Earnings Release • Jul 25, 2025
Earnings Release
Open in ViewerOpens in native device viewer

PRESS RELEASE | Brussels, 25 July 2025, 7:00 am – Elia Group (Euronext: ELI)
Dear analysts, investors, partners, colleagues, and wider stakeholders,
As we close the first half of 2025, we at Elia Group would like to share an update with you about recent key developments that have occurred across the organisation.
Over the past few months, we have further strengthened the Group's leadership team to support the delivery of our ambitious investment programme. On 15 January, Bernard Gustin took on the role of Elia Group's Chief Executive Officer. This appointment was accompanied by the successful integration of strong new profiles into our Board of Directors and executive management team. Marco Nix was appointed as the Group's Chief Financial Officer, while Nicolas Pire and Christine Janssen were appointed as the local CFOs of Elia Transmission Belgium and 50Hertz respectively. These appointments will ensure that our financial leadership remains solid and anchored in each of our home countries, enabling the Group to confidently steer record-level investments into its activities.
1 Net profit Elia Group share refers to the net profit attributable to owners of ordinary shares.

In both of our core markets, we have made critical progress on infrastructure projects that are preparing our system for the future.
In Belgium, the construction of the Princess Elisabeth Island — a cornerstone for the development of offshore wind — is progressing steadily. The first steel cut for the high-voltage alternating current (HVAC) infrastructure marked the start of its technical deployments in June, while the installation of the island's caissons at sea is underway. Although significant progress was made, it is possible that the construction of the island may not be completed by end of June 2026, as required under the Recovery and Resilience Facility (RRF). In the revised RRF File submitted by Belgium to the EU the subsidy request from the authorities has hence been reduced to a pro-rata of what can be realized by 30th of June 2026.
In June, Elia Transmission Belgium (ETB) acknowledged the Belgian government's decision to optimise the next phase of the project. The ambition remains unchanged: to maximise wind generation in Belgium's second offshore wind zone and build a second interconnector that will link the country to the United Kingdom. These updates are a response to steep global increases in the cost of high-voltage direct current (HVDC) technology and associated services.
Good progress has also been made on the Ventilus project: key permitting steps and multiple discussions with different stakeholder groups have been completed to date. Along with the Boucle du Hainaut, the project will form the backbone of Belgium's future grid, enabling the integration of offshore wind energy into the system while safeguarding the country's security of supply. At the same time, ETB is implementing a multi-year upgrade of its 380 kV grid with stronger conductors to accommodate higher electricity flows; this includes the final phase of BRABO III: a project which is aimed at reinforcing the grid in and around the Port of Antwerp.
Another milestone celebrated by ETB was the publication of Belgium's Adequacy and Flexibility Study (2026-2036). This confirms that the spread of electrification should significantly increase the level of demand from 2028 onwards, pushing it beyond current levels of available capacity. While the capacity remuneration mechanism (CRM) will remain a key lever for helping to address this, additional measures could be mobilised to complement the capacity developed through it.
A major challenge will be to unlock new forms of flexibility – both on the consumption and generation sides – within a system that is increasingly powered by variable renewable energy sources. Delivering the right market frameworks and incentives will require close cooperation with policymakers, regulators and market participants alike.
In Germany, 50Hertz has made steady progress on its major onshore and offshore infrastructure expansion projects. The SuedOstLink project, which will become one of the country's key onshore DC corridors, is advancing well. The link will play a vital role in transporting renewable electricity from the north to south of the country. Moreover, developments in the German North and Baltic Seas, including 50Hertz's involvement in the Bornholm Energy Island

