ASX RELEASE
Release Date: 1 November 2007 To: Australian Stock Exchange Ltd No of Pages: 4 From: Eric Streitberg Re: Stokes Bay-1 Update
Please find attached an update on the Stokes Bay-1 well.
The attached release will also be available on the Company’s website at; www.arcenergy.com.au.
For inquiries please contact:
Eric Streitberg, Managing Director Telephone +61 8 9480 1300 Freecall 1800 337 330 Email [email protected]
About ARC Energy Limited ARC Energy is one of Australia’s pre-eminent energy companies, owning and operating oil and gas interests in the Perth, Canning and Bass basins, and internationally. Listed on the Australian Stock Exchange with a market capitalisation of approximately A$500 million, ARC has an aggressive onshore and offshore exploration and development drilling program. It continues to drive increased shareholder value by the early adoption of innovative technical and commercial practices.
Page 1
Level 4, 679 Murray Street, West Perth, Perth Western Australia 6005 Freecall: 1800 337 330 Tel: 61 8 9480 1300 Fax: 61 8 9480 1388 Website: www.arcenergy.com.au, Email: [email protected], ASX Code: ARQ
STOKES BAY-1 DRILLING REPORT CANNING BASIN, WESTERN AUSTRALIA
| Date: | 1stNovember 2007 |
|---|---|
| Permit: | R1 |
| Well Location: | Lat : 17o08’ 23.46”S Long : 123o42’ 32.40”E |
| Directional offset to target: | 1024 metres |
| Elevation: | Ground Level is 12.4mAMSL Rotary Table is 18.1mAMSL |
| Proposed Total Depth (measured KB): |
2800 metres |
| Prognosed drilling time: | 15 days |
| Spud Date: | 0930 hrs, WST 3rdOctober 2007 |
| Present Depth at 0600 hrs: | 2777m MD |
| Time of Reporting: | 0600 hrs, WST 1stNovember 2007 |
| Operations Since Last Report: |
Since last report on Thursday, October 25th, 178 mm (7 inch) casing has been run to a depth of 2585m measured depth (MD), and the well deepened a further 22 m from the previous 2755 m to 2777 m MD. In drilling the additional 22 m, further losses of mud at a rate of approximately 250 bbl/hr were experienced. This resulted in no fluid or cuttings returns to surface. In drilling the 22 m of additional hole, several metre-scale intervals of very high penetration rates were encountered, these being interpreted to be due to additional large scale vuggy porosity. Since reaching a total depth of 2777 m MD, efforts have focussed on curing the ongoing fluid losses in the Nullara Fm. This has resulted in intermittent establishment of circulation, and returns to surface with associated intermittent mud gas peaks of up to 10%. In view of the persistent ongoing losses that are now under control, and the accumulating evidence of gas presence in the Nullara, the Operator has recommended to the JV to complete the well (rather than the previously proposed open hole DST) in order to test this interval. The current plan is to complete the well during the next two days, and commence testing operations. |
Page 2
| As previously reported, all JV partners are participating in the shallow part of Stokes Bay-1 (above 2589 m MD). However, less than all parties have participated in the well below 2589 m MD such that equity levels in this part of the Stokes Bay-1 well (below 2589m MD) are: • ARC Energy Limited 69.25% (Operator) • Emerald Oil & Gas NL 12.75% • Pancontinental Oil & Gas NL 10.00% • First Australian Resources Limited 8.00% Under the Joint Venture Operating Agreement, the non- participating parties in the deeper part of the well (Empire, Phoenix and Indigo) retain a future right to earn back into their respective participating interests by the payment of penalties out of future production. |
|
|---|---|
| Current Operations: | POOH to run Completion |
| Hydrocarbon indications: | Mud gas readings of up to 10% have been recorded at surface from intermittent circulation during attempts to cure lost circulation |
| Comment: | The loss of mud to the Nullara Fm has continued to create operational difficulties that have delayed testing the interval. However, we remain very encouraged by the presence of both porosity and significant permeability in the Nullara limestone section, and the more recent intermittent gas shows when mud circulation is established are also viewed positively. The planned test of the Nullara Fm will determine fluid content and potential flow characteristics of the reservoir. The Stokes Bay-1 intersection of the Nullara Fm is 80m up dip of the Pt Torment-1 intersection which did not have the vugular porosity developed, but nevertheless tested gas at low rates. |
| Participants in the Permit (post earning): |
ARC Energy Limited 38.95% (Operator) Empire Oil and Gas NL 14.80% Emerald Oil & Gas NL 12.75% Pancontinental Oil & Gas NL 10.00% Phoenix Resources PLC 10.00% First Australian Resources Limited 8.00% Indigo Oil Pty Ltd 5.50% |
Page 3
- Canning Basin Stokes Bay 1
General Well Data
Spud Date: 09:30hrs 3[rd] October 2007 KO from 975mMD
DATE : 01 Nov 2007
Planned TD : 2500mMD / 2130m TVDSS
Drill Floor Elevation : 18.1m amsl
Actual TD : 2777mMD / 2323m TVDSS
==> picture [504 x 514] intentionally omitted <==
----- Start of picture text -----
Canning Basin Stokes Bay-01
(Exploration Well from KO) Predicted Progress Stokes Bay 1
Actual Progress Stokes Bay 1
Blina
Liveringa
0 Noonkanbah
Poole
Carolyn
Winifred
200 Betty FmAnderson Fm
Rig 18 released from Valentine-1 at 18:00hrs Fairfiled Gp
Clanmeyer
30th September 2007 for Stokes Bay - 1 Virgin Hills
400 Predicted Progress Valentine 1
600
9 5/8" @808mMD
in Valentine 1
800
KO Stokes Bay-1 ftom 975mMD at 09:30hrs 03/10/07
1000
1200 4/10/07 Drilling 8 1/2" at 1226m
1400 5/10/07 Drilling 8 1/2" at 1439m
5/10/07 Drilling 8 1/2" at 1439m
1600 6/10/07 Drilling 8 1/2" at 1652m
7/10/07 Drilling 8 1/2" at 1819m
1800 8/10/07 Drilling 8 1/2" at 1840m Stuck pipe @ 858 while POOH for bit change
9/10/07 Work stuck pipe. 10/10/07 POOH w/Fish 11/10/07 RIH w/new BHA to drill
12/10/07 POOH @ 1913m after total MWD failure
2000
13/10/07 Drilling 8 1/2" at 2013m
2200
14/10/07 Drilling 8 1/2" at 2255m
2400
15/10/07 Drilling 8 1/2" at 2485m .
2600 16/10/07 Drilling 8 1/2" at 2606m
17-30/10/07 control Lost Circ, run Logs , Run & Cmt 7” csg,
2800 .
29/10-01/11/07 drill shoe track,
. Set X-Link Plugs & control losses,
prepare completion assembly.
3000
0 5 10 15 20 25 30 35 40
Days
Depth (Measured below Rotary Table in metres)
----- End of picture text -----