the December 2022 Ore Reserve estimate. The only changes relate to mining depletion and application of the December 2022 Mineral Resource in place of the June 2022 Mineral Resource. All other inputs and assumptions are transferable.

The Ernest Henry (Extension) Ore Reserve estimate is derived from the Mine Extension Pre-feasibility Study (PFS), completed in June 2023. Though many of the underlying inputs and assumptions are shared between the PFS and Ore Reserve, there are material differences. The most significant differentiator between the mine plans is the draw strategy applied to the production rings on the 1100 – 0750 Levels. The production component of the Ernest Henry (Extension) Ore Reserve estimate is 37.4Mt at 0.76% copper and 0.48g/t gold. The same mining block delivers an inventory of 48.8Mt at 0.70% copper and 0.44g/t gold in the PFS.

Figure 18 provides a visual representation of the Base and Extension components of the Ore Reserve with respect to completed mining and available Mineral Resource.

==> picture [398 x 294] intentionally omitted <==

Figure 18: Isometric view looking northwest, showing completed mining (grey), Base Ore Reserve design (gold), Extension Ore Reserve design (brown) and available December 2022 Mineral Resource (orange)

Cut-off parameters

The design cut-off used to generate the SLC footprint relates to geological Domain 7, which defines the Mineral Resource. The boundary of Domain 7 is 0.70% copper, typically 0.85 – 0.95% copper equivalent (CuEq), depending on the copper to gold ratio and economic assumptions. Though Domain 7 has a relatively consistent geometry in most areas, this diminishes slightly at depth. To maintain a footprint amendable to sublevel caving, the Mine Extension levels (1100 – 0750) have been designed to a 0.70% CuEq boundary. Applying a 0.70% CuEq cut-off in place of 0.70% Cu will have negligible impact to the footprint in most areas but does generate a more appropriate footprint where lower grade embayments interrupt the continuity of Domain 7.

The economic shut-off grade applied in the flow model software, Power Geotechnical Cellular Automata (PGCA), is determined through an economic evaluation process. This process is considerate of Net Smelter

Evolution Mining Limited

30

==> picture [83 x 59] intentionally omitted <==

Return (NSR) and a range of business objectives. Flow modelling of shut-off grades between 0.50% and 0.90% CuEq were assessed, with a values of 0.75% and 0.50% CuEq selected for the Base and Extension areas, respectively.

The copper equivalent equation utilised for the flow model process is:

CuEq (%) = Cu (%) + Au (g/t) NSR (A$)/56.4 where; Au NSR (A$) = 38.5 * Au (g/t) - 0.04

Mining factors or assumptions

Pre-feasibility (2006) and Feasibility (2008) studies demonstrated that sub-level caving was the most appropriate mining method for the original Ernest Henry underground operation. This method is well suited to the orebody geometry, grade and rock mass properties. Recent Concept (2021) and Pre-feasibility (2023) studies for the Mine Extension indicate that continuation of the sub-level cave is the most appropriate option for production below the existing mine.

Geotechnical engineering assessments have shown that the rock mass is amenable to caving where appropriate design criteria are utilised. Numerical modelling of the planned cave and mine workings is conducted at regular intervals and calibrated against real world observations. To date, cave growth has been tracked by seismic monitoring, seismic tomography, time domain reflectometry (TDR) systems and regular laser scanning of the surface expression. These systems will be expanded to ensure adequate monitoring of the cave as it progresses into the lower Mine Extension area. A budget of $4M has been allocated and included in the PFS financial model. Effective cave monitoring and management will be essential as the mine progresses deeper, where the orebody geometry becomes less favourable for caving. Modelling conducted as part of the PFS indicates that the preliminary Mine Extension geometry may experience inconsistent caving, potentially forming an air gap if appropriate controls are not implemented. Further assessment will be undertaken as part of the Feasibility Study (FS) to better understand likely cave propagation and the most effective cave management strategies. The mitigants applied as part of the Ernest Henry (Extension) Ore Reserve mining plan include a more conservative draw strategy and schedule than that of the PFS, and a $50M allowance for implementation of control measures such as footprint expansion or pre-conditioning. This allowance combined with the generally conservative assumptions applied in the estimation process, and classification of the Ore Reserve, are considered by the Competent Person to appropriately convey and account for the caveability risk.

The mine design incorporates 25m sub-level spacing, 15m drive spacing (centre to centre), 6m wide crosscuts and a standard 8-hole ring pattern with 2.6m burden. These design parameters are in line with benchmarked operations and have proven to be effective during the previous decade of Ernest Henry underground production. Optimisation of these design parameters will be completed during the FS, with changed mining conditions at depth likely to require minor adjustments, and opportunities to improve mining efficiency.

Sub-level caving is a bulk mining method with limited selectivity, where dilution must be accepted in order to recover blasted ore. Dilution from production activities is quantified through cave flow modelling and is included in the reported Ore Reserve along with supporting economic evaluations. No recovery or dilution factors have been applied to the Ernest Henry (Base) Ore Reserve estimate. For the production component of the Ernest Henry (Extension) Ore Reserve estimate, a 0.98 grade factor has been applied. This factor reflects the flow modelling for the Mine Extension having been completed for a Pre-feasibility Study rather than operational execution.

Assumptions applied for the Ernest Henry (Base) flow model have been derived through the routine calibration process conducted on site and include:

  • Hanging wall failure delay: 50m undercut

  • Dilution flow rate: 180% of blasted material

  • Draw width at 1,000m[3] : 10.0m

The 50m undercut value has been derived with consideration of the site seismic data system, numerical modelling, real world observation and flow model calibration. While this measure will be variable depending on the rock mass and mining geometry, a value of 50m provides a reasonable match on a mine scale. Having dilution flow more readily than blasted material has been determined to be appropriate through the flow model calibration process, reflecting fines generation within the cave and the relative mobility of different rock types. A draw width of 10.0m at 1,000m[3] drawn has been selected based on the findings of marker trials conducted on site and calibration of the flow model against reconciled actuals.

Evolution Mining Limited

31

==> picture [83 x 59] intentionally omitted <==

The Ernest Henry (Extension) flow model was derived using a draw width of 6.2m at 1,000m[3] drawn in place of the settings described above. This value was derived through a calibration process completed as part of the PFS and yields comparable results to the combination of settings applied to the Ernest Henry (Base) flow model at a mine or level scale. At a ring scale, differences are observed but this is an expected outcome given the divergent applications of the two models. The Competent Person considers the methods used to derive the production component of the Ernest Henry (Extension) Ore Reserve estimate to be appropriate.

Blasted rock from development activities reports to the same materials handling system as production ore from the cave. The development material is included in the mine plan, classified by means of block model interrogation and converted to Ore Reserve in the same manner as production material.

Metallurgical factors or assumptions

Processing has been conducted on site for more than 20 years, delivering consistent performance over that period. Comminution is achieved using both SAG and ball mills, with throughput tailored to mine output. Copper and gold are recovered using a floatation process and are contained within the resulting copper concentrate. This concentrate is transported by road to Glencore’s smelting facility in Mount Isa.

Bulk sampling is conducted on a routine basis to confirm plant performance.

The Ore Reserve estimate is reported ‘as mined’ and does not include metallurgical recovery factors. Metallurgical recovery is accounted for by the NSR calculations, which support the selected flow model cut-off grades of 0.75% and 0.50% CuEq.

Environmental and social factors or assumptions

Ernest Henry has been in operation for several decades and fulfils relevant statutory and social obligations. This includes but is not limited to:

  • Completion of environmental studies regarding flora and fauna, hydrogeological conditions, waste rock characterisation and cultural heritage

  • Deed and access agreements have been established with neighbouring landholders

  • The mine has an Environmental Management Plan, with approvals for mine production, waste rock dumps, tailings storage facilities and site clearing having been granted

  • An Environmental Authority (EA) has been granted by the regulator

  • All other permits for current mining operations have been granted

The existing EA will require amendment to facilitate extraction of the stated Ore Reserve. Both the Ernest Henry (Base) Ore Reserve and Ernest Henry (Extension) Ore Reserve will be subject to further approvals from the Queensland Department of Environment and Science (DES). Current guidance from DES does not indicate that the mining plan supporting the stated Ore Reserve will be impacted by the amendment approval process.

Ernest Henry routinely engages with the local and broader community through the support of events and charitable organisations, site visitation days for the general public, a focus on residential employment and working with local businesses. These positive engagement practises contribute to maintaining a social license to operate.

The operation is spread across multiple mining leases, which are listed in Table 11 and illustrated by Figure 17. Multiple leases are due to expire before extraction of the Ore Reserve is complete. Both Ernest Henry and Evolution Group teams are working proactively to ensure the required lease renewals occur in a timely manner and do not impact the production profile.

Infrastructure

The surface infrastructure required to support mining of the reported Ore Reserve is in place. This includes items such as sealed roads for site access, utilities, processing plant, tailings storage facility (TSF), offices, workshops and stores. Major underground infrastructure required to extract the Ernest Henry (Base) Ore Reserve is in place, with mine construction having been completed in 2014.

For the Ernest Henry (Extension) Ore Reserve to be extracted, additional major infrastructure will be required. This includes but is not limited to upgrades for the ventilation and dewatering systems, primary access (decline), emergency egress, workshops, stores, extended materials handling system, electrical and communication systems. Surface works including Tailing Storage Facility (TSF) raises will also be required as part of the mine life extension and have been demonstrated as technically feasible through the PFS.

Evolution Mining Limited

32

==> picture [83 x 59] intentionally omitted <==

Infrastructure required to facilitate extraction of the Mine Extension has been designed and costed as part of the PFS.

Access to the underground mine is via an in-pit portal and decline, with additional means of egress via a ladderway system and the hoisting shaft.

Costs

Estimates for major capital items that facilitate extraction of the Ore Reserve have been informed by supplier quotes where available, industry benchmarks and previous site experience with similar projects. An appropriate contingency for capital requirements associated with the Mine Extension has been utilised in the financial evaluation.

Sustaining capital is forecast annually as part of the Budget and Life of Mine (LOM) planning cycle, reflecting actual performance and the mine schedule. As the basis of the Mine Extension is a continuation of the current mining method, these costs are well understood.

Operating costs are calculated using a first principles approach and reconciled with actual costs on a monthly basis and as part of annual financial reviews. The availability of reliable historic data for the site provides a robust basis for estimating the operating costs. Suitable allowances have been made for additional costs incurred as the production front moves deeper.

Transport, treatment, refining and royalty charges are included in financial models and are based on smelting at Glencore’s facilities in Mount Isa. A long-term sales contract is in place between Evolution and Glencore, supporting the applied cost assumptions.

Revenue

Net Smelter Return for the reported Ore Reserve has been derived using the Ernest Henry concentrate sales model. The model accounts for concentrate specification, transport cost, royalty payment, treatment and refining charges. Queensland Government Royalty payments of 4% for copper (after a 20% discount for smelting in Queensland) and 5% for gold and silver are included in revenue calculations.

Revenue generation for the Ore Reserve was assessed with four different commodity price decks, as detailed in Table 12 Table 12 . The utilised price range was derived from Evolution Mining’s December 2022 Mineral Resource and Ore Reserve guidance. The Ernest Henry (Base) Ore Reserve estimate was shown to generate a positive Net Present Value (NPV) with price deck 2, 3 or 4 applied. The Ernest Henry (Extension) Ore Reserve estimate generated a positive NPV with price deck 4 applied. The total Ernest Henry Ore Reserve, with the Base and Extension components considered as a single entity, generated a positive NPV with either price deck 3 or 4 applied. The pricing assumptions used by Evolution Mining for long-term planning are guided by historical prices and consensus broker forecasts. The stated prices are assumed to be constant for the duration of the Ore Reserve mining period.

Table 12: Assessed commodity price decks

Metric 1 2 3 4
Copper ($/t) 7,000 8,500 10,000 12,000
Gold ($/oz) 1,600 1,900 2,200 2,400
Silver ($/oz) 20.00 23.00 26.00 27.50

Economic Assumptions

Ernest Henry has produced at consistent rates for several years, allowing cost and revenue to be well understood. The mine plan from which the Ore Reserve is derived, including cut-off and shut-off grade selection, was tailored to maximise NPV using Evolution’s LOM pricing assumptions. These assumptions are $12,000/t for copper, $2,400/oz for gold and $27.50/oz for silver.

A discount rate of 7.8% has been used in the economic evaluation process. An AUD:USD exchange rate of 0.75 was also utilised.

The Ore Reserve has been assessed using a financial model, with sensitivity to internal and external factors being included in the evaluation. The assessment process has demonstrated that extraction of the reported Ore Reserve can be reasonably justified.

Evolution Mining Limited

33

==> picture [83 x 59] intentionally omitted <==

Classification

The Mineral Resource is converted to Ore Reserve using the method depicted in Figure 19. This process requires material within Domain 7 (0.7% copper grade shell) and Domain 1 (0.1% copper grade shell) to be classified according to geological confidence and provides a basis for the extracted metal to be appropriately converted to Ore Reserve.

The Ore Reserve estimate includes all planned tonnes, reflecting the limited selectivity of SLC mining and the Ernest Henry materials handling system. The metal included in the Ore Reserve estimate is derived from Measured and Indicated resource classes only.

Consideration of mining factors has also been made. Based on the consistency of mine to mill reconciliation and proven operational performance, there is sufficient confidence to convert Measured Resource to Proved Reserve. Though there are additional mining considerations specific to the Ernest Henry (Extension), these do not materially impact the likelihood of recovering the Measured Resource associated with that portion of the Ore Reserve estimate.

This methodology is deemed by the Competent Person to be an appropriate way of accounting for both geological confidence and the mining method.

==> picture [488 x 185] intentionally omitted <==

----- Start of picture text -----

Tonnes
D7 D1 Other
Measured Indicated Inferred External Measured Indicated Inferred External Unclassified
Proved Probable Probable Probable Proved Probable Probable Probable Probable
Metal
D7 D1 Other
Measured Indicated Inferred External Measured Indicated Inferred External Unclassified
Proved Probable Proved Probable
----- End of picture text -----

Figure 19: Flow diagram illustrating the conversion of tonnes and contained metal from Mineral Resource to Ore Reserve

Audits or reviews

Internal peer review of the mine planning process that supports the Ore Reserve estimate is conducted each year by personnel within the site technical and leadership teams. The review forms part of the LOM, Budget and Mineral Resource and Ore Reserve (MROR) planning cycles. Typical inclusions are the validation of key productivity assumptions, mine design, flow model, mine schedule, financial inputs and outcomes. In addition to the site-based review process, the Ore Reserve estimate has been reviewed internally by the Evolution Transformation and Effectiveness (T&E) team. T&E are an oversight group within Evolution that is independent of both the site and study teams.

The PFS has been conducted by a multidisciplinary team of external parties with appropriate experience in the relevant areas. In conjunction with a staged review of the study by Evolution personnel, the Ernest Henry (Extension) Ore Reserve estimate has received input from a broad and appropriate audience.

External reviews are completed periodically to validate mine planning processes and ensure technical risks are managed appropriately. Most recently, SRK Consulting Australia completed a site visit and detailed audit of the MROR processes in 2023 Q3. The audit found that processes used to estimate the Mineral Resource and Ore Reserve are appropriate. Recommendations from the audit focussed on providing more clarity of material risks and assumptions in relevant documentation. This feedback has been acknowledged and applied in the latest Market Statemenreft.

Evolution Mining Limited

34

==> picture [83 x 59] intentionally omitted <==

Discussion of relative accuracy and confidence

Both mine and mill processes are well proven, having greater than ten and twenty years of experience respectively. With continued use of the same methods there is high confidence in being able to extract and process the stated Ore Reserve. Metallurgical testing of core samples from within the Mine Extension area has been conducted as part of the PFS. This test program has shown the material properties to be comparable to those of the existing mine, supporting application of the same recovery factors at depth.

The accuracy of the Ore Reserve estimate is largely dependent on the accuracy of key inputs, the Mineral Resource and cave flow model. These inputs are reviewed independently and then validated together through the flow model calibration process. Flow model calibration is conducted by site at six-month intervals and also as part of the PFS. The calibration is based upon more than ten years of reconciled mine and mill data. To date, forecast metal outputs for the mine have been within 5% of the reconciled metal output on an annual basis.

The underground operation has been designed to handle a 1:100 year rainfall event over 72 hours without significant disruption to mining activities. An event of this magnitude occurred in February 2019, resulting in only minor delays to production and validating effectiveness of the water management system. Water ingress to the underground workings does, however, remain a material risk. This is evidenced by the adverse weather event that occurred in 2023 Q1 and resulted in several months of reduced production. Though the event recovery did negatively impact business outcomes for the affected period, the likelihood of a similar event occurring and being of sufficient severity to materially impact viability of the Ore Reserve is considered low. Findings of the 2023 Q1 adverse weather event incident investigation have been used to improve the Ernest Henry water management system and further reduce the risk associated with water ingress in the future.

Ventilation will be a key enabler for the Ernest Henry operation, particularly during the period where peak capital development rates for the Extension area overlap with production trucking for the Base area. This high demand period is planned to be managed through an upgrade of the primary ventilation circuit. There is, however, a risk associated with the potential for delayed commissioning of the ventilation upgrade. To manage this risk, alternate mine plans have been investigated through the 2023 H2 LOM process, with an aim of reducing or deferring peak ventilation requirements. This work has demonstrated that there are multiple strategies that achieve the objective, providing confidence that any reasonably expected delays to the ventilation system upgrade will not materially impact the viability of the Ernest Henry (Extension) Ore Reserve.

Evolution Mining Limited

35

==> picture [83 x 59] intentionally omitted <==

Mungari Mineral Resource Statement

The Mungari Mineral Resource statement included with this announcement has been prepared in accordance with the 2012 Edition of the “Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves” (the JORC Code 2012) and the ASX Listing Rules.

This Material Information summary has been provided for the Mungari Mineral Resource pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 – Table 1 is presented in Appendix A2.

The December 2023 Mungari Mineral Resource is estimated at 126Mt at 1.45g/t Au for 5,870koz (Table 13). This is a net increase of 532koz (+10%) compared to the December 2022 estimate of 97.5Mt at 1.70g/t Au for 5,338koz ( Table 14 ).

The Mineral Resource was reported within optimised mining shapes using a $2,500/oz price assumption and is inclusive of Ore Reserves but excludes mined areas and areas sterilised by mining activities.

Table 13. Mungari Mineral Resource as at 31st December 2023

Resource
Type
Cut-Off
(g/t Au)
Measured Measured Measured Indicated Indicated Inferred Total Resource Total Resource Total Resource
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
OP 0.29 - - - 75.6 0.97 2,347 28.3 1.02 926 103.9 0.98 3,273
UG 2.04 1.5 4.63 219 8.6 4.34 1,199 8.7 3.98 1,120 18.8 4.20 2,538
SP - - - 3.0 0.60 58 0.0 1.14 2 3.1 0.60 59
Total 1.5 4.63 219 87.2 1.29 3,603 37.1 1.72 2,048 126 1.45 5,870

‘OP’ denotes open pit, ‘UG’ denotes underground, ‘SP’ denotes stockpiles Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding. Mineral Resources are reported inclusive of Ore Reserves Mungari Open Pit Mineral Resource cut-off varies from 0.26g/t Au – 0.33g/t Au. The weighted average open pit cut-off is 0.29g/t Au. Mungari Underground Mineral Resource cut-off varies from 1.46g/t Au – 2.47g/t Au. The weighted average underground cut-off is 2.04g/t Au. Competent Person for MGO Mineral Resource reporting is Bradley Daddow.

Table 14. Comparison of December 2022 and December 2023 Mungari Mineral Resource

Period Measured Measured Indicated Indicated Inferred Total Resource Total Resource Total Resource
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Dec-22 1.4 4.66 205 63.5 1.57 3,196 32.7 1.84 1,937 97.5 1.70 5,338
Dec-23 1.5 4.63 219 87.2 1.29 3,603 37.1 1.72 2,048 126 1.45 5,870
Absolute
Change
0.1 -0.04 14 23.7 -0.28 407 4.4 -0.13 111 28.3 -0.25 532
Relative
Change
8% -1% 7% 37% -18% 13% 14% -7% 6% 29% -15% 10%

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding.

Changes in the reported Mineral Resource from the 31 December 2022 Mineral Resource estimate are due to design changes (+443koz), new data (+202koz), stockpile movements (+16koz), additions (+8koz), subtractions (-8koz), and mining depletion (-129koz). These categories of change are defined below and charted in Figure 20.

Evolution Mining Limited

36

==> picture [83 x 59] intentionally omitted <==

==> picture [488 x 298] intentionally omitted <==

Figure 20: Net changes to the Mungari Mineral Resource statement between December 2022 and December 2023 by category

Additions in the waterfall chart are defined as material that lies outside of the 2022 Resource but was mined during the year. The majority of this came from the Pope John and Christmas (Xmas) underground mines where underground grade control drilling defined extensions to known mineralisation which was subsequently mined in the calendar year.

Subtractions in the waterfall chart are defined as material which was reported within the 2022 Mineral Resource that is no longer considered to have reasonable prospects of economic extraction. A total of 8koz of previously reported Mineral Resource near the surface of Xmas underground was sterilised by previous mining activities and was considered to no longer be potentially economically viable.

New Data is defined as a change in the Resource driven by a change in the either the methodology or interpretation of the resource estimate and incorporates the impact of new drilling data on the model. This 202koz increase in reported Mineral Resource is based on resource development and exploration drilling completed within the reporting period, coupled with the review of historical data. This review included the reinterpretation of existing drilling data resulting in the delivery of a maiden Mineral Resource at Kurrawang (29koz). A maiden Mineral Resource was also delivered for Solomon (73koz) and a significant increase reported in Mineral Resources at the Genesis (+30koz) underground mine and Paradigm (+49koz) open pit mine due to new drilling data.

Design Change is defined as a change in the modifying factors used to generate the Mineral Resource. This includes an increase to the gold price and changes to costs. Modifying factors more closely aligned to the Future Growth Project feasibility study (assessing the viability of the MGO processing facility upgrade to 4.2Mtpa) have been applied following JORC guidance for reasonable prospects of economic extraction of the Mineral Resource. The application of these modifying factors has resulted in a 443koz increase in the reported Mineral Resource attributable to changes in modifying factors.

Evolution Mining Limited

37

==> picture [83 x 59] intentionally omitted <==

The design changes are attributable to:

  • Reduced processing costs based on development of a 4.2Mtpa plant (Future Growth Project – Feasibility Study)

  • Gold price assumption increased to $2,500/oz (previously $2,200/oz)

  • Underground and open pit mining costs increased in line with review of actual mining costs

Stockpile inventory has increased by 16koz due to mining activity and is supported by reconciliation data. An overall increase in the Mungari stockpile inventory accounts for this change.

Depletion in the waterfall chart is defined as the component of the 2022 Mineral Resource that has been mined during the year plus any additional material outside the reported Mineral Resource which has been defined by grade control activities and has also been mined (refer 'Additions'). Depletion is applied to resource block models using as built mining shapes and sterilisation strings.

The December 31, 2023 Mungari Mineral resource includes the following updated geological models:

  • Millennium, July 2023 Resource Update

  • Centenary, August 2023 Resource Update

  • Pope John, July 2023 Resource Update

  • Strzelecki, July 2023 Resource Update

  • Xmas, September 2023 Resource Update

  • Genesis, August 2023 Resource Update

  • Solomon, August 2023 Resource Update

  • Moonbeam, July 2023 Resource Update

  • Kurrawang, October 2023 Resource Update

  • Castle Hill, October 2023 Resource Update

  • Paradigm, August 2023 Resource Update

  • Hornet Open Pit (EKJV), April 2023 Resource Update

  • Hornet Underground (EKJV), September 2023 Resource Update

  • Pegasus & Drake (EKJV), June 2023 Resource Update

  • Pode & Hera (EKJV), October 2023 Resource Update

  • Rubicon (EKJV), August 2023 Resource Update

  • Golden Hind (EKJV), March 2023 Resource Update

The following geological models remain unchanged from the December 31, 2022 Mungari Mineral Resource Statement: White Foil, Frog’s Leg, Boomer, Cutters Ridge, Rayjax, Falcon, Raleigh, Star Trek, Johnsons Rest, Broads Dam, Blue Funnel, Red Dam, Backflip, Nazzaris, Boundary, Carbine North, Lady Jane, Picante, Kintore, Ridgeback, Burgundy-Telegraph, Catherwood, Emu, Bluebell, Premier, Rayjax, Barkers, Arctic, Ant Hill, Wadi and Carbine-Phantom.

Evolution Mining Limited

38

==> picture [83 x 59] intentionally omitted <==

Mungari Ore Reserve Statement

The Mungari Ore Reserve statement included with this announcement has been prepared in accordance with the 2012 Edition of the “Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves” (the JORC Code 2012) and the ASX Listing Rules.

This Material Information summary has been provided for the Mungari Ore Reserve pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 – Table 1 is presented in Appendix A2.

The December 2023 Evolution attributable Mungari Ore Reserve estimate is 37.4Mt at 1.33g/t Au for 1,595koz (Table 15). This represents an increase of 357koz or 29% when compared to the December 2022 Ore Reserves estimate of 24.3Mt at 1.6g/t Au for 1,238koz (Table 16).

Key changes to the December 2023 Ore Reserve estimate include an increase of the minimum gold price used for generating cut-off grades and optimisations from $1,600 to $1,800 per ounce. In addition, the December 31, 2023 Ore Reserve estimate is aligned to Mungari Gold Operation’s (MGO) FY25 ‘Life of Mine’ (LOM) plan. This plan includes larger pits optimised at up to $2,400 per ounce and using Inferred Mineral Resource as well as incrementally profitable underground material that may sit below the planned cut off grade. For the Ore Reserve estimate an $2,500 gold price is used for revenue. The MGO December, 31 2023 Ore Reserve estimate also includes updated geotechnical guidance for the RHP and Raleigh assets with full extraction of stoping blocks to reduce the incidence of isolated pillars subject to high stress conditions. Material extracted due to this and where incremental costs exceed revenue but sit below the planned cut-off grade is included in the Ore Reserve estimate.

The majority of the Ore Reserve estimate increase for CY23 comes from Open Pit design changes and associated alignment to the Life of Mine designs. This increased the estimate by 437koz. Depletion for CY23 was 117koz which includes 10koz from Frog’s Legs Underground mine which was put into care and maintenance.

The reported Ore Reserve estimate is defined within appropriately designed open pit shapes or underground stope shapes which have considered relevant modifying factors and include planned dilution and ore loss. The Ore Reserve estimate outlined in this statement is the component fully attributable to Evolution Mining with Joint Venture material factored by applicable ownership structures.

Table 15. MGO Total Ore Reserve reported as of 31 December 2022

Period Proved Probable Total
Tonnes
(Mt)
Grade
Au
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Grade
Au
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Grade
Au
(g/t)
Gold
Metal
(koz)
MGO OP - - - 34.1 1.04 1,146 34.1 1.04 1,146
MGO UG 0.4 4.42 60 2.81 4.30 388 3.2 4.31 449
Total 0.4 4.42 60 36.9 1.29 1,534 37.4 1.33 1,595

‘‘OP’ denotes open pit, ‘UG’ denotes underground

Ore Reserve estimate is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding

Evolution Mining Limited

39

==> picture [83 x 59] intentionally omitted <==

Table 16. Comparison of December 2021 and December 2022 MGO Ore Reserves

Period Proven Probable Total
Tonnes
(Mt)
Grade
Au (g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Grade
Au (g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Grade
Au (g/t)
Gold
Metal
(koz)
Dec-22 0.4 5.5 78 23.9 1.51 1,160 24.3 1.58 1,238
Dec-23 0.4 4.4 60 36.9 1.29 1,534 37.4 1.33 1,595
Absolute Change -0.0 -1.06 -17 13 -0.22 374 13 -0.26 357
Relative Change -3% -19% -22% 55% -15% 32% 54% -16% 23%

Ore Reserve estimate is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding

Table 17 is a summary of the Ore Reserve estimates for the Mungari Gold Operation by deposit as at 31 December 2023.

Table 17. December 2023 MGO Ore Reserves by deposit

Proven Probable Total
Reserves Type Tonnes
(Mt)
Grade
Au (g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Grade
Au (g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Grade
Au (g/t)
Gold
Metal
(koz)
White Foil OP OP - - - 3.2 1.34 136 3.2 1.34 136
Red Dam OP OP - - - 2.9 1.27 117 2.9 1.27 117
Cutters Ridge OP SP - - - 0.5 0.68 12 0.5 0.68 12
Castle Hill OP OP - - - 21.4 0.89 615 21.4 0.89 615
Burgundy OP OP - - - 1.3 1.23 51 1.3 1.23 51
Kintore SP SP - - - 0.1 0.83 2 0.1 0.83 2
Hornet OP OP - - - 0.2 2.46 15 0.2 2.46 15
Golden Hind OP OP - - - 0.0 1.91 2 0.0 1.91 2
Kundana UG UG 0.1 4.71 14 1.5 4.33 214 1.6 4.35 228
RHP UG UG 0.3 4.31 45 1.0 4.04 130 1.3 4.10 175
Raleigh UG UG 0.0 5.35 1 0.3 5.09 44 0.3 5.10 46
Anthill OP OP - - - 1.7 1.25 69 1.7 1.25 69
Carbine North OP OP - - - 1.4 1.29 59 1.4 1.29 59
Paradigm OP OP - - - 0.9 1.57 46 0.9 1.57 46
Rayjax OP OP - - - 0.5 1.31 21 0.5 1.31 21
TOTAL 0.4 4.42 60 36.9 1.29 1,534 37.4 1.33 1,595

‘OP’ denotes open pit, ‘UG’ denotes underground, ‘SP’ denotes stockpiles *JV asset (EVN Attributable only)

Evolution Mining Limited

40

==> picture [83 x 59] intentionally omitted <==

==> picture [488 x 233] intentionally omitted <==

Figure 21: Waterfall diagram showing change in contained gold ounces between the December 2022 & December 2023 Ore Reserve estimates.

Evolution Mining Limited

41

==> picture [83 x 59] intentionally omitted <==

MATERIAL INFORMATION SUMMARY

Material Information Summaries are provided for the Mungari Mineral Resource and Ore Reserves pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 are presented in Appendix A.

Mungari Mineral Resource

Material Assumptions for Mineral Resources

The Mungari Gold Operation (MGO) Mineral Resource estimate was reported within optimised mining shapes, in line with the Evolution Mining guidance for the evaluation of the Mineral Resources of mining assets. A commodity price assumption of $2,500/oz gold was used to estimate the December 2023 Mineral Resource.

Open Pit Mineral Resources were reported within optimised pit shells using cut-off grades varying from 0.26g/t to 0.33g/t Au, with a weighted average of 0.29g/t Au (weighted by ounce endowment). Pit optimisations assumed truck and excavator mining techniques with mining selectivity based on deposit style and fleet size. Optimised pit shells were generated in Whittle software using end of ‘Life of Mine’ (LOM) cost assumptions: Mining costs + Processing costs + G&A (excluding sustaining capital and haulage costs). Metallurgical recovery is based on metallurgical testwork and an established recovery curve supported by historic processing performance. Mineral Resources were calculated after re-blocking the model to a cell size in line with the minimum selectable mining unit.

Underground mining shapes developed for Mineral Resource reporting assume conventional sub-vertical open stoping typical of current underground mining operations at Mungari. Optimised mining shapes were generated in Datamine software (Minable Shape Optimiser) using end of LOM cost assumptions: Incremental Stoping cost + Processing costs + G&A (excluding sustaining capital and haulage costs). Metallurgical recoveries were based on metallurgical studies and supported by historic processing performance including results from batch processing of selected source material. Underground cut off grades vary between 1.46g/t Au to 2.47g/t Au depending on underground mining cost structures. The weighted average cut-off grade is 2.04g/t Au (weighted by ounce endowment). Isolated or otherwise unfavourably located mining shapes were excluded from the reported Mineral Resource.

Property Description, Location and Tenement Holding

The Mungari Gold Operations (MGO) are located 600km east of Perth and 20km west of Kalgoorlie, in the Eastern Goldfields Region of Western Australia. The operation consists of the Raleigh, East Kundana and Kundana underground mines, the Paradigm and Cutter’s Ridge open pit mines, and the Mungari 2Mtpa carbon-in-leach processing plant. In addition to the operating mines, Evolution owns a regional tenement package to the north of the Mungari Mill centered around Kunanalling, Carbine and the Ora Banda project areas. The total tenement package consists of 329 leases totaling 837 square kilometers of tenure (Figure 22 ).

The Mineral Resource consists of 55 deposits within a 70-kilometer radius from the Mungari 2Mtpa carbon-inleach processing plant processing plant. In 2023, the Paradigm and Cutters Ridge Open Pits mined a total of 0.5Mt at 1.32g/t Au for 22 koz.; Underground mines at Frogs Legs, Kundana and East Kundana Joint Venture (51% EVN) mined a total of 0.9Mt at 4.32g/t Au for 124koz. The Mungari processing facility consists of a three-stage crushing, single-stage (ball) milling, leaching and refining circuits where the ore is refined into doré bars and sold to the Perth Mint.

Evolution Mining Limited

42

==> picture [83 x 59] intentionally omitted <==

==> picture [488 x 345] intentionally omitted <==

Figure 22 . Map of Mungari Operations, lease packages and prospects as of September 2022.

Geology and Geological Interpretation

The Mungari Operation lies within the Kalgoorlie Terrane of the Wiluna-Norseman Greenstone Belt, part of the greater Archaean Yilgarn Craton of Western Australia. The region has been extensively studied, the host rocks date to 2.7 billion years with the main episode of deformation, granitoid intrusion, metamorphism, and gold mineralisation between 2.66 to 2.64 billion years. The structural framework can be summarised by 5 major events (gold mineralisation associated with D3 & D4):

  • D1e Early extension – Syn-volcanic emplacement if komatiite and basalt sequences D1 Broad upright folding and north-south directed thrusting

  • D2 ENE – WSW shortening resulting in significant regional folding D3 Activation north-northwest trending shear zones (including the Zuleika Shear). D4 North-northeast brittle faults, offsetting the stratigraphic sequence and mineralisation

The Kalgoorlie Terrane comprises five major stratigraphic successions; (from oldest to youngest) lower basalt, komatiite, upper basalt, felsic volcanic and sedimentary, and a polymictic conglomerate. The terrane is highly folded and disrupted by faults and major shear zones; the rocks are metamorphosed to greenschist facies with local areas metamorphosed to amphibolite facies, associated with deformation and granitoid intrusion.

The Zuleika Shear Zone, Kunanalling Shear Zone and Carbine Thrust Zone are the dominant corridors of mineralisation at Mungari.

The Zuleika Shear Zone is the major structural element of the area. It is a suite of anastomosing sub-parallel shears that together comprise a major terrane-scale structure. The Zuleika Shear Zone hosts many of the active mines at Mungari including East Kundana Joint Venture and Kundana Underground. Two major mineralised shears within the zone have been identified as the Strzelecki and K2 shears with high-grade gold mineralisation which host laminated quartz veins.

The Carbine Thrust corridor intersects the Zuleika Shear in the north of the tenement package. The CarbineZuleika area geology is predominantly a sedimentary sequence known as The Black Flag Group containing volcaniclastic and deep marine sediments. The two major mineralised planes in the Carbine area, the Carbine

Evolution Mining Limited

43

==> picture [83 x 59] intentionally omitted <==

thrust and Lincancabur Fault, host brecciated and laminated veins respectively, with high-grade gold mineralisation. The Carbine and Phantom deposits are associated with the Carbine Thrust, while the Paradigm deposit is hosted on the Fault. Mineralisation related to the Carbine Thrust is typically observed as brecciated, coarse crystalline veins and laminated veins similar to those seen in the Zuleika Shear Zone observed in the Lincancabur Fault. The Anthill deposit lies to the east of Paradigm on the Zuleika Sheer mineralisation is defined as stockwork veining in an altered pillow basalt.

The Kunanalling Shear Zone also hosts significant gold mineralisation with Cutters Ridge being mined recently and advanced projects including Rayjax, Castle Hill and Kintore. The Kunanalling Shear Zone (KSZ) is a trans-crustal feature that cuts through anticlinal fold hinges in the Coolgardie North region. The area has been intruded by conformable syntectonic dolerites, gabbros and stocks of monzogranitic, tonalitic, and granodioritic composition. Gold mineralisation is hosted in areas of high strain and in and around felsic intrusives.

The interpreted lithology models are constructed based on geological logging of drill holes and geological mapping. The interpretations involve extensive review of logging data, drill chips if retained, drill core, historical sections and maps and core photographs. Wireframes representing different lithological units and regolith domains are generated in geological modelling software. Wireframes are generated by implicit and explicit modelling methods. Wireframes are peer reviewed before being finalised for further estimation work.

Structures logged and mapped include brittle, brittle-ductile and ductile features as well as lithological and bedding contacts. Structural measurements are routinely obtained from orientated drill core, underground and open pit mapping. Routine Geotechnical logging is done by field technicians and geologists. Logging is on a per metre basis and includes percentage core recovery, percentage RQD, fracture count, and an estimate of hardness. The geotechnical data is entered into the database. Interpreted surfaces are generated by implicit and explicit modelling methods. Wireframes are peer reviewed.

Mineralisation and alteration models were constructed based on geological logging of drill holes and geological mapping. Mineralisation is characterised as orogenic, narrow vein gold deposits and, mineralised alteration envelopes, stockworks and mineralised intrusives and supergene enrichment horizons.

Orogenic, narrow vein gold mineralisation is typically hosted within brittle (extension vein arrays and breccias), brittle-ductile (laminated veins) and ductile (shear zones) structural zones and typically exhibit a sodic and potassic alteration assemblage, proximal to the structure. Alteration minerals include sericite, epidote, chlorite, albite, muscovite and biotite. Gold mineralisation is often observed in conjunction with sulphide crystals such as pyrite, pyrrhotite, arsenopyrite, galena and sphalerite. Visible gold has been observed in drill core and rock exposures.

A regolith model was generated to aid estimating density, geological domains and targeting supergene gold horizons. The interpreted regolith model was constructed based on geological logging of drill holes and geological mapping. Historically mined open pits were also referenced. Regolith zones are well developed with secondary enrichment of gold (supergene gold) remobilised to geochemical horizons documented within the regolith profile.

Evolution Mining Limited

44

==> picture [83 x 59] intentionally omitted <==

==> picture [483 x 558] intentionally omitted <==

Figure 23: The Kundana project area sub-surface Geology.

Evolution Mining Limited

45

==> picture [83 x 59] intentionally omitted <==

==> picture [484 x 556] intentionally omitted <==

Figure 24: The Carbine Zuleika project area sub-surface Geology.

Evolution Mining Limited

46

==> picture [83 x 59] intentionally omitted <==

==> picture [480 x 554] intentionally omitted <==

Figure 25. The Kunanalling project area sub-surface Geology.

Mineralisation and alteration models were constructed based on geological logging of drill holes and geological mapping. Mineralisation is characterised as orogenic, narrow vein gold deposits and, mineralised alteration envelopes, stockworks and mineralised intrusives and supergene enrichment horizons.

Orogenic, narrow vein gold mineralisation is typically hosted within brittle (extension vein arrays and breccias), brittle-ductile (laminated veins) and ductile (shear zones) structural zones and typically exhibit a sodic and potassic alteration assemblage, proximal to the structure. Alteration minerals include sericite, epidote, chlorite, albite, muscovite and biotite. Gold mineralisation is often observed in conjunction with sulphide crystals such as pyrite, pyrrhotite, arsenopyrite, galena and sphalerite. Visible gold has been observed in drill core and rock exposures.

Evolution Mining Limited

47

==> picture [83 x 59] intentionally omitted <==

Drilling and Survey Techniques

The Mineral resource is informed by over 60,000 drillholes and over 2 million samples. Drilling techniques included in the resource estimates are limited to Reverse Circulation (RC) drilling from surface and diamond coring (DDH) from both surface and underground.

RC drilling utilises a down-the-hole face sampling hammer with hole sizes varying between 4.25” (105mm) to 5.5” (140mm). Earlier RC drilling techniques (generally pre-1995) such as cross-over sub and open hole hammer were largely omitted from the resource estimates as they were considered low quality. Diamond coring from surface is generally NQ to HQ (47.6mm to 63.5mm respectively) core size depending on ground conditions. Underground based drill core holes have drilled NQ sized core.

Drill hole collar positions were surveyed by either contract or site-based surveyors. Collar surveys were by theodolite or differential GPS, to varying precision and accuracy relative to the AHD. Data was collected on local grids, AMG84 and/or MGA94 co-ordinates. Topographic control was generated from survey pick-ups of the area over the last 20 years.

Down hole surveys consist of regular spaced Eastman single shot (generally at 30m intervals), electronic multi-shot surveys and north seeking Gyro instruments obtained every 5 – 10m down hole. Historically drillholes shorter than 50m used the design azimuths and dips with no downhole surveys taken.

Data, Data spacing and distribution

Drill activities at Mungari Operation are staged and ongoing. An initial drill program is designed to penetrate target zones on a nominal even spaced grid pattern (40m by 40m – 80m by 80m), as perpendicular to the ore zone as practicable. This approach defines and demarcates economic mineralisation to a level which supports estimation of a global Mineral Resource, to an Inferred Resource classification. Further drilling of 20m by 20m – 40m by 40m spaced holes may confirm economic mineralisation to an Indicated Mineral Resource Classification sufficient to support interim mine design and scheduling. A phase of less than 20m by 20m spaced grade control drilling, and/or underground face sampling may be completed to estimate a Measured Mineral Resource and inform accurate economic extraction of ore.

The drill hole database is based on an AcQuire database model and forms a relational database linking the geological and geochemical information to a measured drill hole location (collar, direction and depth). The acQuire database model provides a governance function for the drilling and sampling data by tailoring primary keys and parent-child relationships between collar, survey, geology sampling and assay information.

Field and project Geologists are responsible for data entry, using existing protocols to ensure data functionality and quality. Data templates with lookup tables and fixed formatting are used for collecting primary data on field laptops. The software has validation routines and data is subsequently imported into a secure central database.

The SQL server database is configured for validation through constraints, library tables, triggers and stored procedures. Data that fails these rules on import is rejected or quarantined until it is corrected. Drilling data is validated by the site Geological team through visual checks, validation reports, Quality Assurance and Quality Control checks as well as automated scripts, triggers, and prompts. Once validity of the drill hole and associated data has passed data entry QC checks, it is flagged in the database as having sufficient quality to be included in a resource estimate.

Sampling and Sub-sampling

Sampling for gold utilised a combination of Reverse Circulation (RC), Diamond Core (DC) holes and underground face sampling. Drilling and sampling for gold has been conducted by various companies since 1987. Sampling techniques described below as reported by Mineral Resources Australia (MRA), La Mancha Resources, Centaur Mining and Exploration, Placer Dome Asia Pacific Ltd (Placer), Barrick, Phoenix Gold, Northern Star Resources (NSR) and Evolution Mining (EVN).

Sample representivity is guided by field-based observations from geological supervision, logging and other field records referring to sample quality, content and recovery.

Underground face sampling is completed at a standard height of the grade line, with historic minimum and maximum sample lengths of 0.05m to 2m. Face sampling is taken along the grade line to obtain a

Evolution Mining Limited

48

==> picture [83 x 59] intentionally omitted <==

representative sample for each geological division. Underground face sample weights vary, with a maximum around 3kg.

Centaur Mining and Exploration (CME) (1995-2001)

Reverse Circulation (RC) split to 1m intervals with 1kg to 2kg samples collected using using a riffle splitter for dry samples; grab samples were taken from wet material. Composites of 2 to 4 consequtive 1m samples were also collected. Diamond drilling produced HQ, NQ or NQ2 size core. The core was cut, or if soft, divided into half or quarter samples.

Samples were oven dried, pulverised to 75 micron; a 40g sub-sample was assayed for Au by Aqua Regia at ALS (Kalgoorlie). Selected repeats by fire assay.

Placer Dome Asia Pacific and Barrick (2003-2007)

The Black Flag RC samples were riffle split to obtain a two to five kilo split sample for every metre. Four metre composite samples were taken utilising a spear sample tool and submitted to the laboratory. Samples were dried, crushed and pulverised to 90 per cent passing minus 75 microns and a 50gram fire assay digest, analysing for gold and arsenic. Routine QC included certified reference material and blanks were inserted every 20 samples (Cha, 2003).

The Black Flack RC grade control drilling of 2007 was sampled utilising a cone splitter to nominally collect 2.5 kilogram samples. Samples were sent to a commercial laboratory where they were split to less than three kilograms (if required), pulverised to 90 percent passing minus 75 microns before undergoing 50 gram fire assay digest and ICP AAS analysis. Routine QC samples were collected including a field duplicate every 18 metres and a standard inserted at the end of each drill hole.

Mines and Resources Australia (1994-2006)

RC samples were collected at 1m intervals and split using a 3-way splitter to generate a one eighth (12%) sub sample. Four metre composite samples were collected from the primary sample using a PVC spear and assayed at ALS Kalgoorlie by Aqua Regia. Anomalous grades were followed up with the 1m sub-sample assayed at Kalgoorlie Assay Laboratories by bottle roll cyanide leach analysis. Duplicate samples were taken for every twentieth sample. Check samples were taken for every twentieth four metre composite sample by sending the ALS pulps to Kalgoorlie Assay Laboratories for Au analysis to 0.01ppm.

Diamond drill core was cut in half, sampled at 1m increments and assayed for gold at Genalysis Laboratory by fire assay with AAS finish. Bottle roll tails residue was assayed by fire assay where initial results were greater than 1g/t Au (later changed to 3g/t Au)

La Mancha (2012 to 2013)

RC samples at 1m increments, with 4m composites collected using a spear for preliminary Aqua Regia with AAS finish assays at Genalysis Laboratories. 1 metre samples were submitted for anomalous zones to Genalysis Laboratory for 50gram fire assay and AAS finish.

Diamond core was sampled on a 1m interval basis or narrower if geological features were sampled separately. Assay methodology was the same with a 50g Fire Assay and AAS finish.

Phoenix Resources (2014-2018)

RC Samples at one metre intervals, split via a rig mounted cone splitter and submitted to SGS Laboratory or KalAssay in Kalgoorlie for analysis of Au. Samples are first pulverised before they are analysed for gold via a 30 - 40gram Fire Assay with an AAS finish and lower detection limit of 0.01ppm.

Diamond core was half core sampled at varying intervals based on geology. Samples were crushed to 20mm and then pulverised and assayed by the same methodology as the RC drilling at Bureau Veritas’ KalAssay Laboratory in Kalgoorlie. Some pulp umpire checks were completed by Genalysis Laboratories in Perth using a 50g Fire Assay.

Northern Star Resources (2015-2021)

Evolution Mining Limited

49

==> picture [83 x 59] intentionally omitted <==

Reverse Circulation samples were collected at 1m intervals re-split by riffle splitter into 1/8th ratio for the primary sample, 1/8th ratio field duplicate sample and 6/8th ratio as spoils. Select samples were sent for multielement analysis based on lithology, mineralisation, and grade. Blanks and standards were inserted at a ratio of 1 in 20 per primary sample.

Diamond core was sampled at 1m intervals or to selected geological, mineralisation and/ or alteration boundaries. Half- core samples were sent to MinAnalytical Laboratories for gold analysis with 50g Fire Assay by AAS.

Evolution Mining (2015 to present)

Reverse Circulation samples were collected at one metre intervals, split by cone splitter into 1/8th ratio for the primary sample, 1/8th ratio field duplicate sample and 6/8th ratio as spoils. Blanks and standards were inserted at a ratio of 1 in 20 per primary sample. The spoils were retained in a plastic bag and/or arranged in rows direct onto the ground next to the drill rig. All samples are assayed by fire assay with determination by AAS.

Diamond core was sampled at 1m intervals or narrower to selected geological, mineralisation and/ or alteration boundaries. Samples were sent to the laboratories for sample preparation and for gold analysis with 30g to 50g lead collection Fire Assay and determination by AAS.

All results are returned in digital (Microsoft .csv) format providing the weight of individual samples, gold grade, any repeats and grind quality checks.

Sample analysis methods

Sample preparation and analysis for gold was undertaken at independent commercial assay laboratories. Samples were oven dried, coarse crushed as required and pulverised to 75µm – the size fraction of pulverized samples regularly checked to maintain a standard of >90% passing a 75µm screen. A 30g – 50g pulverised sub-sample was used to determine gold grades by Fire Assay with AAS (atomic absorption spectrometry) finish.

Density

Dry bulk density values have been assigned based on regolith, lithology, ore domain and disturbance. Material types are defined by the regolith profiles based on base of oxidation and top of fresh rock horizons. Data is collated and reviewed by project area with typical values shown below:

1. Above the base of complete oxidation: 1.9 tonnes per cubic metre
2. Transition zone: 2.3 tonnes per cubic metre
3. Fresh rock: 2.8 tonnes per cubic metre
4. Tailings/waste fill 1.6 tonnes per cubic metre

Dry bulk density of drill core was measured on site by trained field assistants, using the water immersion method. Specific gravity provides the relative density of an object to water, where the density of water is 1kg/m[3] the measurement also serves as a proxy for density.

Downhole gamma density measurements were also used at Mungari on some drillholes, the tool measures electron density of the rock along the depth of the borehole. Electron density is converted to mass density and records uploaded to the database.

Density measurements are checked and validated at point of capture and during analysis, scales and tools are calibrated regularly. Calibration of scales uses known density drill core samples (density standards).

Quality Assurance and Quality Control

MGO has developed a Quality Assurance and Quality Control program for the processing and reporting of samples and assays that are used in the Mineral resource estimations. Assay laboratories are ISO9001:2015 certified and take part in Round Robin inter-laboratory quality assurance programs. Regular laboratory audits

Evolution Mining Limited

50

==> picture [83 x 59] intentionally omitted <==

are completed by the MGO personnel and the performance of Certified Reference Materials (standards) and other checks including blanks, duplicates, size fraction checks and turnaround time is monitored.

Since 2015 the following QAQC checks and protocols have been in place:

  • 1:30 fine crush residue has an assay duplicate

  • 1:20 pulp residue has an assay duplicate

  • 1:20 wet screen grind checks

  • 1:20 site blanks are inserted into each dispatch with a minimum of at least 1 blank per assay fire (50 samples)

  • 1:20 CRMs submitted in the dispatch with a minimum of at least 1 CRM per assay fire (50 samples)

  • Field duplicates (for RC drilling) set at 1 in 20 samples.