project and new offshore connection points, will form the essential building blocks of a more resilient and meshed grid which is capable of integrating massive amounts of renewable energy into the system.
Progress on the offshore connection projects Ostwind 3 and 4 remains steady. The Ostwind 3 cable has now been fully laid, marking a key milestone in the project. Additionally, the jacket for the offshore substation (OSS) has been completed at the yard, preparing the way for the next phase of installation. These achievements underscore the ongoing momentum in delivering critical offshore infrastructure.
50Hertz recently successfully completed the tunnel drilling for the Berlin diagonal power link, a new underground 380 kV connection that will boost transmission capacity by around 40% to meet the city's growing energy needs. Over the past two and a half years, the tunnel boring machine has created a 7 km tunnel. The project forms part of a broader programme to modernise and expand Berlin's high-voltage grid.
Our work also extends beyond national borders.
Our unique connection to both the North Sea and the Baltic Sea is not just a technical advantage — it's a strategic gateway to a more integrated, affordable and sustainable European energy system. Our access to two seas places us at the centre of Europe's harnessing of offshore energy: we are supporting the development of a meshed offshore grid and enabling cross-border electricity flows.
By championing and driving forward a coordinated approach to offshore planning, we are helping to accelerate the energy transition while ensuring that its benefits are shared fairly across society. We at the Group and the other founding partners of the Offshore Transmission Cooperation (OTC) published a joint paper aimed at accelerating a coordinated approach to the planning of offshore grid infrastructure. We are working closely with governments and peers to help build the offshore backbone that Europe urgently needs to establish an independent, affordable and decarbonised energy system. These efforts will feed into the third North Sea Summit which will be held in Hamburg in early 2026, during which we will aim to make a tangible contribution to Europe's shared energy goals.
The Iberian blackout in April, which left millions in Spain and Portugal without power, served as a stark reminder of how vulnerable interconnected, renewable-heavy grids can be if frequency and voltage control are not sufficiently robust. The blackout highlighted the importance of our continued investments in dynamic system services and modern grid control architecture.
We are also continuing to address the areas of physical and cyber security with unwavering focus. During the first half of the year, we made progress on our security strategy, working closely with national and European authorities to protect critical energy infrastructure. We also strengthened our partnerships with the police, civil protection units and international partners such as NATO to safeguard our physical assets. Security — of whichever kind — is, and will remain, a non-negotiable priority for our Group.

None of this progress would be possible without the dedication and expertise of our staff. Attracting, developing and retaining talent is essential in these times of high demand for scarce technical skills. During the first half of 2025, we continued to expand our workforce by successfully recruiting 421 new employees. Our commitment to talent was also reflected in key initiatives such as the ETB Leadership Day, which brought 800 or so members of its staff together, and in our strong collaboration with the 50Hertz work council - reinforcing our shared focus on employee engagement and co-creation. This is why we will continue to invest in our staff, their safety and their development.
Amidst a context of rising material costs, volatile supply chains and increasingly complex permitting procedures, securing the necessary resources and partnerships is more important for us than ever. Our successful capital increase earlier this year was a critical step towards safeguarding our financial resilience and guaranteeing that we can keep investing in our grid and projects at the pace society requires. Our solid funding plan, combined with our strong relationships with our reference shareholder, high-quality investors, suppliers and business partners, will allow us to stay ahead.
Looking to the second half of 2025, our key priority will be to strike the right balance between staying committed to our vision and objectives while remaining attentive to stakeholder expectations. As we implement our investment programme, maintaining a sharp focus on cost efficiency will be crucial.
Given the high costs of the energy transition, some major projects across Europe have already experienced delays. It is vital to avoid a stop-and-go dynamic and instead aim for a steady, manageable pace of growth. This more measured pace, beyond 2030 targets, may allow for a better alignment between industrial capacity, regulatory timelines and investment flows. Rather than pushing forward at full speed in all areas of our business, we must carefully evaluate our priorities to ensure we make sustainable progress.
We set the course for sustainable growth during the first six months of 2025 – and much work lies ahead. To all of our staff: thank you for your tireless efforts and your dedication to the Group. To our shareholders, partners, and regulators: thank you for your continued trust and support.


