EMPIRE OIL & GAS NL

ACN 55 063 613 730 SUITES 7 & 8 154 HAMPDEN ROAD NEDLANDS 6009 WESTERN AUSTRALIA TELEPHONE 61 8 6389 2687 FACSIMILE 61 8 9386 6812 EMAIL [email protected] WEBSITE www.empireoil.com.au\

24 September 2007

ASX Limited Company Announcements Office Level 4 20 Bridge Street SYDNEY NSW 2000

Dear Sirs

RE: EP 104/R1 CANNING BASIN, WESTERN AUSTRALIA – UPDATE ON THE VALENTINE-1 WELL

Please find details of the progress of the drilling of the Valentine-1 exploration well, Canning Basin, Western Australia as of 0600 hours 24 September 2007.

Drilling operations at Valentine-1 have re-commenced and as at 0700 hours operations were drilling ahead at 3382 metres after repairing the drilling rig’s top drive unit.

Top drive breakdown occurred on 22 September 2007 after drilling from 3241 metres on 20 September 2007 to 3377 metres on 22 September 2007.

Electric wireline logs are to be run in the well bore at total depth and will evaluate the sections drilled where minor mud gas shows were observed.

The objective porous sandstones of the Virgin Hills Formation have not been intersected in the well to date.

Regards

==> picture [142 x 45] intentionally omitted <==

J L CRAIG MARSHALL BSc (Hons), F. Aus. IMM, CPGeo Managing Director Empire Oil & Gas NL Suite 7, 154 Hampden Road, Nedlands WA 6009 Telephone: 61 8 6389 2687 Facsimile: 61 8 9386 6812 Email: [email protected]

VALENTINE-1 DRILLING REPORT CANNING BASIN, WESTERN AUSTRALIA

Date: 24 September 2007 24 September 2007
Permit: R1
Well Location: Lat : 17o08’ 23.46”S
Long: 123o42’ 32.40”E
Directional offset to target: 0 metres
Elevation: Ground Level is 12.4mAMSL
RotaryTable is 18.1mAMSL
Prognosed Depths
(measured KB):
Top primary objective Total depth
3,222 metres 3,407 metres
Prognosed drilling time: 25 days
Spud Date: 1230 hrs,WST 12 August 2007
Present Depth at 0600 hrs: 3,377mMD
Time of Reporting: 0600 hrs,WST 24 September 2007
Operations Since Last
Report:
Directionally drilled from 3241m as of 20/9/07 to 3,377m on
22/9/07 when drilling stopped due to a break-down of the top
drive hydraulic unit on 22/9/07
Current Operations: At 0600 hrs this morning 24/9/07, repairs were almost
complete and by 0700hrs the well was drilling ahead at
3382m MD.
Hydrocarbon indications: None
Comment: Lithologies are predominantly tight dolomites and minor
dolomitic sandstones and claystones of Devonian age with
minor mud gas shows observed. The primary reservoir
objective porous sandstones of the Virgin Hills Formation
have not been intersected in the well to date.
Participants in the well
(post earning):
Empire Oil and Gas NL - 14.8%
ARC Energy Limited - 38.95% (Operator)
Emerald Oil & Gas NL - 12.75%
Pancontinental Oil & Gas NL - 10.0%
Phoenix Resources PLC - 10.0%
First Australian Resources Limited - 8.0%
Indigo Oil PtyLtd - 5.5%