Data validation checks are performed within the MGO acQuire database, including (but not limited to);

  • Missing, invalid or duplicate collar surveys

  • Collar coordinates checks, (eg actual collars >5m from planned position)

  • excessive deviation of downhole surveys (>5̊ per 30m),

  • missing, duplicate or invalid downhole survey data

  • logging and/or sampling overlaps or exceeding total depth

  • sample length exceeds guidance for sample type

  • check sample frequency below guidance for sample type

  • Check samples assays outside acceptable limits

  • Expected fields not populated

  • Data entry restricted to library tables values, numerical ranges or formatting criteria.

  • ▪ Validation status recorded in database

Spatial validation of drillhole traces were plotted using 3D software and cross referenced against topography, surveyed mine workings, existing drilling and geological interpretation. Spatial validation of geological logs and assay results were routinely checked against core photographs, surrounding drilling and geological interpretation.

Estimation Methodology

Lithology, structure, and lode interpretation were developed into 3D wireframes based on drillhole data, face data, mapping and photography. A range of mining software packages were used to develop wireframes including Datamine, Leap Frog, Surpac and Vulcan. There have been multiple generations and methods for wireframing at Mungari including sectional based polygons, point clouds based on drillhole intercepts and implicit modelling in Leapfrog. Wireframes are validated to ensure they honours the regolith and/or geological model and peer reviewed prior to estimation. Lode wireframes are used to select and composite included samples, where wireframes intersect or overlap the dominant lode is prioritised during compositing.

Ordinary Kriging (OK) is the preferred method for narrow lodes. Estimates were typically based on 1m intervals, composited within ore wireframes, 0.5m composites were used in some very narrow deposits and 2m composites in broader domains. Domaining and sub-domaining techniques were applied to constrain discreet sub-populations of grade, lode thickness or lode geometry. A review of grade distribution and/or boundary analysis were used to determine the suitability of hard or soft boundaries. Top-cuts were determined for each sub-domain to limit the influence of high-grade outliers, in general top cuts were applied to less than 3% of the samples. In some domains distance limiting or influence limitation techniques were applied to limit the influence of very high-grade samples. Geostatistics were reviewed with variography and search directions established for each sub-domain. Inverse Distance estimates have also been used as a check and where insufficient data is available to support Ordinary Kriging

Categorical Indicator Kriging (CIK) was used to estimate lithological domains (for example the Castle Hill tonalite and the White Foil dolerite) with mixed grade populations. The samples were composited within the

Evolution Mining Limited

51

==> picture [83 x 59] intentionally omitted <==

wireframe. Geostatistical analysis was completed to determine an indicator threshold value, variograms and search directions and a binary flag is applied to composites with grade above the indicator threshold (1) and below the threshold composites (0). An estimate models the probability of each block exceeding the indicator grade, the probability was used to categorize the blocks into two groups. Each category is then reviewed and run ordinary kriged estimation.

Geostatistical analysis was performed using Snowden Supervisor software. Variograms and search orientations are reviewed in 3D software. Univariate statistical was conducted for each domain including histogram, mean variance plots, log probability plots as well as population statistics domain statistical measures like the mean, standard deviation and coefficient of variation.

Estimation Validation

Mineral Resource estimates are validated using the following techniques:

  1. Visual validation

  2. Statistical validation; and

  3. Where applicable, comparison to historic resource estimates and/or reconciled production

A variety of validation checks were performed on the estimations. Visual checks in section, long section and plan were performed comparing the estimated blocks against the input composite data. Review of high-grade top cut composites to assess the impact and influence high-grade samples relative to surrounding blocks. Blocks estimates near domain boundaries were independently randomly checked to ensure sample coding was being honoured during estimation.

Swath plots were created for every domain and, where applicable, every subdomain. The Swath plots compared the estimated top-cut gold grade to the composite mean and declustered top cut mean grades. These plots are completed in sectional and horizontal slices through the model.

Volume variance checks are completed to determine what percentages of the domain wireframes are being estimated and what percentages are being estimated in each estimation pass. Checks and comparisons are made with previous estimations and reconciled production where possible.

Resource Classification

Mineral resource estimations are not precise calculations. Resource estimates are based on interpretations and assumptions made from measurements of the position, shape, continuity and grade of complex mineral occurrences.

Mineral Resource classifications follow the JORC 2012 guidelines for Mineral Resource and Ore Reserve reporting. The JORC Mineral Resource classification definitions qualify the risk associated with a resource estimate, with risk linked to the resource estimate as follows:

  • Measured resource: Low Risk

  • ▪ Indicated resource: Medium Risk ▪ Inferred resource: High Risk

The risk associated with a resource estimate is variation in the physical parameters that will alter the economic outcomes during mining of the resource. As such Mungari Gold Operation has adopted the following principle in classification of mineral resources. For the Mungari Gold Operations Mineral Resource Statement a resource estimate will be classified as:

  • Measured if the expected variation in physical parameters is within the bounds of normal mining practice. In general, for an open pit resource, the Measured component is defined by grade control drilling and modelling. For an underground resource, the Measured component is defined by sufficient face sampling and drill data to generate a grade control model. This also includes close spaced grade

Evolution Mining Limited

52

==> picture [83 x 59] intentionally omitted <==

control drilling that has been used during resource estimation. Measured Resource also typically includes mapping and/or recorded survey points showing the position of the ore body position in the exposed face/floor.

  • Indicated if the expected variation is outside normal mining practice and will not affect overall economic performance. In general, this will be derived from drill hole spacing and where possible kriging variances and relative ref distributions (in line with the AusIMM definition above).

  • Inferred if the expected variation is outside normal mining practice and will alter the overall economic performance. In general, this will be derived from drill hole spacing and where possible kriging variances and relative error distributions (in line with the AusIMM definition above).

As part of the philosophy outlined above, where previous resource models have been used to report the current mineral resource and the classification of the previous resource does not fit with Mungari Gold Operations definitions, then the resource will be re-classified appropriately.

Classifications have been based upon distance and qualitative criterion, with consideration for the number of holes used during interpolation, sampled/unsampled data, grade variations between holes, drill spacing, hole orientation, interpolation pass, and geological confidence.

Mineral Resource Reporting and assigned cut-off criteria

The Mungari Operation Mineral Resource estimate was reported within optimised mining shapes. In line with the Evolution Mining guidance for the evaluation of the Mineral Resources of mining assets. A commodity price assumption of $A2,500/oz. gold price was used to estimate the December 2022 Mineral Resource. Optimisations are based on cost, recovery and geotechnical factors which are benchmarked against historical metrics for the Mungari operation. Optimised Mining shapes were amended where required to meet minimum practical mining parameters. Cut-off grades were estimated using projected site mining costs, processing costs and site general administration costs; a gold price of A$2,500/oz. was utilised.

Audits or Reviews

External reviews are completed periodically to review the mine and ensure technical risks are managed appropriately. Feedback from these reviews has been positive to date. The last review was conducted by Cube Consulting Pty Ltd in 2022 on the CY2021 Mineral Resource and Ore Reserves. All material items identified by the audit have been actioned for the CY2022 Ore Reserve estimate.

In addition, internal technical reviews and checks are undertaken by Evolution Mining’s Transformation and Effectiveness (T&E) team which manage and monitor corporate governance and reporting activities. An internal review of the methodology used to determine the CY2021 Mineral Resource estimate has been conducted and all material items identified within have been actioned for the CY2022 Mineral Resource estimates.

Evolution Mining Limited

53

==> picture [83 x 59] intentionally omitted <==

Mungari Operations Ore Reserve

Material Assumptions for conversion to Ore Reserves

The Ore Reserve estimate is based on the current Mineral Resource estimate described in Section 1.1. The Mineral Resource estimate is reported inclusive of the Ore Reserve estimate. The Ore Reserve has been declared within pit designs or underground mining shapes developed and considering all modifying factors and has been financially evaluated to ensure it is both practical and economically viable. The reported Ore Reserve only includes material within the mine designs which has been classified as either Measured or Indicated Mineral Resource. Inferred Resource blocks are excluded from the reported Open Pit Ore Reserve. Inferred Resources are excluded from the Underground Ore Reserve except for when included in shapes where dominant gold mass is either Measured or Indicated. Checks of contained Inferred material in the Underground Ore Reserve estimate showed that it accounted for less than 1% of the total Ore Reserve estimate.

Cut-off parameters

Mungari Gold Operations applied cut-off grades as per the Evolution Mining’s Strategic Planning Standards. The cut-off grades used for the CY2023 Ore Reserve estimate were calculated using a range of gold prices from A$1,800 to A$2,400 per ounce. The following costs are included in the cut-off grade calculation:

  • Stockpiles reclaiming COG: [End of LOM Processing] + [End of LOM G&A] + [Rehandle]

  • Open Pit COG: [Processing] + [G&A] + [Incremental Haulage, if any] excluding [Sustaining Capital]

  • ▪ Underground COG: [Processing] + [G&A] + [Stoping Cost] excluding [Sustaining Capital]

Material below the Underground cut-off grades is included in the Underground Ore Reserve estimate where revenue exceeds incremental costs. Surface Stockpiles are included in the Ore Reserve estimate where revenue exceeds incremental costs. The cut-off grades used for the MGO Ore Reserve estimation are outlined in Table 18 below.

Table 18. MGO Ore Reserve estimate - Cut-off Grade by Asset - December 2023

Deposit Type Gold Price Cut-off
Grade (Au
g/t)
White Foil OP OP $2,400 0.39
Golden Hind OP $2,400 0.45
Hornet OP $2,400 0.45
**Red Dam ** OP $2,400 0.53
Anthill OP $2,400 0.55
Carbine North OP $2,400 0.56
Castle Hill OP $2,400 0.50
Burgundy OP $1,800 0.65
**Paradigm ** OP $2,400 0.55
RHP UG $1,800 3.63
**Raleigh ** UG $1,800 3.63
Kundana UG $1,800 2.80

‘OP’ – open pit, ‘UG’ – underground

Evolution Mining Limited

54

==> picture [83 x 59] intentionally omitted <==

Mining factors or assumptions

MGO Ore Reserve estimates were designed using current mining methods employed at Mungari Gold Operations matched with the Mineral Resource characteristics. These methods are appropriate for the style of Mineral Resource and fall into the following main categories:

  • Conventional Open Pit mining with parameters and minimum mining widths defined by the selected fleet size and production rates with slope designs and hydrological considerations based on technical assessments

  • Conventional sub-vertical open stoping with level spacing generally between 20 to 25 meters and accessed from within a previous open pit via a decline ramp. The stoping method includes either using pillars or paste fill for stability with some areas employing hybrid stoping methods (transverse access) to reduce personnel exposure to seismicity

The Ore Reserve designs and schedules were developed based on geotechnical guidance for both Open Pit and Underground Reserve estimates. The Underground Ore Reserve estimates are subject to a degree of seismic risk. The risk increases with depth and is higher in specific ore bodies. The December 31, 2023 reported Underground Ore Reserve estimates represent, in the opinion of the Competent Person, the recoverable portion of the reported Mineral Resources. Some high seismic risk areas at Raleigh and RHP have been excluded from the reported Ore Reserve estimates.

Dilution and recovery factors for both the Open Pit and Underground Ore Reserve estimates were developed based on historical performance. For the Underground Ore Reserve estimates additional dilution from paste was included where paste exposures were present. In some instances, recovery factors have been used as pillar factors (material left behind in pillars).

Metallurgical factors or assumptions

The Mungari operation is a mature operation with well understood mineralogy and metallurgical recovery. Detailed metallurgical test work has been completed on all operational projects with a lesser amount of test work being completed on distal projects which are not scheduled to be mined in the near term. A program of additional metallurgical test work is planned in these regions to obtain additional information to support currently applied metallurgical recoveries. The existing processing facility employs a conventional three stage crushing and grinding circuit with both gravity and carbon-in-pulp recovery.

Metallurgical recoveries used for the Ore Reserve estimates processed through the current mill were based on historical recoveries as compiled and provided by the MGO Senior Metallurgist. For material processed by the expanded mill recoveries were compiled by the Processing and Metallurgy lead for the Future Growth Project. These processing recoveries are in line with existing recoveries and expectations.

Environmental and Social factors

The deposits contained within the Ore Reserve estimate are located in a mature mining district with significant work completed on Environmental and Social factors. The majority of waste material within the district does not contain ‘Potentially Acid Forming’ (PAF) material and where included in the mining plan material is planned to be fully encapsulated within an appropriate facility. For the reporting of Ore Reserve estimates it is considered that all known environmental issues are appropriately managed via the site’s environmental management systems and competent persons.

A Social Impact Assessment has been undertaken to evaluate the site’s social context and interactions with community and other stakeholders. Legal and regulatory requirements for proposed projects are understood and a schedule for applications and future work is in place. Approvals in place for waste dumps and process residue storage provide sufficient storage for proposed operations in the LOM schedule.

There are no known Environmental or Social reasons which are expected to materially impact the Ore Reserve estimate.

Infrastructure

The Mungari operation is an established mine site with all major infrastructure in place. No upfront capital costs are applicable for the existing processing plant, surface infrastructure, Paradigm Open Pit and Underground Ore Reserve estimates (Raleigh, Kundana, RHP). The Mungari 4.2 Project will expand the processing capacity from 2.0 Mtpa to 4.2 Mtpa production rate and forms the base case for the operation.

Evolution Mining Limited

55

==> picture [83 x 59] intentionally omitted <==

Estimated capital for this project has been included in financial modelling as per the MGO ‘Future Growth Project Feasibility Study’ cost estimates.

Development of the regional open pits will require upfront capital for construction of infrastructure. Preproduction capital required includes the development of haul roads, water supply and dewatering, communication, offices and ablutions, workshops and fuel storage and explosive magazines. Costs for these have been included in the financial modelling as per latest estimates.

Costs

All financial modelling for the December 2023 Mungari Ore Reserve estimates has been completed in Australian dollars.

Major infrastructure at MGO has been constructed and is operational. Sustaining capital is forecast based on the requirements for each operation and is included in the financial modelling for the Ore Reserve estimation. Operating costs have been derived from either project or site cost models and consider mining, processing, and G&A costs.

Mining costs used for the calculation of cut-offs and the evaluation of the Ore Reserve estimates have been derived from either historical or future cost forecasts. Mining costs include load and haul costs, drill and blast costs, dewatering costs, maintenance costs, geotechnical, and grade control costs.

For all projects except for White Foil (which direct tips to the Mungari plant ROM pad) the unit cost of road haulage is calculated based on the haulage distance and road type (private haul road or public shire road). The haulage model includes allowances for loading, truck haulage, road maintenance and fuel.

Processing costs used in the cut-off grades and modelling were based on either the current processing cost structure or the Mungari 4.2 cost structure depending on when the material was likely to be processed. Royalty payments of 2.5% for gold to the Western Australian government and all other applicable Royalties are included in the financial models.

Revenue

All financial modelling for the December 2023 Mungari Ore Reserve estimates has been completed in Australian dollars.

A gold price of $2,500 per ounce has been used to generate revenue for the Ore Reserve estimate with sensitivity analysis conducted using a range of assumed gold prices from $1,800 to $2,500 per ounce. Evolution uses an internal gold price assumption of $2,650 for Life of Mine (LOM) planning which is set with reference to both historical prices and consensus broker forecasts.

Economic

Mungari Gold Operations has produced at consistent rates for several years which allows cost and revenue to be well understood. The mine plan from which the Ore Reserve estimate is derived, including cut-off grade selection, is tailored to maximise Net Present Value (NPV) using Evolution Mining’s Strategic Planning guidelines. Economic testing includes all capital applicable costs and is performed via a sensitivity analysis using a range of assumed gold prices from $1,800 to $2,400 per ounce and considers a range of financial metrics including AISC, NPV and FCF. The evaluation process has demonstrated that extraction of the reported Ore Reserve estimate can be reasonably justified.

Classification

The classification of the Mungari Ore Reserve estimate reflects the view of the Competent Person and is in accordance with the JORC 2012 Code.

Measured Resources recovered in the Ore Reserve estimate pit design or underground mining shapes have been converted to Proven Reserves.

Indicated Resources recovered in the Ore Reserve estimate pit design or underground mining shapes have been converted to Probable Reserves.

Evolution Mining Limited

56

==> picture [83 x 59] intentionally omitted <==

Inferred Resources within the pit design are excluded from the reported Ore Reserve estimate. Inferred Resources within the reported underground Ore Reserve estimates are excluded for all shapes which have a dominant gold mass of Inferred Resource.

Audits or reviews

External reviews are completed periodically to review the mine and ensure technical risks are managed appropriately. Feedback from these reviews has been positive to date. The last review was conducted by Cube Consulting Pty Ltd in 2022 on the CY2021 Mineral Resource and Ore Reserve estimates. All material items identified by the audit have been actioned for the CY2023 Ore Reserve estimate.

In addition, internal technical reviews and checks are undertaken by Evolution Mining’s Transformation and Effectiveness (T&E) team which manage and monitor corporate governance and reporting activities. An internal review of the methodology used to determine the CY2022 Ore Reserve estimate has been conducted and all material items identified within have been actioned for the CY2023 Ore Reserve estimate.

Discussion of relative accuracy / confidence

The accuracy of the Ore Reserve estimate is largely dependent on the accuracy of the block model used to determine the Mineral Resource. Risk associated with the reported Mineral Resource is impacted by the style of mineralisation present and the extent of drilling completed. The nature of mineralisation differs significantly between deposits from broad low-grade zones of mineralisation to narrow, discontinuous high-grade veins. The underlying risk in the Mineral Resource is reflected in the applied resource classification.

Comparison of ore mining forecasts and reconciled ore grade presented to the processing plant indicate that the assumptions used in the model to calculate the Ore Reserve estimates are valid. Reconciliation of the Ore Reserve against actual production figures is completed monthly, quarterly, and annually. All assumptions used in financial models are subject to internal peer review and external auditing.

In addition to risk with the reported Mineral Resource, there is also general risk associated with the costs applied for the financial evaluations. Capital costs represent a small proportion of the total cost of production for the Ore Reserve estimate, but operating costs are impacted by many factors both internal (productivity, estimation) and external (cost of consumables, fuel and contract/hire services). Applied costs for the Ore Reserve estimate are from either budget level project costs or calibrated site cost models. Some projects will not be mined for several years and external factors may influence costs in the interim.

In the opinion of the Competent Person:

  • the modifying factors and long-term assumptions used in the Ore Reserve estimate are appropriate and reasonable

  • the Ore Reserve estimate is supported by appropriate design, scheduling, and cost estimates

  • there is a reasonable expectation of achieving the reported Ore Reserve estimates commensurate with the Ore Reserve classifications

Key risks to the Ore Reserve estimate include statutory approvals, gold price, production rates, open pit mining costs, and metallurgical recovery.

Evolution Mining Limited

57

==> picture [83 x 59] intentionally omitted <==

Overview - Northparkes Mineral Resource Statement

Evolution Mining (EVN) acquired 80% ownership of the Northparkes Operation (NPO) from CMOC Mining effective as of 16 December 2023.

The Northparkes December 31 2023, Mineral Resource is estimated at 525.9 million tonnes at 0.55% copper and 0.19g/t gold (exclusive of Ore Reserves) (Table 19). Evolution’s 80% attributable component equates to 420.8Mt @ 0.55% copper and 0.19g/t gold, totalling 2,316kt of contained copper and 2,609koz of contained gold. Mineral Resources are generally reported within designed mining shapes which have been developed taking into account the estimated copper and gold grades of blocks and the expected metallurgical recovery. A copper equivalent block grade is calculated and used in the development and economic evaluation of designed mining shapes. The reported Mineral Resource includes any zones of internal waste or low-grade material which cannot be selectively mined by the chosen sub-level caving or block caving mining method used at the Northparkes mine. Where resource mining shapes were not available, grade shells based on cutoff grades were used to constrain the reported Mineral Resource within contiguous mineable blocks. All material reported within the Mineral Resource is considered by the Competent Person (CP) to meet reasonable prospects for eventual economic extraction, taking into account the proposed mining technique and historical metallurgical recoveries. The Mineral Resource update is current as of 31 December 2023 and takes into account all mining activities undertaken to this date.

Table 19: Northparkes Mineral Resource totals as at 31 December 2023

Dec 2023 Total Dec 2022
Measured Indicated Inferred
Resource Resource
Tonnes (Mt) 249.1 218.6 58.3 525.9 526.9
Copper grade (%) 0.57 0.53 0.57 0.55 0.55
Copper tonnes (kt) 1,410 1,155 331 2,895 2,906
Gold grade (g/t) 0.22 0.16 0.19 0.19 0.19
Gold ounces (koz) 1,747 1,157 357 3,261 3,294

Northparkes Mineral Resource is reported exclusive of reported Ore Reserves. Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding Evolution’s 80% attributable component equates to 420.8Mt totalling 2,316kt of contained copper and 2,609koz of contained gold. Northparkes Mineral Resource Competent Persons are Mr. David Richards and Mr. Geoff Smart.

The 31 December, 2023 Mineral Resource consists of 11 zones (from 7 ore bodies) in both underground and open cut mining environments. A breakdown by zone of the contained gold content and contained copper content within the reported Mineral Resource is summarised in Table 20 and Table 21 respectively.

.

Evolution Mining Limited

58

==> picture [83 x 59] intentionally omitted <==

Table 20: Northparkes Mineral Resource by area and category – contained gold

Contained gold Contained gold Contained gold Measured Measured Measured Indicated Indicated Indicated Inferred Inferred Total Mineral
Resource
Total Mineral
Resource
Total Mineral
Resource
Project Type Cut-off Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
E221 UG $18NSR 3.4 0.28 30 10.0 0.18 58 1.1 0.20 7 14.5 0.20 95
E48 L21 UG 0.40% Cu 90.2 0.25 733 67.4 0.17 358 0.0 0.00 0 157.6 0.22 1091
E26 L2 UG $40NSR 0.0 0.00 0 11.5 0.15 57 0.0 0.00 0 11.5 0.15 57
E26 L31 UG 0.40% Cu 111.8 0.15 554 49.8 0.12 200 0.0 0.00 0 161.6 0.15 753
GRP314
L11
UG 0.40% Cu 0.0 0.00 0 23.0 0.12 89 22.2 0.14 100 45.2 0.13 189
GRP314
L21
UG 0.40% Cu 0.0 0.00 0 46.5 0.17 254 34.8 0.22 242 81.3 0.19 497
MJH2 UG $25NSR 34.6 0.11 124 7.5 0.10 25 0.0 0.00 0 42.0 0.11 149
E44
Sulphide3
OP 0.65g/t Au 4.9 1.51 238 2.6 1.24 102 0.1 1.20 6 7.6 1.42 345
E44
Oxide3
OP 0.65g/t Au 0.7 0.97 21 0.5 0.99 15 0.0 1.01 1 1.2 0.98 37
E31
Sulphide4
OP 0.34%
CuEq
3.4 0.42 46 0.0 0.00 0 0.0 0.00 0 3.4 0.42 46
E31
Oxide4
OP 0.50%
CuEq
0.1 0.67 2 0.0 0.00 0 0.0 0.00 0 0.1 0.67 2
Total 249.1 0.22 1748 218.6 0.16 1157 58.3 0.19 357 525.9 0.19 3261
  • ‘UG’ denotes underground, ‘OP’ denotes open pit.

  • Metal prices and exchange rate assumptions used for cut-off grade selection by project. The E26L3, E22, E48L2, GRP314 projects are based on a 2013 study which assumes US$1.69/lb Cu, US$660/oz Au, 0.75 AUD:USD.

  • Metal prices and exchange rate assumptions used for cut-off grade selection by project. The MJH project assumes US$3.00/lb Cu, US$1,350/oz Au, 0.73 AUD:USD

  • Metal prices and exchange rate assumptions used for optimisation of the open-pit Resources vary by project. The E44 project assumes US$3.30/lb Cu, US$1,320/oz Au, US$21/oz Ag, 0.73 AUD:USD

  • Metal prices and exchange rate assumptions used for optimisation of the open-pit Resources vary by project. The E31 project assumes US$3.30/lb Cu, US$1,320/oz Au, US$18/oz Ag, 0.73 AUD:USD

Evolution Mining Limited

59

==> picture [83 x 59] intentionally omitted <==

– Table 21: Northparkes Mineral Resource by area and category contained copper

Contained copper Contained copper Contained copper Measured Measured Indicated Indicated Inferred Inferred Total Mineral Resource Total Mineral Resource Total Mineral Resource
Project Type Cut-off Tonnes
(Mt)
Grade
(Cu%)
Metal
(kt)
Tonnes
(Mt)
Grade
(Cu%)
Metal
(kt)
Tonnes
(Mt)
Grade
(Cu%)
Metal
(kt)
Tonnes
(Mt)
Grade
(Cu%)
Metal
(kt)
E221 UG $18
NSR
3.4 0.40 14 10.0 0.36 36 1.1 0.36 4 14.5 0.37 53
E48 L21 UG 0.40%
Cu
90.2 0.54 488 67.4 0.51 344 0.0 0.00 0 157.6 0.53 832
E26 L2 UG $40
NSR
0.0 0.00 0 11.5 0.78 89 0.0 0.00 0 11.5 0.78 89
E26 L31 UG 0.40%
Cu
111.8 0.62 694 49.8 0.53 262 0.0 0.00 0 161.6 0.59 957
GRP314
L11
UG 0.40%
Cu
0.0 0.00 0 23.0 0.57 131 22.2 0.59 131 45.2 0.58 262
GRP314
L21
UG 0.40%
Cu
0.0 0.00 0 46.5 0.54 251 34.8 0.56 196 81.3 0.55 447
MJH2 UG $25
NSR
34.6 0.57 199 7.5 0.54 41 0.0 0.00 0 42.0 0.57 239
E44
Sulphide3
OP 0.65g/t
Au
4.9 0.03 1 2.6 0.03 1 0.1 0.03 0 7.6 0.03 2
E44
Oxide3
OP 0.65g/t
Au
0.7 0.03 0 0.5 0.03 0 0.0 0.02 0 1.2 0.03 0
E31
Sulphide4
OP 0.34%
CuEq
3.4 0.37 13 0.0 0.00 0 0.0 0.00 0 3.4 0.37 13
E31
Oxide4
OP 0.50%
CuEq
0.1 0.24 0 0.0 0.00 0 0.0 0.00 0 0.1 0.24 0
Total 249.1 0.57 1410 218.6 0.53 1155 58.3 0.57 331 525.9 0.55 2895

‘UG’ refers to underground, ‘OP’ refers to open pit.

  1. Metal prices and exchange rate assumptions used for cut-off grade selection by project. The E26L3, E22, E48L2, GRP314 projects are based on a 2013 study which assumes US$1.69/lb Cu, US$660/oz Au, 0.75 AUD:USD.

  2. Metal prices and exchange rate assumptions used for cut-off grade selection by project. The MJH project assumes US$3.00/lb Cu, US$1,350/oz Au, 0.73 AUD:USD

  3. Metal prices and exchange rate assumptions used for optimisation of the open-pit Resources vary by project. The E44 project assumes US$3.30/lb Cu, US$1,320/oz Au, US$21/oz Ag, 0.73 AUD:USD.

  4. Metal prices and exchange rate assumptions used for optimisation of the open-pit Resources vary by project. The E31 project assumes US$3.30/lb Cu, US$1,320/oz Au, US$18/oz Ag, 0.73 AUD:USD.

Evolution Mining Limited

60

==> picture [83 x 59] intentionally omitted <==

Evolution Mining (EVN) acquired 80% ownership of the Northparkes Operation (NPO) from CMOC Mining effective as of 16 December 2023.The December 2023 Northparkes Ore Reserve estimate is 93.7Mt at 0.51% copper and 0.27g/t gold for 482 kt of contained copper (Table 22) and 828koz of contained gold (Table 23).

Table 22. Northparkes Ore Reserves as at 31 December 2023 – contained copper

Contained Copper Contained Copper Contained Copper Proved Probable Total Ore Reserve Total Ore Reserve Total Ore Reserve
Cut-off Tonnes Copper
Copper
Tonnes Copper
Copper
Tonnes Copper
Copper
Project Type
(CuEq%)

(Mt)
Grade
(%)
Metal
(kt)

(Mt)
Grade
(%)
Metal
(kt)

(Mt)
Grade
(%)
Metal
(kt)
E261,2 UG 0.42%-
0.58%3
0 0 0 35.7 0.60 213 35.7 0.6 213
E224 UG 0.38% 0.7 0.49 4 41.3 0.51 211 42.0 0.51 215
E485 UG 0.40% 0 0 0 0 0 0 0 0 0
E31N
Oxide6
OP 0.50% 0.9 0.31 3 0 0 0 0.9 0.31 3
E31N
Sulphide6
OP 0.34% 3.5 0.29 10 0 0 0 3.5 0.29 10
E31
Sulphide6
OP 0.34% 1.4 0.51 7 0.4 0.39 2 1.8 0.49 9
E28NE
Sulphide7
OP 0.35% 4.7 0.36 17 1.2 0.28 3 5.9 0.34 20
Oxide
Stockpiles8
SP 0.50% 0.7 0.32 2 0 0 0 0.7 0.32 2
Sulphide
Stockpiles8
SP 0.33% 3.2 0.31 12 0 0 0 3.2 0.31 10
Total 15.1 0.35 53 78.6 0.55 430 93.7 0.51 482

‘UG’ refers to underground, ‘OP’ refers to open pit, ‘SP’ refers to stockpiles Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding Competent Person for Operating Underground Reserves (E26, E48) is Mark Flynn, Project Reserves (E22) is Sarah Webster, Open Pit Reserves is Sam Ervin

  1. The E26 SLC Ore Reserves are supported by historic feasibility studies completed in 2015 and 2019. E26 L1N Ore Reserve is supported by a historic Feasibility Study completed in 2018

  2. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E26 SLC assumes US$2.75/lb Cu, US$1,300/oz t, 0.73 AUD:USD, E26 L1N BC assumes US$3.00/lb Cu, US$1,250/oz t, 0.78 AUD:USD

  3. Shutoff values vary by mining block, E26 uses 0.58% CuEq for SLC, reducing to 0.42% CuEq for L1N BC

  4. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E22 assumes US$3.77/lb Cu, US$1,750/oz t, 0.73 AUD:USD

  5. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E48 BC assumes US$3.80/lb Cu, US$1,800/oz t, 0.75 AUD:USD

  6. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E31 and E31N assumes US$3.58/lb Cu, US$1,700/oz t, 0.72 AUD:USD

  7. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E28NE assumes US$3.30/lb Cu, US$1,320/oz t, 0.73 AUD:USD

  8. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, stockpiles assume US$3.72/lb Cu, US$1,750/oz t, 0.74 AUD:USD

Evolution Mining Limited

61

==> picture [83 x 59] intentionally omitted <==

Table 23: Northparkes Ore Reserves as at 31 December 2023 – contained gold

Contained Gold Contained Gold Proved Probable Probable Total Ore Reserve Total Ore Reserve Total Ore Reserve
Project Type Cut-off
(CuEq%)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(%)
Gold
Metal
(koz)
E261,2 UG 0.42%-
0.58%3
0 0.00 0 35.7 0.09 100 35.7 0.09 100
E224 UG 0.38% 0.7 0.37 9 41.3 0.37 496 42.0 0.37 505
E485 UG 0.40% 0 0.00 0 0 0 0 0 0.00 0
E31N Oxide6 OP 0.50% 0.9 0.93 27 0 0 0 0.9 0.93 27
E31N Sulphide6 OP 0.34% 3.5 0.69 77 0 0 0 3.5 0.69 77
E31 Sulphide6 OP 0.34% 1.4 0.45 20 0.4 0.35 5 1.8 0.44 25
E28NE Sulphide7 OP 0.35% 4.7 0.28 43 1.2 0.28 11 5.9 0.28 54
Oxide
Stockpiles8
SP 0.50% 0.7 0.97 23 0 0 0 0.7 0.97 23
Sulphide
Stockpiles8
SP 0.33% 3.2 0.16 17 0 0 0 3.2 0.16 17
Total 15.1 0.44 216 78.6 0.24 611 93.7 0.27 828

‘UG’ refers to underground, ‘OP’ refers to open pit, ‘SP’ refers to stockpiles

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding Competent Person for Operating Underground Reserves (E26, E48) is Mark Flynn, Project Reserves (E22) is Sarah Webster, Open Pit Reserves is Sam Ervin

  1. Shutoff values vary by mining block, E26 uses 0.58% CuEq for SLC, reducing to 0.42% CuEq for L1N BC

  2. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E26 SLC assumes US$2.75/lb Cu, US$1,300/oz t, 0.73 AUD:USD, E26 L1N BC assumes US$3.00/lb Cu, US$1,250/oz t, 0.78 AUD:USD

  3. The E26 SLC Ore Reserves are supported by historic feasibility studies completed in 2015 and 2019. E26 L1N Ore Reserve is supported by a historic Feasibility Study completed in 2018.

  4. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E22 assumes US$3.77/lb Cu, US$1,750/oz t, 0.73 AUD:USD

  5. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E48 BC assumes US$3.80/lb Cu, US$1,800/oz t, 0.75 AUD:USD

  6. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E31 and E31N assumes US$3.58/lb Cu, US$1,700/oz t,

0.72 AUD:USD

  1. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, E28NE assumes US$3.30/lb Cu, US$1,320/oz t, 0.73 AUD:USD

  2. Metal price and foreign exchange rate assumptions used for cut off assessment vary by project, stockpiles assume US$3.72/lb Cu, US$1,750/oz t, 0.74 AUD:USD

Evolution Mining Limited

62

==> picture [83 x 59] intentionally omitted <==

Northparkes Mineral Resource Material Information Summary

A Material Information Summary is provided for the Mineral Resource at Northparkes Operation (NHO) pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 is presented in Appendix A.

Geology and Geological Interpretation

The Northparkes deposits occur within the Ordovician Goonumbla Volcanics of the Goonumbla Volcanic Complex (Simpson, et al., 2000). The Goonumbla Volcanics form part of the Junee-Narromine Volcanic Belt of the Lachlan Orogen (Glen, et al., 2007). At Northparkes, the Goonumbla Volcanics are a folded sequence of trachyandesitic to trachytic volcanics and volcaniclastic sediments that are interpreted to have been deposited in a submarine environment associated with island arc volcanism. Younger unmineralised sediment cover crops out within a kilometre of the deposit to the west and north. The Goonumbla Volcanics at Northparkes have undergone little deformation, with gentle to moderate bedding dips as a result of regional folding. The dominant structure observed to date in the Northparkes area is the Altona Fault, an east dipping thrust fault, which truncates the top of E48, and is known to extend from east of E26 to north of E27.

Within the region, the Goonumbla Volcanics have been intruded by equigranular monzonitic stocks. Quartz monzonite porphyry pipes and dykes, some of which are associated with mineralisation, have intruded both the Goonumbla Volcanics and the equigranular monzonite stocks, as schematically depicted below in Figure 26.

==> picture [433 x 202] intentionally omitted <==

----- Start of picture text -----

E26 E48 E22 E27
0 1 km
Quartz Monzonite Porphyry Monzodiorite Latitic Sediments
Monzonite Stocks Latite dominant volcanics Trachytic Sediments
Altona Fault 0.5% Cu U/G Drives
----- End of picture text -----

Figure 26: South to North Cross-Section of Northparkes geology showing main mineral resources

Sulphide mineralisation occurs as quartz stockwork veins, as disseminations, and as fracture coatings. The highest grades are generally associated with the most intense stockwork veining. Sulphide species in the systems are zoned from bornite-dominant cores, centred on the quartz monzonite porphyries, outwards through a chalcopyrite-dominant zone to distal pyrite. As the copper grade increases (approximately >1.2% Cu), the content of covellite, digenite and chalcocite associated with the bornite mineralisation also increases. Gold normally occurs as fine inclusions within the bornite or more rarely as free gold.

The alteration zoning is complex but tends to be zoned around the quartz monzonite porphyries with a central K-feldspar altered zone surrounded by biotite-magnetite alteration. The K-feldspar alteration zone at E26 is well developed and extends up to 100 metres outboard from the porphyry. This contrasts with the E22, E27 and E48 deposits where K-feldspar alteration is generally less than 10 metres outboard from the porphyries.

Evolution Mining Limited

63

==> picture [83 x 59] intentionally omitted <==

The biotite-magnetite zone is strongly developed at the E22, E27 and E48 deposits, and forms a zone up to 200 metres from the porphyry. It is this biotite-magnetite zone that generates the distinctive annular magnetic features at E22 and E27.

A central white sericite-quartz +/- alunite alteration zone occurs at E26, and to a lesser extent at E48, and is generally associated with the high grade zones within the deposits (Wolfe, 1994), (Wolfe, et al., 1996); (Harris, et al., 2002) At E48, an alteration assemblage of hematite-sericite +/- carbonate occurs both within and proximal to the mineralisation.

All of the Northparkes deposits are cross-cut by late faults/veins filled with quartz-carbonate+/- gypsum, anhydrite, pyrite, chalcopyrite, sphalerite and galena. The associated sericite alteration extends up to 10 metres from fault/veins.

Oxide mineralisation blankets were well developed over the E22 and E27 deposits. The upper blanket was gold rich and copper poor. The dominant copper oxide minerals at E22 and E27 were copper carbonates (malachite and azurite) and phosphates (pseudomalachite and libethenite) with lesser chalcocite, native copper, cuprite and chrysocolla. A gold poor, less well developed, lower supergene copper blanket was also developed over the E26 (and E31N) deposits. At E26 the oxide copper minerals included atacamite, clinoatacamite and sampleite, in addition to those copper minerals observed in E22 and E27.

Two styles of mineralisation are seen at E44: a stratiform south-east dipping 10-20m thick skarn deposit and a set of subparallel and subvertical vein/fault-hosted lenses which may or may not have formed contemporaneously. Both zones are terminated against a NW splay of the Dalveen Fault.

Native gold and gold-silver alloy occurs disseminated in the skarn and carbonate-quartz-haematite-base metal sulphide veins (including silver telluride) and breccias around both the skarn and faults.

Drilling and Survey Techniques

Drilling at Northparkes has been completed between 1980 and 2023. Diamond drill holes (HQ, HQ3, NQ3 and NQ size) are the primary source of geological and grade data informing the grade estimate. Reverse Circulation (RC) drilling was also used to delineate oxide areas of several resources. Core has been oriented using a variety of techniques in line with standard industry practice of the time. Core recovery through the deposit is excellent (>99.5%).

Collar coordinates were picked up by site surveyors using a Leica total station survey instrument and reported in DGA94 MGA Zone 55 grid. A variety of downhole survey methods have been utilised in resource definition drilling, historically most of the diamond drill holes have been surveyed using magnetic instruments whilst more recently high-quality gyroscopic instruments have been used to record down hole survey data in 3-6m intervals.

Data, Data spacing and distribution

Initial resource definition drillhole programs are designed to achieve a nominal mineralisation intersection spacing of 60 m centres. Drillholes are designed and drilled to intersect perpendicular to mineralisation and shear zones bounding mineralisation wherever possible. Subsequent to the initial phase of resource definition drilling, infill drilling is completed to nominal mineralisation intersection spacing of between 30m and 40m centres.

All drilling data located within the block model extents are exported from the Northparkes acQuire drilling database. Following this export, a validation of applicable diamond and reverse circulation (RC) drill holes is performed to produce a modelling sub-set of data to be used for estimation. The majority of near-surface drilling techniques such as rotary-air-blast (RAB), auger (A), air-core (AC) and select open-hole percussion drillholes are eliminated from the modelling database due to sampling biases and integrity issues associated with these drilling techniques. For each of the orebodies, data is restricted to holes that intersect each model volume.

Evolution Mining Limited

64

==> picture [83 x 59] intentionally omitted <==

Database validation is performed by the resource modeller in addition to the validation checks built into acQuire. General, univariant statistics and histograms are generated for each variable to be modelled to understand distribution, skewness, outliers, and general data population character. More detailed checks are performed on variables such as Specific Gravity by comparing the two determination methods for consistency. Finally, a high-level review of the drillhole database is conducted by the resource modeller to identify errors or inconsistencies that could affect estimation.

Sampling and Sub-sampling

Following logging to a standardised geological legend, each core sample is sawn in half with a diamond saw. One half is placed back in the core tray with the other submitted to ALS laboratory in Orange.

Samples undergo further preparation and analysis by an external laboratory, involving crushing to 2 mm, rotary splitting and pulverising using an LM5 mill to 90% passing 75 microns. Crushing and grinding equipment is cleaned using compressed air and brushes between each sample and blanks are inserted at a rate of 1:20 samples to ensure sample contamination is not occurring. Following the pulverisation of the sample a 0.4 g sub-sample is prepared for base metal analysis via multi acid digestion and a 30g sub-sample is taken for analysis via fire assay.

Ore grade analysis for is performed on all samples above 0.40% Cu and determined by AAS.

Sample Analysis Methods

Following sample preparation, a 30 g sub-sample is analysed for Au using a fire assay method at ALS Orange facility. Multi-element analysis (for 48 elements including Copper, Silver, Molybdenum and Sulphur) is completed on a 0.4g sample using multi acid digestion including HF with an ICPAES and ICPMS finish at ALS Brisbane’s laboratory. Samples are not routinely analysed for fluorite. Concentrate samples however are analysed for all potentially deleterious elements.

Historic quality assurance (QA) procedures include the use of multiple certified standards as well as field duplicates inserted at 1:20 ratio for all sample batches sent to the ALS laboratory. A coarse crushed basalt blank sample has been used by Northparkes for QA from 2017-2020. An uncertified basalt blank sample has been used since 2020.

Density

The method of density determination in the current model follows the same process outlined in previous models. Since the discovery of Northparkes, an extensive database of in-situ density measurements has been collected using the Archimedes water displacement principal formula from wet and dry sample weights. The displacement densities are checked using a volumetric calliper determination.

Density measurements are used in conjunction with an elemental assay analysis to generate a stoichiometric regression formula that is applied to every sample and subsequently used in resource estimation.

Quality Assurance and Quality Control

NPO currently uses multiple matrix matched CRMs and a pulverised blank and coarse basalt blank sample to monitor preparation and assaying processes. CRMs were inserted at a rate of 1 in every 15 samples and blanks are inserted at 1 in every 20 samples. Field duplicates inserted at 1 in every 20 samples for RC drill sampling and at a rate of approximately 1 in 50 for evaluation diamond drill programs and crush and pulp duplicates inserted at 1 in every 20 samples were used to monitor the deposit variability and analytical precision. ALS laboratory inserts QA samples during the analytical process in line with their internal protocols.

The Competent Person has completed a review of the QC results received between December 2022 and December 2023 and considers that the data utilised to complete this estimate is accurate and precise and has been collected and stored using industry standard practices. The site also has a long history of production and reconciliation against Mineral Resource models providing further confidence in the quality of analytical data.

Evolution Mining Limited

65

==> picture [83 x 59] intentionally omitted <==

Estimation Methodology

The reported resource block models have been generated by Resource Specialists H&S Consultants Pty Ltd (H&SC).

Downhole composites are compiled using Datamine RMTM software within each of the interpreted domains. Samples are composited to a minimum 0.99m length (nominally 2 or 4m depending on the size of the ore zones) and composite start depths honour the domain boundaries.

Variography on the major elements Cu, Au, Ag, and As is used to guide sample search ellipse dimensions and orientations tempered with the interpreted plunges and extents of mineralisation envelopes. Estimation domains are based on mineralisation style (e.g. oxide vs primary) and similarities of exploratory population statistics which generally results in an almost unconstrained estimate due to the fact that mineralisation is not limited to a particular rock type or within “hard” geological boundaries. In all deposits except E44, ordinary kriging (OK) was used to estimate Cu%, Au g/t, Ag g/t, As g/t and density (t/m3) into parent blocks of either 10m or 20m dimension depending on deposit geometry, selective mining method and drill sample spacing. Because E44 is envisioned to be a gold pit MIK was chosen as the more appropriate method (to enable a recoverable resource estimate).

The tonnes and grade estimates were validated by comparing global totals and averages to previous estimates if available, mean drill sample composited grades to mean estimated grades (pass 1 only), mill production statistics if available, grade trends in easting, northing and elevation slices (swath plots), visual check of estimated grades against composited grades, and debugging the estimation process. Mine to mill reconciliation data gathered over the past 10 years for E48 lift 1 block cave indicates that estimate of reserve to be accurate +/- 5% in both tonnes and copper grade.

Resource Classification

Block model cells are assigned an estimation search pass number according to distance from block to samples for each element. For most estimates the Cu pass number is converted to a preliminary classification: Pass 1= Measured; pass 2= Indicated; pass 3= Inferred while for deposits with a high Au to Cu ratio an average of the Cu and Au pass numbers is used. The geostatistical slope of regression is used to downgrade individual blocks that have lower geostatistical confidence. Finally, the classification is smoothed to reduce the occurrence of patchy classification. The approach is consistent to that used previously.

The classification appropriately reflects the estimator’s (H&S) view of the deposit. The NPO CP reviews the classification in the block models generated by H&S consultants and decides with guidance from the project geologists, if the classification adequately reflects the current geological confidence and knowledge of controls and continuity. The final classification may be altered by the CP prior to reporting.

Mineral Resource Reporting and assigned Cut-off criteria

Resources are reported within mine design volumes if available, either above zero cut-off grade (COG) to reflect the non-selective block cave method or above a cut off based on Nett Smelter Return (NSR) and site costs to reflect the use of shut-off grades. For resources that have been converted to reserve, the resource is reported outside of the mine design volumes used for the reserve assessment.

Cut-off grades have been calculated using a copper equivalence based on commodity prices. Some of the resources were first reported in 2013 as part of the Step Change Project and have not been changed since that time.

Depletion

Depletions are made based on development surveyed volumes, conveyor weightometers and grades from samples taken from drawpoints. These are reconciled to processing plant output and surveyed stockpile volumes using additional information available such as loader bucket weights and counts (for E26 SLC and L1N) as well as truck volume scanning and counts (for E26 SLC). Depletions are considered up to 31

Evolution Mining Limited

66

==> picture [83 x 59] intentionally omitted <==

December 2023. Previously mined areas that are exhausted of Ore Reserves, including development areas, are not reported as Mineral Resource.

Reserves

Resource that has been converted to Reserves is not included in the Mineral Resource reported at Northparkes.

Sterilisation

Remnant areas of Mineral Resource outside of Ore Reserve volumes which no longer have reasonable prospects of economic extraction are removed from the reported Mineral Resource inventory.

Audits or reviews

Internal peer reviews of the reported Mineral Resource and Ore Reserve are undertaken annually by Evolution’s Transformation & Effectiveness / Technical Services team. Internal corporate governance systems and processes are in place to ensure all required supporting data and documentation is securely stored for future reference.

An external audit of the reported Mineral Resource & Ore Reserve technical report was competed by Xtract Mining Consultants in 2019. Although the review found the report to contain no material issues affecting the reported Mineral Resource and Ore Reserve, several improvements were recommended. All key recommendations have been implemented in the December, 31 2023 Mineral Resource and Ore Reserve estimate.

Evolution Mining Limited

67

==> picture [83 x 59] intentionally omitted <==

Northparkes Ore Reserve

Material Assumptions for conversion to Ore Reserves

The Ore Reserve estimate for 2023 is based on updated and validated Mineral Resource block models developed between 2013 and 2023 which take into account all completed drilling and updated geological interpretation and estimation. Pre-Feasibility and Feasibility studies were subsequently completed between 2017 and 2022. Changes in the reported Ore Reserve for E26, E48, E31, E31N and E28NE ore bodies, have been driven by mining depletion and in the case of E48, removal of the remaining residual reserve which is uneconomic. For E22, total tonnage and grades have changed as a result of revisions to the cave flow modelling and cave shapes. The mixing parameters were revised to reduce the amount of horizontal mixing within the estimation software. Caveability modelling and refining of the undercut initiation location produced new cave shapes that were used to constrain the production simulation.

Cut-off parameters

Cutoff criteria at Northparkes is determined via economic evaluation considering the Net Smelter Return (NSR) and operating costs at the Northparkes site. Cutoff criteria vary per deposit and have been evaluated based on studies completed at different times using differing copper and gold price assumptions. Table 24 summarises the price assumptions used and the cutoff criteria applied. For Ore Reserve reporting the cut-off grade determined for each deposit is applied in either the PCSLC sublevel caving production model or PCBC block caving production model’s which taking into account material flow and dilution within the sub-level or block cave.

Table 24: Northparkes Ore Reserves price assumptions for cut off evaluation

E26 SLC E26 L1N BC E22 BC E31/E31N OP E28NE OP
Date of Study 2017 2018 2023 2022 2022
Copper (USD$/lb) 2.75 3.00 3.77 3.58 3.30
Gold (USD$/oz) 1,300 1,250 1,750 1,700 1,320
(AUD: USD) 0.73 0.78 0.73 0.72 0.73
Shut Off Grade
(CuEq)
0.58% 0.42% 0.38% 0.34% 0.34%
Mining Cost
($/t)
$35.00 $27.50 $28.00 $7.51 $5.30

For E26 L1N BC, the footprint was assessed using a AUD$27.5/tonne cut off and is applied in the PCBC cave production model and determined through economic evaluation, considering the Net Smelter Return (NSR) and operating costs of the Northparkes site.

For E26 SLC shut off is set at AUD$35 NSR, with sensitivities completed between AUD$30 - $40. The cut-off grade of 0.58% CuEq is applied in the PCSLC sublevel caving production model and determined through economic evaluation, considering the NSR and operating costs of the Northparkes site.

For E22, AUD$28 mining cost cut-off value used for footprint and best height of draw. The cost to develop a draw point was assessed in MJH order of magnitude study based on E26L1N construction actuals. This value was again used for E22 when considering the footprint extent stage. The cost per draw point is assessed at

Evolution Mining Limited

68

==> picture [83 x 59] intentionally omitted <==

AUD$566k. The final tonnes are complete when the 0.30% Cu is reached. This corresponds also with the active draw point numbers declining below economic tonnages for a loader.

For the open-pits (E31, E31N and E28NE) all material contributing to the NPV of the deposit within the existing mine designs is included within the Ore Reserves. A cutoff grade of 0.34% CuEq has been calculated.

Mining factors or assumptions

Mining studies and current underground cave mining activities at Northparkes support the appropriateness of the selected mining methods as the basis of the forward Ore Reserve estimate. Ongoing geotechnical studies and monitoring utilising experience and data from the current underground operations provide ongoing key direction for stability, design and schedule sequence parameters.

E26 L1N Block Cave

For E26 L1N BC, pre-feasibility (completed in 2017) and feasibility (completed in 2018) studies have been conducted which show that the block caving method provides the highest value and best fit for the deposit and operation.

Geotechnical engineering assessments have shown that the rock mass is amenable to caving. Numerical modelling forecasts are reflected by cave propagation interpretations to date, with consideration to the observed surface expression, cave trackers and seismic system data.