Our ActNow programme embeds sustainability into our strategy and business activities through concrete and measurable targets for the Group to reach.
Dimension 1: Climate action In line with our ActNow roadmap, we have developed and adopted a Scope 3 emissions intensity reduction target and have begun the process of seeking validation from the Science Based Targets initiative (SBTi) for this by signing an official commitment with SBTi. 50Hertz is advancing on the certification of its energy management system under ISO 50001, demonstrating its focus on energy efficiency across our operational sites. To maximise synergies, this certification will be fully integrated into our existing environment and health and safety management systems at Group level.
Since 2018, ETB has championed sustainability by repurposing IT equipment, reducing its carbon emissions and promoting a circular economy approach to its operations. Last year, ETB donated 2,500 pieces of IT equipment to 60 organisations, mainly schools. To address food waste, the new kitchen at our Belgian headquarters now uses a high-performance composter that transforms kitchen scraps into compost using enzymes, so reducing food waste by 90% and eliminating the need for water, with just 20 kg of waste produced each week.
Dimension 3: Health & safety
Our Global Prevention Plan 2025–2030 puts the health and safety of our staff and contractors first; in line with our ActNow programme, it focuses on physical safety, wellbeing, compliance and leadership. Our 2025 Safety & Health Week featured the 'Go for Zer0' campaign on road safety. Semi-annual quick checks in Belgium and Germany are being used to gather feedback to improve our working environments. 50Hertz offers psychological first aid to encourage staff wellbeing, while the 4TSO brochure supports a shared safety culture and high standards amongst Germany's TSOs.
Dimension 4: Diversity, equity & inclusion (DEI)
.
Through our ActNow programme, we're making diversity, equity and inclusion (DEI) part of our everyday work. Our DEI campaign in May encouraged staff to increase their focus on DEI, whilst our Diversity Day featured open discussions about allyship and creating an inclusive culture across the Group. Our DEI intranet page provides staff with interactive training sessions and resources for building inclusive skills.

Moreover, this year, 50Hertz participated in 'Girls' Day' by inspiring young girls to take an interest in the energy sector, and Elia engaged children in the 'Da's Geniaal' initiative, which is aimed at sparking young people's interest in science, technology, engineering and mathematics (STEM) and in wider careers in the energy sector.
Dimension 5: Governance, ethics & compliance
In May, our corporate governance structure was reinforced during our Ordinary General Meeting, as three new directors were appointed to our Board of Directors (two of these appointments related to new independent directors, whilst one independent director was reappointed). Michel Sirat and Olivier Chapelle were appointed as new independent board members, each for four-year terms. They have both brought valuable expertise with them which will support the establishment of a reliable, sustainable and innovative energy system. Saskia Van Uffelen was appointed as a director for a one-year term, while Pascale Van Damme was reappointed as an independent director for a four-year term.
50Hertz met the requirements of the German Supply Chain Act, with its first report submitted to the German Federal Office for Economic Affairs and Export Control in April. This key step marked the Group's support for stronger human rights and environmental standards and will involve annual risk analyses of its operations and suppliers from this autumn onwards. ETB also reinforced its position as a leader in the Belgian energy sector during the Municipalia Exhibition in April by building partnerships with local authorities. Additionally, ETB's discussions with Revolht, a residents' association, which were initiated by Minister François Desquesnes – the Vice-President and Walloon Minister for Spatial Planning, Business Parks, Public Works, Mobility, Road Safety and Local Authorities – are aimed at ensuring that different stakeholders are aligned on the technology, timelines and costs for the Boucle du Hainaut project.

