Energix Renewable Energies Ltd.

Legal Proceedings Report Aug 4, 2025

6776_rns_2025-08-04_f7641b1c-6ab2-4315-b9af-5965a7299603.pdf

Legal Proceedings Report

Open in Viewer

Opens in native device viewer

This is an unofficial AI generated translation of the official Hebrew version and has no binding force. The only binding version is the official Hebrew version. For more information, please review the legal disclaimer.

ENERGIX-RENEWABLE ENERGIES LTD ("the Company")

Ramat-Gan, August 4, 2025

To:

Israel Securities Authority Via MAGNA

Tel Aviv Stock Exchange Ltd. Via MAYA

www.isa.gov.il www.tase.co.il

Subject: Receipt of Grid Connection Approvals in Poland with a Total Capacity of Approximately 1GW

Further to the Company's reports in its financial statements ¹⁰¹, regarding the Company's activities (through wholly owned subsidiaries in Poland) to obtain grid connection approvals, which are critical for the development and advancement of the Company's project pipeline in initiation, the Company is pleased to update that on July 31, 2025, grid connection approvals were received for the development and connection to the grid of new Company projects in Poland with a capacity of 840MW, and together with previous connection approvals received by the Company in July 2025, approximately 1GW ("New Connection Approvals").

Accordingly, as of the reporting date, the Company has grid connection approvals for initiated projects in Poland, for the years 2026-2031, with a total capacity of approximately 1.35GW - of which about 880MW for wind facilities, about 230MWp for photovoltaic facilities, and about 240MW for storage facilities. In addition, the Company has submitted further applications for grid connection approvals for projects with a capacity of over 2GW, which have not yet received a response from the Polish grid operator.

It should be noted that grid connection approvals currently constitute the main bottleneck and obstacle to the advancement of new electricity generation projects in Poland, and their receipt significantly reduces the entrepreneurial risk associated with projects in various stages of development as well as future projects the Company may acquire.

This is an unofficial AI generated translation of the official Hebrew version and has no binding force. The only binding version is the official Hebrew version. For more information, please review the legal disclaimer.

For more details regarding the Company's activities in Poland, see section 4.1 of the Board of Directors' report to the Company's financial statements for the first quarter of 2025, published on May 12, 2025, reference number 2025-01-032972, and section 7 of chapter A of the Company's annual report for 2024 dated March 3, 2025 (reference 2025-01-014025), as amended on March 9, 2025 (reference: 2025-01-015516).

It is clarified that the above information regarding project development, their total scope, their actual establishment, and their connection to the grid (including the timing of their connection) are future events not under the Company's control, and at this stage there is no certainty that they can be completed, including as described above. This information constitutes forward-looking information according to section 32A of the Securities Law, 1968, based on the Company's business plans and assessments as of this date, whose realization is uncertain and not under the Company's control. Such information may not materialize, in whole or in part, both in relation to the Company's forecasts and in relation to the working assumptions, inter alia due to decisions of regulatory bodies in Poland, obtaining the necessary approvals for the projects, market conditions, and risk factors characterizing the Company's activities as detailed in section 32 of chapter A of the annual report.

Respectfully,

ENERGIX-RENEWABLE ENERGIES LTD

By: Mr. Asa Levinger, CEO Dafna Reznik, Legal VP

ENERGIX-RENEWABLE ENERGIES LTD / Atrium Tower, 2 Jabotinsky St., Ramat-Gan 5250501 / Tel: 073-3739224 / www.energix-group.com / [email protected]

FOOTNOTE:

¹⁰¹ See section 3.2 of the Board of Directors' report, chapter B of the Company's annual report for 2024, as amended on March 9, 2025 (reference: 2025-01-015516).