The mine design for the extraction level incorporates drawbell spacing of 30mx18m, extraction drives at 30m centre to centre spacing. These design parameters are in line with on-site experience and assessed to be geotechnically stable within the bounds of the mine plan that supports the stated Ore Reserve.

Block caving is a bulk mining method with limited selectivity, where dilution must be accepted in order to recover caved ore columns. Dilution from production activities is quantified through cave flow modelling and is included in the reported Ore Reserve along with supporting economic evaluations. Recovery and dilution factors are not used as part of the Ore Reserve estimation process.

All major infrastructure supporting the E26 L1N BC Ore Reserve has been constructed, including the underground crushing and conveying system, hoisting shaft, pumping and ventilation systems.

Access to the E26 L1N BC is via surface portal and decline, with additional means of egress via a ladderway system and redundant declines and the hoisting shaft.

E26 SLC

For E26 SLC, pre-feasibility and feasibility studies have been conducted which show the sublevel caving method provides the best value for the recovery of the material between the L1 and L2 Block caves.

Geotechnical engineering assessments have shown that the rock mass is amenable to caving and is reflected in the observed results from mining the top levels of the SLC.

The mine design for the remaining levels incorporates 30m sub-level spacing, 15m drive spacing (centre to centre), 5m wide cross cuts and a standard 11-hole ring pattern with 3.0m burden. These design parameters are in line with benchmarked operations and assessed to be geotechnically stable within the bounds of the mine plan that supports the stated Ore Reserve.

Sub-level caving is a bulk mining method with limited selectivity, where dilution must be accepted in order to recover blasted ore. Dilution from production activities is quantified through cave flow modelling and is included in the reported Ore Reserve along with supporting economic evaluations. Recovery and dilution factors are not used as part of the Ore Reserve estimation process.

Evolution Mining Limited

69

==> picture [83 x 59] intentionally omitted <==

The remaining level draw rates are set at 150% and 200% of the fired material for level 5 and level 6 respectively, with previously fired material and caved material between the E26 SLC and E26 L1 BC diluting the fired material.

Blasted rock from development activities reports to the same materials handling system as production ore from the cave. The development material is included in the mine plan, classified by means of block model interrogation and converted to Ore Reserve in the same manner as production material.

All major infrastructure supporting the E26 SLC Ore Reserve has been constructed, including the underground crushing and conveying system, hoisting shaft, pumping and ventilation systems.

Access to the E26 SLC is via surface portal and decline, with additional means of egress via a ladderway system, redundant declines and the hoisting shaft.

E22 Block Cave

E22 Block Cave pre-feasibility was completed in 2022 and feasibility study is underway with completion scheduled for 2024. Trade off studies have been conducted which show that the block caving method provides the highest value and best fit for the deposit and operation.

Geotechnical engineering assessments have shown that the rock mass is amenable to caving. Numerical modelling of cave propagation has been undertaken and included in the PCBC production estimates.

The mine design for the extraction level incorporates an El Teniente layout with draw bell spacing of 30mx18m. The undercut geometry is an inclined sawtooth design as used in E26L1N. These design parameters are in line with on-site experience and assessed to be geotechnically stable within the bounds of the mine plan that supports the stated Ore Reserve.

Block caving is a bulk mining method with limited selectivity, where dilution must be accepted in order to recover caved ore columns. Dilution from production activities is quantified through cave flow modelling and is included in the reported Ore Reserve along with supporting economic evaluations.

E31, E31N and E28NE

The E31, E31N and E28NE feasibility studies were completed in 2022, demonstrating the suitability of conventional open-pit mining techniques to the deposits.

Geotechnical assessments were carried out, indicating no unfavourable pre-existing conditions.

The use of smaller open-pit mining equipment has been deemed to allow ample selectivity given the deposits’ disseminated nature and geological extent.

Metallurgical factors or assumptions

Processing has been conducted on site for more than 25 years through the Northparkes treatment plan and concentrators. Northparkes operates a conventional flow sheet for ore processing, which consists of four stages: crushing, grinding, flotation and thickening/filtering. The plant was commissioned in September 1995 and designed to process both copper gold oxide and sulphide ore; the cyanide/oxide processing circuit was decommissioned in 1996. Copper and gold are recovered using a floatation process and are contained within the resulting copper concentrate. This concentrate is transported by road to Goonumbla where it is railed to the port of Newcastle.

A combination of bulk sampling and on -stream analysis is conducted to confirm plant performance.

The Ore Reserve estimate is reported ‘as mined’ and does not include metallurgical recovery factors. Metallurgical recovery is accounted for by the NSR calculations, which support the selected cut of grades.

Evolution Mining Limited

70

==> picture [83 x 59] intentionally omitted <==

Comminution and flotation test work is performed throughout the study stages. Composites are selected from diamond drilling and designed to representative geometallurgical domains. Where multiple ore sources are mined concurrently, blend test work on mixed ore is performed to evaluate impacts and estimate recoveries during processing.

Infrastructure

The surface infrastructure required to support mining of the reported Ore Reserve is in place. This includes items such as sealed roads for site access, electrical supply, water supply, processing plant, tailings storage facility (TSF), offices, workshops and stores.

Major underground infrastructure required to extract the E26 SLC and E26 L1N BC Ore Reserve is in place, with L1N BC mine construction having been completed in 2022 and capital development for E26 SLC completed in 2023. The existing open-pit crusher facility is deemed adequate to meet the primary crushing requirements of the open-pit reserves, with no impediments envisaged to haulage thereof.

The E22 block cave will be connected to existing facilities at the surface secondary crusher and processed though the existing concentrator plant. The E22 block cave will require the following mining infrastructure to support the extraction level development:

  • Box cut, portal and decline access

  • Ventilation shafts and fans

  • Conveyor material handling system extension

  • Primary crushing chamber and equipment

  • Underground workshop

Costs

Estimates for minor capital items that support the Ore Reserve have been informed by current industry benchmarks and previous site experience with similar projects.

Sustaining capital is forecast annually as part of the Budget and Life of Mine (LOM) planning cycle, reflecting actual performance and the mine schedule.

Operating costs are calculated and reconciled with actual costs on a monthly basis and as part of annual financial reviews. The availability of reliable historic data for the site provides a robust basis for estimating the operating costs.

Transport, treatment, and refining charges are included in financial models and are based on existing sales agreements.

Revenue

Net Smelter Return for the reported Ore Reserve has been derived using the site concentrate sales model. The model accounts for concentrate specification, transport cost, treatment and refining charges.

A range of commodity prices have been used to evaluate the revenue based on the timing of the studies and the timing of periodic reviews. Refer Table 24 for assumptions used for cut-off calculation.

Evolution Mining Limited

71

==> picture [83 x 59] intentionally omitted <==

Economic

Northparkes has produced at consistent rates for several years, allowing cost and revenue to be well understood. The mine plan from which the Ore Reserve is derived, including cut-off grade selection, is tailored to maximise Net Present Value (NPV) using LOM pricing assumptions.

The Ore Reserve has been assessed using a financial model. The assessment process has demonstrated that extraction of the reported Ore Reserve can be reasonably justified.

Classification

For E26, resource classification sits within measured or indicated for the L1N BC and the SLC, this data informs the cave flow models.

The ore reserve estimate for the L1N Block Cave in consideration of the mining modifying factors, specifically cave propagation underbreak risk and dilution from the adjacent cave, the reserve is deemed to be probable by the competent person. Noting that there is no evidence of underbreak from current monitoring and dilution of material from Lift 1 is limited to drawpoints near to the interface of the two caves.

The ore reserves estimate for the E26 SLC in consideration of the high draw factor for the final levels the reserve is deemed to be probable by the competent person.

For E22 the resource classification in the PCBC schedule is within measured and indicated with <1% inferred material. The consideration for mining modifying factors as noted above with caveability of E26L1N, the reserve is deemed to be probable by the competent person. The development portion of the reserves is a % of the blasted tonnages in the draw bells and undercut and thus has an increased confidence of recovery. On this basis the development is classified as proved reserves.

For the open-pit reserves, E31 and E31N measured resources have been fully converted to proved reserves, given that modifying factors are well understood. The indicated resource has been converted to probable reserve.

The measured component of E28NE is considered proved given the advanced understanding of the deposit and its mining parameters, while the indicated portion is converted to probable.

Audits or reviews

Internal peer review and external review form part of the feasibility study process and has been completed on areas including geotechnical stability, costs, cave flow, ventilation, operability and infrastructure.

In 2023, SRK Consultants completed a high-level review of the E26 L1N Block cave, including the draw strategy and cave propagation, which underpin the Ore Reserve.

In 2021, SRK Consultants reviewed the E22 PFS work covering geological interpretation, geotechnical studies, mining assumptions, ventilation, material handling system and major risks. There were no material concerns identified by SRK.

Discussion of relative accuracy / confidence

Both mine and mill processes are well proven, having greater than twenty-five years of experience. With continued use of the same methods there is high confidence in being able to extract the stated Ore Reserve.

The accuracy of the Ore Reserve estimate is largely dependent on the accuracy of key inputs, the Mineral Resource and cave flow models. These inputs have been reviewed independently as part of the feasibility study works and as part of ad-hoc validation works.

Evolution Mining Limited

72

==> picture [83 x 59] intentionally omitted <==

Red Lake Operation (RLO) Mineral Resource Statement

The Red Lake Operation Mineral Resource estimate has been prepared in accordance with the 2012 Edition of the “Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves” (the JORC Code 2012) and the ASX Listing Rules.

This information summary has been provided for the Red Lake Operation Mineral Resource pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 – Table 1 is presented in Appendix A4.

The 31 December 2023 Red Lake Operation (‘RLO’) Mineral Resource has been estimated at 55.1Mt at 6.56g/t Au for 11,631koz gold. This represents a 9% (5.31Mt) decrease in tonnes and 6% (711koz) decrease in ounces compared with the December 2022 Mineral Resource reported at 60.4Mt @ 6.35 g/t Au for 12,342 koz gold. Mining depletion for the period accounts for a decrease of 121koz, reclassification of mineral resource category at the Aviation deposit accounted for a decrease of 120koz, whilst a review of costs and cutoff criteria at Lower Red Lake, Lower Campbell and Cochenour resulted in a decrease of 481koz. This was slightly offset by addition’s due to new drilling defining extensions to known mineralisation (increase of 17koz).

The Mineral Resource has been reported within optimised stopes which were developed using a A$2,500 per ounce price assumption, it is inclusive of Ore Reserves but excludes mined areas and remnant resource areas sterilised by mining activities.

Table 25. Red Lake Operation Total Mineral Resource at 31 December 2023

Gold Gold Measured Measured Measured Indicated Indicated Total Mineral Resource Total Mineral Resource Total Mineral Resource
Inferred
Project Type Cut-
Off
(g/t)
Tonnes
(kt)

Gold
Grade
(g/t)

Gold
Metal
(koz)

Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Lower
Campbell
UG 2.9 - - - 3.73 6.61 793 2.48 5.41 432 6.22 6.13 1,225
Upper
Campbell
UG 3.3 - - - 8.67 10.55 2,942 4.46 10.23 1,466 13.13 10.44 4,408
Lower Red
Lake
UG 2.9 - - - 10.71 5.34 1,839 4.77 5.22 800 15.48 5.30 2,639
Upper Red
Lake
UG 3.3 - - - 4.31 5.62 778 2.07 6.26 417 6.38 5.83 1,196
HG Young UG 2.5 - - - 1.38 5.06 224 1.47 4.63 219 2.85 4.84 443
Cochenour UG 2.7 - - - 1.47 5.91 280 5.68 4.94 902 7.15 5.14 1,182
McFinley UG 2.5 - - - 2.13 4.63 317 1.78 3.84 220 3.91 4.27 537
Stockpile - - - 0.01 4.57 2 - - - 0.01 4.57 2
Total 0.00 0.00 0 32.40 6.89 7,174 22.72 6.10 4,456 55.12 6.56 11,631

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding. Mineral Resources are reported inclusive of Ore Reserves. UG denotes underground. Red Lake Mineral Resources Competent Person is Alain Mouton

Table

Evolution Mining Limited

73

==> picture [83 x 59] intentionally omitted <==

. Comparison of December 2022 and December 2023 RLO Total Mineral Resource Estimates

RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023 RLO Mineral Resources Comparison - December 2022 to December 2023
Period Measured Indicated I nferred Total
Tonnes Grade
Au
(g/t)
Cont.
Metal
Au
(koz)
Tonnes Grade
Au
(g/t)
Cont.
Metal
Au
(koz)
Tonnes Grade
Au
(g/t)
Cont.
Metal
Au
(koz)
Tonnes Grade
Au
(g/t)
Cont.
Metal
Au
(koz)
(Mt) (Mt) (Mt) (Mt)
Dec-22 0 0.00 0 35.65 6.66 7,639 24.78 5.90 4,702 60.44 6.35 12,342
Dec-23 0 0.00 0 32.40 6.89 7,174 22.72 6.10 4,456 55.12 6.56 11,631
Absolute
Change
0 0.00 0 -3.25 0.22 -465 -2.06 0.20 -246 -5.31 0.21 -711
Relative
Change
0% 0% 0% -9% 3% -6% -8% 3% -5% -9% 3% -6%

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding.

==> picture [489 x 264] intentionally omitted <==

Figure 27. Waterfall diagram illustrating areas of change in ounces in reported Mineral Resource (Dec 2022 -Dec 2023)

Evolution Mining Limited

74

==> picture [83 x 59] intentionally omitted <==

Red Lake Ore Reserve Statement

The Red Lake Operation Ore Reserve estimate has been prepared in accordance with the 2012 Edition of the “Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves” (the JORC Code 2012) and the ASX Listing Rules.

This Material Information summary has been provided for the Red Lake Reserve pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 – Table 1 is presented in Appendix A4.

The December 2023 Red Lake Operation Ore Reserve has been estimated at 12.4Mt at 6.87g/t gold for 2,748koz (Table 26). This represents a decrease of 130koz compared to the December 2022 Ore Reserve estimate of 13.0Mt at 6.90g/t gold for 2,878koz (Table ). Changes in the reported Ore Reserve were driven by mining depletion (-121koz), design changes (16koz), changes in geological interpretation and estimation (- 6koz) and additions of 13koz for material defined and mined outside the 2022 Ore Reserves. Refer Figure 2 for waterfall graph illustrating changes year on year for the reported Ore Reserve.

Table 26. Red Lake Operation Ore Reserve 31 December 2023

Gold Gold Proved Probable Total Ore Reserve Total Ore Reserve Total Ore Reserve
Project Type Cut-
off
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
Metal
(koz)
Lower
Campbell
UG - - - 1.0 5.71 185 1.0 5.71 185
Upper
Campbell
UG - - - 7.8 7.38 1,859 7.8 7.38 1,859
Lower Red
Lake
UG - - - 2.1 6.32 435 2.1 6.32 435
Upper Red
Lake
UG - - - - - - - - -
Cochenour UG - - - 0.7 6.12 129 0.7 6.12 129
HG Young
UG - - - 0.4 5.26 60 0.4 5.26 60
McFinley
UG 0.4 5.66 78 0.4 5.66 78
Inventory - - - 0.01 4.72 2 0.01 4.72 2
Total - - - 12.4 6.87 2,748 12.4 6.87 2,748

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding Red Lake Operation Ore Reserve Competent Person is Brad Armstrong

Table . Comparison of December 2022 and December 2023 Red Lake Operation Ore Reserve

Period Proved Probable Total Ore Reserves
Tonnes Gold
Grade
(g/t)
Gold
metal
(koz)
Tonnes Gold
Grade
(g/t)
Gold
Metal
(koz)
Tonnes Gold
Grade
(g/t)
Gold.
Metal
(koz)
(Mt) (Mt) (Mt)
Dec-22 - - - 13.0 6.90 2,878 13.0 6.90 2,878
Dec-23 - - - 12.4 6.87 2,748 12.4 6.87 2,748
Absolute
Change
- - - -0.5 -0.03 -130 -0.5 -0.03 -130
Relative
Change
- - - -4% -0.4% -4% -4% -0.4% -4%

Data is reported to significant figures to reflect appropriate precision and may not sum precisely due to rounding

Evolution Mining Limited

75

==> picture [83 x 59] intentionally omitted <==

==> picture [489 x 285] intentionally omitted <==

  • Figure 28. Waterfall diagram illustrating areas of change in ounces for reported RLO Ore Reserve December 2022 to December 2023

Evolution Mining Limited

76

==> picture [83 x 59] intentionally omitted <==

MATERIAL INFORMATION SUMMARY

Material Information Summaries are provided for the Red Lake Operation Mineral Resource and Ore Reserve at Red Lake pursuant to ASX Listing Rules 5.8 and 5.9 and the Assessment and Reporting Criteria in accordance with JORC Code 2012 requirements. The Assessment and Reporting Criteria in accordance with JORC Code 2012 is presented in Appendix 2.

Red Lake Mineral Resource

Material Assumptions for Mineral Resources

The RLO Mineral Resource estimate is defined by an underground mining shape optimiser using an A$2,500/oz gold price assumption. The RLO underground mines have assumed conventional mining techniques and parameters typical of current Evolution underground operations. Assigned mining and processing costs and metallurgical recoveries used in the development of underground Mineral Resource reporting shapes and are supported by current mining data and metallurgical recoveries.

Property Description, Location and Tenement holding

Red Lake Operations is located near the municipality of Red Lake, approximately 180km North of the town of Dryden, Ontario, and 100km east of the Manitoba-Ontario border. Red Lake is accessed by car by the TransCanada Highway (#17) and north on Highway 105. The town is also accessible by air via the Red Lake airport located near the town of Cochenour (Figure 29).

==> picture [492 x 342] intentionally omitted <==

Figure 29. Surface map of the Red Lake Operations

Evolution Mining Limited

77

==> picture [83 x 59] intentionally omitted <==

Geology and Geological Interpretation

Red Lake mineralisation is hosted in the Red Lake greenstone belt. Mineralisation is associated with multiple episodes of volcanism, sedimentation, plutonism and deformation and is hosted in a variety of rock types within the Red Lake Greenstone belt. Economic zones of mineralisation are characterised by vein hosted gold systems accompanying sulphide replacement within sheared mafic to komatiitic basalts Figure 30.

The Red Lake/Campbell, Cochenour, HG Young and McFinley deposits are hosted within significantly folded and sheared portions of the Balmer Assemblage dominated by tholeiitic basalt and komatiitic basalt intruded by felsic, mafic and lamprophyric intrusive rocks. Shear zones act as primary hydrothermal fluid corridors and host significant portions of the gold mineralisation in the area. Other significant mineralised structures occur within lower-strain areas of the stratigraphy, usually associated with brittle conjugate fracture systems proximal to rheologically contrasting lithology contacts.

Orebodies are generally steep dipping -50 to -60 degrees; lode geometry varies with relative position within the folded stratigraphy. Individual lenses of mineralisation vary considerably in thickness being mostly very narrow 0.3 – 1.0m but locally can contain multiple stacked lenses and stockworks and disseminations in excess of 10m in width. Gold appears as free milling gold, gold associated with sulphides, with magnetite as well as refractory, arsenopyrite-associated gold. It is common for zones to have multiple styles of mineralisation within the same host lithology.

The Red Lake/Campbell system has been defined to date to extend approximately 3,000m along strike and has drilling intercepts over a vertical extent of 3,000m. The Cochenour mine as modelled in this report which excludes the historically mined upper zones, commences approximately 750m below surface and has been defined along a strike length of 600m and extends 700m vertically. The updated McFinley model has been defined over a 1350m strike length, 1750 vertical extent and 800m across strike.

==> picture [480 x 333] intentionally omitted <==

Figure 30. Surface Geology map of Red Lake Operation

Evolution Mining Limited

78

==> picture [83 x 59] intentionally omitted <==

Drilling Techniques

Multiple contractors have been used at the RLO over the project life. Drilling has been completed predominantly by surface and underground drill rigs using diamond drillcore drilling methods. Surface diamond drilling was completed to obtain NQ (47.6mm) drillcore. Underground diamond drillcore holes were typically BQ (36.5mm) and AQTK (30.5mm) sizes with a minor amount of NQ2 (50.5mm) holes. Underground definition and delineation (grade control) drilling has been completed to obtain AQTK (30.5mm) diameter drillcore. At the Bateman project drilling was completed predominantly using diamond drillcore methods to attain NQ (47.6mm) drillcore. In some instances, in areas where a small drill rig was required BQ sized drillcore was attained.

Data spacing and distribution

Drill programs within the Red Lake deposits are ongoing and staged; the drill spacing is designed to adequately delineate the lode and confirm geological and grade continuity of the mineralisation. An initial drill program is designed to penetrate target zones on a nominal even spaced grid pattern (40m by 40m), as perpendicular to the ore zone as practicable. This approach defines and demarcates economic mineralisation to a level which supports estimation of a global Mineral Resource, to an Inferred Resource classification (80m by 80m for McFinley). This initial phase of drilling is then followed by an infill 20m by 20m spaced program to define economic mineralisation to an Indicated Mineral Resource Classification (40m by 40m for McFinley) sufficient to support interim mine design and scheduling. A phase of less than 20m by 20m (typically between 6m by 6m to 10m by 10m) spaced grade control drilling, and/or underground face sampling may be completed to delineate ore and waste and support the accurate economic extraction of ore.

Sampling and Sub-sampling

Drill core of NQ2 and BQTK core size are cut in half using an automatic core saw to produce an approximate 3kg to 5kg sample. The remaining half of the core is kept in labeled core boxes and stored on site. Where core is oriented, it is cut to preserve the bottom of hole orientation line. In some instances, core may be quarter cut and sent for analysis. The smaller drill core size (ATQ) was whole core sampled. More recently (since 2022) grade control (production) NQ2 drill core is whole core sampled to maximise the mass of sample sent for analysis.

Drill core and rock chips (from UG ore drive development headings) samples are sent to an external laboratory. External labs used continuously for the past several years are: Actlab in Thunder Bay, Ontario since 2015 and SGS in Red Lake, Ontario since 2006.

Sample Analysis Methods

When received at the external laboratories SGS or Actlab the samples are oven dried for 12 hours (60°C), jaw crushed to 90% passing <2mm and riffle split to a maximum sample weight of 0.5kg. This sub sample is then pulverised in a one stage process, using a LM2 pulveriser, to a particle size of >90% passing 75um. Approximately 250g of the pulverised sample is extracted by spatula to a numbered paper pulp bag that is used for a 30g fire assay charge (before 2020) or a 50g FA charge (post January 2020). The pulp is retained, and the bulk residue is disposed of after four months

Quality Assurance and Quality Control

Single shot downhole surveys were used to monitor hole deviation during drilling. Geologists are contacted by the drillers if the single shot data is outside of the designated tolerances (3° on dip and azimuth). Downhole multi-shot surveys were also performed using a north-seeking gyro. Collar positions are surveyed and checked against the proposed collar position.

All core is metre marked and where orientation has been stipulated marked with a bottom of hole orientation line. Certified Reference Materials (CRM) and blanks are inserted 1 in 10 samples. The frequency of field duplicates is determined by drill area. Laboratory check samples (including laboratory repeat assays, crushed

Evolution Mining Limited 79

==> picture [83 x 59] intentionally omitted <==

sample duplicates and pulp duplicates) are reviewed monthly. CRM and Blank performance are checked on a batch-by-batch basis during the assay import process and reviewed over time. Automated validation flags are in place within the database import process and are reviewed by the geologist and actioned. Re-assays are ordered for the sequence of samples around the failed sample up to and including the nearest passing check samples. The re-assay values are reviewed in the same way and if acceptable passed into the database. All assays are stored in the database, failed results are downgraded with a priority field.

Grind quality is audited during laboratory inspections and sieve test reviews. Any issues discovered during the lab audit are brought to the attention of the lab manager or proxy at that time. All findings from the laboratory are actioned and copies of the report are saved in the sites QA/QC documents on a secure server.

Density

Dry bulk density of drill core was measured on site by trained field assistants, using the water immersion method. Dry bulk density is calculated as:

𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑚𝑝𝑙𝑒 𝑖𝑛 𝐴𝑖𝑟 𝐷𝑟𝑦 𝑏𝑢𝑙𝑘 𝑑𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑐𝑜𝑟𝑒= (𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑚𝑝𝑙𝑒 𝑖𝑛 𝐴𝑖𝑟−𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑚𝑝𝑙𝑒 𝑖𝑛 𝑊𝑎𝑡𝑒𝑟)

Statistical analysis and review of dry bulk density results is completed per lithology. They range from 2.65t/m[3] to 3.0t/m[3] .

Estimation Methodology

Processes involved in the creation of the resource models are saved in Datamine macros (*.mac) on a secure Evolution SharePoint site.

In summary, validated drillhole samples are composited to 1m lengths using Datamine software and honour interpreted estimation domain boundaries. Estimation domains are developed taking into account geological logging and assay data from drillholes and underground grab samples, as well as geological mapping and structural information for underground development.

Following internal peer review of draft estimation domains, statistical analysis of coded composite data and if required refinement of estimation domains is undertaken. Once final estimation domains have been developed, statistical and spatial analysis is undertaken to model the spatial continuity of mineralisation for each of the modelled lenses.

Given the relative nuggety nature of gold mineralisation and the faulted and folded nature of the ore at RLO, a restrictive kriging, dynamic anisotropy (DA) estimation approach has been used to ensure robust local block estimates are obtained. The restrictive kriging methodology in conjunction with the application of appropriate search criteria and the application of appropriate top cuts help control the effect of extreme grades on the estimate. This process involves categorizing the composited data into a low-grade population and high-grade population based on a grade threshold decided based on the statistical analysis of each individual lode/estimation domain. Indicator variography is performed on the composite data using the chosen grade threshold and the resultant variography is used to estimate a probability of a block being in the high-grade core of the domain versus the surrounding lower grade mineralised portion of the domain using Ordinary Kriging.

The estimated probability is flagged back onto the composites and data is sorted into low grade and highgrade bins based on a 40% probability threshold that the block was in a high-grade area. Top cuts are established for the low and high-grade binned data. The low-grade top cut is decided based on the presence of high-grade data in the low-grade bin and the distribution of grade for the low-grade dataset. The high-grade top cut is established using all the data for the domain applying the disintegration method on a probability plot.

Spatial analysis and development of variogram models for use in grade estimation is completed using all coded composite data within each of the modelled lodes / estimation domains. In cases, where there is insufficient data for the development of robust variogram models then a variogram model from a domain that has adequate samples and is of a similar mineralisation type and style will be used for estimation.

Evolution Mining Limited

80

==> picture [83 x 59] intentionally omitted <==

A multi-pass search strategy is used in the estimation process and search dimensions, sample selection and estimation criteria are optimised taking into account the modelled semi-variogram ranges for each domain, the drillhole spacing present and the results of kriging neighbourhood analysis (KNA) for each domain.

The final gold estimate involves running an ordinary kriging estimate taking into account the probability of the block being within the high-grade or low-grade portion of the domain and the associated estimates taking into account the application of different top cuts based on whether the block is coded as a low-grade or high-grade block.

As models are being updated with additional drilling information it is possible to accurately demarcate the high grade internal core of domains. Consequently it is then possible to develop separate estimation domains to demarcate the high grade cores from surrounding lower grade material and apply a hard boundary ordinary kriging estimation approach instead of the restrictive kriging approach used for region with wider spaced drilling.

Parent block sizes vary from 4m2m4m to 5m5m5m depending on model area where the latter parent size was implemented for Cochenour, HGY and McFinley. Block grades were compared with composite of cut data to ensure kriging grades were represented in block grades.

Inverse Distance squared (ID2) and Nearest Neighbour (NN) estimates are also run as a check estimate against the Ordinary Kriged estimate to compare global domain estimates and investigate differences between applied estimation techniques and approach.

No assumption of mining selectivity has been incorporated in the estimate.

Estimation Validation

Validation of the Mineral Resource comprised comparing block grades (OK, ID2 and NN) against the data used to inform the estimate on a domain by domain basis, visual comparison of the informing data against the estimate and the use of swath plots showing grade trends by easting northing and elevation of the input data against the estimate. The de-clustered top cut mean is also compared to the block grades for each domain. Changes between estimates (year on year) and changes in designed optimised underground mining shapes (MSO’s) are also investigated on a local level to ensure changes are appropriate and are supported by new and existing drilling.

Resource Classification

The RLO Mineral Resource has been classified using the guidelines set out in the JORC Code (2012). The RLO Mineral Resource comprises a mixture of Indicated and Inferred resource categories. No Measured Resource classification has been applied at RLO given the inherent grade variability and geological complexity present at the deposit.

Resource classification coding is applied to the block model using classification polylines developed by the senior Resource Geologist who considers the quality of data, quality of estimation, geological complexity and drill spacing present when developing the classification polylines.

In general the application of an Indicated classification is restricted to areas which have been drilled to a nominal 20m by 20m spacing that have observed grade continuity. The exception is McFinley, where a 40m by 40m drill spacing is considered appropriate for the application of an Indicated classification due to the greater spatial continuity present. The application of an Inferred Resource category occurs in regions which are covered by 40m by 40m spaced drilling. The exception is McFinley, where an 80m by 80m drill spacing is considered appropriate for the application of an Indicated classification due to the greater spatial continuity present. Poorly drilled regions (>40m spacing) or areas where controls on mineralisation are unknown and no grade continuity is observed are assigned an unclassified category.

Assigned resource classification coding and resource classification shapes are internally peer reviewed and validated.

Evolution Mining Limited

81

==> picture [83 x 59] intentionally omitted <==

Mineral Resource Reporting and assigned Cut-off criteria

The Red Lake Operation Mineral Resource estimate is constrained to material that only falls within optimised economically viable underground mining shapes (MSO’s) which were developed in Deswik software and take into account Mineral Resource reporting price assumptions (A$2,500/oz) and metallurgical recoveries. MSO’s are developed with a minimum mining width in the range of 1.8 m to 2.4 m with a minimum footwall and hangingwall slope of 50 degrees. The minimum strike of the panels is 5.0m with a vertical extent ranging from 15m to 26m.

Conventional mechanised mining techniques and parameters typical of current Evolution underground operations were applied. Assigned mining costs, processing costs and metallurgical recoveries used in the development of underground Mineral Resource reporting shapes are supported by current mining data and metallurgical recoveries.

A cut-off grade of 2.87g/t Au was applied to Lower Red Lake and Lower Campbell deposits, 2.74g/t Au for the Cochenour deposit, 3.3g/t Au for Upper Campbell and Upper Red Lake deposits and 2.5 g/t Au for HG Young and McFinley. The cut-off grades were estimated using the site mining, processing and general & administrative (G&A) costs. No changes in cutoff occurred for Upper Campbell and Upper Red Lake as these regions were re-reported using last years cutoff’s which were based on a $1450/oz gold price assumption. A ‘Hill of Value’ study is scheduled to be completed in 2024 which will optimise the mine plan and applied cutoff grades to maximise value from the operation.

A metallurgical recovery of 88% has been assumed and a gold price of A$2,500/oz with a CAD:AUD exchange rate of 0.9 has been used.

Audits or reviews

Internal technical peer reviews of the Mineral Resource process and results have been undertaken by the Evolution Transformation and Effectiveness team (T&E). T&E are an oversight and governance group within Evolution, independent of the resource site study team.

In addition, an external audit program on the reported Mineral Resource and Ore Reserve is completed by independent 3[rd] party consultants on a regular basis. The last external audit was completed by SRK Consulting in September 2022.

Evolution Mining Limited

82

==> picture [83 x 59] intentionally omitted <==

Red Lake Ore Reserve

Material Assumptions for conversion to Ore Reserves

The Ore Reserve estimate is based on the December31, 2023 Mineral Resource estimate as described in the Red Lake Mineral Resource statement above and Table 1, Sections 1 to 3 in Appendix A4. The Mineral Resource estimate is reported inclusive of the Ore Reserve estimate. The Ore Reserve has been declared at the point where ore is delivered to the processing facility.

Cut-off parameters

Ore Reserve stoping cut-off grades have been updated for Red Lake, Cochenour, HG Young and McFinley using the stoping, processing, general & administrative costs for the gold price of $1,800/oz and foreign exchange rate of 0.9 AUD:CAD. The Ore Reserve stoping cut-off grade for Upper Campbell used the stoping, processing, general & administrative costs for the gold price of $1,450/oz and foreign exchange rate of 0.9 AUD:CAD.

Upper Campbell cut-off grades are expected to be updated following the completion of the ‘Hill of Value’ study in late 2024 based upon the program of drilling and mineralisation re-interpretation and estimation currently underway.

Mining factors or assumptions

Stopes are designed for either longitudinal open stoping with paste fill or waste fill using the Deswik Stope Optimizer tool (Deswik.SO) to generate the designs based on specified input parameters and optimized for grade.

Table 27: Stope parameters
Parameter Value
Section Interval 5m to 6m
Vertical Extent / Stope Height 20m to 26m
Minimum Hangingwall Dip 50
Minimum Mining Width 1.8m to 2.4m

Internal geotechnical data analysis on rock quality, stope dimensions and past stope performance provides guidance on stope dimensions required to minimize unplanned dilution. Stope design shapes are grouped into nominal stope blocks on strike ranging between 12m to 24m. Unplanned mining dilution and recovery estimates have been established by analysis of historical stope performance for the various geological zones at the Red Lake Operation.

Unplanned dilution was included by applying a skin as an equivalent linear overbreak slough to the hanging wall and footwall between 0.6m to 1.2m. The grade of the unplanned dilution was assumed to be 0g/t Au except in cases where the geological model was intersected by the design shape. Mining recovery was assumed as 85% for up-hole and down-hole stopes.

For Ore Reserves, Inferred Resources are excluded and treated as waste material.

Metallurgical factors or assumptions

RLO operates two processing plants, the Campbell, and Red Lake plant. The Campbell plant uses a traditional carbon-in-leach (CIL) and carbon-in-pulp (CIP) process. The Red Lake plant uses a traditional CIP process. Refractory gold is recovered by pressure oxidation. Sulphide concentrates produced by both the Campbell and Red Lake flotation circuits are processed at the Campbell plant autoclave.

Evolution Mining Limited

83

==> picture [83 x 59] intentionally omitted <==

Historical metallurgical process plant data have been used to develop a recovery model to estimate the metallurgical recovery in the process plants dependent upon the head grade of the mill feed.

2022 Ore Reserve Metallurgical Recovery Guidance:

𝑀𝑒𝑡𝑎𝑙𝑙𝑢𝑟𝑔𝑖𝑐𝑎𝑙 𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑦=[0.9696 × 𝐻𝑒𝑎𝑑 𝐺𝑟𝑎𝑑𝑒−0.2892] 𝐻𝑒𝑎𝑑 𝐺𝑟𝑎𝑑𝑒

There are no deleterious elements that are modelled.

Infrastructure

RLO is an established site, comprised of three separate operational mine sites. Major infrastructure e.g. road access, processing plant, electrical power, potable and process water etc. are available and adequate to support current and future mining operations. Excavations for underground infrastructure e.g. service bays, ventilation and dewatering etc. are accounted in the Ore Reserve development designs and operational costs are included in the mining cost.

Costs

Costs for Red Lake and Cochenour have been based on historical site costs with projected cost reduction initiatives. Cost reduction initiatives are based on current plans or projects that are in the implementation phase.

Costs for Upper Campbell were prepared in 2020 based on historical site costs, first principle labour and consumable costs. Costs reductions are justified by increased effectiveness and lowered indirect costs by way of the portal access and economies of scale for larger capacity mobile equipment.

Transportation and refinery treatment charges are based on current agreements.

Cochenour is subject to a 5% net profit and a 1% net smelter return royalty on less than 3% of the reported Ore Reserves. McFinley is subject to a 2% net smelter return and a 1% net smelter return royalty on 80% of the reported Ore Reserves. No additional royalties are payable on tenures that host the remaining current Ore Reserves.

Revenue

The gold price assumption used to estimate the December 2023 Ore Reserves revenue for Red Lake, Cocehnour, HG Young and McFinely was A$1,800/oz and foreign exchange rate of 0.9 AUD:CAD. The gold price assumption used to estimate the December 2023 Ore Reserves revenue for Upper Campbell was A$1,450/oz and foreign exchange rate of 0.9 AUD:CAD.

Economic

Ore Reserves were calculated on an incremental cost basis with economic assessments completed on levelby-level basis. The Ore Reserves were subjected to an economic test that includes all applicable costs and is performed via a sensitivity analysis using a range of assumed gold prices from A$1,800/oz to A$2,650/oz and considers a range of financial metrics including AISC, NPV and FCF.

Classification

The Ore Reserves are derived from Indicated Resources. No Proved Reserves or Probable Reserves derived from Measured Resources have been reported. The reserve classification was based on the assessment of the metal content by each Resource category on the stope and development designs. Only Measured or Indicated Resources are assumed to contribute to revenue, Inferred Resources do not contribute to the grade or revenue. In the opinion of the Competent Person the Ore Reserve classification is appropriate.

Evolution Mining Limited

84

==> picture [83 x 59] intentionally omitted <==

Audits or reviews

The Ore Reserve design has been audited the Evolution Transformation & Effectiveness (T&E) team, that acts as an engineering and geology oversight group. External consultants have been used to evaluate Upper Campbell and complete the mine design, schedule, and economic evaluation.

No external audits of the December 31, 2022 Ore Reserves have been conducted in 2023. The last external audit was completed in September 2022 by SRK Consulting on the 2021 Ore Reserve.

Discussion of relative accuracy / confidence

The relative accuracy of the Mineral Resource estimate is in accordance with the guidelines of the 2012 JORC Code. The site has maintained an ongoing register of production reconciliations with varied short-term performance. It is expected that reconciliation will continue to confirm that the new Mineral Resources are suitable global estimates to be used as the basis to estimate Ore Reserves. The Competent Person is comfortable that these estimates are classified in accordance with the JORC 2012 guidelines and will be suitable for appropriate conversion to Ore Reserves where applicable and will form the basis of ongoing Mine Planning at Red Lake Operations.

The accuracy of the Ore Reserve estimate is dependent upon the accuracy of the Mineral Resource model and the long-term cost and revenue assumptions. Modifying factors have been developed from current mine performance data. In the opinion of the Competent Person the long-term assumptions and modifying factors are reasonable.

Ore Reserves estimates are reconciled against actual mining performance, Results to date in areas that have been well drilled and are well understood geologically, highlight good performance and that the reported Ore Reserve is achievable in practice and that the applied modifying factors are appropriate. Reconciliation results in areas of limited drilling and in areas of complex geology have been somewhat varied and highlight the requirement of ore control activities for local demarcation of ore and waste.

Ongoing drilling targeting Inferred and Indicated Mineral Resource regions is occurring with the aim of converting reported Mineral Resources to Ore Reserves. Of particular focus this year are the Upper Campbell and Upper Red Lake regions given their proximity to the planned CYD Decline. A significant program of drilling, re-interpretation and estimation is currently underway. This program of work will be followed by a ‘Hill of Value’ study which will optimise the mine plan and applied cutoff grades to maximise value from the operation. Results of this study are expected late 2024 with an updated Mineral Resource for these regions scheduled to be reported as at 31 December, 2024.

Evolution Mining Limited

85

==> picture [83 x 59] intentionally omitted <==

APPENDIX A1: Ernest Henry. JORC CODE 2012 ASSESMENT AND REPORTING CRITERIA

The following information is provided in accordance with Table 1 of Appendix 5A of the JORC Code 2012 - Section 1 (Sampling Techniques and Data), Section 2 (Reporting of Exploration Results), Section 3 (Estimation and Reporting of Mineral Resources) and Section 4 (Estimation and Reporting of Ore Reserves).

Section 1: Ernest Henry Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections)

Criteria JORC Code Explanation Commentary Commentary
Sampling techniques
Nature and quality of sampling (eg cut channels, random
chips,
or
specific
specialised
industry
standard
measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.

Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.

Aspects of the determination of mineralisation that are
Material to the Public Report.

In cases where ‘industry standard’ work has been done this
would be relatively simple (eg ‘reverse circulation drilling
was used to obtain 1 m samples from which 3 kg was
pulverised to produce a 30 g charge for fire assay’). In
other cases more explanation may be required, such as
where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg
submarine nodules) may warrant disclosure of detailed
information

Diamond core drill holes are the primary source of geological and grade information for the
resource at Ernest Henry. Drilling has been completed between 1980 and 2023. A total of
1,239 holes were extracted from the acQuire database of which 969 drill holes containing Cu
assays and Au assays were used in the Mineral Resource estimate.

Reverse circulation (RC) drilling was completed to base of oxidation with some holes hosting
diamond tails.

The diamond core is routinely sampled to geological contacts and predominantly 2m intervals
from ½ core over the entire length of the drill hole, producing approximately 5kg samples.
Holes drilled from the surface and underground are oriented perpendicular to orebody
mineralisation where possible.

UG channel samples taken from chip sampling of development drives at 2m intervals are
also used to help define mineralogical domains. Whilst they are not used directly in
estimation, chip samples typically yield 4kg – 5kg masses.

Between February 2023 and July 2023, samples underwent further preparation and
analysis by ALS Brisbane laboratory (and OSLS Bendigo for gold analysis), involving
crushing to 2mm, riffle splitting and pulverising to 85% passing 75 microns. Of this
material a 0.4g sample is prepared for analysis via aqua regia digestion and 25g for
analysis via fire assay. After July 2023, core samples sent to ALS Brisbane for preparation
and base metal analysis were forwarded to ALS Perth for gold analysis via fire assay
Drilling techniques
Drill type (eg core, reverse circulation, open-hole hammer,
rotary air blast, auger, Bangka, sonic, etc) and details (eg
core diameter, triple or standard tube, depth of diamond
tails, face-sampling bit or other type, whether core is
oriented and if so, by what method, etc).

Drill types utilised in grade estimation are diamond core including HQ, NQ2 & NQ sizes
yielding core diameters of 63.5mm, 50.6mm & 47.6mm respectively. Drill core is collected
with a 3m barrel and standard tubing.

Only selected drill holes have been oriented using an ezi mark orientation system for
structural and geotechnical requirements.
Drill sample recovery
Method of recording and assessing core and chip sample
recoveries and results assessed.

Measures taken to maximise sample recovery and ensure
representative nature of the samples.

Whether a relationship exists between sample recovery

Current practice ensures all diamond core intervals are measured and recorded for rock
quality designation (RQD) and core loss.

Core recovery through the ore portion of the deposit is high (>99.5%).

No bias is observed due to core loss.

Evolution Mining Limited

86

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary Commentary
and grade and whether sample bias may have occurred
due to preferential loss/gainof fine/coarse material.
Logging
Whether core and chip samples have been geologically
and geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining studies
and metallurgical studies.

Whether logging is qualitative or quantitative in nature.
Core (or costean, channel, etc) photography.

The
total
length
and
percentage of
the
relevant
intersections logged.

All diamond core has been logged, geologically and geotechnically to a level that supports
Mineral Resource estimation, mining studies and metallurgical studies. The geologic and
geotechnical records are considered qualitative and quantitative with the following items
being captured:

Lithology

Texture

Alteration

Mineralisation

Structures – including veining & faults

Weathering

RQD

Photography of diamond core has captured approximately 60% of the data set
Sub-sampling
techniques and
sample preparation

If core, whether cut or sawn and whether quarter, half or all
core taken.

If non-core, whether riffled, tube sampled, rotary split, etc
and whether sampled wet or dry.

For
all
sample
types,
the
nature,
quality
and
appropriateness of the sample preparation technique.

Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.

Measures
taken
to
ensure
that
the
sampling
is
representative of the in situ material collected, including for
instance results for field duplicate/second-half sampling.

Whether sample sizes are appropriate to the grain size of
the material being sampled

Drill core is cut in half to produce an approximate 5kg sample using an automatic core
saw, with one half submitted for assay, and the other half retained on site. Where core is
oriented, it is cut on the core orientation line.

Diamond core and channel samples are predominantly sampled to geological contacts
and at 2m intervals. Samples are sent to ALS Brisbane for crushing and pulverisation.
Samples are crushed to 2mm, split via a riffle or rotary splitter and then pulverised using
an LM5 mill to a nominal 85% passing 75 microns. A 0.4g sub-sample of pulverised
material is taken for ICP analysis via aqua regia digestion. Between February 2023 and
July 2023, a 25g sub-sample was taken for analysis via fire assay at OSLS. After July
2023, ALS Perth completed fire assay on a 50g sub-sample. The remaining pulverised
sample is returned to site and stored for future reference.

Sub-sampling is performed during the sample preparation stage in line with ALS internal
protocol.

Field duplicates are collected for all diamond core at a rate of one in every 15 samples
and for channel sample at a rate of one in every 10 samples.

Comparison of field duplicates is performed routinely to ensure a representative sample is
being obtained and that the sample size captures an adequate sample volume to
represent the grain size and inherent mineralogical variability within the sampled material.
Quality of assay data
and laboratory tests

The nature, quality and appropriateness of the assaying
and laboratory procedures used and whether the technique
is considered partial or total.

For geophysical tools, spectrometers, handheld XRF
instruments, etc, the parameters used in determining the
analysis including instrument make and model, reading
times, calibrations factors applied and their derivation, etc.

Nature
of
quality
control
procedures
adopted
(eg
standards, blanks, duplicates, external laboratory checks)

Samples are assayed at ALS Brisbane for a multi element suite using ME-ICP41, Cu-
OG46 & MEOG46 methods, which analyses a 0.4g sample in aqua-regia digestion with an
ICP-AES finish. Gold analysis completed at OSLS Bendigo was done by fire assay on a
25g sample with an AA instrument finish. Gold analysis completed at ALS Perth was done
by fire assay on a 50g sample with an AA instrument finish. Analytical methods are
deemed appropriate for this style of mineralisation.

Historic quality control procedures include the use of six certified standards (CRMs) which
cover the expected grade range of mineralisation encountered within the deposit. In
addition, field duplicates are inserted at 1:25 ratio for all sample batches sent to the ALS

Evolution Mining Limited

87

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
and whether acceptable levels of accuracy (ie lack of bias)
and precision have been established.
laboratory.

The quality assurance program includes repeat and check assays from an independent
third-party laboratory as deemed necessary.

There have been no blanks used on the diamond core historic data set. Both ALS and
OSLS laboratories provide their own quality control data, which includes laboratory
standards and duplicates.

EHO currently uses nine CRMs, pulverised and coarse blanks, field, crush and pulp
duplicates to monitor sample preparation and analytical processes. The rate of insertion
was 1:15 for CRMs, 1:15 for blanks within mineralised units and 1:30 in waste zones,
Field duplicates were inserted at 1:15 while crush and pulp duplicates were at 1:25
samples.

Analysis of quality control sample assays indicate the accuracy and precision is within
acceptable limits and suitable for inclusion in the underground resource estimate.
Verification of
sampling and
assaying

The verification of significant intersections by either
independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry procedures,
data verification, data storage (physical and electronic)
protocols.

Discuss any adjustment to assay data.

All diamond drill holes are logged remotely on a laptop utilising AcQuire software and
stored digitally in an AcQuire database on a network server.

Drill holes are visually logged for copper content prior to sampling and assay. This visual
assessment is used to verify assay data.

The strong correlation between copper and gold enables additional quality control checks
to be enacted on returned assays.

Procedures have been developed to ensure a repeatable process is in place for
transferring, maintaining & storing all drilling, logging and sampling data on the network
server, which has a live upload to a local device and daily back up to an offsite device.

Following review of the historical dataset, no adjustments have been made to any assay
data. All files are reported digitally from ALS laboratories in CSV format, which are then
imported directly into the AcQuire database. Checks of the assay results in AcQuire and
results returned from the laboratory are performed at the completion of each drilling &
sampling campaign. Laboratory certificates for returned assays are stored for future
reference and checks against values contained within the AcQuire database.

Twinned holes have not been completed. Given the low-grade variability and the good
agreeance between drilling and underground observations, the Competent Person
considers the lack of twinned holes immaterial to the confidence in subsequent Mineral
Resource estimates.
Location of data
points

Accuracy and quality of surveys used to locate drill holes
(collar and down-hole surveys), trenches, mine workings
and other locations used in Mineral Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.

Collar coordinates are picked up by EHO site surveyors using a Leica total station survey
instrument. All underground excavations are monitored using the same instrument.

The topography was generated from a LIDAR survey completed over EHO mining leases
in 2018 with outputs in GDA94 coordinate system.

A variety of downhole survey methods have been utilised in the underground resource,
however 93% of the diamond drill holes have been surveyed using a gyroscopic
instrument recording down hole survey data in 3m intervals.

Alldata points arereportedin MGA94 zone 54.

Evolution Mining Limited

88

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
Data spacing and
distribution

Data spacing for reporting of Exploration Results.

Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.

Whether sample compositing has been applied.

Drill holes are variably spaced with the following broad resource classifications applied:

Between 30m x 30m and 40m x 40m for Measured

60m x 60m for Indicated

100m x 100m Inferred

This drill hole spacing is considered sufficient given the deposit grade and geological
continuity and Mineral Resource classification definitions as outlined in the 2012 JORC
Code, which is also supported by historic reconciliation data from the mill.

Samples are weighted by length and density when composited to 2m in length for use in
the estimation.
Orientation of data in
relation to geological
structure

Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which this
is known, considering the deposit type.

If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to
have introduced a sampling bias, this should be assessed
and reported if material.

Holes drilled from the surface and underground are oriented perpendicular to orebody
mineralisation and orebody bounding shear zones wherever possible. UG channel
samples are oriented along the strike of orebody mineralisation and are conducted on a
lateral 25m spacing, in line with sub-level mine excavations.

There has been no orientation bias recognised within the data used for the underground
Resource estimate..
Sample security
The measures taken to ensure sample security

Diamond core samples are securely stored onsite prior to being despatched to the ALS
laboratory in Townsville.
Audits or reviews
The results of any audits or reviews of sampling techniques
and data.
▪ An external audit conducted in 2014 on the data management & QAQC procedures
including drilling & sampling. These were found to be in line with industry standards. SRK
completed an audit of the Ernest Henry Mineral Resource estimate in August 2023 with
onlyminor improvementitemsidentified.

Evolution Mining Limited

89

==> picture [83 x 59] intentionally omitted <==

Section 2: Ernest Henry Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section)

Criteria JORC Code Explanation Commentary Commentary
Mineral tenement and
land tenure status

Type, reference name/number, location and ownership
including agreements or material issues with third parties
such as joint ventures, partnerships, overriding royalties,
native title interests, historical sites, wilderness or national
park and environmental settings.

The security of the tenure held at the time of reporting along
with any known impediments to obtaining a licence to
operate in the area.

