EVOLUTION MINING LIMITED — Investor Presentation 2005
Apr 10, 2005
64885_rns_2005-04-10_7a1403af-995e-4ec4-82d8-b26569a3e96d.pdf
Investor Presentation
Open in viewerOpens in your device viewer

WESTONIA MINES LIMITED
THE NEW INITIATIVE BY DAVID HATCH APRIL 2005
Recent History
Project not yet developed due to:
- Substantial increase in open pit contract mining costs
- Significant increase in plant construction costs
Strong AUD
Confidence issues surrounding apparently low grade resource
What's Different About Westonia?
$\mathcal{N}$
Size of resource
Regional tenement position and prospectivity

Westonia Geological Resource Comparison
| July 2004 | ||||||||
|---|---|---|---|---|---|---|---|---|
| Indicated | Inferred | Total | ||||||
| 0.7 g/t Cut-off | ||||||||
| Tonnes (MT) | 23.10 | 7.29 | 30.39 | |||||
| Grade (g/t) | 1.41 | 1.35 | 1.39 | |||||
| Total (kozs) | 1046 | 315 | 1361 | |||||
| 1.0 g/r Cut-off | ||||||||
| Tonnes (MT) | 14.30 | 3,96 | 18.26 | |||||
| Grade (g/t) | 1.76 | 1.77 | 4.76 | |||||
| Total (kozs) | 808 | 226 | 4084 |
$\mathbf{M}$
Westonia Gold Project
Mineral Resource (July 2004) 0.7 g/t Cut-Off

Westonia Gold Project
Mineral Resource (July 2004) 0.7 g/t Cut-Off

Long Section


Yilgarn Block
Dewater Westonia Pit
Scope of Site Work Includes
- Rehabilitation of existing evaporation ponds and construction of new/temporary pond
- Acquisition and installation of a +2.5km pipeline
- Re-establish pit access
- Acquisition and installation of pumps Supervision and monitoring
- Pumping rate of 15ML/day (11ML/day gain)
Grade Control Drill Programme
- Estimated 10,000m RC programme along pit floor
- Leachwell assaying technique
- 8m x 5m pattern, vertical holes to 25m deep
Validate contained metal per vertical increment from 70m to 100m depth and calibrate the resource model
Resource Drilling
- Infill drill gaps between 100m and 200m in expectation of adding resource ounces
- Infill drill to convert inferred mineralisation to indicated category between 100m and 200m
- Further drill test beyond 200m to increase level of confidence in resource at depth
Timeline

| Task Name | Duration | $Jun-05$ | $Jul-05$ | Aug-05 | Sep-05 | Oct-05 | Nov-05 | Dec-05 | $Jan-06$ | $Feb-06$ | Mar-06 | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Dewatering | 4 months | |||||||||||
| Grade Control | 3 months | |||||||||||
| Resource Drilling | 3 months | |||||||||||
| New Resource Model | 1 month | |||||||||||
| Optimise, Re-design & Re-schedule | Santa de Salvador (1980). Nacional de Salvador (1980). Ŵ. 2 months |
KO 77. | S. | |||||||||
| New Feasibility Study | 3 months |
Cost Summary
- Dewatering
- Drilling
- Feasibility, Other
- Contingency
- Exploration
AUD 2.1M AUD 1.7M AUD 0.7M AUD 0.5M AUD 0.5M
Total AUD 5.5M
Objectives
- Establish robust economic base case open pit mine and promote Company's progress
- Aim for commissioning early 2007
- Soon after demonstrating viability and cash earning potential of open pit, recommence development and resource drilling to test underground potential
- Systematic regional exploration Structured growth based on Westonia Greenstone Belt to value-add and create shareholder wealth
More from EVOLUTION MINING LIMITED
Investor Presentation
2026
May 4
Regulatory Filings
2026
Apr 30
Capital/Financing Update
2026
Apr 14
Interim / Quarterly Report
2026
Apr 14
Share Issue/Capital Change
2026
Apr 6
Share Issue/Capital Change
2026
Apr 1
Regulatory Filings
2026
Apr 1
Major Shareholding Notification
2026
Mar 24
Regulatory Filings
2026
Mar 19
Notice of Dividend Amount
2026
Mar 11