ASX RELEASE

Release Date: 4 October 2007 To: Australian Stock Exchange Ltd No of Pages: 4 From: Eric Streitberg Re: Valentine-1 Update and Spudding of Stokes Bay-1

Please find attached an update on the Valentine-1 and Stokes Bay-1 exploration wells.

The Stokes Bay-1 well is planned as a test of the extent and reservoir development of the gas accumulation intersected by the Point Torment-1 well and will be drilled as a deviated well with a total depth of approximately 2,500 metres. Point Torment-1 was drilled in 1992 and subsequently flowed gas at a rate of up to 4.3 million cubic feet of gas per day from the Carboniferous aged Anderson Formation sandstones. Subsequent tests of these sands produced ambiguous information on potential volumes and reservoir quality and the Stokes Bay-1 well is designed to provide a definitive test of the reservoir quality and extent of the accumulation.

The Valentine-1 well intersected very strong gas shows and indications of porosity in the Anderson and Laurel Formations downdip from the target interval in the Stokes Bay-1 well. This is a very positive indication for Stokes Bay-1 which is targeted to intersect these objectives within closure, some 90 meters updip from the Valentine-1 intersection.

For inquiries please contact:

Eric Streitberg, Managing Director Telephone +61 8 9480 1300 Freecall 1800 337 330 Email [email protected]

About ARC Energy Limited

ARC Energy is one of Australia's pre-eminent energy companies, owning and operating oil and gas interests in the Perth, Canning and Bass basins, and internationally. Listed on the Australian Stock Exchange with a market capitalisation of approximately A\$450 million, ARC has an aggressive onshore and offshore exploration and development drilling program. It continues to drive increased shareholder value by the early adoption of innovative technical and commercial practices.

STOKES BAY-1 DRILLING REPORT CANNING BASIN, WESTERN AUSTRALIA

Date: 4th October 2007
Permit: R1
Well Location: 17o
Lat :
08' 23.46"S
123o
Long :
42' 32.40"E
Directional offset to target: 1024 metres
Elevation: Ground Level is 12.4mAMSL
Rotary Table is 18.1mAMSL
Proposed Total Depth
(measured KB):
2505 metres
Prognosed drilling time: 15 days
Spud Date: 0930 hrs, WST 3 October 2007
Present Depth at 0600 hrs: 1226 mMD
Time of Reporting: 0600 hrs, WST 4th October 2007
Operations Since Last
Report:
Electric wireline logging operations on Valentine-1 was
completed at 23:30 hrs on 28th September. Cement plugs
were set to abandon the Valentine-1 borehole and enable a
sidetrack of the well to the Stokes Bay-01 target location.
The rig was released from Valentine-1 at 18:00 hrs on 30th
September. A kick off cement plug was then set with top at
906mMD
at
the
base
of
the
Noonkanbah
Formation.
Valentine-1 was sidetracked as Stokes Bay-1 at 0930 hrs on
3 October from 975mMD.
Current Operations: Drilling ahead in 8 ½" hole at 1226mMD
Hydrocarbon indications: None
Comment:
Participants in the well
(post earning):
Empire Oil and Gas NL - 14.8%
ARC Energy Limited - 38.95% (Operator)
Emerald Oil & Gas NL - 12.75%
Pancontinental Oil & Gas NL - 10.0%
Phoenix Resources PLC - 10.0%
First Australian Resources Limited - 8.0%
Indigo Oil Pty Ltd - 5.5%