The EHO operation is located 38km north-east of Cloncurry, 150km east of Mount Isa
and 750km west of Townsville, in north-west Queensland, Australia. The EHO
operations extend across 8 current mining leases all owned by Ernest Henry Mining Pty
Ltd, the details of these leases are summarized in the following table:
Lease
Ownership
Expiry
ML2671
Ernest Henry Mining Pty Ltd 100%
30/11/2025
ML90041
Ernest Henry Mining Pty Ltd 100%
30/11/2037
ML90072
Ernest Henry Mining Pty Ltd 100%
30/11/2025
ML90085
Ernest Henry Mining Pty Ltd 100%
31/03/2026
ML90100
Ernest Henry Mining Pty Ltd 100%
31/05/2026
ML90107
Ernest Henry Mining Pty Ltd 100%
31/08/2026
ML90116
Ernest Henry Mining Pty Ltd 100%
30/09/2026
ML90075
Ernest Henry Mining Pty Ltd 100%
30/11/2025

As of 6 January 2022, Evolution Mining Limited has 100% ownership of the EHO
Exploration done by
other parties

Acknowledgment and appraisal of exploration by other
parties.

The EHO orebody was discovered by Western Mining Corporation Limited in 1991. The
size and potential of the discovery became obvious with further drill definition following
soon after, leading to a Feasibility Study and subsequently the open pit mine and mill. In
2006 a deep drilling campaign was initiated to explore the down dip extension of the
deposit ultimately leading to the development of the current underground mining project.

Data used in the current estimate is a compilation of several phases of exploration
completed since the early 1990s. This data has been assessed for quality as outlined in
‘Section 1’ and deemed suitable for use as the basis of the Mineral Resource estimate.
Geology
Deposit type, geological setting and style of mineralisation.

The Ernest Henry Deposit is an Iron Oxide Copper Gold (IOCG) hosted within a
sequence of moderately SSE-dipping, intensely altered Paleoproterozoic intermediate
metavolcanic and metasedimentary rocks of the Mt Isa group. Copper occurs as
chalcopyrite within the magnetite-biotite-calcite-pyrite matrix of a 250 x 300m pipe like
breccia body. The breccia pipe dips approximately 40 degrees to the South and is
bounded on both the footwall and hanging wall by shear zones. The main orebody starts
to split from the 1575 level into a South-East lens, and from the 1275 level into the
South-West lens. Both lenses are separated from the main orebody by waste zones,
termed theInter-lens and South-West Shear Zone,respectively. The orebodyis openat

Evolution Mining Limited

90

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
depth.
Drill hole Information
A summary of all information material to the understanding
of the exploration results including a tabulation of the
following information for all Material drill holes:

easting and northing of the drill hole collar

elevation or RL (Reduced Level – elevation above
sea level in metres) of the drill hole collar

dip and azimuth of the hole

down hole length and interception depth

hole length.

If the exclusion of this information is justified on the basis
that the information is not Material and this exclusion does
not detract from the understanding of the report, the
Competent Person should clearly explain why this is the
case.

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Data aggregation
methods

In reporting Exploration Results, weighting averaging
techniques, maximum and/or minimum grade truncations (eg
cutting of high grades) and cut-off grades are usually
Material and should be stated.

Where aggregate intercepts incorporate short lengths of high
grade results and longer lengths of low grade results, the
procedure used for such aggregation should be stated and
some typical examples of such aggregations should be
shown in detail.

The assumptions used for any reporting of metal equivalent
values should be clearly stated.

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Relationship between
mineralisation widths
and intercept lengths

These relationships are particularly important in the reporting
of Exploration Results.

If the geometry of the mineralisation with respect to the drill
hole angle is known, its nature should be reported.

If it is not known and only the down hole lengths are
reported, there should be a clear statement to this effect (eg
‘down hole length, true width not known’).

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Diagrams
Appropriate maps and sections (with scales) and tabulations
of intercepts should be included for any significant discovery
being reported These should include, but not be limited to a
plan view of drill hole collar locations and appropriate

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves

Evolution Mining Limited

91

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
sectional views
Balanced reporting
Where comprehensive reporting of all Exploration Results is
not practicable, representative reporting of both low and high
grades and/or widths should be practiced to avoid
misleading reporting of Exploration Results.

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Other substantive
exploration data

Other exploration data, if meaningful and material, should be
reported
including
(but
not
limited
to):
geological
observations; geophysical survey results; geochemical
survey results; bulk samples – size and method of treatment;
metallurgical
test
results;
bulk
density,
groundwater,
geotechnical and rock characteristics; potential deleterious
or contaminating substances.

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Further work
The nature and scale of planned further work (eg tests for
lateral extensions or depth extensions or large-scale step-
out drilling).

Diagrams clearly highlighting the areas of possible
extensions, including the main geological interpretations and
future drilling areas, provided this information is not
commercially sensitive.

The Ernest Henry deposit has significant potential to extend the resource at depth. An
underground drilling program is planned to assist in defining this potential.

Evolution Mining Limited

92

==> picture [83 x 59] intentionally omitted <==

Section 3: Ernest Henry Estimation and Reporting of Mineral Resources

(Criteria listed in Section 1, and where relevant in Section 2, also apply to this section)

Criteria JORC Code explanation Commentary
Database integrity
Measures taken to ensure that data has not been corrupted
by, for example, transcription or keying errors, between its
initial collection and its use for Mineral Resource estimation
purposes.

Data validation procedures used.

All drill hole data is securely stored and backed up daily in an AcQuire database on a
single server located on site at EHO. Assay data is quality controlled upon receipt and
imported directly into the database via import templates. User access to the database is
controlled by a hierarchy of permissions as defined by the database administrator.
Site visits
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the
case.

The Competent Person has reviewed and observed data collection, sampling and
geological modelling practices and associated procedures on site which could impact the
Mineral Resource estimation process. It is the Competent Persons opinion that the
collection, quality and interpretation of data on site is completed to an appropriate
standard for use in Mineral Resource estimation and reporting.
Geological
interpretation

Confidence in (or conversely, the uncertainty of the
geological interpretation of the mineral deposit.

Nature of the data used and of any assumptions made.

The effect, if any, of alternative interpretations on Mineral
Resource estimation.

The use of geology in guiding and controlling Mineral
Resource estimation.

The factors affecting continuity both of grade and geology.
▪ The distribution of copper and gold at Ernest Henry is directly proportional to the degree
of brecciation occurring, with chalcopyrite, magnetite and associated gold occupying the
matrix within the breccia. Deformation porosity is therefore considered the primary
control on the mineralisation. The domains used to constrain mineralisation for
estimation are largely grade driven, constructed using Seequent’s Leapfrog implicit
modelling software. Statistically there are two grade populations existing within the
deposit; a high-grade core domain above 0.7% Cu and a surrounding lower grade halo
(>0.1% Cu) domain sharply in places and gradual in other areas. Where the grade
transition is gradual, a 0.5% Cu domain has been developed. Contact analyses of each
element between mineralised and unmineralised domains has been completed with
results indicating a hard boundary estimation approach is most appropriate between the
interpreted domains.
▪ Six high grade gold domains were developed internal to the 0.7% Cu domain. These
gold domains were developed taking into account geological logging and using a nominal
lower grade threshold of 1.0 g/t Au. The lower grade threshold was selected based on
observations of Au assays downhole and the inflection point on the log-probability plot of
Au, which indicates the grade at which a higher-grade population exists within the total
Au distribution.
Dimensions
The extent and variability of the Mineral Resource expressed
as length (along strike or otherwise), plan width, and depth
below surface to the upper and lower limits of the Mineral
Resource.

Looking east to west, the Ernest Henry deposit extends 1800m along strike (north-south)
and 1700m below the surface. The width of mineralisation varies as the deposit
becomes elongated below 1300mRL. Above 1300mRL, mineralisation is approximately
340m wide (east to west) and approximately 250m wide below 1300mRL. The deposit
dips at 40 degrees to the south, extending from 60m under a sedimentary blanket to
beyond 1700m in depth. Below 1575mRL a secondary lens is partitioned to the

Evolution Mining Limited

93

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary southeast appearing to be strongly influenced by the shearing. The current EHO resource estimate reports blocks below 1705mRL that form a contiguous mineable entity within the 0.7% Cu grade shell.

  • Estimation andThe nature and appropriateness of the estimation ▪ Grade estimations for copper (Cu), gold (Au), silver (Ag), arsenic (As), cobalt (Co), iron modelling techniques (Fe), molybdenum (Mo), nickel (Ni), sulphur (S), uranium (U) and density were technique(s) applied and key assumptions, including completed using ordinary kriging in Datamine Studio RM software. Block dimensions

  • treatment of extreme grade values, domaining, interpolation (XYZ =10x10x10) used are reflective of the selective mining unit and the geometry of the

  • parameters and maximum distance of extrapolation from mineralisation. Sub-cells of 2mE by 2mN by 2mRL were used to accurately reflect

  • data points. If a computer assisted estimation method was domain volumes. Samples were composited to 2m in length within five Cu domains and

  • chosen include a description of computer software and six Au domains. No top cuts were applied to Cu, Au or density. Top cuts for Ag within

  • parameters used.

  • The availability of check estimates, previous estimates Domain 7 were applied to minimise grade smearing. Top cuts to Au and Cu were applied to the lower grade (Domain 1) and surrounding waste domain (Domain 0) to minimise

  • and/or mine production records and whether the Mineral grade smearing during estimation.

  • Resource estimate takes appropriate account of such data. The assumptions made regarding recovery of by-products. ▪ A multi-pass search strategy using dynamic anisotropy was utilised to adjust the search • Estimation of deleterious elements or other non-grade ellipse when estimating grades. True dip and dip direction was estimated into each block using the interpreted fold surface developed during domain generation. A high

  • variables of economic significance (eg sulphur for acid mine confidence, 1st search pass used a minimum of 12 samples and maximum of 32

  • drainage characterisation). samples with a minimum number of 3 octants required. The range of the search ellipse

  • In the case of block model interpolation, the block size in was set at approximately one quarter of the range of the modelled Cu variogram. The

  • relation to the average sample spacing and the search search neighbourhood criteria were selected based on test estimates using differing

  • employed. versions of search criteria and supported by kriging neighbourhood analysis.

  • Any assumptions behind modelling of selective mining units.

    • Most blocks have been estimated in the first estimation pass (~96% of blocks), which used a 210m search. A second, lower confidence estimation pass, which used a 420m search (approximately two thirds the variogram range of Cu and Au) was used to incorporate samples further from the block being estimated.
  • Any assumptions about correlation between variables.

  • Description of how the geological interpretation was used to control the resource estimates.

  • Discussion of basis for using or not using grade cutting or capping.

    • Copper and gold mineralisation are intimately associated throughout the deposit with a Cu to Au ratio of 2:1 common throughout the deposit. This ratio changes notably in the Au domains where an increase in gold mineralisation is present and the Au to Cu ratio is ≥ 1.
  • The process of validation, the checking process used, the comparison of model data to drill hole data, and use of reconciliation data if available

  • Deleterious elements occurring in the deposit include Arsenic and Uranium. Both are in low abundance and do not present an issue at the mill or in the concentrate. Sulfur is estimated into the model and can be used to characterise waste rock. All production from underground however is considered acid forming and is treated as such. All other deleterious elements fall well below penalty thresholds.

  • ▪ Validation tools employed to scrutinize the model include:

  • Statistical summary of block values to check outlying values and confirm all blocks were estimated.

  • Statistical comparisons between mean estimated grades and mean composited grades for each domain are within ±5%.

  • Swath plots of mean estimated grades against mean composite grades within 20m wide easting, northing and elevation slices shows composite grade trends have been closely replicated in the model.

Evolution Mining Limited

94

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

Visual comparison in section between block grades and composite grades
indicate the estimated grades closely reflect the surrounding composite grades
and grade smearing has been controlled.
Moisture
Whether the tonnages are estimated on a dry basis or with
natural moisture, and the method of determination of the
moisture content.

Tonnage estimates for the purpose of estimating in-situ ore resources are determined
based on dry bulk density.
Cut-off parameters
The basis of the adopted cut-off grade(s) or quality
parameters applied.

The resource cut-off at EHO since 2018 has used a $50 Net Smelter Return (NSR),
which roughly aligned with the 0.7% Cu wireframe. The sub-level caving mining method
precludes the ability to selectively mine blocks below a given cut-off grade.
Consequently, the Mineral Resource has been reported within the interpreted 0.7% Cu
grade shell without using a cut-off grade. Approximately 0.2% of reported tonnes are
below 0.7% Cu. This material is considered by the Competent Person (CP) to meet
reasonable prospects for eventual economic extraction, considering the proposed mining
technique and historical metallurgical recoveries.
Mining factors or
assumptions

Assumptions made regarding possible mining methods,
minimum mining dimensions and internal (or, if applicable,
external) mining dilution. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential mining methods,
but the assumptions made regarding mining methods and
parameters when estimating Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the mining
assumptions made.

The Ernest Henry deposit lends itself to a low-cost high production mass mining
technique such as sub level caving. It is anticipated the successful extraction of the
deposit as demonstrated through the underground mine since 2012 using the sub level
caving technique will continue.

Depletion and sterilization due to mining is estimated using a Power Geotechnical
Cellular Automata (PGCA) flow model. The flow model estimates the relative proportions
of resource category reporting to draw points for extraction with production actual tonnes
and grade to 31 December 2023 used for calibration of the model
Metallurgical factors
or assumptions

The basis for assumptions or predictions regarding
metallurgical amenability. It is always necessary as part of
the process of determining reasonable prospects for
eventual
economic
extraction
to
consider
potential
metallurgical methods, but the assumptions regarding
metallurgical treatment processes and parameters made
when reporting Mineral Resources may not always be
rigorous. Where this is the case, this should be reported with
an explanation of the basis of the metallurgical assumptions
made.

The ore at Ernest Henry has been successfully milled since the open cut started in 1997.
Historical mill recoveries for copper and gold in the primary sulfide ore are approximately
95% and 83% respectively.

Metallurgical test work has been completed as part of the current FS. Whilst the results
indicate minimal change in metallurgical assumptions, the metallurgical tests have
highlighted a minor increase in ore hardness for material within the FS area.
Environmental
factors or
assumptions

Assumptions made regarding possible waste and process
residue disposal options. It is always necessary as part of
the process of determining reasonable prospects for
eventual economic extraction to consider the potential
environmental impacts of the mining and processing

All the relevant environmental licenses are in place for the current mining operation,
including tails storage facility capacity for all reserves. A number of the mining leases will
require renewal to extract all of the Ore Reserve.

Evolution Mining Limited

95

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
operation. While at this stage the determination of potential
environmental impacts, particularly for a greenfields project,
may not always be well advanced, the status of early
consideration of these potential environmental impacts
should be reported. Where these aspects have not been
considered this should be reported with an explanation of the
environmental assumptions made.
Bulk density
Whether assumed or determined. If assumed, the basis for
the assumptions. If determined, the method used, whether
wet or dry, the frequency of the measurements, the nature,
size and representativeness of the samples.

The bulk density for bulk material must have been measured
by methods that adequately account for void spaces (vugs,
porosity, etc), moisture and differences between rock and
alteration zones within the deposit.

Discuss assumptions for bulk density estimates used in the
evaluation process of the different materials.

An extensive database of Dry Bulk Density measurements has been collected since
deposit discovery using the Archimedes water displacement principal on core samples
every 20m downhole. These measurements are used in conjunction with an elemental
assay analysis to generate a stoichiometric regression formula that is applied to every
sample. Dry bulk density is then estimated into the block model using ordinary kriging.

Until December 2022, samples were dried in an oven prior to density measurements. A
campaign of measuring density on air-dried core compared to oven-dried core was
completed in 2022. This highlighted negligible difference in measured density between
air-dried core and oven-dried core. Consequently, to improve core processing, oven
drying was abandoned with density measurements completed on air-dried core.

There are very few open voids in the EHO orebody and the crystal structure of the rock
exhibits minimal porosity. These factors are considered to have little influence on the
estimated global density.

The variability of density across the width of mineralisation is low.
Classification
The basis for the classification of the Mineral Resources into
varying confidence categories.

Whether appropriate account has been taken of all relevant
factors (ie relative confidence in tonnage/grade estimations,
reliability of input data, confidence in continuity of geology
and metal values, quality, quantity and distribution of the
data).

Whether the result appropriately reflects the Competent
Person’s view of the deposit

The EHO Mineral Resource (including material in the 0.1% Cu grade shell) has been
classified using the following general criteria:

Measured: Drill data used for estimation not exceeding 30m-40m spacing and
including full drill coverage on adjacent sections to the north and south.
Estimated with a full compliment of composites selected in the kriging process
(32).

Indicated: Drill data used for estimation between 40m–60m, estimated with a full
complement of composites selected in the kriging process (32).

Inferred: Drill data used for estimation between 60m-100m

Other general conditions taken into consideration in the classification are as follows;

Kriging Efficiency (KE);

Continuity of grades between drillholes;

Confidence in the geological interpretation of structures and interpretation of
mineralisation boundary;

The mining cut-off at EHO since 2018 has used a $50 Net Smelter Return (NSR), which
roughly aligned with the 0.7% Cu wireframe. Blocks outside this wireframe are
considered “External” for the purposes of the flow model. The Mineral Resource is
depleted through the flow modelling process, utilising PGCA software.

Evolution Mining Limited

96

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Audits or reviews
The results of any audits or reviews of Mineral Resource
estimates.

Resource estimates have been reviewed several times since the 2011 underground
feasibility study by external geostatistical consultants.

Each review has endorsed the estimate while also recommending minor potential
improvements for the next estimate.

The 30 June 2023 Mineral Resource has been internally peer reviewed by Evolution’s
Transformation & Effectiveness (T&E) team who undertake technical reviews and
manage corporate governance activities.

An external audit of the 30 June 2023 Mineral Resource was completed in August 2023.
This audit did not identify any fatal flaws and highlighted four minor improvement items
to be incorporated in subsequent estimates.
Discussion of relative
accuracy/ confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Mineral Resource estimate using an
approach or procedure deemed appropriate by the
Competent Person. For example, the application of statistical
or geostatistical procedures to quantify the relative accuracy
of the resource within stated confidence limits, or, if such an
approach is not deemed appropriate, a qualitative discussion
of the factors that could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages,
which should be relevant to technical and economic
evaluation. Documentation should include assumptions
made and the procedures used.

These statements of relative accuracy and confidence of the
estimate should be compared with production data, where
_available. _

The Mineral Resource accuracy is communicated through the classification assigned to
this Mineral Resource.

The Mineral Resource estimate has been classified in accordance with the JORC Code,
2012 Edition using a qualitative approach. All factors that have been considered have
been adequately communicated in Section 1 and Section 3 of this Table.

Reconciliation data from Mine to Mill since the beginning of the underground operation
has ultimately validated the global accuracy of the resource estimate with total received
metal within +/-5%.

The nature of a caving operation means there is a lag between reserves and ore
delivered to the mill over short time frames reflecting the challenges of accurately
predicting flow within a cave.

Mine production for the life of mine is estimated using Power Geotechnical Cellular
automata (PGCA) flow modelling software. The December 2023 resource model
appears to enable a satisfactory correlation with historical reconciled production data
when calibrations are applied to the flow model.

Evolution Mining Limited

97

==> picture [83 x 59] intentionally omitted <==

Section 4: Ernest Henry Estimation and Reporting of Ore Reserves

(Criteria listed in Section 1, and where relevant in Sections 2 and 3, also apply to this section)

Criteria JORC Code explanation Commentary
Mineral Resource
estimate for
conversion to Ore
Reserves

Description of the Mineral Resource estimate used as a
basis for the conversion to an Ore Reserve.
Clear statement as to whether the Mineral Resources are
reported additional to, or inclusive of, the Ore Reserves.


A detailed description of the Mineral Resource estimate is provided in Sections 1 - 3 of
this Table.
Mineral Resources at Ernest Henry are reported within Domain 7 (0.7% copper).
Recovered production ore, including dilution, is forecast using Power Geotechnical
Cellular Automata (PGCA) software. This software simulates cave flow and ore recovery
based on the current block model, mine design, Life of Mine (LOM) schedule and model
input parameters. The model is calibrated using mine to mill reconciliation data and
recovery of markers installed in the cave.
The block model is discretised into 1.25 m3particles within the PGCA model. Each block
retains the attributes of the respective parent block, including density, grade and
resource classification. These blocks flow within the cave model based on stochastic
rules developed from large scale recovery studies conducted in similar SLC operations.
The model calculates ore recovery based on the simulated mine schedule and planned
production draw strategy. The recovered tonnes, grade and resource classification is
calculated by the proportion (of tonnes and metal) of each resource category reporting to
the individual rings. This method enables Ore Reserves to be estimated using the
Mineral Resource classification, accounting for ore recovery and dilution.
Reported Mineral Resources are inclusive of the Ore Reserve
Site Visits
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.
_If no site visits have been undertaken_indicate why this is the
The Competent Person is a full-time employee of Evolution and conducts regular site
visits to the Ernest Henry Operation.
case.
Study Status
The type and level of study undertaken to enable Mineral
Resources to be converted to Ore Reserves.
The Code requires that a study to at least Pre-Feasibility
Study level has been undertaken to convert Mineral
Resources to Ore Reserves. Such studies will have been
carried out and will have determined a mine plan that is
_technically_achievable and economically viable, and that
material Modifying Factors have been considered.



The Ernest Henry (Base) Ore Reserve estimate is supported by Pre-feasibility (2006)
and Feasibility (2008) studies. The mine also has a decade of proven production
performance upon which the Ore Reserve estimate assumptions are based.
The Ernest Henry (Extension) Ore Reserve estimate is supported by a Pre-feasibility
Study (2023).
A detailed mine design and schedule exists for the planned Life of Mine (LOM), which
includes both the Base and Extension components of the mine. This plan has been
assessed and is economically viable.
A 0.98% grade factor has been applied to the production component of the Ernest Henry
(Extension) Ore Reserve estimate.
Cut-off parameters The basis of the cut-off grade(s) or quality parameters
applied
The design cut-off used to generate the sub-level cave (SLC) footprint relates to
geological Domain 7, which defines the Mineral Resource. This 0.7% Cu boundary
typically equates to 0.85 – 0.95% CuEq, dependent upon copper:gold ratio and
economic assumptions.

Evolution Mining Limited

98

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary ▪ Where Domain 7 is less continuous, the footprint must deviate slightly from the 0.70% Cu boundary to ensure a footprint amenable to caving is maintained. This requirement becomes more apparent at depth, leading to use of a 0.70% CuEq for definition of the Extension level footprints (1100 – 0750).

  • ▪ The economic shut-off grade applied in the cave flow model is 0.75% CuEq for the Base component and 0.50% CuEq for the Extension component. These values have been selected following assessment of multiple scenarios and validated through an economic evaluation process.

  • Mining factors orThe method and assumptions used as reported in the Pre- ▪ The Mineral Resource has been converted to Ore Reserve through detailed design assumptions (Base) and preliminary design (Extension). Feasibility or Feasibility Study to convert the Mineral ▪ Pre-feasibility (2006) and Feasibility (2008) studies demonstrated that sub-level caving Resource to an Ore Reserve (i.e. either by application of is the most appropriate mining method for the Ernest Henry underground operation. This

  • appropriate factors by optimisation or by preliminary or method is well suited to the orebody geometry, grade and rock mass properties. Recent

  • detailed design).

  • The choice, nature and appropriateness of the selected Concept (2021) and Pre-feasibility (2023) studies for the Mine Extension indicate that continuation of the sub-level cave is the most appropriate option for production below

  • mining method(s) and other mining parameters including the existing mine.

  • associated design issues such as pre-strip, access, etc. The assumptions made regarding geotechnical parameters ▪ $Geotechnical engineering assessments have shown that the rock mass is amenable to caving where appropriate design criteria are utilised. Numerical modelling of the planned

  • (eg pit slopes, stope sizes, etc), grade control and pre- cave and mine workings is conducted at regular intervals and calibrated against real

  • production drilling.

  • The major assumptions made and Mineral Resource model world observations. To date, cave growth has been tracked by seismic monitoring, seismic tomography, time domain reflectometry (TDR) systems and regular laser

  • used for pit and stope optimisation (if appropriate). scanning of the surface expression. These systems will be expanded to ensure

  • The mining dilution factors used. adequate monitoring of the cave as it progresses into the lower Mine Extension area. A

  • The mining recovery factors used. $4M budget has been allocated and included in the PFS financial model. Effective cave

  • Any minimum mining widths used. monitoring and management will be essential as the mine progresses deeper, where the

  • The manner in which Inferred Mineral Resources are utilised orebody geometry becomes less favourable for caving. Modelling conducted as part of in mining studies and the sensitivity of the outcome to their the PFS indicates that the preliminary Mine Extension geometry may experience inclusion. inconsistent caving, potentially forming an air gap if appropriate controls are not

  • The infrastructure requirements of the selected mining implemented. Further assessment will be undertaken as part of the Feasibility Study methods. (FS) to better understand likely cave propagation and the most effective cave management strategies. The mitigants applied as part of the Ernest Henry (Extension) Ore Reserve mining plan include a more conservative draw strategy and schedule than that of the PFS, and a $50 M allowance for implementation of control measures such as footprint expansion or pre-conditioning. This allowance combined with the generally conservative assumptions applied in the estimation process, and classification of the Ore Reserve, are considered by the Competent Person to appropriately convey and account for the caveability risk.

  • The mine design incorporates 25m sub-level spacing, 15m drive spacing (centre to centre), 6m wide cross cuts and a standard 8-hole ring pattern with 2.6m burden. These design parameters are in line with benchmarked operations and have proven to be effective during the previous decade of Ernest Henry underground production.

Evolution Mining Limited

99

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Optimisation of these design parameters will be completed during the FS, with changed
mining conditions at depth likely to require minor adjustment, and opportunities to
improve mining efficiency.
No mining dilution factors are applied as dilution is included in the cave flow model
simulation. The tonnage attributed to dilution is included in the reported Ore Reserves
due to the non-selective nature of the mining method.
No mining recovery factors are applied as the recovery of blasted ore is an output of the
cave flow model simulation. A 0.98% grade factor has been applied to the flow model
output that informs the production component of the Ernest Henry (Extension) Ore
Reserve estimate.
A minimum mining width for cave establishment and propagation is in the order of 140m
based on empirical cavability assessments. A draw width of 10.0m at 1,000 m3drawn is
applied in the cave flow model software. This value has been selected based on
recovery of markers installed inside the cave and calibration of the flow model against
reconciled actuals.
Sub-level caving is a bulk mining method with limited selectivity, where dilution must be
accepted in order to recover blasted ore. Dilution from production activities is quantified
through cave flow modelling and is included in the reported Ore Reserve along with
supporting economic evaluations.
Due to the non-selective nature of sub-level caving, Inferred and Unclassified tonnes are
included in the Ore Reserve estimate. Metal associated with the Inferred, External and
Unclassified tonnes is excluded from the Ore Reserve estimate.
All major infrastructure supporting the Ernest Henry (Base) Ore Reserve estimate has
been constructed, including the underground crushing and conveying system, hoisting
shaft, pumping and ventilation systems. These systems will need to be expanded to
facilitate extraction of the Ernest Henry (Extension) Ore Reserve.
Access to the underground mine is via an in-pit portal and decline, with additional means
of egress via a ladderway system and the hoisting shaft.
Metallurgical factors
or assumptions





The metallurgical process proposed and the appropriateness
of that process to the style of mineralisation.
Whether the metallurgical process is well-tested technology
or novel in nature.
The nature, amount and representativeness of metallurgical
test work undertaken, the nature of the metallurgical
domaining applied and the corresponding metallurgical
recovery factors applied.
Any assumptions or allowances made for deleterious
elements.
The existence of any bulk sample or pilot scale test work and




Comminution is achieved using an underground gyratory crusher followed by SAG and
Ball mills in the processing plant. Copper and gold are recovered using a proven
floatation circuit. Recovered gold is contained within the copper concentrate.
The metallurgical process utilises well tested technology and has been conducted onsite
for approximately 20 years with consistent results.
The uranium and fluorine content of the ore steam is monitored and managed during
processing to ensure the final concentrate meets or exceeds the agreed sale
specification. No other impurities have been experienced in deleterious quantities. This
is expected to be the case for the stated Ore Reserve based on the drilling and sampling
conducted to date, including a campaign targeting the Extension area.
Bulk sampling is conducted on a routine basis to confirm plant performance.
Not applicable as minerals are not defined by a specification.

Evolution Mining Limited

100

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
the degree to which such samples are considered
representative of the orebody as a whole.
For minerals that are defined by a specification, has the ore
reserve
estimation
been
based
on
the
appropriate
mineralogy to meet the specifications?
Environmental
factors
assumptions
or The status of studies of potential environmental impacts of
the mining and processing operation. Details of waste rock
characterisation and the consideration of potential sites,
status of design options considered and, where applicable,
the status of approvals for process residue storage and
waste dumps should be reported.


Environmental studies regarding flora and fauna, hydrogeological conditions, waste rock
characterisation and cultural heritage have been carried out for the mine.
An Environmental Authority (EA) has been granted by the regulator.
The existing EA will require amendment to facilitate extraction of the stated Ore
Reserve. Both the Ernest Henry (Base) Ore Reserve and Ernest Henry (Extension) Ore
Reserve will be subject to further approvals from the Queensland Department of
Environment and Science (DES). Current guidance from DES does not indicate that the
mining plan supporting the stated Ore Reserve will be impacted by the amendment
approval process.
A key element of the Major Amendment to the EA relates to an increase in total height of
the Tailings Storage Facility (TSF). The technical work to support the increase has been
completed as part of the PFS, and this is the preferred option over changing the footprint
or constructing a new TSF.
The mine has an Environmental Management Plan to appropriately manage mine
production, waste rock dump, tailings storage facilities and site clearing.
Acid forming material is contained in approved storage facilities and controlled using a
waste rock management plan.
Infrastructure The existence of appropriate infrastructure: availability of
land for plant development, power, water, transportation
(particularly for bulk commodities), labour, accommodation;
or the ease with which the infrastructure can be provided, or
accessed.

All of the major infrastructure required to extract the Ernest Henry (Base) Ore Reserve is
in place.
For the Ernest Henry (Extension) Ore Reserve to be extracted, additional infrastructure
will be required. This includes but is not limited to upgrades for the ventilation and
dewatering systems, primary access, emergency egress, workshops, stores, extended
materials handling system, electrical and communication systems. Surface works
including Tailings Storage Facility (TSF) raises will also be required as part of the mine
life extension and have been demonstrated as technically feasible through the PFS.
Infrastructure required to facilitate extraction of the Mine Extension has been designed
and costed as part of the PFS.
Access to the utilities that support mining activities has been secured.
Ernest Henry owns and operates a mining camp to house the Fly-in Fly-out (FIFO)

Evolution Mining Limited

101

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
contingent of the workforce. This facility will be expanded to accommodate the increased
workforce required during the construction phase of the Mine Extension. The local
workforce resides in the town of Cloncurry.
Costs





The derivation of, or assumptions made, regarding projected
capital costs in the study.
The methodology used to estimate operating costs.
Allowances made for the content of deleterious elements.
The source of exchange rates used in the study.
Derivation of transportation charges.
The basis for forecasting or source of treatment and refining
charges, penalties for failure to meet specification, etc.
The
allowances
made
for
royalties
payable,
both
Government and private.


Estimates for major capital items that facilitate extraction of the Ore Reserve have been
informed by supplier quotes where available, industry benchmarks and previous site
experience with similar projects. An appropriate contingency for capital requirements
associated with the Mine Extension has been utilised in the financial evaluation.
Sustaining capital is forecast annually as part of the Budget and Life of Mine (LOM)
planning cycle, reflecting actual performance and the mine schedule. As the basis of the
Mine Extension is a continuation of the current mining method, these costs are well
understood.
Operating costs are calculated using a first principles approach and reconciled with
actual costs on a monthly basis and as part of annual financial reviews. The availability
of reliable historic data for the site provides a robust basis for estimating the operating
costs. Suitable allowances have been made for additional costs incurred as the
production front moves deeper.
No impurities are expected to occur in deleterious quantities. The concentrate sales
model does account for penalties should any be incurred.
The exchange rate for long term financial assessment is based on Evolution corporate
assumptions (AUD:USD of 0.75).
Transport costs are based on the site concentrate sales model and assume concentrate
is transported by road to Mount Isa.
Treatment and refining charges are included in financial models with a base assumption
of smelting in Mt Isa and refining in Townsville at Glencore facilities.
Royalty payments of 4% (inclusive of 20% discount for smelting in Queensland) for
copper and 5% for gold and silver to the Queensland government are included in
financial models.
Revenue factors
The derivation of, or assumptions made regarding revenue
factors including head grade, metal or commodity price(s)
exchange rates, transportation and treatment charges,
penalties, net smelter returns, etc.
The derivation of assumptions made of metal or commodity
price(s), for the principal metals, minerals and co-products.

The projected head grade is an extract of the mine schedule, reflecting the reported Ore
Reserve inventory. The head grade used to generate revenue for the Ore Reserve
estimate includes all extracted tonnes but Measured and Indicated metal only. A 0.98%
grade factor has been applied to the flow model output that informs the production
component of the Ernest Henry (Extension) Ore Reserve estimate.
Transport and treatment charges are based on the site concentrate sales model and
included in financial evaluations.
Revenue generation for the Ore Reserve was assessed with four different commodity
price decks, as detailed in the table below. The utilised price range was derived from
Evolution Mining’s December 2022 Mineral Resource and Ore Reserve guidance. The
Ernest Henry (Base) Ore Reserve estimate was shown to generate a positive Net
Present Value (NPV) with price deck 2, 3 or 4 applied. The Ernest Henry (Extension)
Ore Reserve estimate generated a positive NPV with price deck 4 applied. The total
ErnestHenry OreReserve,withtheBase andExtensioncomponents considered as a

Evolution Mining Limited

102

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
single entity, generated a positive NPV with either price deck 3 or 4 applied. The pricing
assumptions used by Evolution Mining for long-term planning are guided by historical
prices and consensus broker forecasts. The stated prices are assumed to be constant
for the duration of the Ore Reserve mining period.
Metric
1
2
3
4
Copper ($/t)
7,000
8,500
10,000
12,000
Gold ($/oz)
1,600
1,900
2,200
2,400
Silver ($/oz)
20.00
23.00
26.00
27.50
Credited value from silver is included in revenue calculations used to evaluate the Ore
Reserves, though the associated value is insignificant.
Market assessment

The demand, supply and stock situation for the particular
commodity, consumption trends and factors likely to affect
supply and demand into the future.
A customer and competitor analysis along with the
identification of likely market windows for the product.
Price and volume forecasts and the basis for these forecasts.







Copper and gold products are sold to Glencore through a long-term offtake agreement.
Supply and demand of copper and gold is not a constraint used in the estimate of the
Ore Reserve at Ernest Henry.
Copper and gold volumes are forecast over the life of mine and included in the
company’s long term price forecasts.
Not applicable as Ernest Henry does not produce industrial minerals.
For industrial minerals the customer specification, testing and
acceptance requirements prior to a supply contract.
Economic The inputs to the economic analysis to produce the net
Mine revenue and NPV are calculated using reconciled cost models as previously
present value (NPV) in the study, the source and confidence
of these economic inputs including estimated inflation,

described. With ten years of comparable production the confidence for forecast
economic outcomes is high.
discount rate, etc. The Ore Reserve has been evaluated using a financial model, with sensitivity to internal
NPV ranges and sensitivity to variations in the significant and external factors being included in the evaluation.
assumptions and inputs. A discount rate of 7.8% has been applied in the financial model.
Social The status of agreements with key stakeholders and matters
leading to social licence to operate.


Deed and access agreement are in place with neighboring landholders.
The Major Amendment to the existing EA will require community engagement. Ernest
Henry Mining Pty Ltd actively maintains good relations with stakeholders and the local
community. There is currently no indication that ongoing community engagement would
impede the EA amendment process.
Other To the extent relevant, the impact of the following on the
project and/or on the estimation and classification of the Ore
Reserves:


Cyclones and high rainfall events present a risk to short term production targets and are
managed through site risk mitigation processes. These events have not been included in
the estimation of the Ore Reserves.
Any identified material naturally occurring risks. Long term sales agreement with Glencore is in place.

The status of material legal agreements and marketing
arrangements.
The status of governmental agreements and approvals



Mining operations at the site have been conducted for 20 years under existing
approvals.
The latest geotechnical modelling completed for the PFS indicates that mining of the

Evolution Mining Limited

103

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation

==> picture [105 x 311] intentionally omitted <==

critical to the viability of the project, such as mineral tenement status, and government and statutory approvals. There must be reasonable grounds to expect that all necessary Government approvals will be received within the timeframes anticipated in the Pre-Feasibility or Feasibility study. Highlight and discuss the materiality of any unresolved matter that is dependent on a third party on which extraction of the reserve is contingent.

Classification

  • The basis for the classification of the Ore Reserves into varying confidence categories.

  • Whether the result appropriately reflects the Competent Person’s view of the deposit.

  • The proportion of Probable Ore Reserves that have been derived from Measured Mineral Resources (if any).

Commentary

lowest levels within the Ernest Henry (Base) Ore Reserve may result in a different surface expression than previously forecast. Steps are currently being taken to validate the model results, informing the EA Amendment process.

  • The necessary steps are being taken by Evolution Mining to ensure that any amendments are granted in a time frame that does not impact the planned production profile.

  • ▪ A number of the Ernest Henry Mining Pty Ltd leases will require renewal to facilitate extraction of the stated Ore Reserve. The necessary steps required to renew these leases are being undertaken by Evolution Mining.

Lease
Ownership
Expiry Date
ML2671
Ernest Henry Mining Pty Ltd 100%
30/11/2025
ML90041
Ernest Henry Mining Pty Ltd 100%
30/11/2037
ML90072
Ernest Henry Mining Pty Ltd 100%
30/11/2025
ML90085
Ernest Henry Mining Pty Ltd 100%
31/03/2026
ML90100
Ernest Henry Mining Pty Ltd 100%
31/05/2026
ML90107
Ernest Henry Mining Pty Ltd 100%
31/08/2026
ML90116
Ernest Henry Mining Pty Ltd 100%
30/09/2026
ML90075
Ernest Henry Mining Pty Ltd 100%
30/11/2025



Measured Resources recovered through development and production activities
converted to Proved Reserve.
Indicated Resources recovered through development and production activities
converted to Probable Reserve.
Inferred Resource tonnes recovered through development and production activities
converted to Probable Reserve.
Inferred Resource metal recovered through development and production activities
are
are
are
are
excluded from the Ore Reserve.
External and Unclassified Resource tonnes recovered through development and
production activities are converted to Probable Reserve.
Externaland UnclassifiedResourcemetal recovered throughdevelopment and

Evolution Mining Limited

104

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary production activities are excluded from the Ore Reserve.

  • ▪ The conversion process appropriately reflects selectivity of the mining method and confidence in the geological, geotechnical, metallurgical and mine planning processes.

  • ▪ Consideration of mining factors has also been made. Based on the consistency of mine to mill reconciliation and proven operational performance, there is sufficient confidence to convert Measured Resource to Proved Reserve. Though there are additional mining considerations specific to the Ernest Henry (Extension), these do not materially impact the likelihood of recovering the Measured Resource associated with that portion of the Ore Reserve estimate

    • The result of the process used to convert the Mineral Resource into the Ore Reserve is deemed appropriate by the Competent Person.
  • Audits or reviewsThe results of any audits or reviews of Ore Reserve estimates.

==> picture [399 x 308] intentionally omitted <==

----- Start of picture text -----

Tonnes
D7 D1 Other
Measured Indicated Inferred External Measured Indicated Inferred External Unclassified
Proved Probable Probable Probable Proved Probable Probable Probable Probable
Metal
D7 D1 Other
Measured Indicated Inferred External Measured Indicated Inferred External Unclassified
Proved Probable Proved Probable
▪ Internal review of the methodology used to produce the Ore Reserve estimate has been
conducted routinely by site technical and leadership teams as part of the MROR and
LOM planning cycles.
▪ Evolution’s Transformation & Effectiveness (T&E) team undertake an internal but
independent review of the Mineral Resource and Ore Reserve prior to each release.
▪ The PFS has been conducted by a multidisciplinary team of external parties with
appropriate experience in the relevant areas. In conjunction with a staged review of the
study by Evolution personnel, the Ernest Henry (Extension) Ore Reserve estimate has
received input from a broad and appropriate audience.
▪ External reviews are completed periodically to review the mine and ensure technical
risks are managed appropriately. Feedback from these reviews has been positive to
date.
▪ SRK Consulting Australia completed a site visit and detailed audit of the MROR
processes in 2023 Q3. The audit found that processes used to estimate the Mineral
Resource and Ore Reserve are appropriate.
----- End of picture text -----

Evolution Mining Limited

105

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Discussion of relative
accuracy/ confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Ore Reserve estimate using an


The accuracy of the Ore Reserve estimate is largely dependent on the accuracy of the
Mineral Resource and the cave flow model.
approach or
procedure deemed
appropriate
by
the
Competent Person. For example, the application of statistical


The December 2022 Mineral Resource model has undergone a detailed internal review
to validate the inputs and technical approach. The model is further validated through the
or geostatistical procedures to quantify the relative accuracy End of Month (EOM) reconciliation process, which shows a consistent alignment of
of the reserve within stated confidence limits, or, if such an forecast and actual metal content.
approach is not deemed appropriate, a qualitative discussion
Calibration of the flow model is conducted by site at six-month intervals and now
of the factors which could affect the relative accuracy and includes more than ten years of reconciliation data. The modelled grade is consistently
confidence of the estimate. within 5% of the reconciled metal output on an annual basis.
The statement should specify whether it relates to global or
The Mineral Resource to Ore Reserve conversion method, whereby only Measured and
local estimates, and, if local, state the relevant tonnages, Indicated metal is included, is conservative with respect to the approach taken by some
which should be relevant to technical and economic comparable caving operations.
evaluation. Documentation should include assumptions
The mining and processing practices that have demonstrated reliable performance to
made and the procedures used. date will be applied to the stated Ore Reserve, with comparable performance expected.
Accuracy and confidence discussions should extend to
All assumptions used in financial models are subject to internal review.
specific discussions of any applied Modifying Factors that
The underground operation has been designed to handle a 1:100 year rainfall event
may have a material impact on Ore Reserve viability, or for over 72 hours without significant disruption to mining activities. An event of this
which there are remaining areas of uncertainty at the current magnitude occurred in February 2019, resulting in only minor delays to production and
study stage. validating effectiveness of the water management system. Water ingress to the
It is recognised that this may not be possible or appropriate
in all circumstances. These statements of relative accuracy
and confidence of the estimate should be compared with
production data, where available.


underground workings does, however, remain a material risk. This is evidenced by the
adverse weather event that occurred in 2023 Q1 and resulted in several months of
reduced production. Though the event recovery did negatively impact business
outcomes for the affected period, the likelihood of a similar event occurring and being of
sufficient severity to materially impact viability of the Ore Reserve is considered low.
Findings of the 2023 Q1 adverse weather event incident investigation have been used to
improve the Ernest Henry water management system and further reduce the risk
associated with water ingress in the future.
Ventilation will be a key enabler for the Ernest Henry operation, particularly during the
period where peak capital development rates for the Extension area overlap with
production trucking for the Base area. This high demand period is planned to be
managed through an upgrade of the primary ventilation circuit. There is, however, a risk
associated with the potential for delayed commissioning of the ventilation upgrade. To
manage this risk, alternate mine plans have been investigated through the 2023 H2
LOM process, with an aim of reducing or deferring peak ventilation requirements. This
work has demonstrated that there are multiple strategies that achieve the objective,
providing confidence that any reasonably expected delays to the ventilation system
upgrade will not materially impact the viability of the Ernest Henry (Extension) Ore
Reserve.

Evolution Mining Limited

106

==> picture [83 x 59] intentionally omitted <==

APPENDIX A2: MUNGARI. JORC CODE 2012 ASSESMENT AND REPORTING CRITERIA – TABLE 1

The following information is provided in accordance with Table 1 of Appendix 5A of the JORC Code 2012 - Section 1 (Sampling Techniques and Data), Section 2 (Reporting of Exploration Results), Section 3 (Estimation and Reporting of Mineral Resources) and Section 4 (Estimation and Reporting of Ore Reserves).

Section 1: Mungari Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections)

  • Criteria JORC Code Explanation CommentaryNature and quality of sampling (eg cut channels, random ▪ Sampling of gold mineralisation at Mungari Gold Operations (MGO) that constitutes the

  • Sampling techniques chips, or specific specialised industry standard measurement Mineral Resource estimates for the 2023 MROR was undertaken using diamond core tools appropriate to the minerals under investigation, such as (surface and underground), Reverse Circulation (RC) drilling and underground down hole gamma sondes, or handheld XRF instruments, development face samples. etc). These examples should not be taken as limiting the ▪ Drilling and sampling for gold has been conducted by various companies since 1987. broad meaning of sampling. Sampling techniques is a summary of drilling and sampling methods as reported by

  • Include reference to measures taken to ensure sample Mineral Resources Australia (MRA), La Mancha Resources, Centaur Mining and representivity and the appropriate calibration of any Exploration, Placer Dome Asia Pacific Ltd (Placer), Barrick, Phoenix Gold, Northern Star measurement tools or systems used. Resources (NSR) and Evolution Mining (EVN).

  • Aspects of the determination of mineralisation that are ▪ RC drilling was sampled at 1m or 2m intervals. Material to the Public Report. In cases where ‘industry ▪ RC samples were dried, crushed and pulverised (total preparation) to produce a 30g to 50g standard’ work has been done this would be relatively simple charge for fire assay or Aqua Regia assay for gold. (eg ‘reverse circulation drilling was used to obtain 1 m ▪ Diamond drill core sample intervals are based on geology to ensure a representative samples from which 3 kg was pulverised to produce a 30 g sample, mostly at lengths ranging from 0.1m to 1m. Diamond drilling for exploration and charge for fire assay’). In other cases more explanation may regional resource definition was half core sampled. Diamond drilling for near mine resource be required, such as where there is coarse gold that has definition and grade control was half or full core sampled. Diamond core samples were inherent sampling problems. Unusual commodities or dried, crushed and pulverised (total preparation) to produce a 30g to 50g charge for fire mineralisation types (eg submarine nodules) may warrant assay of gold. disclosure of detailed information ▪ All drill core was photographed and logged prior to sampling. Diamond drill core was

  • All drill core was photographed and logged prior to sampling. Diamond drill core was sampled to lithological, alteration and mineralisation related contacts.

  • Face sample intervals are based on geological features and sampled by channel chip sampling across the face. The sequence of intervals and samples across the face then is recorded as a drillhole in the acQuire database.

  • Underground face sampling is completed at a standard height of the grade line, with historic minimum and maximum sample lengths of 0.05m to 2m. Face sampling is taken along the grade line to obtain a representative sample for each geological division. Underground face sample weights vary, with a maximum around 3kg.

  • Sampling was carried out according to Mungari Operations protocols and QAQC procedures.

  • ▪ Sample representivity is guided by field-based observations from geological supervision, logging and other field records referring to sample quality, content and recovery.

Evolution Mining Limited

107

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
**Drilling techniques **
Drill type (eg core, reverse circulation, open-hole hammer,
rotary air blast, auger, Bangka, sonic, etc) and details (eg core
diameter, triple or standard tube, depth of diamond tails, face-
sampling bit or other type, whether core is oriented and if so,
by what method, etc).

Drilling incorporated in the Mineral Resource estimate has been collected using diamond
drill rigs, RC drill rigs and development face samples.

Drill core is extracted using a standard tube and core diameter in either NQ2 (47.6mm) or
HQ (63.5mm) size.

Prior to 2015, diamond core orientation is limited.

Diamond core was orientated utilizing either a bottom of hole spear, EZI-Mark or a real -
time orientation device (ACE system, Tru-Core device).

RC drilling utilises a down-the-hole face sampling hammer with hole sizes varying between
4.25” (105mm) to 5.5” (140mm). Earlier (cross-over sub and open hole hammer techniques
was used (usually pre-1995).
**Drill sample recovery **
Method of recording and assessing core and chip sample
recoveries and results assessed.

Measures taken to maximise sample recovery and ensure
representative nature of the samples.

Whether a relationship exists between sample recovery and
grade and whether sample bias may have occurred due to
preferential loss/gain of fine/coarse material.

RC drillers were instructed to adopt an RC drilling strategy for the ground conditions
advised by geologist expected for each hole to maximize sample recovery, minimize
contamination and maintain specified spatial position.

RC sample recovery was not recorded quantitatively prior to 2000. Sample quality and
moisture content was recorded in some instances, but in qualitative terms. Post 2000, RC
drill samples were visually logged for moisture content, sample recovery and
contamination.

Diamond Core (DC) contractors use a core barrel and wire line unit to recover the DC,
adjusting drilling methods and rates to minimize core loss (e.g., changing rock type, broken
ground conditions etc.). Triple tubing method may be used DC was orientated, length
measured and compared to core blocks denoting drilling depths by the drilling contractor.
Anyrecoveryissues arerecorded.
Logging
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining studies and
metallurgical studies.

Whether logging is qualitative or quantitative in nature. Core
(or costean, channel, etc) photography.

The total length and percentage of the relevant intersections
logged.

RC samples are geologically logged. Specifically, each interval is inspected and the
weathering, regolith, rock type, alteration, mineralisation and structure recorded.

The entire length of RC holes are logged on a 1m interval basis (i.e.100% of the drilling is
logged). Where no sample is returned due to voids or lost sample, it is logged and
recorded as such. Drillcore is logged over its entire length and any core loss or voids are
recorded.

Drillcore is orientated then geologically and geotechnically logged, photographed and cut in
half. Any drillcore loss is recorded by the drillers and during the logging process.

Geological logging is qualitative and quantitative in nature. Logged data is currently
captured by a portable data logger utilising AcQuire software.
Sub-sampling
techniques and
sample preparation

If core, whether cut or sawn and whether quarter, half or all
core taken.

If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.

For all sample types, the nature, quality and appropriateness
of the sample preparation technique.

Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.

Measures taken to ensure that the sampling is representative
The sample preparation and analysis procedure is as follows:

The samples arrive at laboratory where they are profiled, reconciled, weighed and
recorded.

They are dried for a duration dictated by analysis parameters at a temperature of 105°C.

The samples are crushed using a Jaw Crusher to achieve 90% passing 3mm and then
pulverised in a LM5 pulveriser to a minimum of 90% passing 75µm.

A 200g sub-sample is scooped out, placed in a sample sachet and a 40g sample weighed
out for fire assay.

Evolution Mining Limited

108

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
of the in situ material collected, including for instance results
for field duplicate/second-half sampling.

Whether sample sizes are appropriate to the grain size of the
material being sampled

The 40g charge is mixed with 170g of flux (flux contains lead monoxide, sodium carbonate,
sodium tetraborate) for firing.
Quality of assay data
and laboratory tests

The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is
considered partial or total.

For geophysical tools, spectrometers, handheld XRF
instruments, etc, the parameters used in determining the
analysis including instrument make and model, reading times,
calibrations factors applied and their derivation, etc.

Nature of quality control procedures adopted (eg standards,
blanks, duplicates, external laboratory checks) and whether
acceptable levels of accuracy (ie lack of bias) and precision
have been established.

The sampling preparation and assaying protocol used at MGO was developed to ensure
the quality and suitability of the assaying and laboratory procedures relative to the
mineralisation types. No geophysical tools or other remote sensing instruments were
utilised for reporting or interpretation of gold mineralisation.

Assaying has been completed by fire assay on 30 g, 40 g or 50 g subsamples with either
gravimetric or AAS finish. Some screen fire assaying has been used when assays have
returned values at the maximum limits of the FA/AAS technique.

Certified reference material (1:20) and Blanks (1:20) are routinely inserted into the
sampling sequence and inserted at the discretion of the geologist either inside or around
the expected zones of mineralisation. The intent of the procedure for reviewing the
performance of certified standard reference material is to examine for any erroneous
results (a result outside of the expected statistically derived tolerance limits) and to
validate, if required. The acceptable levels of accuracy and precision for all stages of the
sampling and analytical process. Typically, batches which fail quality control checks are re-
analysed.

A suite of multi elements are determined using four-acid digest with ICP/MS and/or an
ICP/AES finish for some sample intervals.
Verification of
sampling and
assaying

The verification of significant intersections by either
independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.

Discuss any adjustment to assay data.

The quality control / quality assurance (QAQC) processes are designed and undertaken to
determine that the intercepts are representative of the mineralised system.

Half core is retained for further verification if and when required.

Where appropriate, drill holes are twinned to validate specific geological observations and
measurements that maybe material to the resource estimate or could be interpreted as
having more than one geological interpretation.

All sample and assay information are stored utilising the acQuire database software
system. Data undergoes QAQC validation prior to being accepted and loaded into the
database. Assay results are merged when received electronically from the laboratory. The
geologist reviews the database checking for the correct merging of results and that all data
has been received and entered. Any adjustments to this data are recorded permanently in
the database. Historical paper records (where available) are retained in the exploration and
mining offices. Original laboratory digital assay files are stored in the site data system.

No adjustments or calibrations have been made to the final assay data reported by the
laboratory.
Location of data
points

Accuracy and quality of surveys used to locate drill holes
(collar and down-hole surveys), trenches, mine workings and
other locations used in Mineral Resource estimation.

Specification of the grid system used.

On completion of drilling, drill hole collar positions were surveyed by either contract or site-
based surveyors. Some earlier drilling was surveyed prior to drilling, but not resurveyed on
completion. Survey was by theodolite or differential GPS, to varying precision and
accuracyrelative to the AHD.

Evolution Mining Limited

109

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary

Quality and adequacy of topographic control.

Down hole surveys consist of regular spaced Eastman single shot, electronic multi-shot
surveys (generally <30m apart down hole) and north seeking gyro instruments obtained
every 5m down hole. Ground magnetics can affect the result of the measured azimuth
reading for these survey instruments except gyro.

Many of the earlier shallower drill holes (≤50m) were not down-hole surveyed and collar
azimuth and dip applied.

Data was collected on local grids, AMG84 and/or MGA94 co-ordinates.

Topographic control was generated from survey pick-ups of the area over the last 20
years, aerial surveys and Lidar surveys.
Data spacing and
distribution

Data spacing for reporting of Exploration Results.

Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.

Whether sample compositing has been applied.

Drill spacing in the deposit areas varies considerably from close spaced, less than 10m by
10m spaced drilling (grade control drilling) to wide spaced 80m by 80m resource drilling
(Inferred Resource classification). The drill spacing to define geological continuity is
dictated by the level of understanding required to determine geological and grade
continuity study work of the mineralisation for Mineral Resource estimation. Data spacing is
carefully considered when assigning Mineral Resource classification categories.
Orientation of data in
relation to geological
structure

Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which this is
known, considering the deposit type.

If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to have
introduced a sampling bias, this should be assessed and
reported if material.

Drilling directions are commonly designed to intersect the interpreted mineralisation at
angles which are near perpendicular to the dip and strike of mineralisation to obtain
representative samples for robust geological interpretation and estimation.

No drilling orientation and sampling bias has been recognised at this time.
Sample security
The measures taken to ensure sample security

MGO has in place drilling and sampling protocols and systems which ensure drilling and
sampling processes are unbiased and do not incur are completed Drilling and sampling
management occurs s are assumed to have been under the security of the respective
tenement holders or until delivered to the laboratory where they are assumed to have been
under restricted access.
**Audits or reviews **
The results of any audits or reviews of sampling techniques
and data.

No documented Audits or Reviews have been conducted by independent third parties.

Internal reviews were completed on sampling techniques and data as part of the various
operating companies’quality assessment practices.

Evolution Mining Limited

110

==> picture [83 x 59] intentionally omitted <==

Section 2: Mungari Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section)

  • Criteria JORC Code Explanation Commentary

  • Mineral tenement andType, reference name/number, location and ownership ▪ The gold deposits are located within the 329 Mining, Prospecting, Exploration tenements (covering 837km2) owned, joint ventured and/or operated Evolution Mining Ltd (EVN) and

  • including agreements or material issues with third parties

  • land tenure status or joint ventured. such as joint ventures, partnerships, overriding royalties, native title interests, historical sites, wilderness or national ▪ The tenements that host the East Kundana deposits are held by the East Kundana Joint Venture (EKJV). The EKJV is majority owned and managed by EVN (51%). The minority

  • park and environmental settings.

  • The security of the tenure held at the time of reporting along holding held in the EKJV is Tribune Resources Ltd (36.75%) and Rand Mining Ltd (12.25%).

  • with any known impediments to obtaining a licence to operate ▪ Access to the project areas is via gazetted roads and fair-weather haul routes located on

  • in the area. EVN owned Miscellaneous and Mining leases or, via Access Agreement from a third party. ▪ The State Government royalty of 2.5% NSR applies on gold produced. ▪ An MGO royalty book is active and updated regularly that records and stores royalty information for specific leases.

  • ▪ Some resources have third party royalties based on: ▪ Ore tonnes mined or processed payable to a 3rd party. These royalties can be capped.

  • ▪ A $/oz. or percentage EVN produced from the lease.

  • ▪ The tenements are in good standing and no known impediments exist.

  • Acknowledgment and appraisal of exploration by other ▪ All the historic mining, exploration and resource development for the Mungari Gold

  • Exploration done by parties. Operation deposits was completed by companies which held tenure over the Project since

  • other parties before 1987 up to 2023. The companies include Newcrest Mining, Mineral Resources Australia (MRA), Rand Mining Ltd, and Tribune Resources Ltd, Gilt Edge Mining, La Mancha Resources, Centaur Mining and Exploration, Placer Dome Asia Pacific Ltd (Placer), Barrick, Phoenix Gold, Northern Star Resources (NSR) and Evolution Mining (EVN).

  • ▪ Results of exploration and mining activities by these companies aid EVNs exploration, resourceesourcercece developmentvelopmentelopmentlopmentopmentmententntt and mining. nd mining. d mining. mining. g. .

  • Deposit type, geological setting and style of mineralisation. ▪ The geology is varied over the greater Mungari Operations project area and can be broken

  • Geology

  • Access to the project areas is via gazetted roads and fair-weather haul routes located on EVN owned Miscellaneous and Mining leases or, via Access Agreement from a third party.

  • ▪ The State Government royalty of 2.5% NSR applies on gold produced. ▪ An MGO royalty book is active and updated regularly that records and stores royalty information for specific leases.

  • Results of exploration and mining activities by these companies aid EVNs exploration, resourceesourcercece developmentvelopmentelopmentlopmentopmentmententntt and mining. nd mining. d mining. mining. g. .

  • ▪ The geology is varied over the greater Mungari Operations project area and can be broken up into three broad geological camps being the: ▪ Kundana Gold Camp ▪ Carbine Gold Camp ▪ Kunanalling Gold Camp

  • ▪ The Kundana deposits are hosted by a structurally prepared sequence of sediments, volcaniclastics, mafic and ultramafic volcanic and intrusive rocks typical of the greenstone sequences in the Archaean Yilgarn Block. The deposits are spatially associated with the craton-scale Zuleika Shear Zone. The Zuleika Shear Zone represents the boundary between the Coolgardie domain to the west and the Ora Banda domain to the east.

  • ▪ Lithologies at the Carbine-Zuleika Project consist of a series of feldspathic to quartzofeldspathic tuffs intercalated with shales, siltstones, and sandstones. The Zuleika Shear

Evolution Mining Limited

111

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary Commentary
Zone is the major structural element of the area. The two major mineralised planes in the
Carbine area, the Carbine thrust and Lincancabur shear, host brecciated and laminated
veins respectively, with high-grade gold mineralisation.

The Kunanalling project area covers the Kunanalling Shear Zone (KSZ) which is a trans-
crustal feature separating the Coolgardie domain from the Ora Banda domain to the east.
The Coolgardie domain comprises a folded sequence of metamorphosed tholeiitic, high
magnesian, and komatiitic basalts with minor intercalated felsic to intermediate volcanic
sediments. Gold mineralisation within the Kunanalling area is hosted by the Coolgardie
Domain and is preferentially located in areas of high strain associated with the Zuleika and
Kunanalling Shears.
Drill hole Information
A summary of all information material to the understanding
of the exploration results including a tabulation of the
following information for all Material drill holes:

easting and northing of the drill hole collar

elevation or RL (Reduced Level – elevation above
sea level in metres) of the drill hole collar

dip and azimuth of the hole

down hole length and interception depth

hole length.

If the exclusion of this information is justified on the basis that
the information is not Material and this exclusion does not
detract from the understanding of the report, the Competent
Person should clearly explain why this is the case.

No exploration results have been reported in this release.
Data aggregation
methods

In reporting Exploration Results, weighting averaging
techniques, maximum and/or minimum grade truncations
(eg cutting of high grades) and cut-off grades are usually
Material and should be stated.

Where aggregate intercepts incorporate short lengths of
high grade results and longer lengths of low grade results,
the procedure used for such aggregation should be stated
and some typical examples of such aggregations should be
shown in detail.

The assumptions used for any reporting of metal equivalent
values should be clearly stated.

No exploration results have been reported in this release.
Relationship between
mineralisation widths
and intercept lengths

These relationships are particularly important in the
reporting of Exploration Results.

If the geometry of the mineralisation with respect to the drill
hole angle is known, its nature should be reported.

If it is not known and only the down hole lengths are reported,
there should be a clear statement to this effect (eg ‘down hole

No exploration results have been reported in this release.

Evolution Mining Limited

112

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
length, true width not known’).
Diagrams
Appropriate maps and sections (with scales) and tabulations
of intercepts should be included for any significant discovery
being reported These should include, but not be limited to a
plan view of drill hole collar locations and appropriate
sectional views

No exploration results have been reported in the release; therefore, no diagrams have
been produced.
Balanced reporting
Where comprehensive reporting of all Exploration Results is
not practicable, representative reporting of both low and high
grades and/or widths should be practiced to avoid misleading
reporting of Exploration Results.

No exploration results have been reported in this release.
Other substantive
exploration data

Other exploration data, if meaningful and material, should be
reported including (but not limited to): geological
observations; geophysical survey results; geochemical survey
results; bulk samples – size and method of treatment;
metallurgical test results; bulk density, groundwater,
geotechnical and rock characteristics; potential deleterious or
contaminating substances.

No unreported exploration data has been collected relevant to these deposits considered
material to this announcement.
Further work
The nature and scale of planned further work (eg tests for
lateral extensions or depth extensions or large-scale step-out
drilling).

Diagrams clearly highlighting the areas of possible
extensions, including the main geological interpretations and
future drilling areas, provided this information is not
commercially sensitive.

Further work will include mining studies appropriate to EVNs current open-cut and
underground mining methods. If mining studies yield a positive result, infill resource
definition is planned to convert Inferred Mineral Resource category to Indicated Mineral
Resource category and to test for extensions to mineralisation along strike and down-dip
that would likely impact the economic outcome.

A feasibility study has been completed to determine the economics of reducing the Mungai
Processing facility unit cost by increasing throughput from 2.0Mpta to 4.2Mtpa. The EVN
board has approved this upgrade and this has reduced COGs for the MGO Mineral
Resource Statement.

Evolution Mining Limited

113

==> picture [83 x 59] intentionally omitted <==

Section 3: Mungari Estimation and Reporting of Mineral Resources

(Criteria listed in the preceding section also apply to this section)

Criteria JORC Code explanation Commentary
Database integrity
Measures taken to ensure that data has not been corrupted
by, for example, transcription or keying errors, between its
initial collection and its use for Mineral Resource estimation
purposes.

Data validation procedures used.

Data is hosted on a SQL backend database with Geologists interfacing via the AcQuire
software front end. User access to the database is controlled via user permissions which
are configured both at the group level by Systems Administration and the user level by the
Database Administrator.

The AcQuire drill hole database is based on a database model and forms a relational
database linking the geological and geochemical information to a measured drill hole
location (collar, direction and depth). The AcQuire database model provides a governance
function for the drilling and sampling data by tailoring primary keys and parent-child
relationships between collar, survey, geology sampling and assay information.

The SQL server database is configured for validation through constraints, library tables,
triggers and stored procedures. Data that fails these rules on import is rejected or
quarantined until it is corrected.

The database is centrally managed by a Database Manager who is responsible for all
aspects of data entry, validation, development, quality control and specialist queries.
There is a standard suite of rigorous validation checks for all data.

A geologist familiar with the project needs to flag data as validated in the database before
it canbe usedinanyresource estimation.
**Site visits **
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the
case.

The Competent Person for this update is a full-time employee of EVN and based on site,
verifying company standards of the Mineral Resource estimation process from sampling
through to final block model.

The deposit areas around Kundana, East Kundana, Frogs Leg, White Foil, Paradigm and
Cutter’s Ridge are recently active mining areas for EVN and as such regular site visits
have been undertaken.

Site visits are completed at the commercial laboratories that undertake the sub-sampling
and analysis to ensure process standards and sample chain of custody
Geological
**interpretation **

Confidence in (or conversely, the uncertainty of the
geological interpretation of the mineral deposit.

Nature of the data used and of any assumptions made.

The effect, if any, of alternative interpretations on Mineral
Resource estimation.

The use of geology in guiding and controlling Mineral
Resource estimation.

The factors affecting continuity both of grade and geology.

The confidence of the geological interpretation is based on geological knowledge
acquired from detailed geological DC and RC logging, mapping, assay data, and data
obtained from mining of adjoining deposits.

The dataset (geological mapping, RC and DC logging, assays etc.) is considered
acceptable for determining a geological model. Key interpretation assumptions made for
this estimation are the existence of supergene zones at the oxide and transitional
interfaces as distinct from the primary mineralisation.

The geological interpretation is considered robust overall and well supported by mapped
exposures in outcrop and mine workings. Alternative interpretation is routinely
investigated and tested to improve confidence and reduce risk.

The geological interpretation is specifically based on identifying geological lithologies and
structures, weathering profiles, associated alteration and gold content.

Evolution Mining Limited

114

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary Commentary Commentary Commentary


Whilst the geological features are deemed to be continuous, the gold distribution within
them can be highly variable.
Geology information has formed the basis for controlling the development of ore
wireframes to constrain the Mineral Resource estimations. Ore wireframes were
validated against geology and structural models.
Modelling for the resource estimates focused on structural and lithological controls as well
and incorporating lower grade mineralisation adjacent to and along strike of high-grade
intercepts to create more continuous mineralised lenses.
**Dimensions **
The extent and variability of the Mineral Resource expressed
as length (along strike or otherwise), plan width, and depth
below surface to the upper and lower limits of the Mineral
Resource.
The approximate dimensions of the MGO Operations Mineral Resource deposits are:
2023 MRE Deposit Dimensions
Deposit
Length (m)
Depth (m)
Average
Width (m)
Number of
domains
Anthill
460
275
5
14
Arctic
1305
525
2
5
Backflip
965
325
8
18
Barkers
1500
1,100
1
6
Blue Bell
1000
175
5
9
Broads Dam
2200
300
5
27
Blue Funnel
600
200
5
44
Burgundy
2525
200
7
26
Boomer
330
550
0.5
1
Boundary
700
235
10
46
Carbine North
1250
175
10
25
Castle Hill
2500
200
10
26
Catherwood
550
235
4
10
Centenary
625
600
2
6
Cutters Ridge
700
210
10
4
Drake
1800
980
1
3
Emu
500
150
10
17
2023 MRE Deposit Dimensions
Deposit Length (m) Depth (m) Average
Width (m)
Number of
domains
Anthill 460 275 5 14
Arctic 1305 525 2 5
Backflip 965 325 8 18
Barkers 1500 1,100 1 6
Blue Bell 1000 175 5 9
Broads Dam 2200 300 5 27
Blue Funnel 600 200 5 44
Burgundy 2525 200 7 26
Boomer 330 550 0.5 1
Boundary 700 235 10 46
Carbine North 1250 175 10 25
Castle Hill 2500 200 10 26
Catherwood 550 235 4 10
Centenary 625 600 2 6
Cutters Ridge 700 210 10 4
Drake 1800 980 1 3
Emu 500 150 10 17

Evolution Mining Limited

115

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Falcon 1500 80 20 25
Frogs Leg 1300 1250 3 31
Genesis 700 250 0.3 3
Golden Hind 1160 680 0.6 2
Hornet 960 1350 0.75 16
Johnsons Rest 1100 720 5 13
Kintore 1150 310 5 7
Kurrawang 350 150 5 13
Lady Jane 380 175 10 3
Millennium 940 800 2 6
Moonbeam 750 680 2 3
Nazzaris 700 10 315 10
Paradigm 970 530 5 13
Pegasus 1840 1000 1 12
Premier 900 180 4 8
Carbine-
Phantom
2130 400 5 12
Picante Trend 1750 315 5 14
Pode-Hera 1200 675 2 16
Pope John 480 800 2 3
Rayjax 870 100 3 32
Red Dam 1750 550 5 22
Ridgeback 1230 220 5 28
Raleigh 2040 1025 1 8
Rubicon 725 875 0.5 8
Solomon 380 200 0.4 3
Star Trek 2070 430 6 9

Evolution Mining Limited

116

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Strzelecki 400 460 2 1
Wadi 2400 200 10 46
White Foil OP 1350 640 10 5
White Foil UG 1150 620 10 2
Xmas 800 800 1 4
Estimation and
**modelling techniques **

The
nature
and
appropriateness
of
the
estimation
technique(s) applied and key assumptions, including
treatment of extreme grade values, domaining, interpolation
parameters and maximum distance of extrapolation from
data points. If a computer assisted estimation method was
chosen include a description of computer software and
parameters used.

The availability of check estimates, previous estimates
and/or mine production records and whether the Mineral
Resource estimate takes appropriate account of such data.

The assumptions made regarding recovery of by-products.

Estimation of deleterious elements or other non-grade
variables of economic significance (eg sulphur for acid mine
drainage characterisation).

In the case of block model interpolation, the block size in
relation to the average sample spacing and the search
employed.

Any assumptions behind modelling of selective mining units.

Any assumptions about correlation between variables.

Description of how the geological interpretation was used to
control the resource estimates.

Discussion of basis for using or not using grade cutting or
capping.

The process of validation, the checking process used, the
comparison of model data to drill hole data, and use of
reconciliation data if available

















A conventional block modelling approach was adopted with wireframes generated in
Leapfrog Geo or Datamine Studio RM, and block models completed in Datamine Studio
RM, Surpac or Vulcan.
The workflow adopted for all deposits is very similar and involved:
Fixed length compositing to 0.4m, 0.5m, 1m or 2m.
Estimation within well defined domains and sub-domains to enable the appropriate
application of grade capping, sample search parameters and high-grade restrictions for
the estimate.
Geostatistical analysis to determine appropriate grade caps for applying to the composite.
Interpolation using Ordinary Kriging (OK), Categorical Indicator Kriging or Inverse
Distance Squared methods.
Classification of blocks as Measured, Indicated or Inferred Mineral Resources using
distance based and qualitative criterion.
For the MGO Mineral Resource estimates the following units of measure were applicable:
1.
Drill hole information, wireframes, mined out, and blocks are in metres.
2.
Densities are measured in tonnes per cubic metre, block densities are assigned as
tonnes per cubic metre.
3.
Gold grades are expressed as grams per metric tonne.
4.
Mineral Resource results are reported as metric tonnes, grams per metric ton, and troy
ounces.
5.
Block dimensions (X, Y and Z) vary by deposit and mining scenario. Blocks were sub-
celled, with parent cell estimation.
Given the typically skewed populations and abundance of extreme values in the dataset,
grade top cutting and distance limiting at estimation rules were applied. The aim is to limit
the overestimation of high grades into lower grade blocks.
Spatial data analysis or variography was completed using Snowden’s Supervisor
software.
Interpolation strategies were applied to suit the data for each zone with the aim of keeping
the estimates relatively local, honouring the drilling data without excessive smoothing that
could result in smearing of high grades.
Estimates were validated using various techniques and were peer reviewed at each step
in the process by site prior to finalisation.
The estimates areforgold only.Otherelements arenot considered to bematerialto the

Evolution Mining Limited

117

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
overall Mineral Resource estimate.
**Moisture **
Whether the tonnages are estimated on a dry basis or with
natural moisture, and the method of determination of the
moisture content.

All estimates of tonnages are reported on a dry basis.
Cut-off parameters
The basis of the adopted cut-off grade(s) or quality
parameters applied.

The cut-off grades were estimated using either current and projected site mining costs,
processing costs and general administration costs.
gold price of $2,500/oz. was utilised.

The cut-off grades applied to the deposit areas are listed below:
Deposit
COG (g/t Au) (m)
Open Pits (weighted average – 0.28-0.34)
0.29 g/t Au
Kundana UG
1.89 g/t Au
Frog’s Leg UG
1.46 g/t Au
White Foil UG
1.81 g/t Au
Carbine UG
1.94 g/t Au
Paradigm UG
1.94 g/t Au
Boomer UG
1.71 g/t Au
Raleigh & Raleigh North UG
2.47 g/t Au
East Kundana JV UG
2.47 g/t Au
Mining factors or
**assumptions **

Assumptions made regarding possible mining methods,
minimum mining dimensions and internal (or, if applicable,
external) mining dilution. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential mining methods,
but the assumptions made regarding mining methods and
parameters when estimating Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the mining
assumptions made.

The Mineral Resource estimations for open pit resource have been reported within pit
optimisation shells generated in Whittle software. Mining costs are based on regolith type
and depth below surface. Mining selectivity of 5m (X) by 5m (Y) by 2.5m (Z) has been
applied.

The Mineral Resource estimations for underground have been reported within Mining
Shape Optimiser objects (MSOs) generated in Datamine or Deswik software. These
shapes assume a minimum mining width of 2.4m with a minimum footwall and hanging-
wall slope of 50 to 80 degrees. The minimum strike of the panels is 10.0m and a vertical
extent of 5.0m. No external dilution has been applied to the shapes however internal
dilution
has
been
applied
where
required
(no
estimated
grade
or
sub
Inferred Mineral Resource blocks) at 0.0 g/t.

Evolution Mining Limited

118

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

All Mineral Resources have been depleted by prior mining. The prior mining is
represented by detailed surveys completed over the life of the project. These surveys are
represented by 3D models which have been used to flag blocks as mined or not. MSO’s
are also validated and removed if they are considered to be sterilised (low likelihood of
being mined) by current mine development.
Metallurgical factors
**or assumptions **

The basis for assumptions or predictions regarding
metallurgical amenability. It is always necessary as part of
the process of determining reasonable prospects for
eventual
economic
extraction
to
consider
potential
metallurgical methods, but the assumptions regarding
metallurgical treatment processes and parameters made
when reporting Mineral Resources may not always be
rigorous. Where this is the case, this should be reported with
an explanation of the basis of the metallurgical assumptions
made.

Reasonable assumptions for metallurgical extraction factored into the resource estimate
are based on previous processing of the ore from the nearby deposits at Kundana,
Kunanalling and Carbine through the various historic and operational CIP/CIL processing
facilities within the district (including the Mungari Mill).

Where a deposit has not been previously mined or processed, preliminary deportment
and geo-metallurgical studies are completed on ore types to generate metallurgical
factors and assumptions to be included in the resource estimate.

Target gold recoveries range from 86% to 95% recovery.
Environmental factors
**or assumptions **

Assumptions made regarding possible waste and process
residue disposal options. It is always necessary as part of
the process of determining reasonable prospects for
eventual economic extraction to consider the potential
environmental impacts of the mining and processing
operation. While at this stage the determination of potential
environmental impacts, particularly for a greenfields project,
may not always be well advanced, the status of early
consideration of these potential environmental impacts
should be reported. Where these aspects have not been
considered this should be reported with an explanation of the
environmental assumptions made.

No significant environmental factors are expected to be encountered regarding the
disposal of waste or tailing material. This expectation is based on previous mining and
milling history of existing open pit operations with the project area.

Mungari Gold Operations has in place regulatory permits and approvals to continue
operations.

A site Environmental team monitors ongoing compliance with approvals and maintains the
site in good standing with regulators.
**Bulk density **
Whether assumed or determined. If assumed, the basis for
the assumptions. If determined, the method used, whether
wet or dry, the frequency of the measurements, the nature,
size and representativeness of the samples.

The bulk density for bulk material must have been measured
by methods that adequately account for void spaces (vugs,
porosity, etc), moisture and differences between rock and
alteration zones within the deposit.

Discuss assumptions for bulk density estimates used in the
evaluation process of the different materials.
Density data is collected via:

Measuring specific gravity (utilising the water immersion method) or representative rock
types; or

Down hole geophysical means utilising a gamma survey and determining in-situ bulk
density.

Specific Gravity of drill core or rock samples is measured on site by trained field
assistants prior to core photography. Specific gravity is calculated as:
𝑆𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝐺𝑟𝑎𝑣𝑖𝑡𝑦
=
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑚𝑝𝑙𝑒 𝑖𝑛 𝐴𝑖𝑟
(𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑚𝑝𝑙𝑒 𝑖𝑛 𝐴𝑖𝑟−𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑚𝑝𝑙𝑒 𝑖𝑛 𝑊𝑎𝑡𝑒𝑟)

Evolution Mining Limited

119

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary ▪ The oxide and transitional rocks are wax coated. The wax coating was factored into the specific gravity calculation. Specific gravity is converted to bulk density based on the principle that the SG and bulk density of water is a common factor of 1.

  • ▪ The gamma density tool measures the electron density of the geological formation, adjacent to the borehole, using Compton Scattering effect of the gamma rays. Electron density can be converted to bulk density.

     - Density values have been derived from empirical values for oxide, transitional and fresh material for mafic rock types and are consistent with previous resource estimates and mining reconciliation data:
    
  • ClassificationThe basis for the classification of the Mineral Resources into varying confidence categories.

    • Whether appropriate account has been taken of all relevant factors (ie relative confidence in tonnage/grade estimations, reliability of input data, confidence in continuity of geology and metal values, quality, quantity and distribution of the data).

    • Whether the result appropriately reflects the Competent Person’s view of the deposit

  • Regolith/material type Bulk density t/m3 Above the base of complete <1.9 t/m3

  • oxidation Transition zone 2.1-2.5 t/m3 Fresh rock 2.6-3.0 t/m3 Tailings/waste fill 1.6–1.8t/m3

  • ▪ Material types are defined by the regolith profiles based on base of oxidation and top of fresh rock horizons.

  • ▪ Density measurements are checked and validated; scales are regularly calibrated. MGO calibrate scales by the use of density standards which have been sourced from drill core samples obtained in EVN drilling programs

  • ▪ Density data is also validated from mining and processing of deposits whereby tonnages for specific volumes of rock are measured.

  • ▪ Mineral Resource classifications follow the JORC 2012 guidelines for Mineral Resource and Ore Reserve reporting. The JORC Mineral Resource classification definitions qualify the risk associated with a resource estimate, with risk linked to the resource estimate as follows:

  • Measured resource: Low Risk

  • Indicated resource: Medium Risk

  • ▪ Inferred resource: High Risk

  • Measured resource classification is assigned if the expected variation in physical parameters is within the bounds of normal mining practice. In general, for an open pit resource, the Measured component is defined by grade control drilling and modelling. For an underground resource, the Measured component is defined by sufficient face sampling and drill data to generate a grade control model. This also includes close spaced grade control drilling that has been used during resource estimation. Measured Resource also typically includes mapping and/or recorded survey points showing the position of the ore body position in the exposed face/floor.

  • ▪ Indicated resource classification is assigned if the expected variation is outside normal

Evolution Mining Limited

120

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
mining practice and will not affect overall economic performance. In general, this will be
derived from drill hole spacing and where possible kriging variances and relative error
distributions.

Inferred resource classification is assigned if the expected variation is outside normal
mining practice and will alter the overall economic performance. In general, this will be
derived from drill hole spacing and where possible kriging variances and relative error
distributions.

Resource classifications are based on drill spacing, search parameters including search
distance and number of informing samples, and on data quality, including the existence of
associated quality assurance programs.

The classification resultreflects theviewofthe CompetentPerson.
**Audits or reviews **
The results of any audits or reviews of Mineral Resource
estimates.

All resource estimates are internally peer reviewed by the on-site geology team.

EVN internal peer reviews have bene completed on resource estimates by the EVN
Transformation and Effectiveness team on and off site.

An external peer review of the 2021 Mineral Resource was conducted by Cube
Consulting with no fatal flaws found. All findings and recommendations have had actions
assigned and completed.
Discussion of relative
**accuracy/ confidence **

Where appropriate a statement of the relative accuracy and
confidence level in the Mineral Resource estimate using an
approach or procedure deemed appropriate by the
Competent Person. For example, the application of statistical
or geostatistical procedures to quantify the relative accuracy
of the resource within stated confidence limits, or, if such an
approach is not deemed appropriate, a qualitative discussion
of the factors that could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages,
which should be relevant to technical and economic
evaluation. Documentation should include assumptions made
and the procedures used.

These statements of relative accuracy and confidence of the
estimate should be compared with production data, where
available.

The Mineral Resources have been reported in accordance with the guidelines of the 2012
edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves and reflects the relative accuracy of the Mineral Resources estimate.
The Competent Person deems the process to be in line with industry standards for
resource estimation and therefore within acceptable statistical error limits.

The statements relate to global estimates of tonnes and grade for likely open pit mining,
underground mining and CIP/CIL processing scenarios.

Evolution Mining Limited

121

==> picture [83 x 59] intentionally omitted <==

Section 4: Mungari Estimation and Reporting of Ore Reserves

(Criteria listed in the preceding section also apply to this section)

Criteria JORC Code explanation Commentary Commentary
Mineral Resource
estimate for
conversion to Ore
Reserves

Description of the Mineral Resource estimate used as a basis
for the conversion to an Ore Reserve.

Clear statement as to whether the Mineral Resources are
reported additional to, or inclusive of, the Ore Reserves.

The Ore Reserve estimates are based on the current Mineral Resource estimates as
described in Section 3.

The Mineral Resources are reported inclusive of the Ore Reserve estimate
**Site visits **
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the
case.

Competent Person is an Evolution employee and based at the Mungari Operations (Blake
Callinan)
Study status
The type and level of study undertaken to enable Mineral
Resources to be converted to Ore Reserves.

The Code requires that a study to at least Pre-Feasibility
Study level has been undertaken to convert Mineral
Resources to Ore Reserves. Such studies will have been
carried out and will have determined a mine plan that is
_technically_achievable and economically viable, and that
material ModifyingFactorshave beenconsidered.

All assets included in the CY2023 Ore Reserve estimate have been completed to a Pre-
Feasibility Study level or better with the following assets currently actively mining:

Paradigm Open Pit

Kundana Underground

Raleigh Underground

RHP (Rubicon/Hornet/Pegasus) Underground

The Mungari Future Growth Project (FGP) Feasibility Study was completed in FY23 and
outlined updates to openpit miningcosts, processingcost,metallurgical recoveries
Cut-off parameters
The basis of the cut-off grade(s) or quality parameters
applied

The Evolution Mining’s Strategic Planning Standards were used to determine the cut-off
grades for the Ore Reserve estimate with the following costs included:

Incremental Mining Costs

for Open Pit Reserve estimates these were incremental cost of mining ore

for Underground Reserve estimates these were stoping costs

Processing costs

Current costs for assets prior to the mill upgrade

Projected costs (from the Future Growth Project) and material likely to be
processed by the FGP mill

General and Administration costs

Current costs for assets prior to the mill upgrade

Projected costs based on increased processing throughput and calculated cost
uplifts

Surface rehandle (or haulage) costs

Based on current contracted cost structure

Metallurgical recoveries used for cut-off grade determination have been derived from the
Mungari Future Growth Project Feasibility Study and are between 91% and 94%

Gold price of $1,800 was used to calculate cut-off grades for the Underground Ore
Reserve estimate

Gold prices between$1,800 and $2,400/ouncewere used to calculate cut-offgradesfor

Evolution Mining Limited

122

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Open Pit Ore Reserve estimate

Evolution Mining Limited

123

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanationThe method and assumptions used as reported in the Pre-

  • Mining factors or Feasibility or Feasibility Study to convert the Mineral

  • assumptions Resource to an Ore Reserve (i.e. either by application of appropriate factors by optimisation or by preliminary or detailed design).

  • The choice, nature and appropriateness of the selected mining method(s) and other mining parameters including associated design issues such as pre-strip, access, etc.

  • The assumptions made regarding geotechnical parameters (eg pit slopes, stope sizes, etc), grade control and preproduction drilling.

  • The major assumptions made and Mineral Resource model used for pit and stope optimisation (if appropriate).

  • The mining dilution factors used.

  • The mining recovery factors used.

  • Any minimum mining widths used.

  • The manner in which Inferred Mineral Resources are utilised in mining studies and the sensitivity of the outcome to their inclusion.

  • The infrastructure requirements of the selected mining methods.

  • Commentary

  • ▪ The methodology for converting the CY23 Mineral Resource to Ore Reserve estimate at Mungari is as follows:

  • ▪ Derivation of cut-off grades as determined from the cut-off parameters to define Ore / Low Grade / Waste

  • ▪ Definition of optimisation parameters and modifying factors from either empirical data (operating mines) or project work

  • Optimisation of Mineral Resource using recognised software

  • Open Pit optimisations were completed using GEOVIA Whittle™

  • Gold prices between $1,800-$2,400 were used for optimisation

  • As per the FY25 MGO LOM Pits were optimised using Measured, Indicated, and Inferred Resource (except for Burgundy which excluded Inferred Resources)

  • Underground Optimisations were completed using Deswik.SO using a COG of 1.5g/t to allow definition of the Ore Reserve estimates at different revenue prices

  • Evaluation and selection of optimal mining pits/shapes at the applicable gold price

  • Complete minable design (Open Pit – Pit Design, Underground – final stopes and required development)

  • Apply modifying factors, review Resource classification, and technical requirements to be defined as a Proven or Probable Reserve

Ore Reserves are subject to an economic test at a revenue of $2,500 to verify extraction is justified. The economic test includes all applicable costs considering an integrated mine plan and is performed via a sensitivity analysis using a range of assumed gold prices from $1,800 to $2,500 per ounce and considers a range of financial metrics

  • Geotechnical considerations have been included during the Ore Reserve process:

  • ▪ Open Pit geotechnical studies provide detailed pit slope angle for consideration during the optimisation and design process

  • Underground : each of the Underground mines are exposed to some degree to seismic risk. Multiple studies have been conducted with regular internal and external geotechnical reviews to ensure the most effective design, support, and extraction sequence are employed. These are captured in the individual Ground Control Management for each underground mine and were adhered to during the mine design and sequencing of the Reserves. Each Underground Ore Reserve is an active operation and the Ore Reserve has been created in consultation with site-based geotechnical engineering and audited by group level function

  • Open Pit Resource models were converted to a regularised block model based on appropriate smallest mining units (SMU) to enable the use of Open Pit optimisation software. SMU was determined by a combination of fleet size and style of ore body mineralisation.

  • Underground Mineral Resource models were specifically developed for underground mine planning. Mining shapes were created at the current site operational minimum mining width or development profiles

Evolution Mining Limited

124

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Mining factors or
assumptions
continued

The metallurgical process proposed and the appropriateness
of that process to the style of mineralisation.

Whether the metallurgical process is well-tested technology
or novel in nature.

The nature, amount and representativeness of metallurgical
test work undertaken, the nature of the metallurgical
domaining applied and the corresponding metallurgical
recovery factors applied.

Any assumptions or allowances made for deleterious
elements.

The existence of any bulk sample or pilot scale test work and
the degree to which such samples are considered
representative of the orebody as a whole.
For minerals that are defined by a specification, has the ore
reserve estimation been based on the appropriate mineralogy
to meet the specifications?
Evolution Mining Limited
125
Dilution

For Open Pit Reserves a dilution factor of 10% was applied

For Underground Reserves both paste dilution (for mines where stoping with paste
exposures) and waste dilution (to represent expected blast overbreak on stope shapes)
have been used. These have been derived from stope reconciliation data for each of the
Underground mines. The following dilution factors were used in the Underground Reserve
calculations:

Kundana: Dilution = 25% (pillar stopes) and 15% (pastefill stopes), Paste Dilution = 15%

RHP: Dilution = 15% to 21%, Paste Dilution = 2% to 9% (based on ore zones)

Raleigh: Dilution = 23%, Paste Dilution = 4%

All dilution is considered as zero grade
Mining Recovery

A mining recovery factor of 95% was used for Open Pit Ore Reserve estimates

For underground mines the mining recovery factors were derived from a combination of:

Mining method recovery which accounts for pillar sterilisation of the in-situ stoping block

65% for longhole open stoping with pillars

100% for longhole open stoping with pastefill

Stope reconciliations for each of the deposits which reflect current drill and blast
performance of the planned stoping block

KUN: 85% for longhole open stoping with pillars, 92% for longhole open stoping with
pastefill

RAL: 55% to 94% depending on ore zone

RHP: 81% to 94% depending on ore zone
Minimum Mining Width

The minimum mining widths for the Open Pit Reserve estimates were defined by the
planned mining fleet and vary between 2.5 to 10m. The block model was regularised to a
defined SMU based on the Mineral Resource

UG minimum mining widths reflect the narrow ore zones targeted with 2.5m to 3m used
for all stope optimisation depending on the deposit

Development shapes are based on current underground mining profiles

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Mining factors or
assumptions
continued
The status of studies of potential environmental impacts of
the mining and processing operation. Details of waste rock
characterisation and the consideration of potential sites,
status of design options considered and, where applicable,
the status of approvals for process residue storage and
waste dumps should be reported.
Evolution Mining Limited
126
Inclusion of Inferred Resource classification material within the reported Ore Reserve

For the reported Open Pit Ore Reserve estimate all Inferred mineralisation is treated as
waste. The Open Pits Ore Reserve estimates follow the MGO Life of Mine plan and
include Inferred Resource in optimisations but not in economic analysis or the Ore
Reserve estimate

All underground mining shapes were tested for Resource classification with any shapes
with dominant gold of mass more than 49% of Inferred material not included in the Ore
Reserve estimate

Inferred Resource is included in some Open Pit optimisations but excluded from all
financial analysis

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
Metallurgical factors
or assumptions

The existence of appropriate infrastructure: availability of land
for plant development, power, water, transportation
(particularly for bulk commodities), labour, accommodation;
or the ease with which the infrastructure can be provided, or
accessed.

All ore deposits included in the MGO CY2023 Ore Reserve estimates are conventional
free-milling ores which are amenable to processing through a carbon-in-leach (CIL) gold
processing plant.

All Ore Reserve estimates declared in this statement are assumed to be treated at the
Mungari Process Plant (commissioned 2014)

All assets mined after the commissioning date for the expanded Mungari Plant are
assumed to be treated at the expanded process plant (with lower unit costs, higher
throughputs, and changed metallurgical recoveries).

All current mining operations are presently feeding the Mungari plant with average
recoveries between 91% and 95%. The following recoveries have been used in
development of the Ore Reserve estimates:

Kundana = 93.5%

RHP = 93.5-94.5%

Raleigh = 93.5-94.5%

Paradigm OP = 91-93%

Future open pits = between 91% to 94.5% (based on completed asset metallurgical test
work and the MGO FGP FS)

Mungari Gold Process Plant is a conventional CIL process plant with inline gravity circuit
and is a well-tested technology for free-milling type ores

Current mining operations confirm the amenability of these ore zones to extraction with
varying degrees of metallurgical test work completed for each of the projects included in
the Ore Reserve estimates

All current operations have proven metallurgical characteristics shown by the consistent
recoveries through the process plant.

Project work conducted by both Evolution and Northern Star have been used to confirm
the ore from both the Kunanalling and Zuleika ore zones

No evidence of deleterious elements in any ores within the Ore Reserve estimates

No bulk sampling has been conducted through the Mungari Mill outside of normal
operating processes
Environmental
The derivation of, or assumptions made, regarding projected
capital costs in the study.

The methodology used to estimate operating costs.

Allowances made for the content of deleterious elements.

The source of exchange rates used in the study.

Derivation of transportation charges.

The basis for forecasting or source of treatment and refining
charges, penalties for failure to meet specification, etc.

The
allowances
made
for
royalties
payable,
both
Government and private.

Current mining operations are fully compliant with legal and regulatory requirements with
all government permits and licenses and statutory approvals granted

Legal and regulatory commitments for other projects are understood and a schedule for
applications and future work is currently in place
Infrastructure
The derivation of, or assumptions made regarding revenue
factors including head grade, metal or commodity price(s)

All operating mines currently have the required infrastructure to ensure ongoing
operations and where necessary capital has been included for any extensions to existing

Evolution Mining Limited

127

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary exchange rates, transportation and treatment charges, infrastructure, including, access/materials handling/services (power, water management penalties, net smelter returns, etc. and vent)/safety systems and emergency egress)

  • The derivation of assumptions made of metal or commodity ▪ A current capital cost schedule for the Processing Plant expansion and future mines was price(s), for the principal metals, minerals and co-products. used in the financial modelling for the Ore Reserve estimates. Current operations are well serviced by the required service infrastructure as follows: ▪ Mungari Gold Process plant and office complex services the administration while individual office/workshop/magazine etc. complexes are available for operational purposes.

  • ▪ Current Life of Mine (LOM) planning includes the expansion of the current Mungari Mill from ~2 mtpa to 4.2 mtpa

  • ▪ Mine is connected to the main highway between Kalgoorlie and Coolgardie ▪ Current operations are connected to grid power with the Kundana Diesel Power Station providing back up power as required

  • ▪ Water supplied and discharge reticulation is in place ▪ Kalgoorlie is a major regional centre for supplies and labour with direct flights to Perth for FIFO of labour not based in Kalgoorlie

  • ▪ Projects away from the current mining areas have been assessed for infrastructure requirements and capital and been included in the project evaluation for: ▪ Site set up ▪ Haul Roads

        - Water Supply & Dewatering
    
        - Communication, Offices & Ablutions
    
        - ▪ Workshops & Fuel Storage ▪ Magazines etc.
    
  • CostsThe demand, supply and stock situation for the particular commodity, consumption trends and factors likely to affect supply and demand into the future.

     - _A customer and competitor analysis along with the identification of likely market windows for the product._
    
    • Price and volume forecasts and the basis for these forecasts.

    • For industrial minerals the customer specification, testing and acceptance requirements prior to a supply contract.

  • For operating mines current LOM capital forecast have been included where relevant

  • ▪ For future projects the project capital schedules have been included ▪ Current first principals costings have been used to derive the operating costs for the Underground Ore Reserve estimates. Operating costs are based on current wages, materials, consumables and equipment prices, and are aligned to forward looking cost structures

  • Budget level open pit costing developed by the Mungari FGP Project has been used for the Open Pit Ore Reserve estimate. These future looking costs were developed by the project team from a combination of benchmarking and supplied contractor costs. An Early Contractor Engagement process is currently in progress to advance the accuracy of these costs

  • Costs are all expressed and calculated in Australian dollars

  • The inputs to the economic analysis to produce the net present value (NPV) in the study, the source and confidence of these economic inputs including estimated inflation,

  • No cost impact is expected from deleterious elements and no costs have been included in the Ore Reserve estimate for these

  • ▪ State Government and third-party royalties are built into the cost model ▪ The Ore Reserve estimate has been converted predominantly based on confidence with Measured Resource to Proven Reserve and Indicated Resource to Probable Reserve

  • These classifications align with the Competent Person’s view of the deposits

Evolution Mining Limited

128

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
discount rate, etc.

NPV ranges and sensitivity to variations in the significant
assumptions and inputs.

Mineral Resource that is not, in the opinion of the Competent Person, extractable without
significant risk due to geotechnical constraints has been excluded from the estimate as
the confidence of recoveryof this material would be considered low
Revenue factors
The status of agreements with key stakeholders and matters
leading to social licence to operate.

All financial assumptions are in Australian dollars.

A gold price of $2,500 per ounce has been used to generate revenue for the reported Ore
Reserve estimate. Evolution uses an internal gold price assumption of $2,650 per ounce
for Life of Mine (LOM) planning

This gold price is assumed to be constant for the mine plan associated with the Ore
Reserve estimate

Sensitivity is conducted at a range of different gold prices ($1,800 to $2,500/oz)
Market assessment
To the extent relevant, the impact of the following on the
project and/or on the estimation and classification of the Ore
Reserves:

Any identified material naturally occurring risks.

The status of material legal agreements and marketing
arrangements.

The status of governmental agreements and approvals
critical to the viability of the project, such as mineral
tenement status, and government and statutory approvals.
There must be reasonable grounds to expect that all
necessary Government approvals will be received within the
timeframes anticipated in the Pre-Feasibility or Feasibility
study. Highlight and discuss the materiality of any
unresolved matter that is dependent on a third party on
which extraction of the reserve is contingent.

For the purposes of the Ore Reserve estimate it is assumed that all product is sold direct
to refinery at spot market prices

A customer and competitor analysis were deemed unnecessary
Economic
The basis for the classification of the Ore Reserves into
varying confidence categories.

Whether the result appropriately reflects the Competent
Person’s view of the deposit.

The proportion of Probable Ore Reserves that have been
derived from Measured Mineral Resources (if any).

Financial modelling has been completed using reconciled cost models as previously
described with outlined revenue factors. With significant historical precedent the
confidence of the forecast economic outcomes is high

The Ore Reserve estimate has been evaluated using a financial model, with sensitivity to
internal and external factors being included in the evaluation.
Social
The results of any audits or reviews of Ore Reserve
estimates.

Evolution’s Mungari Gold Operations operate in the Goldfields region of Western
Australia, which is a well-established, supportive jurisdiction for mineral operations from
both a statutory and community perspective. There are no outstanding material
stakeholder agreements required

Cultural heritage could be considered as a material risk to the Ore Reserve estimations
for projects not yet in production

The Mungari Cultural Heritage Specialist liaises regularly with Native Title claimant groups
to inform and strategise plans to conduct heritage surveys where required to assess for
areas of cultural significance. These are either approved by claimant groups to proceed,
ora cultural heritagemanagement plan negotiated betweenthe partiesis developed to

Evolution Mining Limited

129

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
allow mining to commence in a sustainable manner protecting any sites of significance to
the traditional owners

In the opinion of the Competent Person there is no known reason that additional required
Cultural Heritage approvals will not be granted in the timeframes used for the schedule
Other
Where appropriate a statement of the relative accuracy and
confidence level in the Ore Reserve estimate using an
approach or procedure deemed appropriate by the
Competent Person. For example, the application of statistical
or geostatistical procedures to quantify the relative accuracy
of the reserve within stated confidence limits, or, if such an
approach is not deemed appropriate, a qualitative discussion
of the factors which could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages,
which should be relevant to technical and economic
evaluation. Documentation should include assumptions
made and the procedures used.

Accuracy and confidence discussions should extend to
specific discussions of any applied Modifying Factors that
may have a material impact on Ore Reserve viability, or for
which there are remaining areas of uncertainty at the current
study stage.

It is recognised that this may not be possible or appropriate
in all circumstances. These statements of relative accuracy
and confidence of the estimate should be compared with
production data, where available.

No major issues have been identified that will materially affect the estimation or
classification of the Ore Reserve estimates

No material risks with the potential to prevent the commencement and operation of any
projects in the Ore Reserve estimate have been identified

No outstanding legal issues exist that could compromise the Ore Reserve estimate have
been identified

All mining tenements and government approvals are in place for current mining
operations with schedules in place for applications and approvals required for future
projects

In the opinion of the Competent Person there are no known likely grounds that statutory
approvals will not be granted in the timeframes required for the schedule
Classification
Description of the Mineral Resource estimate used as a
basis for the conversion to an Ore Reserve.

Clear statement as to whether the Mineral Resources are
reported additional to, or inclusive of, the Ore Reserves.

Only Measured and Indicated Resources have been included in the Ore Reserves
estimation (expect for secondary Inferred material as outlined for the Underground Ore
Reserve estimates) with:

Measured converting into Proven Reserves and

Indicated converting to Probable Reserves

Stockpiles have been classified as Probable Reserves

It is the Competent Person’s view that the classifications used for the Ore Reserve
estimates are appropriate

For the CY2023 Underground Ore Reserve estimates, all stopes that contain less than
49% Measured Resource (and less than 49% Inferred Resource) are classified as
Probable Reserves
Audits or reviews
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the

Evolution Mining’s corporate based Transformation and Effectiveness Department
conduct in-house Ore Reserve estimate peer review annually with periodic internal and
external audits. The last external audit was completed by Cube Consulting Pty Ltd in

Evolution Mining Limited

130

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
case. 2022. All material actions have been completed for the CY2023 Ore Reserve estimate

The last internal audit was completed in 2022. All material actions were completed for the
CY2023 Ore Reserve estimate
Discussion of relative
accuracy/ confidence

The type and level of study undertaken to enable Mineral
Resources to be converted to Ore Reserves.

The Code requires that a study to at least Pre-Feasibility
Study level has been undertaken to convert Mineral
Resources to Ore Reserves. Such studies will have been
carried out and will have determined a mine plan that is
technically _achievable_and economically viable, and that
material Modifying Factors have been considered.

Established Mineral Resource and Ore Reserve estimates processes developed at
Mungari Operations, combined with a detailed peer review corporate process provide
reasonable confidence in the generated December 31, 2023 Ore Reserve Estimates

Ore Reserve estimates are generally developed on global estimates however some local
estimates are used in current operational areas which are generally reflected as Measure
Resources (or Proven Reserves)

Confidence in the Ore Reserve estimates for operating mines is generally higher
reflecting the greater amount of data available to develop modifying factors. Project
estimations for modifying factors and some forward looking costs are based on reduced
data and have a relatively lower confidence

Producing mines include reconciliation process which are used for the forward looking
forecasts

Evolution Mining Limited

131

==> picture [83 x 59] intentionally omitted <==

APPENDIX A3: NORTHPARKES. JORC CODE 2012 ASSESMENT AND REPORTING CRITERIA – TABLE 1

The following information is provided in accordance with Table 1 of Appendix 5A of the JORC Code 2012 - Section 1 (Sampling Techniques and Data), Section 2 (Reporting of Exploration Results), Section 3 (Estimation and Reporting of Mineral Resources) and Section 4 (Estimation and Reporting of Ore Reserves).

Section 1: Northparkes Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections)

Criteria JORC Code Explanation Commentary
Sampling techniques
Nature and quality of sampling (eg cut channels, random
chips,
or
specific
specialised
industry
standard
measurement tools appropriate to the minerals under
investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should
not be taken as limiting the broad meaning of sampling.

Include reference to measures taken to ensure sample
representivity and the appropriate calibration of any
measurement tools or systems used.

Aspects of the determination of mineralisation that are
Material to the Public Report.

In cases where ‘industry standard’ work has been done
this would be relatively simple (eg ‘reverse circulation
drilling was used to obtain 1m samples from which 3kg
was pulverised to produce a 30 g charge for fire assay’).
In other cases more explanation may be required, such
as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types
(eg submarine nodules) may warrant disclosure of
detailed information

Diamond core drill holes are the primary source of geological and grade information for the
Mineral Resource at Northparkes. Drilling has been completed between 1980 and 2023.

Reverse circulation (RC) drilling is also completed to base of oxidation and into fresh rock,
mostly to shallow-moderate depths. Some RC holes may be extended to depth with
diamond tails.

The diamond core is routinely sampled at 2m intervals from ½ core over the entire length
of the drill hole, producing approximately 5kg samples. In some instances where strong
geological/lithological control is evident in the disposition of mineralisation sampling to
geological contacts is undertaken. Holes drilled from the surface and underground are
oriented perpendicular to orebody mineralisation where possible.

Underground (UG) samples taken from chip sampling of development drives at 3-4m
intervals are also used to help define mineralogical domains and geological contacts. Chip
samples typically yield 4kg – 5kg masses and are not used directly in the estimation of
Mineral Resources.

Samples undergo preparation and analysis by ALS laboratories (Orange and Brisbane),
involving crushing to 2mm, rotary splitting and pulverising to 90% passing 75 microns. Of
this material a 0.4g sample is prepared for analysis via multi-acid digestion including
hydrofluoric acid (HF) and a 30g sample is prepared for analysis via fire assay.
Drilling techniques
Drill type (eg core, reverse circulation, open-hole
hammer, rotary air blast, auger, Bangka, sonic, etc) and
details (eg core diameter, triple or standard tube, depth
of diamond tails, face-sampling bit or other type, whether
core is oriented and if so, by what method, etc).

Drill types utilised in grade estimation are diamond core including PQ, HQ, HQ3, & NQ
and NQ3 sizes yielding core diameters of 85.0mm, 63.5mm, 61.1mm, 47.6mm and
45.1mm respectively. Drill core is usually collected with a 3m barrel and triple tubing
(standard tubing used historically).

Most drill holes have been oriented using an ‘Ezi mark’ orientation system (or similar
technology) for structural and geotechnical requirements.

Reverse Circulation drillholes are also used in the estimation, although they from a much
small proportion of the total holes. RC holes are typically 5-5½" diameter (125mm) and are
drilledwithaface-sampling bit andhammer.

Evolution Mining Limited

132

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
Drill sample recovery
Method of recording and assessing core and chip sample
recoveries and results assessed.

Measures taken to maximise sample recovery and
ensure representative nature of the samples.

Whether a relationship exists between sample recovery
and grade and whether sample bias may have occurred
due to preferential loss/gain of fine/coarse material.

Triple-tube diamond core drilling is preferred.

Current practice ensures all diamond core intervals are measured and recorded for rock
quality designation (RQD) and core loss and recovery.

Core recovery through the ore and waste portions of the deposits is high (close to 100%).

No bias is observed due to core loss.

When RC drilling, drilling is usually halted when wet hole conditions are encountered. The
hole may be continued and extended by adding a diamond tail.
Logging
Whether core and chip samples have been geologically
and geotechnically logged to a level of detail to support
appropriate Mineral Resource estimation, mining studies
and metallurgical studies.

Whether logging is qualitative or quantitative in nature.
Core (or costean, channel, etc) photography.

The total length and percentage of the relevant
intersections logged.

All diamond core has been logged, geologically and geotechnically. The geologic and
geotechnical records are considered qualitative and quantitative with the following items
being captured

Lithology - Detailed code-based logging of drill core lithological boundaries using
acQuire™ on- or offline packages since 2010. Drillog™ used prior to 2010.
Logging codes and procedure documented in Geological logging manual for
Northparkes Mines, A. Schwarz, July 2011).

Alteration

Mineralisation

Structures – including veining & faults. Fundamental geotechnical data collected
on most core (core recovery, RQD, fracture frequency, fracture characteristics,
Equo-TipTM measurements, oriented core data and major structures), more
detailed geotechnical logging completed for geotechnical drill holes).

Weathering

Photographs are taken of wet core only using a frame apparatus and light shroud
to standardise the photo quality. Photographs are stored in secure network
directories. Earlier photos stored in a document control system. Moving to
Documentum™ or similar as a standard storage system.

Magnetic susceptibility is measured at 1m intervals.
Sub-sampling
techniques and sample
preparation

If core, whether cut or sawn and whether quarter, half or
all core taken.

If non-core, whether riffled, tube sampled, rotary split, etc
and whether sampled wet or dry.

For
all
sample
types,
the
nature,
quality
and
appropriateness of the sample preparation technique.

Quality control procedures adopted for all sub-sampling
stages to maximise representivity of samples.

Measures taken to ensure that the sampling is
representative of the in situ material collected, including
for instance results for field duplicate/second-half
sampling.

Whether sample sizes are appropriate to thegrain size of

Drill core is cut in half to produce an approximate 5kg sample using an automatic core
saw, with one half submitted for assay, and the other half retained on site. Where core is
oriented, it is cut on the core orientation line.

Diamond core is predominantly sampled at 2m intervals (but in some instances to
geological contacts). Samples are sent to ALS laboratory in Orange for crushing and
pulverisation. Samples are crushed to 2mm, split via a rotary splitter and then pulverised
(RAB and RC samples are riffle split to a mass <3kg, Diamond core samples are rotary
split after 2mm crush to a mass <3kg) using an LM5 mill to a nominal 90% passing 75
microns. A 0.4g sub-sample of pulverised material is taken for ICP analysis via multi-acid
digestion and a 30g sub-sample is taken for analysis via fire assay. The remaining
pulverised sample is returned to site and stored for future reference.

Sub-sampling is performed during the sample preparation stage in line with ALS internal
protocols.

Field duplicates are collectedforalldiamond core at anapproximaterate ofoneinevery

Evolution Mining Limited

133

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary Commentary
the material being sampled 100m. Field duplicates for RC holes are collected at a rate of 1:20 samples. Comparison
of field duplicates is performed routinely to ensure a representative sample is being
obtained and that the sample size captures an adequate sample volume to represent the
grain size and inherent mineralogical variability within the sampled material.
Quality of assay data
and laboratory tests

The nature, quality and appropriateness of the assaying
and laboratory procedures used and whether the
technique is considered partial or total.

For geophysical tools, spectrometers, handheld XRF
instruments, etc, the parameters used in determining the
analysis including instrument make and model, reading
times, calibrations factors applied and their derivation,
etc.

Nature of quality control procedures adopted (eg
standards,
blanks,
duplicates,
external
laboratory
checks) and whether acceptable levels of accuracy (ie
lack of bias) and precision have been established.

Samples are assayed at ALS Brisbane for a multi element suite using ME-MS61 and Cu
(ore grade) OG62, methods, which analyses a 0.4g sample in multi-acid digestion with an
ICP-AES finish. Gold analysis is completed at ALS Orange by fire assay on a 30g sample
with an AA instrument finish (AA21 and AA25 (over range)). Analytical methods are
deemed appropriate for this style of mineralisation.

Historic quality control procedures include the use of multiple certified standards (CRMs)
which cover the expected grade range of mineralisation encountered within the deposit. In
addition, field duplicates are inserted, and bulk blank samples are inserted at a rate of
1:20 samples for all sample batches sent to the ALS laboratory.

The quality assurance program includes repeat and check assays from an independent
third-party laboratory as deemed necessary.

The ALS laboratory provides their own quality control data, which includes laboratory
standards and duplicates.

NPO currently uses ten CRMs, coarse basalt blanks, field, crush and pulp duplicates to
monitor sample preparation and analytical processes. The rate of insertion was 1:20 for
CRMs, 1:20 for blanks across both ore and waste zones, Field duplicates were inserted at
1:20 (RC) and 1:50 (diamond) while crush and pulp duplicates were at 1:20 samples.

Analysis of quality control sample assays indicate the accuracy and precision is within
acceptable limits and suitable for inclusion in the resource estimate.
Verification of
sampling and assaying

The verification of significant intersections by either
independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry procedures,
data verification, data storage (physical and electronic)
protocols.

Discuss any adjustment to assay data.

All diamond drill holes are logged in the core shed facility on a laptop utilising acQuire
software and stored digitally in an acQuire database on a network server.

Drill holes are visually logged/estimated for copper content prior to sampling and assay.
This visual assessment is used to verify assay data.

The strong correlation between copper, silver and gold enables additional quality control
checks to be enacted on returned assays.

Procedures have been developed to ensure a repeatable process is in place for
transferring, maintaining & storing all drilling, logging and sampling data on the network
server, which has a live upload to a local device and daily back up to an offsite device.
▪ The historical datasets are periodically reviewed as required, no adjustments have been
made to any assay data. All files are reported digitally from ALS laboratories in CSV
format, which is then imported directly into the acQuire database. Checks of the assay
results in acQuire and results returned from the laboratory are performed at the completion
of each drilling & sampling campaign. Laboratory certificates for returned assays are
stored for future reference and checks against values contained within the acQuire
database.
Location of data points
Accuracy and quality of surveys used to locate drill holes
(collar and down-hole surveys), trenches, mine workings

Collar coordinates are picked up by NPO site surveyors using a Leica total station survey
instrument. All underground excavations are monitored usingthe same instrument.

Evolution Mining Limited

134

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
and other locations used in Mineral Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.

The topography is generated from a LIDAR survey completed over NPO mining leases on
an annual basis with outputs in GDA2020 coordinate system (previously GDA94).

A variety of downhole survey methods have been utilised. Historically this would have
included Eastman single shots films, various EMS (electronic multi-shot) systems and
most recently the diamond drill holes, and RC holes have been surveyed using a
gyroscopic instrument recording down hole survey data in 2-6m intervals.

All data points are reported in GDA2020 MGA zone 55 (previously GDA94 MGA zone 55).
Data spacing and
distribution

Data spacing for reporting of Exploration Results.

Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.

Whether sample compositing has been applied.

Drill holes are variably spaced with the following broad resource classifications applied:

Between 30m x 30m and 40m x 40m for Measured

60m x 60m for Indicated

100m x 100m Inferred.

This drill hole spacing is considered sufficient given the deposit grade and geological
continuity and Mineral Resource classification definitions as outlined in the 2012 JORC
Code, which is also supported by historic reconciliation data from the processing plant
over a 29-year production history.

Samples are weighted by length and density when composited to 2m in length for use in
the estimation.
Orientation of data in
relation to geological
structure

Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which
this is known, considering the deposit type.

If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to
have introduced a sampling bias, this should be
assessed and reported if material.

Holes drilled from the surface and underground are oriented perpendicular to orebody
mineralisation and orebody boundaries wherever possible.

There has been no orientation bias recognised within the data used for the Resource
estimate.
Sample security
The measures taken to ensure sample security

Diamond core samples are securely stored onsite prior to being despatched to the ALS
laboratory in Orange.
Audits or reviews
The results of any audits or reviews of sampling
techniques and data.

An external audit of the Northparkes Mineral Resources and Ore Reserves was conducted
in 2019 by Xtract Mining Consultants. The audit included review of the data collection and
management & QAQC procedures including drilling & sampling. These were found to be
appropriate and in line with industry standards.

Evolution Mining Limited

135

==> picture [83 x 59] intentionally omitted <==

Section 2: Northparkes Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section)

Criteria JORC Code Explanation Commentary
Mineral tenement and
land tenure status

Type, reference name/number, location and ownership
including agreements or material issues with third parties
such as joint ventures, partnerships, overriding royalties,
native title interests, historical sites, wilderness or national
park and environmental settings.

The security of the tenure held at the time of reporting
along with any known impediments to obtaining a licence
to operate in the area.

The Northparkes Operation is located 32km north of Parkes in central-west New South
Wales, Australia. The Northparkes operation extends across 4 current mining leases all
owned by Evolution Mining (Northparkes) Pty Ltd (and JV partners for ML1247 and
ML1367) and 4 contiguous Exploration Licences, the details of these leases are
summarised in the following table:
Lease
Ownership
Expiry
ML1247
Evolution Mining (Northparkes) Pty Ltd
SC Mineral Resources
Sumitomo Metal Mining Oceania
26/11/2033
ML1367
Evolution Mining (Northparkes) Pty Ltd
SC Mineral Resources
Sumitomo Metal Mining Oceania
26/11/2029
ML1641
Evolution Mining (Northparkes) Pty Ltd
25/03/2031
ML1743
Evolution Mining (Northparkes) Pty Ltd
01/09/2037
EL5323
Evolution Mining (Northparkes) Pty Ltd
18/07/2028
EL5800
Evolution Mining (Northparkes)PtyLtd
08/01/2028
EL5801
Evolution Mining (Northparkes) Pty Ltd
08/01/2024
Renewal Pending
EL8377
Evolution Mining (Northparkes)PtyLtd
12/06/2028

As of 31st December 2022, Evolution Mining Limited has 80% ownership of the
Northparkes.
Exploration done by
other parties

Acknowledgment and appraisal of exploration by other
parties.

The Northparkes orebodies were discovered by Geopeko Exploration in the late 1970’s
and exploration has been undertaken continuously in the district since that time, firstly by
Geopeko Exploration, followed by North Limited (who established the mining operations at
the Northparkes site), then by Rio Tinto, CMOC Limited and most recently by Evolution
Mining following their acquisition of the Northparkes Operations in December 2023.sData
used in the current estimate is a compilation of many phases of continuous exploration
completed since the late 1970s. This data has been assessed for quality as outlined in
‘Section 1’and deemed suitable for use as the basis of the Mineral Resource estimate.
Geology
Deposit type, geological setting and style of mineralisation.

The Northparkes Deposits are copper-gold porphyry systems. Sulphide mineralisation
occurs as quartz stockwork veins, as disseminations, and as fracture coatings. The
highest grades are generally associated with the most intense stockwork veining.
Sulphide species in the systems are zoned from bornite-dominant cores, centred on the

Evolution Mining Limited

136

==> picture [83 x 59] intentionally omitted <==

==> picture [375 x 115] intentionally omitted <==

  • A summary of all information material to the understanding of the exploration results including a tabulation of the following information for all Material drill holes:

quartz monzonite porphyries, outwards through a chalcopyrite-dominant zone to distal pyrite. As the copper grade increases (approximately >1.2% Cu), the content of covellite, digenite and chalcocite associated with the bornite mineralisation also increases. Gold normally occurs as fine inclusions within the bornite or more rarely as free gold.

  • The alteration zoning is complex but tends to be zoned around the quartz monzonite porphyries with a central K-feldspar altered zone surrounded by biotite-magnetite alteration. The K-feldspar alteration zone at E26 is well developed and extends up to 100 metres outboard from the porphyry. This contrasts with the E22, E27 and E48 deposits where K-feldspar alteration is generally less than 10 metres outboard from the porphyries. The biotite-magnetite zone is strongly developed at the E22, E27 and E48 deposits, and forms a zone up to 200 metres from the porphyry.

  • No exploration has been reported in this release, therefore no drill hole information to report. This section is not relevant to this report on Mineral Resources and Ore Reserves

  • easting and northing of the drill hole collar

  • elevation or RL (Reduced Level – elevation above sea level in metres) of the drill hole collar

Drill hole Information

  • dip and azimuth of the hole

  • down hole length and interception depth

  • hole length.

  • If the exclusion of this information is justified on the basis that the information is not Material and this exclusion does not detract from the understanding of the report, the Competent Person should clearly explain why this is the case.

  • In reporting Exploration Results, weighting averaging techniques, maximum and/or minimum grade truncations (eg cutting of high grades) and cut-off grades are usually Material and should be stated.

    • No exploration has been reported in this release, therefore no drill hole information to report. This section is not relevant to this report on Mineral Resources and Ore Reserves
  • Data aggregationWhere aggregate intercepts incorporate short lengths of methods high grade results and longer lengths of low grade results, the procedure used for such aggregation should be stated and some typical examples of such aggregations should be shown in detail.

  • The assumptions used for any reporting of metal equivalent values should be clearly stated.

  • These relationships are particularly important in the

  • Relationship between reporting of Exploration Results. mineralisation widthsIf the geometry of the mineralisation with respect to the drill and intercept lengths hole angle is known, its nature should be reported.If it is not known and only the down hole lengths are reported, there should be a clear statement to this effect

  • No exploration has been reported in this release, therefore no drill hole information to report. This section is not relevant to this report on Mineral Resources and Ore Reserves

Evolution Mining Limited

137

==> picture [83 x 59] intentionally omitted <==

(eg ‘down hole length, true width not known’).
Diagrams
Appropriate maps and sections (with scales) and
tabulations of intercepts should be included for any
significant discovery being reported These should include,
but not be limited to a plan view of drill hole collar locations
and appropriate sectional views

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Balanced reporting
Where comprehensive reporting of all Exploration Results
is not practicable, representative reporting of both low and
high grades and/or widths should be practiced to avoid
misleading reporting of Exploration Results.

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Other substantive
exploration data

Other exploration data, if meaningful and material, should
be reported including (but not limited to): geological
observations; geophysical survey results; geochemical
survey results; bulk samples – size and method of
treatment;
metallurgical
test
results;
bulk
density,
groundwater,
geotechnical
and
rock
characteristics;
potential deleterious or contaminating substances.

No exploration has been reported in this release, therefore no drill hole information to
report. This section is not relevant to this report on Mineral Resources and Ore Reserves
Further work
The nature and scale of planned further work (eg tests for
lateral extensions or depth extensions or large-scale step-
out drilling).

Diagrams clearly highlighting the areas of possible
extensions, including the main geological interpretations
and future drilling areas, provided this information is not
commercially sensitive.

The Northparkes deposits have significant potential to extend the resource at depth. An
underground drilling program is planned to assist in defining this potential.

Evolution Mining Limited

138

==> picture [83 x 59] intentionally omitted <==

Section 3: Northparkes Estimation and Reporting of Mineral Resources

(Criteria listed in Section 1, and where relevant in Section 2, also apply to this section)

Criteria JORC Code explanation Commentary
Database integrity
Measures taken to ensure that data has not been
corrupted by, for example, transcription or keying
errors, between its initial collection and its use for
Mineral Resource estimation purposes.

Data validation procedures used.

Relevant geologic data from drill hole logging and sampling is stored in the secure
acQuire™ database, managed onsite with access controlled by the Data Geologist. The
master drill-hole database is located on the NPO SQL server (AUNPMSQL1) which is
backed up on a daily basis. Most logging data collected after 2012 has been entered
directly into an offline acQuire data package via laptop computer and then transferred to
the main database within a day or two. The logging package includes validation checks to
prevent spurious logging codes etc from being entered. Assays are imported from text files
supplied by the laboratory and routine QC conducted on certified reference material
sample assays, duplicate assays, grind sizing checks.

Holes with un-reliable drilling and sampling methods are excluded from the dataset used
for estimation. This usually excludes all open hole percussion, air-core and auger drill
holes.

Prior to estimation basic checks are done such as checking for overlapping sample
intervals, missing or duplicated collar surveys, collar elevations at variance to other
topographic data, unrealistic collar locations, down-hole deviations and assay values.

Errors and issues are reported back to the Northparkes database geologist by the
consultants undertaking resource estimation.

A list of included/excluded holes is reported but this information is not flagged in the
acQuire database.

Not all variables (elements) are assayed on all drill hole intervals within the resource
volumes.

Non-sampled/assayed intervals are not assigned low grade/zero values. Most deposits
have assays for the major elements.
E22:

Comprehensive independent database validation was on-going until September 2012
(H&S).

Only diamond and reverse circulation percussion holes were used in the estimates.

A minor quantity of historic assays with high detection limits were reset to “absent”.

Validation of density values did not identify any extreme values. There are few
measurements in saprolite and oxide zones.
E26:As per E22 above. Older holes E26D69 and E26D409 were found inconsistent with recent
nearby holes and were excluded. Reason unknown.

Evolution Mining Limited

139

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
E28/E28NE:No density measurements were found for E28 and limited measurements in oxide for
E28NE deposit. A substantial number of unreliable E28 assays were noted.
E31:10% of drill holes were checked and validated, but many records from older holes could not
be found. H&S recommended these be found and checked.
E44:Missing drill data is a significant issue requiring future effort to locate/resolve.
E48:Drill data was collected and validated for the Step Change Project and Pre-feasibility study in
2011-2012. A total of 381 diamond core holes (188,741m) were used.
GRP314:Most holes have logging and assays for the major elements and density measurements.
Holes with missing data tend to be shallow abandoned or re-drilled ones. No interval or assays
errors were identified in the recent review.
MJH:New drilling used for OoM Study in 2022 and for a new resource Dec 2022. No obvious
errors in database were found.
Site visits
Comment on any site visits undertaken by the
Competent Person and the outcome of those visits.

If no site visits have been undertaken indicate why this
is the case.
Competent Persons for Northparkes are all site based employees.
These visits have included extension discussions with site geologists and engineers and
inspections of deposit exposures underground and on the surface.
He has repeatedly reported his opinion that the data collection and quality is of a high standard
and suitable to support the reported resource classifications.
Geological
interpretation

Confidence in (or conversely, the uncertainty of the
geological interpretation of the mineral deposit.

Nature of the data used and of any assumptions made.

The effect, if any, of alternative interpretations on
Mineral Resource estimation.

The use of geology in guiding and controlling Mineral
Resource estimation.

The factors affecting continuity both of grade and
geology.
NPO maintains a detailed, systematic geological logging system. Project re-logging and
updates of systems supported by post graduate studies, occurs from time to time.

Geological interpretation and wireframe modelling of alteration, major lithologies, faults,
oxidation /weathering surfaces and topography is completed by NPO or consultant
geologists drawing on extensive previous work on the orebodies. Interpretations are based
mostly on drill logging supplemented by surface or underground mapping where available.
The geological models guide and control resource estimation.

Cu/Au/Ag mineralisation is generally not restricted to any specific interpreted lithology or
alteration type. This is consistent with recent previous estimates.

Limited alternative domain modelling such as by vein density or indicator grade shells has
been done.

Arsenic (As) continuity is less than Au continuity which in turn is less than Cu continuity.
E22:Wireframe models of lithology, alteration, base of oxidation and base of weathering were
prepared and edited by H&S entirely from drill data and open cut topography surveys. The
relationship between a small pod of mineralisation to the north of the main zone and the main
zone is yet to be established.

Evolution Mining Limited

140

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
E26 (including MJH):

Barren “Zero” and variably mineralised “Half” porphyries intrude mineralised porphyry,
volcanics and monzonite stock. Only the late porphyry wireframes intersected by new drill
holes were updated in the last model. The geology wireframes are generally well modelled
from drill data though less well constrained on the edges where drilling is sparser.
Mapping in the SLC was used to inform the modelling. Recent L1N mapping has not yet
been incorporated.

Mineralisation is related to pipe-like quartz monzonite porphyry (QMP) intrusions. The
modelled pencil porphyries guide search and variogram parameters in the primary domain.

Sub-horizontal weathering and Gypsum leach zones partially control depletion or
enrichment of some elements and wireframes of these guide search and variogram
parameters.

The current mineralised domain modelling strategy is based on the observation that Cu-
Au-Ag mineralisation is pervasive across virtually all interpreted lithology and alteration
contacts. So apart from the later barren porphyries (Zero and Half), which are treated
separately with hard boundaries, the estimates in the primary zone are unconstrained.
This is consistent with recent previous estimates and has been found to be the simplest
and most effective scheme for the NPO style of porphyry mineralisation.

There is limited scope for significantly different alternative geological interpretations, which
are considered unlikely to significantly impact the Mineral Resource estimates.

The continuity of the geological features hosting mineralisation is greater than the
continuity of the mineralisation itself. Gold mineralisation has less continuity than copper
and is more restricted to the core of the deposit.
E28/E28NE:Geological continuity is greater than grade continuity.
E31:Overall orientation of mineralisation controlled by but not constrained by E31 stock contact
and a shallow dipping latite sill at E31N. Geological continuity is greater than grade continuity.
E44:The geological interpretation is considered reasonable although uncertainty remains with
the interpretation of the footwall mineralisation and whether the limestone and skarn domains
should be separated or combined. Missing geology logging has hampered efforts to clarify
these areas. Au mineralisation is constrained to either the skarn or its halo, or to the fault/vein
zone. There is also some mineralisation in the poorly understood footwall zone where the
interpretation could change.
E48:

High grade copper mineralisation is well drilled and understood as spatially associated
with pencil porphyries, particularly when hosted by volcanics package (Lift 1) with broader
lower grade copper mineralisation within the BQM stock (lift2). (Cu) shows gradational
reduction in grade with distance from pencil porphyries. There is a barren basic dyke but
itsnarrow width hasno significantimpact onthe bulkgrade.
Criteria JORC Code explanation Commentary
E26 (including MJH):

Barren “Zero” and variably mineralised “Half” porphyries intrude mineralised porphyry,
volcanics and monzonite stock. Only the late porphyry wireframes intersected by new drill
holes were updated in the last model. The geology wireframes are generally well modelled
from drill data though less well constrained on the edges where drilling is sparser.
Mapping in the SLC was used to inform the modelling. Recent L1N mapping has not yet
been incorporated.

Mineralisation is related to pipe-like quartz monzonite porphyry (QMP) intrusions. The
modelled pencil porphyries guide search and variogram parameters in the primary domain.

Sub-horizontal weathering and Gypsum leach zones partially control depletion or
enrichment of some elements and wireframes of these guide search and variogram
parameters.

The current mineralised domain modelling strategy is based on the observation that Cu-
Au-Ag mineralisation is pervasive across virtually all interpreted lithology and alteration
contacts. So apart from the later barren porphyries (Zero and Half), which are treated
separately with hard boundaries, the estimates in the primary zone are unconstrained.
This is consistent with recent previous estimates and has been found to be the simplest
and most effective scheme for the NPO style of porphyry mineralisation.

There is limited scope for significantly different alternative geological interpretations, which
are considered unlikely to significantly impact the Mineral Resource estimates.

The continuity of the geological features hosting mineralisation is greater than the
continuity of the mineralisation itself. Gold mineralisation has less continuity than copper
and is more restricted to the core of the deposit.
E28/E28NE:Geological continuity is greater than grade continuity.
E31:Overall orientation of mineralisation controlled by but not constrained by E31 stock contact
and a shallow dipping latite sill at E31N. Geological continuity is greater than grade continuity.
E44:The geological interpretation is considered reasonable although uncertainty remains with
the interpretation of the footwall mineralisation and whether the limestone and skarn domains
should be separated or combined. Missing geology logging has hampered efforts to clarify
these areas. Au mineralisation is constrained to either the skarn or its halo, or to the fault/vein
zone. There is also some mineralisation in the poorly understood footwall zone where the
interpretation could change.
E48:

High grade copper mineralisation is well drilled and understood as spatially associated
with pencil porphyries, particularly when hosted by volcanics package (Lift 1) with broader
lower grade copper mineralisation within the BQM stock (lift2). (Cu) shows gradational
reduction in grade with distance from pencil porphyries. There is a barren basic dyke but
itsnarrow width hasno significantimpact onthe bulkgrade.

Evolution Mining Limited

141

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary

Altona Fault and Oxide zone are modelled separately.
GRP314:Geological continuity is greater than grade continuity which extends across all
lithology boundaries. The low-grade half porphyries were modelled separately with hard
boundaries but the overall effect of this separation was assessed to be insignificant globally and
only minor locally. Inconsistencies with logging codes for the intrusives has been flagged as
needing a thorough reviewbefore thenextmodelupdates.
Dimensions
The extent and variability of the Mineral Resource
expressed as length (along strike or otherwise), plan
width, and depth below surface to the upper and lower
limits of the Mineral Resource.
Resource dimensions are determined by the resource block model extents or grade shells for
copper above the relevant break-even cut-off grade.
E22
The current resource volume is limited to enclosing the 2019 proposed cave shape of 270m (NE-
SW), 170m (NW-SE) and 405m vertical extent (from base of pit at 225m below natural surface to
9650mRL or 630m below surface)
E26 (including MJH):
The current model covers a volume up to 600m E-W, 600m N-S and 1300m vertically starting
approximately 30m below surface.
E28/E28NE:Using a cut-off grade of 0.5 CuEq the resources have the following extents:

E28: 200m strike, up to 80m plan width, 90m vertically from surface

E28NE: 260m strike, up to 160m plan width, 150m vertically from surface
E31:Using a cut-off grade of 0.5 CuEq the resources have the following extents:

E31: 360m strike, up to 80m plan width, 230m vertically from surface

E31N: 360m strike, up to 190m plan width, 140m vertically from surface
E44:Using a cut-off grade of 0.5g/t the resource zones have the following extents:

E44 skarn: 340m strike (SW-NE), 60m plan width, 200m vertically from surface

E44 fault/vein: 300m strike (NW-SE), 200m plan (discontinuous), 160m vertically

E7 skarn: 400m strike (SW-NE), 60m plan width, 100m vertically

Footwall: 200m strike (SW-NE), up to 50m plan width, 100m vertically
E48:Using a cut-off grade of 0.3% Cu the resource has the following extents:

Up to 850m (S-N) by 550m (W-E) plan width, 800m vertically from 600 to 1400m below
surface. There is very little drilling below the base of the model.
GRP314:*The Mineral Resources for GRP314 are currently restricted to two underground block
cave design shapes.
GRP314 Lift 1 cave design has the following approximate dimensions:

340mSW-NE

Evolution Mining Limited

142

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary ▪ 200m NW-SE ▪ 350m vertically, from 230m below surface

  • Nerrad Level 1 cave design has the following approximate dimensions: ▪ 240m SW-NE ▪ 160m NW-SE ▪ 230m vertically, from 230m below surface

  • ▪ The nature and appropriateness of the estimation technique(s) applied and key assumptions, including treatment of extreme grade values, domaining, interpolation parameters and maximum distance of this top capping of grades is rarely necessary. extrapolation from data points. If a computer assisted estimation method was chosen include a description of computer software and parameters used.

  • ▪ The availability of check estimates, previous estimates Late stage barren porphyries are an exception to this.

  • and/or mine production records and whether the Mineral Resource estimate takes appropriate account of such data.

  • ▪ The assumptions made regarding recovery of byenvelopes. products.

  • Estimation and ▪ Estimation of deleterious elements or other non-grade modelling techniques variables of economic significance (eg sulphur for acid are explained accordingly. mine drainage characterisation).

Methods have remained consistent over many years. All of the reported estimates at NPO were done by H&S Consultants utilising Ordinary Kriging (OK) of drill hole assay composites with the exception of E44 where Multiple Indicator Kriging (MIK) was used. OK is considered appropriate for most models because of generally low coefficients of variation in the composites, few extreme outliers and good spatial grade continuity in the main value elements: copper and gold. Because of this top capping of grades is rarely necessary.

Estimation domains are based on mineralisation style (e.g. oxide vs primary) and similarities of exploratory population statistics which generally are an almost unconstrained estimate due to the fact that mineralisation is not limited to a particular rock type or within “hard” geological boundaries. Late stage barren porphyries are an exception to this.

Variography on the major elements Cu, Au, Ag, and As is used to guide sample search ellipse dimensions and orientations tempered with the interpreted plunges and extents of mineralisation envelopes.

All new estimates are compared to previous estimates both visually and statistically and differences are explained accordingly.

Gold and silver are assumed to be recovered as by-products of copper for which the processing plant is currently optimised for. They are estimated separately to copper as the correlation between elements can vary from deposit to deposit.

  • In the case of block model interpolation, the block size in relation to the average sample spacing and the search employed.

Several potentially deleterious elements have been estimated separately in most models although the most common is As which is included as a major modelling element.

  • Any assumptions behind modelling of selective mining units.

  • Any assumptions about correlation between variables.

Block size is generally 20mN by 20mE by 20mRL but may be reduced to 10mN by 10mE by 20mRL in well drilled areas. This equates to between one half and one fifth the nominal drill hole spacing which is the main driver of resource confidence category and considered appropriate for porphyry copper deposits mined by block or sub-level cave and open-pit.

  • Description of how the geological interpretation was used to control the resource estimates.

  • Discussion of basis for using or not using grade cutting or capping.

  • The process of validation, the checking process used, the comparison of model data to drill hole data, and use of reconciliation data if available

Although most of the underground deposits are modelled for block cave mining where the block size is related to nominal drawpoint spacing and draw column dimensions, the mining unit is not selective like in most stoping or open cut mining methods. For the open pit deposits SMUs are chosen based on the latest mining study recommendations.

Estimates are validated by visual comparisons of block and drill grade data, summary statistics

Evolution Mining Limited

143

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
comparisons, grade swath plots, grade tonnage examination, comparisons with previous estimates
and models and with any mill reconciled production data if available.
E22

Potentially deleterious elements estimated in primary domain only: As, Sb, Bi, Fe, Pb, Zn,
S, Mn, Mo, Se and P. As is also estimated in oxide domains.

Three estimation domains: oxide, primary upper (pencil porphyry dominated) and primary
lower (broad disseminated stock hosted) relating to style of mineralisation and interpreted
geology.

Minimal top cutting in these elements which showed skewed populations at around the
99.9th percentile: Sb, Pb, Zn, and S. Isolated outlier Au assays reset to 2.5g/t and As to
500ppm to limit grade smearing.

Au variogram is sensitive to high variance.

Most variables estimated unconstrained within primary zone with the exception of the
barren “zero porphyries” which were estimated separately along with the oxide and Altona
Fault zones.
E26 (including MJH):

The primary zone is divided into two estimation domains: pencil porphyry dominated and
lower broad disseminated stock hosted. The oxide zone combines sub-horizontal saprolite
and oxidised sub-zones. Elements in the small Altona fault zone at the top eastern corner
of the model, were not estimated in the latest block model update (June 2020) because no
new drilling intersected this zone.

Minimal top cutting at around the 99.9th percentile was only applied to elements with a
significantly skewed population: As, Sb, Pb and Zn. Bi not cut.

Estimation within the primary or oxide zones was unconstrained but zero and half
porphyries were estimated separately.

Samples were composited to nominal 4.0m intervals for estimation, with a minimum length
of 1.99m, and honouring domain boundaries.

A three-pass estimation using searches as follows:
1.
40x40x80m search ellipse, 16-40 samples, min 4 octants informed
2.
80x80x160m search ellipse, 16-40 samples, min 4 octants informed
3. 160x160x320m search ellipse, 8-40 samples, min 4 octants informed

Major elements Cu Au Ag and As estimated with soft boundaries between the two primary
domains and a hard boundary between oxide and primary.

Z axis of search 80o > 015o for Domain 1, 75o > 325o for Domain 2 and horizontal for the
oxide domain.

The 2022 model was evaluated within 4 underground block or sub-level cave areas and
compared to the previous estimate completed in 2021. Tonnage is effectively unchanged
due to the fixed volume and no significant change in density. Global grades have changed
slightly, with the largest increase in the recently drilled expanded Level 2 East cave.
Therefore, the current Mineral Resource estimate is considered to take appropriate

Evolution Mining Limited

144

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
account of the previous estimate. Previous similar estimates for E26 are understood to
have reconciled well with mine production, so this methodology appears to work well.

It is assumed that Au and Ag will be recovered as by-products – these elements have
been estimated independently of Cu for all domains.

A range of potentially deleterious elements have also been independently estimated. The
most important of these is arsenic, which was estimated for all domains. Estimates have
also been generated for Sb, Bi, Fe, Pb, Zn, S, Mn, Mo, Se and P in the primary domain
only.

Density was estimated directly into the model from the drill hole samples, using a similar
methodology to the other attributes; data values were cut to remove values outside the
range of 2.40-3.00t/m3 in the primary domains. Fewer samples were used in the density
estimates because density samples are wider spaced than assays.

The model block size is 10x10x20m, while the initial search radii were 40x40x80m for a
nominal drill hole spacing of 40x40x80m, A block size one half to one quarter the hole
spacing is considered appropriate for this type of deposit and the proposed mining
method.

The block size is effectively the selective mining unit (SMU). However, as this is a block
cave operation, the concept of SMU is limited in meaning because no selectivity is applied,
apart from the initial cave design. As mining proceeds, the ore columns become mixed, so
material is not recovered at in-situ grade.

No assumptions are made regarding the correlation of variables during estimation as each
element is estimated independently. However, some elements do show moderate to
strong correlation in the drill hole samples, and the similarity in variogram models
effectively guarantees that this correlation is preserved in the estimates.

The new model was validated in a number of ways – visual comparison of block and drill
hole grades, statistical analysis (summary statistics and swath plots), examination of
grade-tonnage data, and comparison with the previous model.

Swath plots show the grade estimates are consistent with the overall grade trends evident
in the composited data. The estimated grade profile is smoother than composites, due to
the expected smoothing effect of kriging and change of support. Estimated grades are
generally slightly lower than composite grades, reflecting the clustering effect in the raw
data.

All the validation checks suggest that the grade estimates are reasonable when compared
to the composite grades, allowing for data clustering.
E28/E28NE:

The primary zone is divided into five estimation domains based on deposit locations and
drilling density. The high-grade massive quartz pods were also treated as a separate
domain. The oxide zone contains sub-horizontal saprolite and oxidised sub-zones
estimated with soft boundaries.

Minimal top cutting at around the 99.8 to 99.9th percentile was only applied to elements
with a significantly skewed population: As, Bi, Sb, and Zn.

Evolution Mining Limited

145

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

Drill samples were composited to nominal 2m lengths honouring domain boundaries.

Estimation was only done above the Altona fault.

Four pass estimation of primary domain using variography Y axis plunging 20o > 135o
with searches as follows:
1.
35m search sphere, 16-40 samples, min 4 octants informed
2.
70m search sphere, 16-40 samples, min 4 octants informed
3.
105m search sphere, 8-40 samples, min 4 octants informed
4.
105m search sphere, 8-40 samples, min 2 octants informed

Oxide domains used same expansions as above but with 10m initial z radius.

Quartz blow and half porphyry hard boundary domains used oxide search with Y axes
plunging 70o > 000o and 66o > 070o respectively.

There are no previous JORC compliant estimates or production data to compare the
current resource with.

Potentially deleterious elements estimated in primary domain only: As, Sb, Bi, Fe, Pb, Zn,
S, Mn, Mo, Se and P. As is also estimated in oxide domains.

Dry Bulk Density was assigned to the model based on global averages for rock types and
with respect to other NPO deposits, as there were insufficient samples for direct
estimation.

Block size is 12.5x12.5x5.0m represent the SMU. Drill spacing is twice that at E28NE but
sparser at E28. The 5m z height is to match the proposed pit bench height.

All the validation checks indicates the model is good, allowing for the smoothing effect of
kriging and the clustering of drill data.
E31:

Hard primary domain boundaries were used but the oxide zone was estimated with soft
boundaries.

No grade cutting was applied

Drill samples were composited to nominal 2m lengths honouring domain boundaries.

Three pass estimation of primary domain using variography orientations as follows:
1.
35m search sphere, 16-40 samples, min 4 octants informed
2.
70m search sphere, 16-40 samples, min 4 octants informed
3.
105m search sphere, 8-40 samples, min 4 octants informed

There are no previous Mineral Resource estimates or production data to compare the
current reported Mineral Resource against.

Potentially deleterious elements estimated in primary domain only: As, Sb, Bi, Fe, Pb, Zn,
S, Mn, Mo, Se and P. As is also estimated in oxide domains.

Dry Bulk Density was assigned to the model based on global averages for rock types and
with respect to other NPO deposits, as there were insufficient samples for direct
estimation.

Evolution Mining Limited

146

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

Block size is 20mN by 20mE by 20mRL for sparsely drilled volumes. In parts of E31 where
drilling is nominally completed on a 50m by 50m spacing a block size of 20x10x20m was
used and at E31N where drilling is 25x25m blocks 10x10x5m and matches the SMU.

All the validation checks indicate the model is good, allowing for the smoothing effect of
kriging and the clustering of drill data.
E44:

Estimation was constrained by hard domain boundaries. The oxide zone was estimated
with the primary and surficial cover estimated with a hard boundary.

Gold was estimated by recoverable Multiple Indicator Kriging (MIK) and all other elements
by Ordinary Kriging (OK). Gold shows a high coefficient of variation so was not amenable
to linear estimation. The mean of each bin was used except for the top bin which used the
average of the mean and median as is common practice.

A small amount of grade top cutting (at the 99.9th percentile) was applied to all OK
estimates as there were several mildly skewed populations.

Drill samples were composited to nominal 2m lengths honouring domain boundaries.

Four pass estimation of primary domain for MIK using variography orientations as follows:
1.
35m max search ellipse, 16-40 samples, min 4 octants informed
2.
70m max search ellipse, 16-40 samples, min 4 octants informed
3.
105m max search ellipse, 16-40 samples, min 4 octants informed
4.
105m max search ellipse, 8-40 samples, min 2 octants informed

The OK estimations used the same searches with all domains orientated according to their
variography.

The resource is similar to previous estimate done in 2018 except for the impact of recent
drilling. There is no production data to compare the current resource with. The MIK
estimate was comparable with both a top cut OK and an E type estimate also completed
by H&S.

It has been assumed that Ag, Pb, Zn and Cu could be recovered as by-products of the Au.

Of the potentially deleterious elements common in the NPO deposits only As was
estimated.

Density was estimated by OK.

Block size is 12.5x12.5x10m which represents approximately half the drill spacing. An
SMU of 5x5x5m is assumed.

All the validation checks indicate the model is good, allowing for the smoothing effect of
kriging and the clustering of drill data.
E48:

As most lithological/alteration contacts are not recognised in grade estimation, the
wireframe modelling is not sensitive to snapping to drill holes.

Modelling approach consistent with grade behaviour at contacts as observed in contact
plots (Cu). Doesnotresultinsmearing ofgradefrom highgrade areas tolowgrade areas

Evolution Mining Limited

147

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

Constraint by a grade shell was attempted to create a sharper grade boundary in estimate,
but the reduced smearing was not a significant improvement on current approach so was
not used for resource reporting.

No top cutting applied to Cu data but a small number of Au and Ag assays were top cut.

There is a steady decrease in data density vertically, with number of data on base level of
Lift 2 cave 20% of what it is at top of cave.
GRP314:
All elements were estimated by ordinary kriging using updated variography.
The primary zone below the AFZ was divided into 2 domains based on location - the main central
GRP314 domain (1) and the smaller Nerrad prospect to the SE (2). The oxide and transition zones
were defined separately but combined into a single oxide domain for grade estimation. The primary
zone above the AFZ was treated as a separate domain.
Grade top cutting for major elements with strongly skewed grade distributions, specifically Ag and
As, which were cut at around the 99.9th percentile. No grade cutting was applied to the minor
elements but might be considered in future.
Samples were composited to nominal 4.0m intervals for estimation, with a minimum length of
1.99m, honouring domain boundaries.
A three-pass search strategy was used for the estimation of the major elements in the primary
domain:
1.
40m by 80m by 80m search, 16-40 samples, minimum of 4 octants informed
2.
80m by 160m by 160m search, 16-40 samples, minimum of 4 octants informed
3.
160m by 320m by 320m search, 8-40 samples, minimum of 4 octants informed
Estimates in primary mineralisation below the AFZ were unconstrained, with soft boundaries
between GRP314 and Nerrad and a hard boundary to the AFZ and oxide. Similarly, the oxide and
primary zones above the AFZ were also estimated separately with hard boundaries to adjacent
domains. Initial radii were 80x80x20m with the same numbers of samples and radii expansion
factors as the primary domains. The oxide search was flat and unrotated, while the primary zone
above the AFZ dipped 20°>060°. Only the major elements (Cu, Au, Ag & As) were estimated above
the AFZ.
The maximum extrapolation distance will be somewhat less than the maximum search radii.
The 2021 model was compared to the previous estimates completed in 2013 for GRP314 and 2019
for Nerrad. Tonnage is effectively unchanged due to the fixed volume of the cave designs used for
reporting and no significant change in density. Grades have decreased slightly at GRP314 but are
effectively unchanged at Nerrad.
Therehas been no production fromthe GRP314deposit, so thereisnoreconciliationdata

Evolution Mining Limited

148

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
available.
It is assumed that Au and Ag will be recovered as by-products – these elements have been
estimated independently of Cu for all domains.
A range of potentially deleterious elements have also been independently estimated. The most
important of these is arsenic, which was estimated for all domains.
Density was estimated directly into the model from the drill hole samples, using a similar
methodology to the other attributes; data values were cut to remove values outside the range of
2.40-3.00t/m3 in the primary domains. Fewer samples were used in the density estimates because
density samples are wider spaced than assays.
Block size is 20x20x20m, identical to previous estimates. The nominal drill hole spacing in the
better drilled parts of the deposit is 40m by 40m in the plane of mineralisation, while the initial
search radii were 40x80x80m. A block size one half to one quarter the hole spacing is considered
appropriate for this type of deposit and the proposed mining method.
No assumptions are made regarding the correlation of variables during estimation as each element
is estimated independently.
The new model was validated in a number of ways – visual comparison of block and drill hole
grades, statistical analysis (summary statistics and swath plots), examination of grade-tonnage
data, and comparison with the previous model.
Swath plots show the grade estimates are consistent with the overall grade trends evident in the
composited data. The estimated grade profile is smoother than composites, due to the expected
smoothing effect of kriging and change of support. Estimated grades are generally slightly lower
than composite grades, reflecting the clustering of samples in the higher-grade parts of the deposit.
This was confirmed using declustered sample statistics.
All the validation checks suggest that the grade estimates are reasonable when compared to the
sample composite grades.
Moisture
Whether the tonnages are estimated on a dry basis or
with natural moisture, and the method of determination
of the moisture content.
All resource tonnages are reported as dry tonnages derived from volumes x dry bulk density as
determined by immersion or calliper method.
Cut-off parameters
The basis of the adopted cut-off grade(s) or quality
parameters applied.
Cut-off grade is calculated for each project using a copper equivalence calculation that incorporates
a net smelter return (NSR) value based on the most recent financial estimates.

The typical equivalent copper calculation is:
Cu equivalent = ((VCu x Cu Grade (%) x Cu Recovery) + (VAu x Au Grade (g/t) x Au
Recovery)) / (VCu X Cu Grade (%) x Cu Recovery) * Cu Grade (%)
where VCu is the NSR of 1% copper in 1t of ore and VAu is the NSR of 1g/t gold in 1t of ore.

Net Present Value is calculated for a number of scenarios and then the optimum cut off is

Evolution Mining Limited

149

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
selected.

For the block caves a declining shut-off is applied to the reserve schedule.

Block cave reserves are generated using GEOVIA’s PCBC software. PCBC has been
used for production scheduling and draw management at NPO since underground mining
commenced and is regarded as the industry standard for block cave modelling.

Resources are reported within mine design volumes either above zero COG to reflect the
non-selective block cave method or above a cut off based on NSR and costs.
E22:COG is based on E48 with E22 NSR and metallurgical recoveries applied. It incorporates the
following calculation of equivalent copper grade.
Cu equivalent = Cu Grade (%) + 0.628779 x Au Grade (g/t) + 0.0079475 x Ag Grade
Since 2013 the resource outside the current reserve cave shape has been reported at >0.35%
CuEq which is believed to represent the NSR of $18 used for the Step Change Project in 2013.
E28/E28NE:A nominal cut-off grade of 0.5 CuEq (based on previous pit mining at NPO) was
applied. It incorporates an equivalent copper calculation as below:
Cu equivalent = Cu Grade (%) + 0.715176 x Au Grade (g/t) + 0.009040 x Ag Grade (g/t)
E31:A nominal cut-off grade of 0.5 CuEq (based on previous pit mining at NPO) was applied.
E44:A nominal cut-off grade of 0.5 g/t Au (based on previous pit mining at NPO) was applied for
reporting purposes.
E48:The resource was reported within a cave shape generated by an NSR of $16/tonne. This
equates to a cut-offgrade ofaround 0.3% Cu.
Mining factors or
assumptions

Assumptions made regarding possible mining methods,
minimum mining dimensions and internal (or, if
applicable, external) mining dilution. It is always
necessary as part of the process of determining
reasonable prospects for eventual economic extraction
to
consider
potential
mining
methods,
but
the
assumptions made regarding mining methods and
parameters when estimating Mineral Resources may
not always be rigorous. Where this is the case, this
should be reported with an explanation of the basis of
the mining assumptions made.

Current mining methods at NPO include (underground) block-caving and sub-level caving
of the low grade massive and reasonably large rock masses with suitable (caveability)
properties. Open cut mining has been used in past and is underway on several small
resources.

Mining dilution (via mixing algorithms) is incorporated into the PCBC or open cut mine
modelling and schedule.
E22:The current mining study for E22 is assessing both sublevel and block cave methods and as
such the block model was constructed to suit both of these scenarios. It is stated in the report that
other methods would require a new block model to be created.
E26:As for E22 above. Note: The current E26 model was constructed for the purpose of evaluating
large volume caving options at NPO. While considered suitable for this purpose, the model may not
be entirely appropriate for other mining options such as open cut mining or more selective
underground mining methods.

Evolution Mining Limited

150

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
E28/E28NE:It is assumed E28 will be mined by open cut using a 5m bench height. External
dilution is not included in the model.
E31:E31 and E31N are being mined by open cut using a 5m bench height. External dilution is not
included in the model.
E44:It is assumed at least the upper part of E44 will be mined by open cut using a 5m bench
height. External dilution is not included in the model.
E48:It is assumed that the resource will be mined by block cave similar to Lift1 in production at
present.
GRP314:The subject of ongoing mining studies. Current resource quoted based on large
tonnage step change project (2013) andmaynolongerbevalid.Updateis expectedin 2022.
Metallurgical factors
or assumptions

The basis for assumptions or predictions regarding
metallurgical amenability. It is always necessary as part
of the process of determining reasonable prospects for
eventual economic extraction to consider potential
metallurgical methods, but the assumptions regarding
metallurgical treatment processes and parameters
made when reporting Mineral Resources may not
always be rigorous. Where this is the case, this should
be reported with an explanation of the basis of the
metallurgical assumptions made.

The metallurgical recovery for each ore source is based on metallurgical test work
completed from core samples and general knowledge from 20+ years of mining and
processing.

The recoveries for each ore source are used in the calculation of the copper equivalence
formula and life of mine studies.
E22:The mining and processing of transitional and fresh open pit ore provides historical data to
supplement the metallurgical test work completed in 2020.
E26:As per E22 above.
E28/E28NE: Assumptions are based on mining study grinding and flotation testwork completed
in 2020 on four drill hole composite samples representing “Average grade”, “Low grade”, “High
Grade” and “High deleterious” elements.
E31: Locked cycle testwork on core and RC samples was completed in 2020 for the feasibility
study. Primary and transitional ore returned favourable results but oxide and transitional ore is
currently being stockpiled for later processing.
E44:Earlier estimates assumed CIP processing with a recovery of around 81% for gold. A
review of alternate treatment options by Worley Services Pty Ltd in 2020, suggested a pyrite-
gold concentrate could be produced with some modifications to the NPO plant.
E48:Over ten years of production and processing history of Lift1 gives good confidence around
metallurgical amenability, however mineral studies done as part of the prefeasibility study for
Lift 2 suggested recovery would not be as good as Lift 1 ore due to lower grade, a lower bornite
to chalcopyrite ratio, higher pyrite to chalcopyrite ratio, and finer sulphide grain size. From
limited test-work on core the PFS report asserts a recovery of between 83 and 88% for
concentrate between 19 and 24% Cu.
Environmental
factors or

Assumptions made regarding possible waste and
process residue disposal options. It is always necessary
as part of the process of determining reasonable
The mine has been developing and processing ore on site for almost 30 years, so most approvals
and disposal methods are in place and reviewed annually.

Evolution Mining Limited

151

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
assumptions prospects for eventual economic extraction to consider
the potential environmental impacts of the mining and
processing
operation.
While
at
this
stage
the
determination of potential environmental impacts,
particularly for a greenfields project, may not always be
well advanced, the status of early consideration of
these potential environmental impacts should be
reported. Where these aspects have not been
considered this should be reported with an explanation
ofthe environmentalassumptionsmade.
A new mining approval is required for E44. Environmental studies are underway.
Bulk density
Whether assumed or determined. If assumed, the basis
for the assumptions. If determined, the method used,
whether wet or dry, the frequency of the measurements,
the nature, size and representativeness of the samples.

The bulk density for bulk material must have been
measured by methods that adequately account for void
spaces (vugs, porosity, etc), moisture and differences
between rock and alteration zones within the deposit.

Discuss assumptions for bulk density estimates used in
the evaluation process of the different materials.
Density varies with lithology and alteration influenced by the volcanic stratigraphy, weathering and
by alteration around vertical porphyries.

Bulk density samples are collected at 20m intervals from drill core and density is usually
determined by both calliper and immersion methods.

Density data is reported to have low variance and variograms lack strong anisotropy.

Anomalous values outside the interval 2.4><3.0, are reset to mean values.

Density values are estimated in the block models using a three-pass kriging similar to the
elemental grades.
E22:A total of 1,630 10-20cm long core samples were used in the resource model, from 71 out of
148 drill holes. Samples are weighed before and after oven drying (excluding some old samples),
and the calliper results (considered more accurate) are used in preference to the immersion results
unless the former is unavailable.
E26:Dry bulk density was determined by calliper (diametric) and saturated immersion methods
(older holes only by simple immersion) and were typically collected at 20m intervals on 10 -20cm
core samples. Most samples were tested by both methods. There is a total of 6,569 intervals with
density measurements in 331 holes, out of a total of 538 holes used in the resource estimate (519
core holes). Density is influenced by lithology, alteration and oxidation/weathering.
The more recent samples are weighed before and after oven drying overnight at 110ºC to
determine dry weight and moisture content. The calliper method entails measuring core length
twice and diameter thrice using a micrometer. The saturated immersion method involves weighing
the sample in air, in water and after immersion. The calliper method is considered more accurate
due to potential for water absorption during immersion, although differences are likely to be minimal
due to the generally low-porosity rock. Therefore, calliper is the preferred method and immersion is
only used in the absence of calliper data
E28/E28NE:A total of 384 10-20cm long core samples, from 45 out of 295 drill holes. Method as
per E22.
E31:A total of 370 10-20cm long core samples, from 22 out of 227 drill holes, all from E31N.
Method as per E22. Plus189 downhole geophysical measurementsfrom 7 holes at1m intervals.

Evolution Mining Limited

152

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
E44:1,242 core measurements from 52 holes although most measurements represent primary
skarn. Some duplicates were removed.
E48:Approximately 1/3 of resource holes have density measurements. Values are broadly
correlated to lithology and alteration.
GRP314:There is a total of 5,881 intervals with density measurements in 194 holes, out of a
total of 335 holes used in the resource estimate (247 core holes). Density is influenced by
lithology, alteration and oxidation/weathering.
Classification
The basis for the classification of the Mineral Resources
into varying confidence categories.

Whether appropriate account has been taken of all
relevant factors (ie relative confidence in tonnage/grade
estimations, reliability of input data, confidence in
continuity of geology and metal values, quality, quantity
and distribution of the data).

Whether the result appropriately reflects the Competent
Person’s view of the deposit
Block model cells are assigned an estimation search pass number according to distance from
block to samples for each element. For most estimates the Cu pass number is converted to a
preliminary classification: Pass 1= Measured; pass 2= Indicated; pass 3= Inferred while for
deposits with a high Au to Cu ratio an average of the Cu and Au pass numbers is used. The
geostatistical slope of regression is used to downgrade individual blocks that have lower
geostatistical confidence. Finally, the classification is smoothed to reduce the occurrence of
patchy classification. The approach is consistent to that used previously.
The classification appropriately reflects the estimator’s (HSC) view of the deposit. The NPO CP
reviews the classification in the block models generated by H&S consultants and decides with
guidance from the project geologists, if the classification adequately reflects the current
geological confidence and knowledge of controls and continuity. The final classification may be
altered by the CP prior to reporting.
E28:The significant proportion of unreliable assays precludes classifying any of this resource
as measured as opposed to E28NE where no serious quality issues were identified.
E44:In addition to the pass-based classification above, depth limits were added to ensure the
resource had a “reasonable prospect of eventual extraction”.
E48:Classification based on search pass.
GRP314:Classification based on step change project model. Initial classification as measured
andindicatedin latestmodelshould be downgraded untilQAQCreview is completed.
Audits or reviews
The results of any audits or reviews of Mineral
Resource estimates.
The resource estimates from H&S consultants are peer reviewed within the consulting company
prior to reporting. The NPO CP also reviews the resource report and discusses with the consultant
any areas of concern. No significant issues have been identified in the currently reported resource
estimates.
The resource and reserves were last externally audited in 2019 by Xtract Mining Services.
Discussion of relative
accuracy/ confidence

Where appropriate a statement of the relative accuracy
and confidence level in the Mineral Resource estimate
using an approach or procedure deemed appropriate by
the Competent Person. For example, the application of
The NPO Competent Person considers the reported resources to be well modelled and
classified appropriately to reflect the geological confidence and likelihood of conversion to
reserves in the foreseeable future. The consultant estimator used for most of the resource block

Evolution Mining Limited

153

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
statistical or geostatistical procedures to quantify the
relative accuracy of the resource within stated
confidence limits, or, if such an approach is not deemed
appropriate, a qualitative discussion of the factors that
could affect the relative accuracy and confidence of the
estimate.

The statement should specify whether it relates to
global or local estimates, and, if local, state the relevant
tonnages, which should be relevant to technical and
economic evaluation. Documentation should include
assumptions made and the procedures used.

These statements of relative accuracy and confidence
of the estimate should be compared with production
data, where available.
modelling has extensive experience with NPO deposits and similar style deposits in other
locations both within NSW and overseas.
Long term reconciliation of mined portions of several orebodies have proven the accuracy of
past models to within expected tolerances.
The confidence level of the estimates is largely determined by drill hole spacing.
The estimates are local, in the sense that they are localised to model blocks of a size
considered appropriate for local grade estimation. The tonnages relevant to technical and
economic analysis are those classified as Measured and Indicated Mineral Resources.
Underground mapping and sampling of development is used to further validate local resource
block model accuracy once developed and prior to production.
E22:Open pit reconciliations with grade control and processing between 1995 and 2005
showed a slight positive adjustment for both tonnes and grade. The volume in the current
resource has not been mined so no production comparison can be made.
E26:Areas of the model which have been mined (L1 L2 and SLC) reconcile well and exceed
reconciliation and mining recovery performance of many other cave mines in both tonnage and
major element grades.
E28/E28NE:Although geology interpretation and understanding is still at an early stage the
likelihood of a significantly different interpretation of mineralisation controls with further work is
considered unlikely.
E31:Due to the greater drill coverage in E31N compared to E31 confidence is greater and
further work is required at E31 before mining commences. Pre-stripping of waste at E31N
exposed the ore zone and confirmed gross ore-waste boundaries.
E44:The deposit has not been mined so no production comparison can be made. The resource
compares well with the previous estimate.
E48:The deposit is well drilled, and mining of Lift 1 has confirmed geological interpretation.
High confidence can be attributed to the upper parts of Lift 2, decreasing to adequate at the
base.
GRP314:The estimate and model were peer reviewed by both NPO and H&SC and no issues
material to the estimate were reported. The deposit has not been mined so no production
comparisoncanbemade. Theresource compareswell withthe previous estimate.

Evolution Mining Limited

154

==> picture [83 x 59] intentionally omitted <==

Section 4: Northparkes Estimation and Reporting of Ore Reserves

(Criteria listed in Section 1, and where relevant in Sections 2 and 3, also apply to this section)

Criteria JORC Code explanation Commentary
Mineral
Resource
estimate
for
conversion
to
Ore
Reserves

Description of the Mineral Resource estimate used as a basis
for the conversion to an Ore Reserve.

Clear statement as to whether the Mineral Resources are
reported additional to, or inclusive of, the Ore Reserves.

A detailed description of the Mineral Resource estimate is provided in the previous
sections of this Table.

Mineral Resources are reported additional to Ore Reserves not inclusive of Ore
Reserves.

For block cave and sublevel cave reserves, recovery and dilution is based on
Personal Computer Block Cave (PCBC) and Personal Computer Sub-Level Cave
(PCSLC) cave flow modelling software, mine design and mine schedules. This
system uses the resource

classification within the block model to determine the maximum reserve classification
which is thendowngraded asrequired based on modifyingfactors.
Site Visits
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

_If no site visits have been undertaken_indicate why this is the
case.

The Competent Persons for each area are permanent employees of Evolution’s
Northparkes Operations and are situated on site.
Study Status
The type and level of study undertaken to enable Mineral
Resources to be converted to Ore Reserves.

The Code requires that a study to at least Pre-Feasibility Study
level has been undertaken to convert Mineral Resources to Ore
Reserves. Such studies will have been carried out and will have
_determined a mine plan that is technically_achievable and
economically viable, and that material Modifying Factors have
been considered.

E26 L1N Block Cave and E26 SLC have been producing from 2021 and 2016
respectively. These are supported by feasibility studies completed in 2018 and 2015,
with updates to the SLC feasibility study completed in 2019 and 2023.

The economics of the E26L1N and E26 SLC operation are well understood and
reviewed annually.

E22 Reserves are supported by a Pre-Feasibility Study completed in 2022 and a
Feasibility Study is underway and due for completion in 2024.

The economics of the E22 Pre-Feasibility Study are based on the Northparkes sites
operating mines costs and construction costs of the E26L1N block cave completed in
2022. Pre-Feasibility Study shows that the mine plan is technically achievable and
economically viable taking into consideration all material Modifying Factors.

The E31 and E31N feasibility studies were completed in 2022, demonstrating the
suitability of conventional open-pit mining techniques to the deposits.
Cut-off parameters
The basis of the cut-off grade(s) or quality parameters applied
Cut-off values for the mine design were based on iterative reviews of the design, cave flow
simulation and economic analysis. NSR has been used as the basis of the cut-off value in this
analysis, incorporating CMOC economic assumptions at the time of evaluation. Draw points
in both the SLC and BC are assumed to be shut off once they are below the grade
determined by the mining method.
The equivalent copper (‘CuEq’) was calculated in the block model using the formula shown

Evolution Mining Limited

155

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary below. Variable metal recoveries were used for copper and gold respectively based on the below formulas; further work is underway to update the recovery formulas used for the longterm planning based on mineralogy. Recovery is modelled based on sized metallurgical test work. NSR values in the models are based on consensus pricing issued by the Business Analyst with forecast average prices and foreign exchange rates.

==> picture [376 x 46] intentionally omitted <==

Where: NSRCu = Net Smelter Return for 1% Copper (based on average prices including all off site costs, shipping, rail, treatment and refining charges.

▪ Cut-off grade in PCBC and PCSLC has been applied to all cave ore sources based on the mining costs and apportioned site costs, For E26 L1N BC this is a $27.5 NSR, for E26 SLC this is $35 NSR, for E22 this is a $28 NSR. Similarly, the open-pit E31, E31N and E28NE cut-off grades have been derived based on assumptions for mining costs in addition to apportioned site costs. Mining and processing costs for each deposit are borne by the High Grade (HG) component of ore, whilst Low Grade (LG) material need only cover the processing and rehandle costs associated with its own processing, given mining costs have already been funded by the HG material.

In contrast to the CuEq formula outlined above, the E31/E31N and E28NE block models utilise a simpler ‘factor’ formula, incorporating assumptions for metal prices, recoveries and NSR calculations into two factors of Au and Ag. The CuEq formula for the E28NE block model is;

▪ CuEq% = % Cu + g/t Au x 0. 628779 + g/t Ag x 0. 007948

  • Mining factors orThe method and assumptions used as reported in the Pre- assumptions Feasibility or Feasibility Study to convert the Mineral Resource to an Ore Reserve (i.e. either by application of appropriate factors by optimisation or by preliminary or detailed design).

  • The choice, nature and appropriateness of the selected mining method(s) and other mining parameters including associated design issues such as pre-strip, access, etc.

  • The assumptions made regarding geotechnical parameters (eg pit slopes, stope sizes, etc), grade control and pre-production

E26 SLC

  • The E26 SLC Feasibility Study was conducted after the ‘2014 Next Ore Source’ Order of Magnitude Study (OoM). The OoM Study identified key E26 Resources that are available for extraction which demonstrate significant business value. This includes E26 SLC and Lift 1 North Block Cave. Copper-gold mineralisation at E26 occurs within stockwork quartz veins, disseminations and breccia associated with the intrusion of pipelike quartz monzonite porphyries. The portion of the orebody studied has been extensively drilled from underground platforms on multiple orientations; therefore, there is a high degree of confidence in the geological architecture.

Evolution Mining Limited

156

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary drilling. ▪ Multiple design and layout options were considered for the SLC. Several overarching

  • The major assumptions made and Mineral Resource model guidelines were used to guide the fundamental SLC design, these included: used for pit and stope optimisation (if appropriate). ▪ A 30m SLC level spacing as the practical limit for accurate production

  • The mining dilution factors used. drilling, and based on benchmarking, this is the highest conventional level • The mining recovery factors used. spacing being used by SLC mines; • Any minimum mining widths used. ▪ Based on the location, viable materials handling options included: • The manner in which Inferred Mineral Resources are utilised in ▪ Trucking to surface or underground primary crusher; or, mining studies and the sensitivity of the outcome to their ▪ Ore pass to the Lift 2 infrastructure and then re-handle to the Lift 2 crusher. inclusion. ▪ Lift 1 and Lift 2 infrastructure (workshops, crib rooms, explosives magazines

  • The infrastructure requirements of the selected mining methods. etc.) are in the vicinity of the Resource; their use will reduce overall project cost. Utilisation of previously excavated drives in the area would save construction cost.

  • ▪ Due to the production ramp up requirements of an SLC, constructing less than 3 levels would not provide adequate recovery of ore.

  • ▪ Simple and proven designs will reduce mining risk. ▪ A 30 – 40m crown pillar sits between the first level and the previous lift 1 cave. This crown pillar provides a high-grade blanket between production levels and a barrier to dilution from the previous cave. A conservative grade of %0 has been attributed to the overlying Lift 1 cave material for modelling purposes. PCSLC outputs include dilution and no additional dilution factors were incorporated in the Ore Reserve estimate for SLC material

▪ Multiple design and layout options were considered for the SLC. Several overarching guidelines were used to guide the fundamental SLC design, these included: ▪ A 30m SLC level spacing as the practical limit for accurate production drilling, and based on benchmarking, this is the highest conventional level spacing being used by SLC mines; ▪ Based on the location, viable materials handling options included: ▪ Trucking to surface or underground primary crusher; or, ▪ Ore pass to the Lift 2 infrastructure and then re-handle to the Lift 2 crusher. ▪ Lift 1 and Lift 2 infrastructure (workshops, crib rooms, explosives magazines etc.) are in the vicinity of the Resource; their use will reduce overall project cost. Utilisation of previously excavated drives in the area would save construction cost. ▪ Due to the production ramp up requirements of an SLC, constructing less than 3 levels would not provide adequate recovery of ore. ▪ Simple and proven designs will reduce mining risk. ▪ A 30 – 40m crown pillar sits between the first level and the previous lift 1 cave. This crown pillar provides a high-grade blanket between production levels and a barrier to dilution from the previous cave. A conservative grade of %0 has been attributed to the overlying Lift 1 cave material for modelling purposes. PCSLC outputs include dilution and no additional dilution factors were incorporated in the Ore Reserve estimate for SLC material ▪ One of the key drivers to a sub level layout extent design is mining cost. Operating unit cost of the SLC used for shut off is $35/t from: ▪ 2018 SLC mining unit cost $12.55/t ▪ 2018 non mining costs of $17.8t ▪ Capital development approximately $5/t ▪ Actual mining cost from 2017 were also referenced. ▪ Based on the design parameters and constraints, levels 4 to 6 were designed in addition to the original 3 levels. ▪ The SLC strategy is to supplement production with higher grade ore. To understand the grades and tonnages available, a number of extraction scenarios were run through PCSLC in order to evaluate the optimum draw for each level. Levels 1-4 have been completed and levels 5 and 6 are planned to have 150% extraction and 250% where the ring in question is the lowest planned production ring. This final extraction figure has been increased from the original feasibility study and is based on the performance of the previous levels. All ore is planned to be trucked to the L1N ore pass and re-handled by LHD to the primary crusher.

Evolution Mining Limited

157

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation Commentary E26 L1N Block Cave ▪ The block cave is a remnant, block cave extension, mining the halo and quartz monzonite porphyries to the north of E26L1 and E26L2 caves.

  • ▪ E26 L1N Block cave completed construction in 2022 and has been operational since then.

  • ▪ An initial resource model for the area of the proposed development at E26L1N was generated in July 2016, with a more comprehensive resource model completed in January 2017 based on data from recent surface and underground drilling. An updated resource model for E26L1N was subsequently generated in November 2017, incorporating the results of surface drilling on the eastern margin of the E26L1N volume, following revisions to the cave footprint for E26L1N.

  • Modelling was completed by external consultants H&SC using Datamine software, with grades estimated using ordinary kriging. The estimate was reviewed internally by H&SC, with some validation completed onsite by the designated Northparkes Competent Person for Mineral Resources. The resource model for L1N contains no inferred material and therefore no requirement to manage in the reserve conversion.

  • ▪ Throughout the FS, the impact of clays on flotation metallurgy was assessed in detail to ensure this risk was adequately quantified and captured during the financial analysis of the E26L1N orebody. The work undertaken in the FS clearly demonstrates that the presence of clays is expected to negatively impact flotation metallurgy. The impacts of clay on recovery and grade reductions have therefore been included when forecasting concentrate tonnes, to enable a more accurate assessment of the full impact of E26L1N.

  • ▪ Both empirical and numerical methods were employed to assess the caveability of the orebody. The empirical methods used were the Extended Matthews method and the Laubscher (1990) method. The numerical analysis was conducted by Beck Engineering using their Abaqus modelling code. Beck Engineering (2018) simulated the surface expression of the cave referred to as the subsidence zone.

  • ▪ To run the production schedule with template mixing, the cave shape needs to be defined to constrain the block model material available for draw. Beck Engineering has provided these cave shapes based on a coupled caveability and flow simulation model. Sensitivity analysis of geotechnical conditions have been completed by Beck Engineering on cavability.

  • E48 L1 Block Cave ▪ The E48 L1 Block cave was placed into care and maintenance at the end of 2023. The remaining material in the flow model was assessed at a range of shut off grades against the sustaining capital and operating costs for the operation of the E48 mining, crushing and MHS system.

  • ▪ All the scenarios were found to be cashflow negative and therefore no reserves have

Evolution Mining Limited

158

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
been generated for E48 L1 BC.
E22 Block Cave

Estimation of the E22 Ore Reserve involved standard steps of mine optimisation,
mine design, production scheduling and financial modelling. Factors and
assumptions have been based on operating experience and performance of the
existing Northparkes caving operations. The basis of the analysis is considered at
Pre-Feasibility Study level or higher.

Ongoing Feasibility Study utilising experience from the current underground
operations provides key Mine Design Parameters.

Geotechnical parameters and engineering assessments have determined that the
rock mass is amenable to block caving. Empirical assessment and numerical
caveability modelling have been performed and included as a constraint in the PCBC
production simulations. The maximum draw column height is 440m.

The E22 block cave utilises an El Teniente extraction level layout on an 18m x 30m
drawpoint spacing. Undercut geometry is inclined sawtooth shape to be mined in
advance of the draw bell extraction. Extraction level cross cuts to be mined in
advance of the undercut firings.

For E22 the resource classification from the PCBC schedule is measured and
indicated with <1% inferred material. With consideration for mining modifying factors
the caved reserve is deemed to be probable by the competent person. The
development portion of the reserves is a % of the blasted tonnages in the draw bells
and undercut and thus has in increased confidence of recovery. On this basis the
development is classified as proved reserves.
Open pit reserves

Geotechnical assumptions for the open-pit reserves were guided by independent
reports from PSM geotechnical consultants. The recommendations are consistent
with those observed at other open-pit campaigns – both, at Northparkes and similar
operations elsewhere.
Metallurgical factors
or assumptions

The metallurgical process proposed and the appropriateness of
that process to the style of mineralisation.

Whether the metallurgical process is well-tested technology or
novel in nature.

The nature, amount and representativeness of metallurgical test
work undertaken, the nature of the metallurgical domaining
applied and the corresponding metallurgical recovery factors
applied.

Any assumptions or allowances made for deleterious elements.

The existence of any bulk sample or pilot scale test work and
the
degree
to
which
such
samples
are
considered

Metallurgical test work has shown that a conventional crushing, grinding and flotation
circuit would produce internationally saleable concentrate with acceptable metal
recoveries. The metallurgical process is well-tested technology. The processing
plant on site is currently operational and has achieved nameplate mill throughput
rates. Monthly reconciled copper recovery is between 83 and 87%.

The recovery for each ore source is based on metallurgical test work completed at
feasibility study time and extensive knowledge gained through mining and treatment
of the ore since 1994.

The inputs to the flotation model – which are ore related – include the following:

Sulphide and gangue mineral head grades and deportment by size class.

Throughput rates and flotation feed density.
Criteria JORC Code explanation Commentary Commentary
been generated for E48 L1 BC.
E22 Block Cave

Estimation of the E22 Ore Reserve involved standard steps of mine optimisation,
mine design, production scheduling and financial modelling. Factors and
assumptions have been based on operating experience and performance of the
existing Northparkes caving operations. The basis of the analysis is considered at
Pre-Feasibility Study level or higher.

Ongoing Feasibility Study utilising experience from the current underground
operations provides key Mine Design Parameters.

Geotechnical parameters and engineering assessments have determined that the
rock mass is amenable to block caving. Empirical assessment and numerical
caveability modelling have been performed and included as a constraint in the PCBC
production simulations. The maximum draw column height is 440m.

The E22 block cave utilises an El Teniente extraction level layout on an 18m x 30m
drawpoint spacing. Undercut geometry is inclined sawtooth shape to be mined in
advance of the draw bell extraction. Extraction level cross cuts to be mined in
advance of the undercut firings.

For E22 the resource classification from the PCBC schedule is measured and
indicated with <1% inferred material. With consideration for mining modifying factors
the caved reserve is deemed to be probable by the competent person. The
development portion of the reserves is a % of the blasted tonnages in the draw bells
and undercut and thus has in increased confidence of recovery. On this basis the
development is classified as proved reserves.
Open pit reserves

Geotechnical assumptions for the open-pit reserves were guided by independent
reports from PSM geotechnical consultants. The recommendations are consistent
with those observed at other open-pit campaigns – both, at Northparkes and similar
operations elsewhere.
Metallurgical factors
or assumptions

The metallurgical process proposed and the appropriateness of
that process to the style of mineralisation.

Whether the metallurgical process is well-tested technology or
novel in nature.

The nature, amount and representativeness of metallurgical test
work undertaken, the nature of the metallurgical domaining
applied and the corresponding metallurgical recovery factors
applied.

Any assumptions or allowances made for deleterious elements.

The existence of any bulk sample or pilot scale test work and
the
degree
to
which
such
samples
are
considered

Metallurgical test work has shown that a conventional crushing, grinding and flotation
circuit would produce internationally saleable concentrate with acceptable metal
recoveries. The metallurgical process is well-tested technology. The processing
plant on site is currently operational and has achieved nameplate mill throughput
rates. Monthly reconciled copper recovery is between 83 and 87%.

The recovery for each ore source is based on metallurgical test work completed at
feasibility study time and extensive knowledge gained through mining and treatment
of the ore since 1994.

The inputs to the flotation model – which are ore related – include the following:

Sulphide and gangue mineral head grades and deportment by size class.

Throughput rates and flotation feed density.

Evolution Mining Limited

159

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
representative of the orebody as a whole.

For minerals that are defined by a specification, has the ore
reserve estimation been based on the appropriate mineralogy to
meet the specifications?

Flotation feed size distributions.

Flotation circuit configuration.

A combination of sources is used to extract this information as detailed below:
1. Flotation feed mineralogy and deportment by size

The primary source for sulphide mineral mineralogy (bornite, chalcopyrite, chalcocite
and pyrite) is carried in the mining block model and the results of the mining
schedule (PCBC and PCSLC), along with the expected total copper feed grade. The
copper sulphide mineralogy is then adjusted (if required) to ensure the calculated
copper feed grade based on mineralogy matches the expected copper feed grade
based on chemical assays. No changes are made to the provided pyrite feed grades.
The overall mineral head grades are then translated to mineral grades by size
through empirical regressions which consider the cumulative weight per cent of a
mineral in the flotation feed, by size, as a function of the cumulative mass per cent of
that stream, by size. These regressions are ore source specific and for bornite and
chalcopyrite.
2. Throughput rates and flotation feed density

The throughput rates were taken as the monthly Ore Processing milling rates (dtph)
from the Production Plan. For the period prior to Expansion, that is 2020 – end of Q3
2020, a flotation feed density of 34% solids by mass was applied. After this the
flotation feed density was reduced to 30% solids by mass.

In the most recent L1N Feasibility Study, the metallurgical test work program was
extended to address gaps in the current understanding of the expected metallurgical
performance of E26L1N ores, particularly in regard to metallurgical variability,
blending reactions with current feed (E48/SLC) and the potential negative impact of
clay minerals within the E26 old cave material.

As a result of the updated metallurgical knowledge for E26L1N, in-house modelling
and simulation activities were also completed to provide information about the
processing characteristics for the life of the E26L1N orebody. Comminution test work
outcomes were applied to determine the expected comminution specific energy
profile as a means of assessing the impact of E26L1N on planned throughput and
flotation feed grind size. Extensive mineralogical characterisation of flotation test feed
and products have also enabled the assumptions regarding the floatability of E26L1N
to be updated, for sulphide minerals as well as its gangue components. This new
information was utilised in estimating the concentrate tonnes and metal content for a
series of mine plans, all part of the overall financial assessment of E26L1N.

A thorough investigation of the flotation performance and likely variability was
undertaken in the FS and this enabled the metallurgical performance to be forecast

Evolution Mining Limited

160

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
based on measured ore parameters.

The variability flotation tests undertaken in this study showed that E26L1N samples
produced very high rougher recoveries (>>90%) even when the feed grades were
below 0.3% Cu. A lithology mass weighted average Cu recovery from locked-cycle
tests produced a Cu recovery of approximately 91.2%, this is 1.5% higher than what
is estimated to be produced at production scale.

The work undertaken to date demonstrates that the presence of clay is expected to
negatively impact flotation metallurgy. The impacts of clay on recovery and grade
reductions have therefore been included when forecasting concentrate tonnes, to
enable a more accurate assessment.

As the presence of pyrite in the concentrate was identified as a major contributing
factor to the low Cu concentrate grades achieved during the PFS phase, a
substantial effort was put towards determining a suitable method for pyrite
depression during the FS. The work demonstrated that to achieve successful pyrite
depression substantial changes to the flotation reagent scheme are necessary. It
was required to remove NaHS and mercaptan before successful pyrite depression
was achieved by replacing PAX and the promotor with a more selective Cu-sulphide
collector. The history of attempts to remove NaHS from the current reagent scheme
at Northparkes is long and all past attempts to do so have resulted in poor
metallurgical performances. As such, a change was required for E26L1N as this
introduced a substantial risk to the study as the use of the new reagent scheme had
not been validated at production scale, and therefore may cast doubt on the
laboratory test work data as these were translated to full scale performance.

The metallurgical test work conducted in the E22 PFS study build on the historic
processing of E22 open pit material. Metallurgical recoveries for gold are anticipated
to range between 76-79% and copper between 86-87%.

The Northparkes Ore Reserves are expected to produce a high-quality copper
concentrate containing gold and silver by-products. Standard industry commercial
scales for payable metals and impurities shall apply. The concentrate produced will
bemarketable tointernationaltraders.
Environmental
factors
or
assumptions

The status of studies of potential environmental impacts of the
mining and processing operation. Details of waste rock
characterisation and the consideration of potential sites, status
of design options considered and, where applicable, the status
of approvals for process residue storage and waste dumps
should be reported.

Northparkes has been operating since 1993. Environmental impacts though to
December 2032 have been approved under Project Approval 11_0060, of which has
been modified nine times since 2014. Future approvals under the NSW
Environmental Planning and Assessment Act 1979 will be required over the life of the
Ore Reserves period to extend the approved life of mine with key consideration to
proposed tailings storage facilities design and subsidence zones modelling.
Infrastructure
The existence of appropriate infrastructure: availability of land
for plant development, power, water, transportation (particularly
for bulk commodities), labour, accommodation; or the ease with
which the infrastructure can be provided, or accessed.

All underground infrastructure to support the mining of the E26 SLC and E26 L1N
Block cave are in place. E26 SLC is blasted and trucked to the E26 L1N ore pass,
where it is then loaded via the E26 L1N loaders on the production level into the E26
L1N Crusher and conveyor circuit, where it is delivered to the storage bins on the
hoistinglevel.

Evolution Mining Limited

161

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

The existing open-pit crusher facility is deemed adequate to meet the primary
crushing requirements of the open-pit reserves.

The E22 block cave will require the following mining infrastructure to support the
extraction level development:

Box cut, portal and decline access

Ventilation shafts and fans

Conveyor material handling system extension

Primary crushing chamber and equipment

Underground workshop

Primary crushed product is delivered from underground via a hoist to the surface and
conveyed to an existing secondary crushing & screening building. The secondary
crushing circuit is to be fed onto existing overland conveyor 123-CV006, which
delivers ore to a new product feed conveyor to the new Secondary Crushing and
Screening Circuit. The outcome of implementation of secondary crushing and
screening facility is to present a P80 of 22mm to the OPD Stockpiles via 123-CV008,
(previously P80 of 40mm).

Following the secondary crushing of underground (primary crushed only) material,
the grinding circuit comprises two parallel modules (Mod 1 and Mod 2), each
incorporating a Semi Autogenous Grinding (SAG) mill, oversize pebble crushing, two
stages of ball milling and froth flotation.

The flotation process produces a sulphide-rich concentrate containing copper and
gold bearing minerals. Following on from flotation, the concentrate is first thickened
through concentrate thickeners followed by the final dewatering stage through filters
before the dewatered concentrate is transferred to the storage shed, ready for
loading and transportation to the port. The tailings component is pumped from the
flotation stage to a tailings thickener for dewatering from where it is then pumped to a
TSF.

The site tailings strategy is regularly reviewed, with the most optimal disposal
strategy utilised. The future tailings deposition strategy involves alternating
deposition between the Estcourt TSF, Rosedale TSF, Infill TSF, TSF2 and TSF1
Closure to allow for periods of drying out prior to constructing new lifts on active
TSFs.

Deposition of tailings is currently into the Rosedale Stage 3 TSF and Estcourt TSF.

Northparkes sources water from numerous locations including imported water from
various licences. Water recycled from the on-site ore processing facility and tailings
dam reclamation system is collected through existing on-site infrastructure. Effective
water management is crucial to the long-term success of Northparkes operations as
it is essential in the processing of ore through the concentrator to produce copper
concentrate. The water management system aims to collect efficiently and
economically, store and re-use water onsite to minimise external water supply inputs
and supplement supply during periods of high consumption.

Evolution Mining Limited

162

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary

Wherever possible, local personnel are employed by Northparkes and its contractors.
With the majority locally based.
Costs
The derivation of, or assumptions made, regarding projected
capital costs in the study.

The methodology used to estimate operating costs.

Allowances made for the content of deleterious elements.

The source of exchange rates used in the study.

Derivation of transportation charges.

The basis for forecasting or source of treatment and refining
charges, penalties for failure to meet specification, etc.

The allowances made for royalties payable, both Government
and private.

The E22 Pre-Feasibility forms the basis of the capital and operating costs supporting
the E22 Ore Reserves. The capital cost estimates are based on construction costs
from E26L1N in 2022 along with assumed contingency and escalation factor.

Sustaining capital costs is forecast annually as part of the planning and budgeting
cycle.

The operating cost estimate is based on the current operating cost base for block
caves and sub-level caves. Tendering has been performed for open pit costs. The
operating costs include the mining cost, processing cost, site general and
administration costs and exploration costs.

The above operating cost estimates are also used for the future estimated costs of
E26 L1N BC and SLC operating mines.

Transport costs are based on the site concentrate sales model and assume
concentrate is transported by road to Goonumbla and railed to Newcastle. Treatment
and refining charges are included in financial models

Royalty payments of 4% on ex-mine value (gross revenue less deductions) to the
NSW government are included in financial models.
Revenue factors
The derivation of, or assumptions made regarding revenue
factors including head grade, metal or commodity price(s)
exchange
rates,
transportation
and
treatment
charges,
penalties, net smelter returns, etc.

The derivation of assumptions made of metal or commodity
price(s), for the principal metals, minerals and co-products.

The financial assessment of the Ore reserve estimate is based on long term
economic parameters of which a range is provided for the calculation of NSR for
optimisation and validation work. The NSR calculation considers the Ore Reserve
revenue factors, metallurgical recovery assumptions, transport costs and refining
charges.

The exchange rate, copper and gold prices for long term financial assessment are
based on CMOC corporate assumptions and range:

AUD/USD exchange 0.73-0.78

Copper US$2.75-3.77/lb

Gold US$1250-1750/oz

Transport and treatment charges are based on the site concentrate sales model and
included in financial evaluations.
Market assessment
The demand, supply and stock situation for the particular
commodity, consumption trends and factors likely to affect
supply and demand into the future.

A customer and competitor analysis along with the identification
of likely market windows for the product.

Price and volume forecasts and the basis for these forecasts.

For industrial minerals the customer specification, testing and
acceptance requirements prior to a supply contract.

Northparkes sells to the Japanese Copper Smelters owned by Pan Pacific Copper
(PPC) and Sumitomo Metal Mining (SMM), and other first-class customers in the
region such as LS Nikko Copper in South Korea. All of these customers prefer a
minimum copper content of 27% in their concentrate but will accept down to 25% for
extended periods of time if the long-term vision is for a 27% minimum grade copper
concentrate. This is the present case with NPO.

Presently Australian produced copper concentrate has been re-introduced into China
smelters and we anticipate Northparkes material will be shipped there in 2024, other
quality friendly smelters are located in Philippines and India within Asia.

NPO copper concentrate is considered a good, clean, high-grade concentrate and
sales terms are at the top end of the revenue scale.

Evolution Mining Limited

163

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Economic
The inputs to the economic analysis to produce the net present
value (NPV) in the study, the source and confidence of these
economic inputs including estimated inflation, discount rate, etc.

NPV ranges and sensitivity to variations in the significant
assumptions and inputs.

Each ore body has been evaluated based on the revenue factors above, capital and
operating costs. Ore bodies that have been found to be economically positive have
been included into the reserves.

Sensitivity to OPEX costs, metal prices, foreign exchange rates and recovery have
been completed. Within the sensitivities completed, the potential profitability was
most sensitive to recovery and OPEX costs.
Social
The status of agreements with key stakeholders and matters
leading to social licence to operate.


Northparkes has been operating within the current mining leases for over 25 years
and has established working relationships with all stakeholders. The orebodies listed
within Northparkes reserves statement are all within the current mining lease
boundaries and permitted within current approvals.

Northparkes continues to place value on engagement undertaken and proactively
working with neighbours, traditional owners, community, businesses, and regulators.
Other
To the extent relevant, the impact of the following on the project
and/or on the estimation and classification of the Ore Reserves:

Any identified material naturally occurring risks.

The status of material legal agreements and marketing
arrangements.

The status of governmental agreements and approvals critical to
the viability of the project, such as mineral tenement status, and
government and statutory approvals. There must be reasonable
grounds to expect that all necessary Government approvals will
be received within the timeframes anticipated in the Pre-
Feasibility or Feasibility study. Highlight and discuss the
materiality of any unresolved matter that is dependent on a third
party on which extraction of the reserve is contingent.

Existing data for open-pit oxide stockpiles metallurgical recovery (through
Northparkes’ current facility) show the stockpile to be economic – despite lower Cu
recoveries that were observed in laboratory testing. Economics have been proven
based on existing recovery data.
Classification
The basis for the classification of the Ore Reserves into varying
confidence categories.

Whether the result appropriately reflects the Competent
Person’s view of the deposit.

The proportion of Probable Ore Reserves that have been
derived from Measured Mineral Resources (if any).

The ore reserve classification has been based on indicated and measured resources.

Measured resources that are converted to reserve are categorised as Proved
Reserves and Indicated resources that are converted to reserve are categorised as
Probable Reserves, with the exceptions below.

In the opinion of the Competent Person for E26 L1N BC, the classification for block
cave ore reserves is probable due to the mechanism of dilution and mixing occurring,
leading to greater uncertainty of the remaining composition of the broken ore
available. The E26 L1N Block Cave probable reserves are 95% measured resources.

In the opinion of the Competent Person for E26 SLC, due to the high draw tonnages
targeted for the final levels (150% and 250% draw) and the compounded mixing
mechanisms from the previous SLC level, the classification of the reserve for this
area is also probable. The E26 SLC probable reserves are 98% measured
resources.

With similar reasoning to the E26L1N BC, the proportion of measured resource in
probable reserves for E22 is approximately 76%.

Evolution Mining Limited

164

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
Audits or reviews
The results of any audits or reviews of Ore Reserve estimates.

There have been multiple technical reviews on ore bodies currently in production and
reviews of the technical studies for ore bodies not at execution stage.

These reviews include flow modelling and reconciliation, cave back positioning,
mixing parameters and project feasibility studies which form the basis of the reserves
reported.
Discussion of relative
accuracy/ confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Ore Reserve estimate using an approach
or procedure deemed appropriate by the Competent Person. For
example,
the
application
of
statistical
or
geostatistical
procedures to quantify the relative accuracy of the reserve within
stated confidence limits, or, if such an approach is not deemed
appropriate, a qualitative discussion of the factors which could
affect the relative accuracy and confidence of the estimate.

The statement should specify whether it relates to global or local
estimates, and, if local, state the relevant tonnages, which
should be relevant to technical and economic evaluation.
Documentation should include assumptions made and the
procedures used.

Accuracy and confidence discussions should extend to specific
discussions of any applied Modifying Factors that may have a
material impact on Ore Reserve viability, or for which there are
remaining areas of uncertainty at the current study stage.

It is recognised that this may not be possible or appropriate in all
circumstances. These statements of relative accuracy and
confidence of the estimate should be compared with production
data, where available.

It is the opinion of the Competent Persons that the Ore Reserve estimate is
supported by appropriate design, scheduling, and costing work reported to at least a
Pre-Feasibility Study level of detail.

The accuracy of the Ore Reserve estimate is largely dependent on the accuracy of
the Mineral Resource and the cave flow model.

There is greater uncertainty inherent in caving mining methods than in more selective
mining methods, due to the variability in cave propagation and internal mechanisms
for mixing and flow of material.

Recovered grades are estimated using industry standard flow modelling software,
using input assumptions developed from extensive site history and experience at
other operations using the same mining methods.

Through the site sampling and reconciliation process, the modelled grades are able
to be compared with the reconciled grades on a monthly basis. While there are
variances, the variation between the mined grades and the reconciled grades is
currently commensurate with the variability implied by the classification.

Evolution Mining Limited

165

==> picture [83 x 59] intentionally omitted <==

APPENDIX A4: RED LAKE. TABLE 1 – ASSESSMENT AND REPORTING CRITERIA, JORC CODE 2012

Section 1: Red Lake. Sampling Techniques and Data

(Criteria in this section apply to all succeeding sections)

  • Criteria JORC Code Explanation Commentary

  • Sampling techniquesNature and quality of sampling (eg cut channels, random ▪ Sampling of gold mineralisation at the Red Lake Operation that constitutes this chips, or specific specialised industry standard measurement Mineral Resource estimate was undertaken using diamond drill core (surface and

  • tools appropriate to the minerals under investigation, such as underground) and underground face samples (rock chips).

  • down hole gamma sondes, or handheld XRF instruments, ▪ Face samples used in the resource estimate were taken at the face of UG etc.). These examples should not be taken as limiting the development ore drives and “grab” sampled across the targeted ore zone. Sample

  • broad meaning of sampling.

  • Include reference to measures taken to ensure sample ▪ lengths varied according to geological contacts observed at the face. All drill core is photographed and logged prior to sampling. The sampling and representivity and the appropriate calibration of any assaying methods are considered by the Competent Person to be appropriate for

  • measurement tools or systems used.

  • Aspects of the determination of mineralisation that are Material orogenic gold deposits. No instruments or tools requiring calibration were used as part of the sampling process.

  • to the Public Report. ▪ Diamond drill core was sampled to lithological, alteration and mineralisation related

  • In cases where ‘industry standard’ work has been done this contacts to ensure representivity. Sample lengths typically range from 0.3m to 1.0m.

  • would be relatively simple (e.g., ‘reverse circulation drilling ▪ Drill core was half core sampled if drilled for Exploration or Resource Definition was used to obtain 1 m samples from which 3 kg was (delineation), whereas grade control (production) drilling is predominantly not cut

  • pulverised to produce a 30 g charge for fire assay’). In other prior to sampling (whole core sampled).

  • cases more explanation may be required, such as where there ▪ Samples undergo further preparation and analysis by external commercial is coarse gold that has inherent sampling problems. Unusual laboratories when core samples were dried, crushed and pulverised (total

  • commodities or mineralisation types (eg submarine nodules) preparation) to produce a 30g or a 50g charge for fire assay of gold.

  • may warrant disclosure of detailed information

  • Drilling techniquesDrill type (eg core, reverse circulation, open-hole hammer, ▪ Drill types utilised in the Mineral Resource estimate are diamond drill core. The core rotary air blast, auger, Bangka, sonic, etc) and details (eg core is extracted using a standard tube and core diameter is either AQTK (30.5mm) BQTK diameter, triple or standard tube, depth of diamond tails, face- (40.7mm) or NQ2 (50.6mm) in size. Prior to 2015 very little drill core was oriented. sampling bit or other type, whether core is oriented and if so, Post 2015, a portion of critical Resource Definition and production drill core was by what method, etc). oriented as deemed necessary to support interpretation in areas of complex geology.

  • Drill sample recoveryMethod of recording and assessing core and chip sample recoveries and results assessed.

  • Measures taken to maximise sample recovery and ensure ▪ Drill core intervals are measured and recorded for rock quality designation (RDQ) representative nature of the samples. and core loss. Core recovery through the ore portions of the deposits is high (>95%).

  • Whether a relationship exists between sample recovery and ▪ No bias is observed due to core loss. grade and whether sample bias may have occurred due to preferential loss/gain of fine/coarse material.

  • Diamond drill core was sampled to lithological, alteration and mineralisation related contacts to ensure representivity. Sample lengths typically range from 0.3m to 1.0m.

  • ▪ Drill core was half core sampled if drilled for Exploration or Resource Definition (delineation), whereas grade control (production) drilling is predominantly not cut prior to sampling (whole core sampled).

  • Drill types utilised in the Mineral Resource estimate are diamond drill core. The core is extracted using a standard tube and core diameter is either AQTK (30.5mm) BQTK (40.7mm) or NQ2 (50.6mm) in size. Prior to 2015 very little drill core was oriented. Post 2015, a portion of critical Resource Definition and production drill core was oriented as deemed necessary to support interpretation in areas of complex geology.

Drill core intervals are measured and recorded for rock quality designation (RDQ) and core loss. Core recovery through the ore portions of the deposits is high (>95%). No bias is observed due to core loss.

Evolution Mining Limited

166

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
Logging
Whether core and chip samples have been geologically and
geotechnically logged to a level of detail to support appropriate
Mineral Resource estimation, mining studies and metallurgical
studies.

Whether logging is qualitative or quantitative in nature. Core
(or costean, channel, etc) photography.

The total length and percentage of the relevant intersections
logged.

All logging is both qualitative and quantitative in nature recording features such as
structural data, lithology, mineralogy, alteration, mineralisation types, vein density,
and colour. All diamond holes were logged entirely from collar to end of hole. All drill
core once logged is digitally photographed using high resolution cameras. The
photographs capture all data presented on the core.
Sub-sampling
techniques and sample
preparation

If core, whether cut or sawn and whether quarter, half or all
core taken.

If non-core, whether riffled, tube sampled, rotary split, etc and
whether sampled wet or dry.

For all sample types, the nature, quality and appropriateness
of the sample preparation technique.

Quality control procedures adopted for all sub-sampling stages
to maximise representivity of samples.

Measures taken to ensure that the sampling is representative
of the in situ material collected, including for instance results
for field duplicate/second-half sampling.

Whether sample sizes are appropriate to the grain size of the
material being sampled

Drill core of NQ2 and BQTK core size are cut in half using an automatic core saw to
produce an approximate 3kg to 5kg sample. The remaining half of the core is kept in
labeled core boxes and stored on site. Where core is oriented, it is cut to preserve
the bottom of hole orientation line. In some instances, core may be quarter cut and
sent for analysis. The smaller drill core size (ATQ) was whole core sampled. More
recently (since 2022) grade control (production) NQ2 drill core is whole core sampled
to maximise the mass of sample sent for analysis.

Drill core and rock chips (from UG ore drive development headings) samples are
sent to an external laboratory. External labs used continuously for the past several
years are: Actlab in Thunder Bay, Ontario since 2015 and SGS in Red Lake, Ontario
since 2006.

When received at SGS or at Actlab the samples are oven dried for 12 hours (60°C),
jaw crushed to 90% passing <2mm and riffle split to a maximum sample weight of
0.5kg. This sub sample is then pulverised in a one stage process, using a LM2
pulveriser, to a particle size of >90% passing 75um. Approximately 250g of the
pulverised sample is extracted by spatula to a numbered paper pulp bag that is used
for a 30g fire assay charge (before 2020) or a 50g FA charge (post January 2020).
The pulp is retained, and the bulk residue is disposed of after four months.
Quality of assay data
and laboratory tests

The nature, quality and appropriateness of the assaying and
laboratory procedures used and whether the technique is
considered partial or total.

For
geophysical
tools,
spectrometers,
handheld
XRF
instruments, etc, the parameters used in determining the
analysis including instrument make and model, reading times,
calibrations factors applied and their derivation, etc.

Nature of quality control procedures adopted (eg standards,
blanks, duplicates, external laboratory checks) and whether
acceptable levels of accuracy (ie lack of bias) and precision
have been established.

The sampling preparation and assaying protocol used at Red Lake Operations was
developed to ensure the quality and suitability of the assaying and laboratory
procedures relative to the mineralisation types. No geophysical tools or other remote
sensing instruments were utilised for reporting or interpretation of gold mineralisation.

Assaying has been completed by two certified external laboratories Actlab in
Thunder Bay, Ontario and SGS in Red Lake, Ontario using fire assay on 30g (before
2020) or 50g (post 2020) subsamples with either gravimetric or AAS finish. Limited
screen fire assay have also been used to validate the fire assay techniques.

The current Quality Assurance and Quality Control (QAQC) program is as follows:
Certified reference material (1:20) and Blank material (1:20) are routinely inserted
into the sampling sequence and also inserted at the discretion of the geologist either
inside or around the expected zones of mineralisation. The intent of the procedure for
reviewing the performance of certified standard reference material is to examine for
any erroneous results (outside of the expected two standard deviation tolerance limit)
and tovalidateif required the acceptablelevels ofaccuracy and precision forall

Evolution Mining Limited

167

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary Commentary
stages of the sampling and analytical process. Batches which fail quality control
checks are re-analysed.

A similar QAQC program was in place for historic samples by previous site owners.

Review of the results of the QAQC program has shown acceptable levels of accuracy
and precision.

When required, a suite of multi elements are determined using four-acid digest with
ICP/MS and/or an ICP/AES finish for some sample intervals. ICP analysis were done
at the external certified laboratory ALS in North Vancouver, British Columbia,
Canada.
Verification
of
sampling and assaying

The
verification
of
significant
intersections
by
either
independent or alternative company personnel.

The use of twinned holes.

Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.

Discuss any adjustment to assay data.

Sample check assays are sent to an Umpire laboratory (AGAT Laboratory in
Thunder Bay, Ontario) at a ratio of 1:50 samples.

The quality assurance / quality control (QAQC) process employed at Red Lake
ensures representative samples are attained and that assay results are accurate and
precise. Half core and sample pulps are retained at Red Lake Operations for two
years if further verification is required.

The twinning of holes is not a common practice undertaken at Red Lake Operations.
Grade variability between samples is examined via the taking of duplicate
underground face samples and duplicate drill core samples in conjunction with
analysis of reconciliation results against input drillhole data and input underground
channel samples. Sample assay results which are inconsistent with surrounding
samples or geological logging undergo additional checks, further verification and re-
assay if deemed necessary.

All sample and assay information are stored utilising the acQuire database software
system. Data undergoes QAQC validation prior to being accepted and loaded into
the database. Assay results are merged when received electronically from the
laboratory. The geologist reviews the database checking for the correct merging of
results and that all data has been received and entered. Any adjustments to this data
are recorded permanently in the database. Historical paper records (where available)
are retained in the exploration and mining offices. Original laboratory digital assay
files are stored in the site data system.

No adjustments or calibrations have been made to the final assay data reported by
the laboratory.
Location of data points
Accuracy and quality of surveys used to locate drill holes
(collar and down-hole surveys), trenches, mine workings and
other locations used in Mineral Resource estimation.

Specification of the grid system used.

Quality and adequacy of topographic control.

Drill hole collar positions are surveyed by the site-based survey department or
contract surveyors (utilising a differential GPS or conventional surveying techniques,
with reference to a known base station) with a precision of less than 0.1m variability.

All drill holes at Red Lake Operations have been surveyed for easting, northing and
reduced level. All data has been translated to NAD83 grid system from the previously
used Red Lake Operations Mine Grid. All work at Red Lake Operations collects and
stores all information in the NAD83 grid system.

Topographic control was generated from aerial surveys and detailed Lidar surveys.
Data
spacing
and

Data spacing for reporting of Exploration Results.

Drill spacing varies considerably throughout the deposit from close spaced <6 m by
6 m to greater than 50 m by 50 m spacing. Drill programs within the Red Lake

Evolution Mining Limited

168

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
distribution
Whether the data spacing and distribution is sufficient to
establish the degree of geological and grade continuity
appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.

Whether sample compositing has been applied.
deposits are ongoing and the final drill spacing chosen is dictated by the level of
understanding required to determine geological and grade continuity of the
mineralisation for Mineral Resource estimation and to ensure that underground ore
development can be appropriately positioned to effectively mine the ore.

Areas of limited drilling will be classified accordingly during the Mineral Resource
classification process. The resource classification process will use the drill spacing
as a guide but will also consider factors such as quality of drillhole surveys and
assays and the risk associated with geological interpretation and estimation. In
general, Mineral Resource classification categories relative to drillhole spacing can
be summarised as:

Unclassified (>40m spacing).

Inferred Resource – General spacing 20 m by 20 m to 40 m by 40 m

Indicated Resource – General spacing 6 m by 6 m to 20 m by 20 m

Measured Resource – Not currently quoted for Red Lake deposits given the highly
variable local grade distribution and complex geology.
Orientation of data in
relation to geological
structure

Whether the orientation of sampling achieves unbiased
sampling of possible structures and the extent to which this is
known, considering the deposit type.

If the relationship between the drilling orientation and the
orientation of key mineralised structures is considered to have
introduced a sampling bias, this should be assessed and
reported if material.

The mineralised structures or zones are generally narrow in width <5.0 m and extend
along strike and up and down dip for more than 100 m and in some cases for
>1000 m. Higher grade or economic shoots exist inside these mineralised zones.
Drilling is planned where possible to intersect the various mineralised zones at as
close to right angles as possible and at a drill spacing that will enable definition of the
economic portions of mineralisation.

The relationship between the drilling orientation and the orientation of key
mineralised structures at Red Lake is not considered to have introduced a sampling
bias and is not considered to be material.
Sample security
The measures taken to ensure sample security

Chain of custody protocols to ensure the security of samples are followed. Prior to
submission, samples are retained on site and access to the samples is restricted.
Collected samples are dropped off at the respective commercial laboratories in North
Western Ontario. Access into the laboratory is restricted and movements of
personnel and the samples are tracked under supervision of the laboratory staff.
During some drill campaigns some samples are collected directly from site by the
commercial laboratory. While various laboratories have been used, the chain of
custody and sample security protocols have remained similar over time.
Audits or reviews
The results of any audits or reviews of sampling techniques
and data.

Evolution mining purchased the Project in 2020 and the previous Competent Person
has audited the database integrity with the site data manager and site geological
team. In addition data has been supplied, as part of the project acquisition, to two
independent parties as CSV text files and incorporated into modelling software with
no integrity issues identified.

Evolution Mining Limited

169

==> picture [83 x 59] intentionally omitted <==

Section 2: Red Lake. Reporting of Exploration Results

(Criteria listed in the preceding section also apply to this section)

Criteria JORC Code Explanation Commentary Commentary
Mineral tenement and
land tenure status

Type, reference name/number, location and ownership
including agreements or material issues with third parties such
as joint ventures, partnerships, overriding royalties, native title
interests, historical sites, wilderness or national park and
environmental settings.

The security of the tenure held at the time of reporting along
with any known impediments to obtaining a licence to operate
in the area.

The Red Lake Operations are located 535km north-west of Thunder Bay, in
northwestern Ontario, Canada. The mine site is on the Evolution Mining’ Contiguous
Land Package which consists of MRO & MRSR patents encompassing a total of
102.6km2.

All mining claims are in good standing. Tenure consists of patents, subject to annual
Mining Land Taxes issued every January. Title registered on land tenure is 100%
owned.

There are five royalties within the Mine Closure Plan, two of the royalties have been
notified of mining conducted (TVX/Kinross and INCO/Vale). Payments have been
accrued for when invoicing is received. All royalty shapes are recorded in
Engineering work files for future reference and mine planning.

Historical sites have been rehabilitated and are monitored by the RLO Environmental
Department.
Exploration done
by
other parties

Acknowledgment and appraisal of exploration by other parties.

Red Lake and Campbell were first staked during the Red Lake Gold Rush in 1926.
Subsequently, there was a period of claim cancellations and re-staking of the area.
Both mines opened in the late 1940s. Red Lake and Campbell Mines were combined
in 2006 when Goldcorp purchased the Campbell Mine.

The earliest known exploration on the Cochenour–Willans property was in 1925.
Cochenour–Willans Gold Mines Ltd. was incorporated in 1936 and production began
in 1939 at a rate of 136–181 t/d. Operations ran for 32 years from 1939–1971. It was
acquired by Goldcorp in 2008.

Aside from the Red Lake gold mines and Cochenour mine, Evolution also holds past
producing operations that include the HG Young, Abino, McMarmac, Gold Eagle
Mine, McKenzie Red Lake mines and Bateman/McFinley.
Geology
Deposit type, geological setting and style of mineralisation.

The mineralisation within the Red Lake Operations can be classified as an Archean
greenstone belt-hosted gold deposit.

The Red Lake Operations are hosted in the Red Lake greenstone belt within the Uchi
Domain on the southern margin of the North Caribou Terrane of the Superior
Province, Canada.

Red Lake Operations is underlain mainly by tholeiitic basalt and locally by komatiitic
basalt of the Balmer Assemblage. The mine sequence also includes felsic,
peridotitic and other mafic to lamprophyric intrusive rocks of various younger ages.
Both Red Lake - Campbell and Cochenour deposits are hosted within significantly
folded and sheared portions of the Balmer Assemblage. Shear zones act as primary
hydrothermal fluid corridors and host significant portions of the gold mineralisation in
the area. Other significant mineralised structures occur within lower-strain areas of
the stratigraphy, usually associated with brittle conjugate fracture systems in close

Evolution Mining Limited

170

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
proximity to lithological boundaries possessing high competency contrasts.

Gold mineralisation is hosted in a variety of rock types within the Red Lake
Greenstone belt, although the majority of the productive zones occur as vein systems
accompanying sulphide replacement within sheared mafic to komatiitic basalts of the
Balmer Assemblage.

Gold bearing zones in the Red Lake-Campbell, HG Young, Cochenour and McFinley
deposits are distinguished first by spatial orientation relative to structural corridors
and second by the style of mineralisation. It is common for zones to have multiple
styles of mineralisation within the same host lithology. There are four styles of
mineralisation common in the Red Lake-Campbell and Cochenour deposit; vein
style, vein and sulphide style, disseminated sulphide (replacement) style and free
gold style.
Drill hole Information
A summary of all information material to the understanding of
the exploration results including a tabulation of the following
information for all Material drill holes:

easting and northing of the drill hole collar

elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar

dip and azimuth of the hole

down hole length and interception depth

hole length.

If the exclusion of this information is justified on the basis that
the information is not Material and this exclusion does not
detract from the understanding of the report, the Competent
Person should clearly explain why this is the case.

No Exploration Results have been reported in this release, therefore no drill hole
information to report. This section is not relevant to this report on Mineral Resources
and Ore Reserves.
Data
aggregation
methods

In
reporting
Exploration
Results,
weighting
averaging
techniques, maximum and/or minimum grade truncations (eg
cutting of high grades) and cut-off grades are usually Material
and should be stated.

Where aggregate intercepts incorporate short lengths of high
grade results and longer lengths of low grade results, the
procedure used for such aggregation should be stated and
some typical examples of such aggregations should be shown
in detail.

The assumptions used for any reporting of metal equivalent
values should be clearly stated.

No Exploration Results have been reported in this release, therefore no drill hole
information to report. This section is not relevant to this report on Mineral Resources
and Ore Reserves.
Relationship
between
mineralisation
widths

These relationships are particularly important in the reporting
of Exploration Results.

No Exploration Results have been reported in this release, therefore no drill hole
information to report. This section is not relevant to this report on Mineral Resources
and Ore Reserves.

Evolution Mining Limited

171

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code Explanation Commentary
and intercept lengths
If the geometry of the mineralisation with respect to the drill
hole angle is known, its nature should be reported.

If it is not known and only the down hole lengths are reported,
there should be a clear statement to this effect (eg ‘down hole
length, true width not known’).
Diagrams
Appropriate maps and sections (with scales) and tabulations
of intercepts should be included for any significant discovery
being reported These should include, but not be limited to a
plan view of drill hole collar locations and appropriate sectional
views

No Exploration Results have been reported in this release, therefore no drill hole
information to report. This section is not relevant to this report on Mineral Resources
and Ore Reserves.
Balanced reporting
Where comprehensive reporting of all Exploration Results is
not practicable, representative reporting of both low and high
grades and/or widths should be practiced to avoid misleading
reporting of Exploration Results.

No Exploration Results have been reported in this release, therefore no drill hole
information to report. This section is not relevant to this report on Mineral Resources
and Ore Reserves.
Other
substantive
exploration data

Other exploration data, if meaningful and material, should be
reported including (but not limited to): geological observations;
geophysical survey results; geochemical survey results; bulk
samples – size and method of treatment; metallurgical test
results; bulk density, groundwater, geotechnical and rock
characteristics;
potential
deleterious
or
contaminating
substances.

No Exploration Results have been reported in this release, therefore no drill hole
information to report. This section is not relevant to this report on Mineral Resources
and Ore Reserves.
Further work
The nature and scale of planned further work (eg tests for
lateral extensions or depth extensions or large-scale step-out
drilling).

Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling
areas, provided this information is not commercially sensitive.

The Red Lake Operations has significant potential to extend the Mineral Resources
laterally and at depth.

Drilling is planned to improve the confidence of the Mineral Resource estimate and to
test for extensions to known mineralisation.

Further refinements to the geological models are planned with the aim of ensuring
the models appropriately reflect the geology and provide for confident mine planning.

Evolution Mining Limited

172

==> picture [83 x 59] intentionally omitted <==

Section 3: Red Lake Estimation and Reporting of Mineral Resources

(Criteria listed in Section 1, and where relevant in Section 2, also apply to this section)

Criteria JORC Code explanation Commentary
Database integrity
Measures taken to ensure that data has not been corrupted
by, for example, transcription or keying errors, between its
initial collection and its use for Mineral Resource estimation
purposes.

Data validation procedures used.

The Red Lake database is stored within an acQuire SQL based system and is
managed on site by appropriately experienced personnel. Management systems are
in place to directly import data from the core logging and sampling and with digital
matching of sample numbers and QA/QC data directly to digital files from the assay
laboratories.

Merging of historical information from prior operating companies of projects that have
become the current Red Lake Operation have been managed by the same
competent database managers that maintain the current system.
Site visits
Comment on any site visits undertaken by the Competent
Person and the outcome of those visits.

If no site visits have been undertaken indicate why this is the
case.

The Competent Person is a full-time employee of Evolution Mining

The Competent Person resides at Red Lake and is the Geology Manager for the Red
Lake Operations.

The Competent Person is involved in detailed reviews and ongoing development of
the data management, logging, geological interpretation, modelling, estimation,
classification and reporting processes employed at the Red Lake Operations.
Geological
interpretation

Confidence in (or conversely, the uncertainty of the geological
interpretation of the mineral deposit.

Nature of the data used and of any assumptions made.

The effect, if any, of alternative interpretations on Mineral
Resource estimation.

The use of geology in guiding and controlling Mineral
Resource estimation.

The factors affecting continuity both of grade and geology.

The geology of the Red Lake Operation including satellite deposits; Cochenour, HG
Young and McFinley that comprise this report is well known.

There is more than 70 years of mining in the Red Lake district and as such a vast
amount of geological information has been collated for the deposits in this estimate.
This information includes geological logging and assay information for over 50,000
drillholes comprising 7,500,000 metres of core. Mapping of development drives has
been completed in detail and utilised to construct lithological and mineralisation
models in 2D and 3D.

This geology information has formed the basis for controlling the development of
wireframes to constrain the Mineral Resource estimate.

Wireframes were constructed using this information as the primary basis to constrain
mineralisation. In prior estimates high grade cut-offs have been a primary control on
the extent of the mineralisation domains both across and along strike.

Modelling for this estimate has focused more on structural and lithological controls as
well and incorporating lower grade mineralisation adjacent to and along strike of
high-grade intercepts to create more continuous mineralised lenses.

The Campbell and Red Lake deposits themselves comprise a significant number of
mineralised structures or lenses that have been modelled and estimated separately.
These lenses can each have differing mineralisation styles and grade distribution.
This has been considered when establishing the wireframes used to constrain the
estimates.

Evolution Mining Limited

173

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary

The Cochenour deposit has similar mineralisation styles to the Campbell/Red Lake
deposits. However, mineralisation outside of the Main zone (UMZ) is less continuous
and better represented by a lower grade envelope at a cut-off of 0.5g/t Au. Shells
have been constructed using Leapfrog models at 0.5g/t to form the basis of the outer
low-grade halos where geological confidence is lacking.

HG Young mineralisation also has similar styles of mineralisation as Campbell/Red
Lake and has been modelled using wireframes that constrain readily interpretable
vein and mineralisation arrays. There is further opportunity to capture additional
mineralisation in the HG Young Mineral Resource by adopting other modelling
methodologies that will be incorporated into future estimates.

McFinley mineralisation occurs within the East Bay Deformation Zone and is
comprised of boudinaged basalt lenses hosted in sheared ultramafic and intruded by
porphyry.
Dimensions
The extent and variability of the Mineral Resource expressed
as length (along strike or otherwise), plan width, and depth
below surface to the upper and lower limits of the Mineral
Resource.

The approximate dimensions of the Red Lake Operations Mineral Resource deposits
are:

Red Lake deposit: 3,000m strike, 3,000m vertical extent, 750m across
strike of mineralisation package

Cochenour deposit: 600 m strike, 700m vertical extent, 250m across
strike of mineralisation package

HG Young (HGY) deposit: 400m strike, 750m vertical extent, 150m
across strike of mineralisation package

McFinley deposit: 1350 strike, 1750m vertical extent, 800m across
strike of mineralisation package
Estimation
and
modelling techniques

The nature and appropriateness of the estimation technique(s)
applied and key assumptions, including treatment of extreme
grade values, domaining, interpolation parameters and
maximum distance of extrapolation from data points. If a
computer assisted estimation method was chosen include a
description of computer software and parameters used.

The availability of check estimates, previous estimates and/or
mine production records and whether the Mineral Resource
estimate takes appropriate account of such data.

The assumptions made regarding recovery of by-products.

Estimation of deleterious elements or other non-grade
variables of economic significance (eg sulphur for acid mine
drainage characterisation).

In the case of block model interpolation, the block size in
relation to the average sample spacing and the search
employed.

Any assumptions behind modelling of selective mining units.

A conventional block modelling approach was adopted with wireframes generated in
Leapfrog Geo, and block models completed in Datamine Studio RM.

The general workflow adopted for all deposits is very similar and involved:

fixed length compositing to 1m honouring interpreted domain
boundaries

data analysis to determine appropriate grade caps for applying to the
composite dataset

Interpolation / estimation of Au g/t grades using Ordinary Kriging (OK)
technique.

classification of blocks as Indicated and Inferred Mineral Resources
using distance based and qualitative criterion.

For this Mineral Resource estimate the following units of measure were applicable;

Drill hole information, wireframes, and blocks of the models are in
metres.

Densities are measured in tonnes per cubic metre, block densities are
assigned as tonnes per cubic metre.

Gold grades are expressed as grams per metric tonne.

Mineral Resource results are reported as metric tonnes, grams per

Evolution Mining Limited

174

==> picture [83 x 59] intentionally omitted <==

  • Criteria JORC Code explanation CommentaryAny assumptions about correlation between variables. metric tonne, and troy ounces. • Description of how the geological interpretation was used to ▪ Block dimensions (X, Y and Z) for all zones except the High Grade Zone (HGZ), HG control the resource estimates. Young (HGY), Cochenour and McFinley were 4m along strike by 2m across strike by

  • Discussion of basis for using or not using grade cutting or 4m in height. Block models are oriented to 045 degrees to approximate the strike of capping. the mineralized structures. Cochenour HGY and McFinley are not rotated. Blocks for

  • The process of validation, the checking process used, the these deposits were sub celled to a chosen size to ensure interpreted volumes were comparison of model data to drill hole data, and use of honoured, with parent cell grade estimation. reconciliation data if available ▪ Given the extreme grade variability present and the presence of extreme gold values within the domain datasets probability thresholds were estimated for blocks at grades that represented low, medium and high-grade sub-domains for each of the structures. This enables separate capping values to be applied for each of these subdomains which helps limit the extent of grade smearing that can occur within the estimation process. The grade capping process results in a 5% to 25% metal reduction depending on the zone being estimated. The applied grade capping approach is supported by reconciliation results.

  • Spatial data analysis or variography was completed using Snowden’s Supervisor software.

  • ▪ Interpolation strategies were applied to suit the data for each zone with the aim of keeping the estimates relatively local, honouring the drilling data without excessive smoothing that could result in smearing of higher grades.

  • ▪ Variable search orientations were applied to honour changes in mineralisation trends by utilising Dynamic Anisotropy functions in the estimation software.

  • ▪ Check estimates were completed using Inverse Distance and Nearest Neighbor estimation methodologies to ensure repeatability and validity on a local and global scale. Any areas of discrepancy were investigated, and results validated accordingly.

  • ▪ A rigorous validation process was followed for each Mineral Resources estimates. This process consist of: ▪ An internal and external technical peer reviews of the geological interpretation and modeling.

  • ▪ Visual and statistical checks on input composite data to ensure coding to interpreted domains has occurred without error and internal / external technical peer review of variogram modelling.

  • ▪ Volume checks of interpreted domain solids against reported block model domain volumes and tonnages.

  • ▪ Visual checks of input composite grades against estimated block grades in section, plan and long section.

  • ▪ Visual checks on interpreted thickness and applied density values in section, plan and long section.

  • ▪ Statistical analysis and comparison of input drillhole data against composite data against capped composite data against estimated block grades per domain.

  • ▪ Internal / external peer review of resource classification approach and

Evolution Mining Limited

175

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary Commentary
statistical and visual validation of block model resource classification
coding

The estimates are for gold only. Other elements whilst of significance to optimising
processing and blend strategies are not considered to be material to the overall
Mineral Resource estimate.
Moisture
Whether the tonnages are estimated on a dry basis or with
natural moisture, and the method of determination of the
moisture content.

All estimates of tonnages are reported on a dry basis.
Cut-off parameters
The basis of the adopted cut-off grade(s) or quality parameters
applied.

The cut-off grades applied to the deposit areas are as follows:

Cochenour – 2.74g/t

Upper Red Lake – 3.3g/t

Lower Red Lake – 2.87g/t

Upper Campbell – 3.3g/t

Lower Campbell – 2.87g/t

HG Young – 2.5g/t

McFinley – 2.5g/t

The cut-off grades were estimated using the site mining, processing and general &
administrative (G&A) costs.

A metallurgical recovery of 88% has been assumed and a gold price of A$2,500/oz
with a CAD:AUD exchange rate of 0.9.
Mining
factors
or
assumptions

Assumptions made regarding possible mining methods,
minimum mining dimensions and internal (or, if applicable,
external) mining dilution. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential mining methods, but
the assumptions made regarding mining methods and
parameters when estimating Mineral Resources may not
always be rigorous. Where this is the case, this should be
reported with an explanation of the basis of the mining
assumptions made.

The Mineral Resource estimate has been reported within Mining Shape Optimiser
objects (MSOs) calculated in Deswik software. These shapes assume a minimum
mining width in the range of 1.8m to 2.4m with a minimum footwall and hangingwall
slope of 50 degrees.

The minimum strike of the panels is 5.0 m and a vertical extent ranging from 15 m to
26 m.

No external dilution has been applied to the shapes however internal dilution has
been applied where required at 0.0g/t Au for waste zones that fall within designed
MSO’s.

Where mining occurred in 2023, the Mineral Resources have been depleted by
detailed surveys (cavity monitoring systems or drone surveys) of mining voids. These
surveys are represented by 3D models which have been used to flag blocks within
the block model to ensure mined regions are not contained within the reported
Mineral Resource or Ore Reserve.

In the upper levels of the Campbell Mine, which has the most extensive existing
workings, a 2.0m skin has been applied to the outer limits of mining voids and all
material inside this skin has also been flagged as mined out.
Metallurgical factors or
assumptions

The
basis
for
assumptions
or
predictions
regarding
metallurgical amenability. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider potential metallurgical

Red Lake Operations operate two process plants, the Campbell plant and Red Lake
plant.

The Campbell plant uses a traditional carbon-in-leach (CIL) and carbon-in-pulp (CIP)
process. The Red Lakeplant uses a traditional CIPprocess.

Evolution Mining Limited

176

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
methods,
but
the
assumptions
regarding
metallurgical
treatment processes and parameters made when reporting
Mineral Resources may not always be rigorous. Where this is
the case, this should be reported with an explanation of the
basis of the metallurgical assumptions made.

Refractory gold is recovered by the pressure oxidation. Sulphide concentrates
produced by both Campbell and Red Lake flotation circuits are processed in the
Campbell plant autoclave, stockpiled and sold externally.

Historical metallurgical and process plant data have been used to develop a recovery
model to estimate the mineral recovery in the process plants dependent upon the
head grade.

Mineral Resource cut-off grades are determined using an average recovery of 88%.
𝑀𝑒𝑡𝑎𝑙𝑙𝑢𝑟𝑔𝑖𝑐𝑎𝑙 𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑦=0.9696 × 𝐻𝑒𝑎𝑑 𝐺𝑟𝑎𝑑𝑒−0.2892
𝐻𝑒𝑎𝑑 𝐺𝑟𝑎𝑑𝑒
Environmental factors
or assumptions

Assumptions made regarding possible waste and process
residue disposal options. It is always necessary as part of the
process of determining reasonable prospects for eventual
economic extraction to consider the potential environmental
impacts of the mining and processing operation. While at this
stage the determination of potential environmental impacts,
particularly for a greenfields project, may not always be well
advanced, the status of early consideration of these potential
environmental impacts should be reported. Where these
aspects have not been considered this should be reported with
an explanation of the environmental assumptions made.

Red Lake Operations has a long history of mining operations and has in place all
permits and approvals to continue operations. There are approvals in place to
establish an underground operation at HG Young.

Active tailings facilities for the operations were designed by third-party consultants.
Annual geotechnical and facility inspections are conducted by these firms. In
addition, engineering assessments and investigations to enhance tails storage
strategies are performed as required.

Water treatment processes are in place at the Red Lake, Campbell and Cochenour
tailings areas to treat metals within solution. Cyanide destruction circuits are
incorporated into the treatment facilities at the Red Lake and Campbell Complexes
where process plants / mills are in operation. All operations utilize passive wetland
treatment technologies to assist with the reduction of ammonia from mining and
milling processes. All effluent discharges to the environment are in compliance with
all applicable laws.

A site Environmental team monitors ongoing compliance with approvals and
maintains the site in good standing with regulators.
Bulk density
Whether assumed or determined. If assumed, the basis for the
assumptions. If determined, the method used, whether wet or
dry, the frequency of the measurements, the nature, size and
representativeness of the samples.

The bulk density for bulk material must have been measured
by methods that adequately account for void spaces (vugs,
porosity, etc), moisture and differences between rock and
alteration zones within the deposit.

Discuss assumptions for bulk density estimates used in the
evaluation process of the different materials.

Bulk density measurements have been taken using a site-based water immersion
method.

The measurements are stored in the site acQuire database on a dry density basis.

Analysis was made of the bulk density by lithology and mineralised domains. Whilst
there is some variation by lithology the main mineralised domains have very similar
bulk densities. They range from 2.65t/m3 to 3.0t/m3.
Classification
The basis for the classification of the Mineral Resources into
varying confidence categories.

Whether appropriate account has been taken of all relevant
factors (ie relative confidence in tonnage/grade estimations,
reliability of input data, confidence in continuity of geology and

Mineral Resource classification have been made in accordance with the JORC 2012
guidelines and are based upon distance and qualitative criterion, with consideration
for the number of holes used during interpolation, sampled/unsampled data, grade
variations between holes, drill spacing, hole orientation, interpolation pass, and
geological confidence.

The applied classification is considered appropriate by the Competent Person to

Evolution Mining Limited

177

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
metal values, quality, quantity and distribution of the data).

Whether the result appropriately reflects the Competent
Person’s view of the deposit
reflect the geological interpretation and estimation risk present at RLO. Given the
inherent grade variability and complex geology present at RLO no regions have been
applied a Measured Resource classification.
Audits or reviews
The results of any audits or reviews of Mineral Resource
estimates.

Internal technical peer reviews of the Mineral Resource process and results have
been undertaken by the Evolution Transformation and Effectiveness team (T&E).
T&E are an oversight and governance group within Evolution, independent of the
resource site study team.

In addition, an external audit program on the reported Mineral Resource and Ore
Reserve is completed by independent 3rd party consultants on a regular basis. The
last external audit was completed by SRK Consulting in September 2022.
Discussion of relative
accuracy/ confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Mineral Resource estimate using an
approach or procedure deemed appropriate by the Competent
Person. For example, the application of statistical or
geostatistical procedures to quantify the relative accuracy of
the resource within stated confidence limits, or, if such an
approach is not deemed appropriate, a qualitative discussion
of the factors that could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages,
which should be relevant to technical and economic
evaluation. Documentation should include assumptions made
and the procedures used.

These statements of relative accuracy and confidence of the
estimate should be compared with production data, where
available.

The relative accuracy of the Mineral Resource estimate has been highlighted as per
the Mineral Resource classification categories applied which were developed in
accordance with the guidelines of the 2012 JORC Code. The applied classification is
considered appropriate by the Competent Person to reflect the geological
interpretation and estimation risk present at RLO. Given the inherent grade variability
and complex geology present at RLO no regions have been applied a Measured
Resource classification.

The site has maintained an ongoing register of production reconciliations over time
which shows varied performance monthly and highlights the inherent risk present in
accurately estimating and mining a high grade, geologically complex & structurally
controlled deposit. Reconciliation results confirm that the reported Mineral Resources
are suitable global estimates to be used as the basis to estimate Ore Reserves,
when drilling, sampling, and mapping are completed to a level to support the
application of an Indicated Resource category. The accurate demarcation of ore from
waste on a local basis requires the completion of ore control activities (drilling,
mapping).

In areas of limited drilling and where an Inferred Resource category has been applied
there is insufficient information to support a robust estimate on which to support the
application of Modifying Factors in sufficient detail to support mine planning and the
evaluation of the economic viability of the deposit. Geological evidence within these
Inferred regions is sufficient to imply but not verify geological or grade continuity. The
31 December 2023 RLO Mineral Resource contains 22.7Mt tonnes of Inferred
material which represents 41% of the total reported Mineral Resource.

Ongoing drilling targeting Inferred and Indicated Mineral Resource regions is
occurring with the aim of converting reported Mineral Resources to Ore Reserves. Of
particular focus this year are the Upper Campbell and Upper Red Lake regions given
their proximity to the planned CYD Decline. A significant program of drilling, re-
interpretation and estimation is currently underway. This program of work will be
followed by a ‘Hill of Value’ study which will optimise the mine plan and applied cutoff
grades to maximise value from the operation. Results of this study are expected late
2024 withanupdatedMineral Resourcefortheseregions scheduled to bereported

Evolution Mining Limited

178

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
as at 31 December, 2024.

For this Mineral Resource estimate the following deposits used new data and
underwent an update of the geological modeling and resource estimation:

MMTP, West R, Aviation, HW 7, Sulphides and Cochenour.

Areas scheduled for drilling and/or update in geological interpretation in 2024 are:

Upper Campbell, Upper Red Lake, Cochenour Footwall, HG Young, DC, EF, HGZ
FootwallandPLM.

Evolution Mining Limited

179

==> picture [83 x 59] intentionally omitted <==

Section 4: Red Lake Estimation and Reporting of Ore Reserves

(Criteria listed in Section 1, and where relevant in Sections 2 and 3, also apply to this section)

  • Criteria JORC Code explanation Commentary

  • Mineral estimate Resource forDescription of the Mineral Resource estimate used as a basis ▪ The Ore Reserve estimate was based on the current Mineral Resource estimate as for the conversion to an Ore Reserve.

  • conversion to Ore described in Section 3. ReservesClear statement as to whether the Mineral Resources are ▪ The Mineral Resources are reported inclusive of the Ore Reserve estimate. reported additional to, or inclusive of, the Ore Reserves.

  • Site visitsComment on any site visits undertaken by the Competent ▪ The Competent Person is registered with a Recognized Professional Organisation Person and the outcome of those visits. and is a full-time employee of Evolution Mining Limited in the role of Principal Long-

  • If no site visits have been undertaken indicate why this is the term Planning Engineer at the Red Lake Operation, with over ten years in practice at case. the site.

  • Study statusThe type and level of study undertaken to enable Mineral ▪ The Red Lake Operation is comprised of the Red Lake, Upper Campbell, Cochenour Resources to be converted to Ore Reserves. and McFinley deposits. The Red Lake Operation is an established operation with

  • The Code requires that a study to at least Pre-Feasibility over 70 years of mining. The updated Ore Reserve estimate was based upon historical costs, first principle labour and consumable costs and projected cost

  • Study level has been undertaken to convert Mineral Resources to Ore Reserves. Such studies will have been reduction initiatives for standardization of mining fleet and consolidation of mining production zones.

  • carried out and will have determined a mine plan that is ▪ Production zones within the deposits are at varying levels of study detail from Pre- technically achievable and economically viable, and that Feasibility to greater than Feasibility based on the stage of development and

  • material Modifying Factors have been considered. production from forecasted to execution.

  • Cut-off parametersThe basis of the cut-off grade(s) or quality parameters applied. ▪ The cut-off grade estimation for Red Lake Operation used mining, processing and general & administrative (G&A) costs. The gold price of A$1,800/oz (A$1,450/oz for Upper Campbell) and foreign exchange rate assumptions of 0.9 AUD:CAD have been used based on guidance provided by Evolution corporate.

  • ▪ The assumed metallurgical recovery was based off a variable metallurgical recovery model dependent upon the head grade of the processed material.

  • ▪ Mining considerations for access, material handling, fill type and width of mineralization affected the stoping cost assumptions between Red Lake, Cochenour, Upper Campbell, HG Young and McFinley. Cut-off grades by area: Red Lake 4.3g/t, Cochenour 4.1g/t, Upper Campbell 2.5g/t, HG Young 3.8g/t and McFinley 3.8g/t.

  • ▪ Development ore tonnes below the cut-off grade that must be hoisted or transported to surface are included in the Ore Reserve estimate considering the cost of processing and haulage. Development cut-off grades by area: Cochenour 1.7g/t, other remaining areas 1.3g/t.

  • Mining factors orThe method and assumptions used as reported in the Pre- ▪ Stopes are designed for either longitudinal open stoping with paste fill or waste fill assumptions Feasibility or Feasibility Study to convert the Mineral Resource (AVOCA). Stope shapes have been generated using the Deswik Stope Optimizer to an Ore Reserve (i.e. either by application of appropriate tool (Deswik.SO) using their respective cut-off grade assumptions for the production factors by optimisation or by preliminary or detailed design). zone and optimised for grade.

  • The choice, nature and appropriateness of the selected mining ▪ The SO stope designs have been generated on section intervals between 5m to 6m

Evolution Mining Limited

180

==> picture [83 x 59] intentionally omitted <==

Criteria

JORC Code explanation

Commentary

==> picture [113 x 166] intentionally omitted <==

on a vertical extent 20m to 26m with a minimum hanging wall and footwall slope of 50⁰. The minimum mining width was between 1.8m to 2.4m, dependent upon the respective geological zone.

  • method(s) and other mining parameters including associated design issues such as pre-strip, access, etc.

  • The assumptions made regarding geotechnical parameters (eg pit slopes, stope sizes, etc), grade control and preproduction drilling.

  • Internal geotechnical data analysis on rock quality, stope dimensions and past stope performance provides guidance on stope dimensions required to minimize unplanned dilution. Stope design shapes are grouped into nominal stope blocks on strike ranging between 12m to 24m.

  • The major assumptions made and Mineral Resource model used for pit and stope optimisation (if appropriate).

  • Unplanned mining dilution and recovery estimates have been established by analysis of historical stope performance for the various geological zones at the Red Lake Operation. Unplanned dilution was included by applying a skin as an equivalent linear overbreak/slough to the hanging wall and footwall between 0.6m to 1.2m. The grade of the unplanned dilution was assumed to be 0g/t except in cases where the geological model was intersected by the design shape. Mining recovery was assumed as 85% for down-hole and up-hole stopes. For Ore Reserves, Inferred Resources are excluded and treated as waste material

  • The mining dilution factors used.

  • The mining recovery factors used.

  • Any minimum mining widths used.

  • The manner in which Inferred Mineral Resources are utilised grade of the unplanned dilution was assumed to be 0g/t except in cases where the

  • in mining studies and the sensitivity of the outcome to their inclusion. geological model was intersected by the design shape. Mining recovery was

  • The infrastructure requirements of the selected mining ▪ assumed as 85% for down-hole and up-hole stopes. For Ore Reserves, Inferred Resources are excluded and treated as waste material methods. that does not contribute to either ounces or revenue.

  • Metallurgical factors orThe metallurgical process proposed and the appropriateness assumptions of that process to the style of mineralisation.

    • Red Lake Operation operates two process plants, the Campbell plant, and Red Lake plant.
  • Whether the metallurgical process is well-tested technology or novel in nature.

The Campbell plant uses a traditional carbon-in-leach (CIL) and carbon-in-pulp (CIP) process. The Red Lake plant uses a traditional CIP process.

  • The nature, amount and representativeness of metallurgical test work undertaken, the nature of the metallurgical domaining applied and the corresponding metallurgical recovery factors applied.

Refractory gold is recovered by pressure oxidation. Sulphide concentrates produced by both Campbell and Red Lake flotation circuits are processed in the Campbell plant autoclave.

  • Any assumptions or allowances made for deleterious elements.

  • The existence of any bulk sample or pilot scale test work and the degree to which such samples are considered representative of the orebody as a whole.

  • For minerals that are defined by a specification, has the ore reserve estimation been based on the appropriate mineralogy to meet the specifications?

Historical metallurgical and process plant data have been used to develop a recovery model to estimate the metallurgical recovery in the process plants dependent upon the head grade. 𝑀𝑒𝑡𝑎𝑙𝑙𝑢𝑟𝑔𝑖𝑐𝑎𝑙 𝑅𝑒𝑐𝑜𝑣𝑒𝑟𝑦=[0.9696 × 𝐻𝑒𝑎𝑑 𝐺𝑟𝑎𝑑𝑒−0.2892] 𝐻𝑒𝑎𝑑 𝐺𝑟𝑎𝑑𝑒

There are no deleterious elements that are modelled.

Evolution has sufficiently addressed the environmental impact of the Red Lake Operation and has obtained all material permits to operate the mine, processing plants, and tailings storage facilities through the life of mine. Any new or amended permits required to mine the Ore Reserves will be obtained within a timeframe that will not disrupt the mine plan. The Red Lake Operation is subject to Evolution’s sustainability policy, which commits the operation to a defined standard of environmental stewardship and social responsibility.

  • EnvironmentalThe status of studies of potential environmental impacts of the mining and processing operation. Details of waste rock characterisation and the consideration of potential sites, status of design options considered and, where applicable, the status of approvals for process residue storage and waste dumps should be reported.

  • Arsenic remains a focus in most environmental programs for all Project operations. Arsenopyrite is a main element in the local geology, contained in ore and waste rock

Evolution Mining Limited

181

==> picture [83 x 59] intentionally omitted <==

Criteria

JORC Code explanation Commentary

that requires specific management in environmental programs.

  • Waste rock and ore are routinely sampled for acid rock drainage (ARD) potential as per the internal programs for ARD and metal leaching. Since there are no significant ARD issues related to the waste and ore at the RLO site, waste rock materials can be used for construction purposes.

  • Waste rock is stored in designated areas at the Red Lake, Campbell, and Cochenour sites. The waste dumps are in a historical tailings area east of the site at the Red Lake site, on the northeast side of the main tailings pond at the Campbell site, and on the northwest side of the Cochenour tailings area.

  • Water discharge is managed by the water treatment facilities and polishing ponds.

  • ▪ The environmental permitting process has begun to redirect tailings from the Campbell Mill to the Red Lake TSF due to the limited lifespan of the Campbell Main Tailings Pond. This redirection necessitates a water treatment plant upgrade and a tailings expansion at the Red Lake TSF, ensuring adequate storage and water management capabilities until 2040. The expanded Red Lake TSF also offers the chance to rehabilitate the Campbell Main Pond during ongoing operations.

  • InfrastructureThe existence of appropriate infrastructure: availability of land ▪ The Red Lake Operation mining activities are conducted in and around the for plant development, power, water, transportation municipality of Red Lake, located 180km north of the town of Dryden, District of Kenora, northwestern Ontario. The Red Lake area is accessible by Highway 105,

  • (particularly for bulk commodities), labour, accommodation; or which joins the Trans-Canada Highway at Vermilion Bay, 175km south and 100km

  • the ease with which the infrastructure can be provided, or accessed. east of Kenora, Ontario. Commercial air services operate to Red Lake from Thunder Bay and Winnipeg.

  • ▪ Power is supplied to the Red Lake Operation through the Hydro One transmission network via a radial line that taps into the 230kV grid at the Dryden transformer station where it is stepped down to 115kV, the line continues up to the Ear Falls transformer station. Red Lake, and Campbell are connected to the Balmer transformer station, which is directly fed from the 115KV line from Ear Falls, with an approximate load of 26MW. Cochenour remains on a separate feeder with a load of approximately 2MW. McFinley remains on a separate feeder with a load of <10MW. Diesel-powered generators provide emergency power to critical areas within the Red Lake Operation in the event of a major electrical disruption.

  • ▪ Potable water is supplied by the municipality and paid for on a usage basis. Process water for the mills is predominantly reclaimed from the tailings areas or underground mine. Additional fresh water is taken from Balmer Lake as required. Process water for underground operations is taken from Sandy Bay–Red Lake for Red Lake and Cochenour and from East Bay-Red Lake for McFinley.

  • ▪ Over 83% of the workforce is local, Red Lake Operation runs a camp facility for the remaining rotational personnel.

  • ▪ In the opinion of the Competent person the current infrastructure is adequate to support current and future mining operations.

  • CostsThe derivation of, or assumptions made, regarding projected ▪ Lateral and vertical capital development costs for the Red Lake Operation have been derived from the Ore Reserve development physicals quantities and the respective

Evolution Mining Limited

182

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation

Commentary

==> picture [113 x 249] intentionally omitted <==

direct mining costs for development.

capital costs in the study.

  • Sustaining capital and mobile equipment capital costs for Red Lake and Cochenour have been derived from the 2024 fiscal year budget and life-of-mine plan.

  • The methodology used to estimate operating costs.

  • Allowances made for the content of deleterious elements.

  • Upper Campbell capital estimates were prepared in 2020 for establishing surface and underground services and facilities, mobile equipment and sustaining capital have been determined through first principles and benchmarking to similar operations of similar size and scope. Updates to capital estimates have been included for individual capital projects where available.

  • The source of exchange rates used in the study.

  • Derivation of transportation charges.

  • The basis for forecasting or source of treatment and refining charges, penalties for failure to meet specification, etc.

  • The allowances made for royalties payable, both Government and private.

  • Operating costs for Red Lake and Cochenour have been based on historical site costs, first principle labour and consumable costs and projected cost reduction initiatives. Cost reduction initiatives are based on current plans or projects that are in the implementation phase.

  • Operating costs for the Upper Campbell were prepared in 2020 based on first principles using site labour and consumable costs. Cost reductions are justified by increased effectiveness and lowered indirect costs by way of the portal access and economies of scale for larger capacity mobile equipment.

  • The foreign exchange rate of 0.9 AUD:CAD was used as per guidance from Evolution Corporate Finance.

  • Transportation and refinery treatment charges are based on current agreements.

  • ▪ Cochenour is subject to a 5% net profit and a 1% net smelter return royalty on less than 3% of the reported Ore Reserves. McFinley is subject to a 2% net smelter return and a 1% net smelter return royalty on 80% of the reported Ore Reserves. No additional royalties are payable on tenures that host the remaining current Ore Reserves.

Cochenour is subject to a 5% net profit and a 1% net smelter return royalty on less
than 3% of the reported Ore Reserves. McFinley is subject to a 2% net smelter
return and a 1% net smelter return royalty on 80% of the reported Ore Reserves. No
additional royalties are payable on tenures that host the remaining current Ore
Reserves.
Revenue factors
The derivation of, or assumptions made regarding revenue
factors including head grade, metal or commodity price(s)
exchange rates, transportation and treatment charges,
penalties, net smelter returns, etc.
The derivation of assumptions made of metal or commodity
price(s), for the principal metals, minerals and co-products.


The Ore Reserve estimate for Red Lake, Cochenour, HG Young and McFinley was
designed assuming a gold price of A$1,800/oz and an AUD:CAD exchange rate of
0.9.
The Ore Reserve estimate for Upper Campbell was designed assuming a gold price
of A$1,450/oz and an AUD:CAD exchange rate of 0.9.
Commodity price assumptions and foreign exchange rates are provided by Evolution
Corporate Finance.
Market assessment


The demand, supply and stock situation for the particular
commodity, consumption trends and factors likely to affect
supply and demand into the future.
A customer and competitor analysis along with the
identification of likely market windows for the product.
Price and volume forecasts and the basis for these forecasts.
For industrial minerals the customer specification, testing and
acceptance requirements prior to a supply contract.


Bullion is sold as the spot market price with a small portion of the gold sold at the
hedge price with hedging managed by the Evolution Corporate Treasury Department.
Agreements are in place for the transport and sale of concentrate if required.
Concentrate would be transported by road to Vermillion Bay ON, transferred to rail
for transport to The Port of Vancouver in Vancouver BC and transferred to container
ship.
Transportation and treatment charge/refining charge are based on historical costs.
Revenue would be accrued upon leaving port and payment would be received upon
arrival at the destination port.
Economic The inputs to the economic analysis to produce the net Ore Reserves have been calculated on an incremental cost basis with economic
assessments completed on level-by-level basis. The Ore Reserves were subjected

Evolution Mining Limited

183

==> picture [83 x 59] intentionally omitted <==

Criteria

JORC Code explanation

present value (NPV) in the study, the source and confidence of these economic inputs including estimated inflation, discount rate, etc.

Commentary

to an economic test that includes all applicable costs and is performed via a sensitivity analysis using a range of assumed gold prices from A$1,800 to A$2,650 per ounce and considers a range of financial metrics including AISC, NPV and FCF.

  • NPV ranges and sensitivity to variations in the significant assumptions and inputs.

Social

  • The status of agreements with key stakeholders and matters leading to social licence to operate.

  • The mining operation is situated on the edges of the Red Lake district communities which make them a part of the community landscapes. Given these proximities, operational and environmental considerations are paramount, as are Evolution’s commitments to social, cultural, and community support. RLO currently has representation on various local organizations such as the local municipal planning boards, economic development board, and maintains an open dialogue with the community.

  • RLO has collaboration agreements with two First Nations that are signatory to Treaty No. 3 and have treaty rights which they assert within the operations area of the Red Lake Mines region:

  • The Obishikokaang Collaboration Agreement with Lac Seul First Nation (LSFN) and Evolution.

  • A second Collaboration Agreement with Wabauskang First Nation (WFN) and Evolution.

  • The LSFN is located to the southeast of Red Lake with a band membership of 3,200 and the WFN is located to the south of Red Lake with a band membership of 315.

  • ▪ These agreements provide a framework for strengthened collaboration in the development and operations of Red Lake and outline tangible benefits for the individual First Nations, including skills training and employment, opportunities for business development and contracting, and a framework for issues resolution, regulatory permitting, and Evolution’s future financial contributions.

  • ▪ RLO is not aware of any significant environmental, social or permitting issues that would prevent continued development of the Project deposits under the current mine plan.

Other

  • To the extent relevant, the impact of the following on the project and/or on the estimation and classification of the Ore Reserves:

  • Any identified material naturally occurring risks.

  • The status of material legal agreements and marketing arrangements.

  • The status of governmental agreements and approvals critical to the viability of the project, such as mineral tenement status, and government and statutory approvals. There must be reasonable grounds to expect that all necessary Government approvals will be received within the timeframes anticipated in the Pre-Feasibility or Feasibility study. Highlight and discuss

  • Environmental permits are required by various Federal, Provincial, and municipal agencies, and are in place for the Operation. The Red Lake Operation maintains a list of active environmental permits covering operation of the Campbell, Red Lake, Balmer, Cochenour, and McFinley sites. The Operation also has a certified Closure Plan filed with the Provincial Government that covers all activities outlined in the current mine plan, including the economical extraction of the ore reserves. No new permits are currently required, but existing permit amendments are required from time to time, and in 2023, applications for amendments may be made for tailings management area upgrades (i.e., dam raises), air/noise permit amendments, permit to take water renewals, exploration permitting, and updates to the site closure plan.

Evolution Mining Limited

184

==> picture [83 x 59] intentionally omitted <==

Criteria JORC Code explanation Commentary
the materiality of any unresolved matter that is dependent on a
third party on which extraction of the reserve is contingent.
Classification
The basis for the classification of the Ore Reserves into
varying confidence categories.

Whether the result appropriately reflects the Competent
Person’s view of the deposit.

The proportion of Probable Ore Reserves that have been
derived from Measured Mineral Resources (if any).

The Ore Reserves are derived from Indicated Resources. No Proved Reserves or
Probable Reserves derived from Measured Resources have been reported.

In the opinion of the Competent Person the Ore Reserve classification is appropriate.

The reserve classification was based on the assessment of the metal content by
each Resource category on the stope and development designs. Only Measured or
Indicated Resources are assumed to contribute to revenue, Inferred Resources do
not contribute to the grade or revenue.
Audits or reviews
The results of any audits or reviews of Ore Reserve estimates.

The Ore Reserve design has been audited the Evolution Transformation &
Effectiveness (T&E) team. Competent external consultants have been used to
evaluate Upper Campbell and complete mine design, scheduling, and economic
evaluation.
Discussion of relative
accuracy/ confidence

Where appropriate a statement of the relative accuracy and
confidence level in the Ore Reserve estimate using an
approach or procedure deemed appropriate by the Competent
Person. For example, the application of statistical or
geostatistical procedures to quantify the relative accuracy of
the reserve within stated confidence limits, or, if such an
approach is not deemed appropriate, a qualitative discussion
of the factors which could affect the relative accuracy and
confidence of the estimate.

The statement should specify whether it relates to global or
local estimates, and, if local, state the relevant tonnages,
which should be relevant to technical and economic
evaluation. Documentation should include assumptions made
and the procedures used.

Accuracy and confidence discussions should extend to
specific discussions of any applied Modifying Factors that may
have a material impact on Ore Reserve viability, or for which
there are remaining areas of uncertainty at the current study
stage.

It is recognised that this may not be possible or appropriate in
all circumstances. These statements of relative accuracy and
confidence of the estimate should be compared with
production data, where available.

The accuracy of the Ore Reserve estimate is dependent upon the accuracy of the
Mineral Resource model and the long-term cost and revenue assumptions.
Modifying factors have been developed from current mine performance data. In the
opinion of the Competent Person the long-term assumptions and modifying factors
are reasonable.

The design and Ore Reserve estimate for Upper Campbell was based on the 2020
geological model. The design was not updated in 2023 as updates to the geological
interpretation are in progress.

On an ongoing basis the Ore Reserves are reconciled against actual performance.
Results to date in areas that have been well drilled and are well understood
geologically highlight good performance and that the reported Ore Reserve is
achievable in practice and that the applied modifying factors are appropriate.
Reconciliation results in areas of limited drilling and in areas of complex geology
have been somewhat varied and highlight the requirement of ore control activities for
local demarcation of ore and waste.

Ongoing drilling targeting Inferred and Indicated Mineral Resource regions is
occurring with the aim of converting reported Mineral Resources to Ore Reserves. Of
particular focus this year are the Upper Campbell and Upper Red Lake regions given
their proximity to the planned CYD Decline. A significant program of drilling, re-
interpretation and estimation is currently underway. This program of work will be
followed by a ‘Hill of Value’ study which will optimise the mine plan and applied cut-
off grades to maximise value from the operation. Results of this study are expected
late 2024 with an updated Mineral Resource and Ore Reserve for these regions
scheduled to bereported as of31 December,2024.

Evolution Mining Limited

185