| Key figures (in € million) | 1H 2025 | 1H 2024 | Difference (%) |
|---|---|---|---|
| Revenue, other income and net income (expense) from settlement mechanism |
2,093.0 | 1,914.3 | 9.3% |
| Equity accounted investees | 15.8 | 23.5 | (32.8%) |
| EBITDA* | 903.3 | 678.9 | 33.0% |
| EBIT | 569.7 | 385.8 | 47.6% |
| Adjusted items | 0.0 | 0.0 | n.r. |
| Adjusted EBIT | 569.7 | 385.8 | 47.6% |
| Net finance costs | (109.2) | (80.5) | 35.6% |
| Adjusted net profit | 325.6 | 218.8 | 48.8% |
| Net profit | 325.6 | 218.8 | 48.8% |
| Non-controlling interests | 41.5 | 22.6 | 83.6% |
| Net profit attributable to the group | 284.1 | 196.2 | 44.8% |
| Hybrid securities | 14.5 | 14.5 | (0.3%) |
| Net profit attributable to owners of ordinary shares | 269.6 | 181.6 | 48.4% |
| Key figures of the financial position (in € million) | 1H 2025 | 2024 | Difference (%) |
| Total assets | 28,870.5 | 24,927.6 | 15.8% |
| Equity attributable to owners of the company | 7,825.2 | 5,556.2 | 40.8% |
| Net financial debt | 11,244.7 | 12,798.2 | (12.1%) |
| Net financial debt, excl. EEG and similar mechanisms | 11,636.8 | 13,158.7 | (11.6%) |
| Key figures per share | 1H 2025 | 1H 2024 | Difference (%) |
| Earnings per share (in €) (Elia share)** | 2.90 | 2.35 | 23.3% |
| Equity attributable to owners of the company per share (in €) | 67.2 | 64.4 | 4.3% |
* Changes in provisions are now included in EBITDA, with 1H 2024 restated accordingly
** Earnings per share (in €) (Elia share) includes the bonus adjustment related to the 2025 rights issue (bonus factor of 0.95)
See the glossary for definitions
See Section 4 for information on adjusted items
Comparative figures for Total assets, Total equity, Net financial debt, Net financial debt excl. EEG and other mechanisms as at 31/12/2024
Pursuant to IFRS 8, the Group identified the following operating segments:

Rounding – In general, all figures are rounded. Variances are calculated from the source data before rounding, meaning that some variances may not add up.
Elia Group's (adjusted) net profit saw a strong increase of 48.8% to €325.6 million. Elia Transmission (Belgium) achieved solid results supported by a growing regulatory asset base, increased equity after the capital increase and a higher return on equity. 50Hertz Transmission (Germany) delivered strong performance driven by higher investment remuneration from asset growth while a growing portion of the asset base benefits from the higher floating rate applied since 2024. This was partly offset by lower performance in the non-regulated segment and Nemo Link, due to higher holding costs and reaching the cumulative cap limited Nemo Link's net contribution, despite strong operational performance.
After deducting the €41.5 million in non-controlling interest and €14.5 million attributable to hybrid securities holders the net profit of Elia Group attributable to the owners of ordinary shares, increased to €269.6 million.
In the first half of the year, Elia Group invested €1,488.6 million to strengthen both the Belgian and German grids, advance offshore projects, and enhancing infrastructure digitisation. By the end of June 2025, Elia Group's total net financial debt, excl. EEG and similar mechanisms, was €11,636.8 million (-€1,521.9 million). This reduction was mainly driven by the proceeds from April's capital increase (€2.2 billion), while a major part of the investment programme in Belgium and Germany was financed from operating cash flow.
In the first half of the year, Elia Group maintained a strong liquidity position, primarily supported by the €2.2 billion capital increase. During the same period, Eurogrid raised €2.0 billion through loans and bond issuances and successfully redeemed a €500 million bond upon maturity. As of the end of June, €11.9 billion remained available across cash management accounts,undrawn credit facilities and commercial paper programmes, underscoring the Group's robust financial flexibility. Elia Group's average cost of debt increased slightly to 2.9% (+10 bps). Standard & Poor's maintained Elia Group's BBB credit rating with a stable outlook.
Equity attributable to owners of the company increased by €2,268.9 million to €7,825.2 million (+40.8%). This increase was mainly due to the net proceeds of the rights issue of €2,179.5 million, the profit attributable to the owners of the company (+€284.1 million) and the valuation of treasury shares following the liquidity agreement (+€1.3 million). These effects were partly offset by the 2024 dividend distribution (-€150.7 million), the costs linked to the hybrid bonds (-€29.3 million), the decrease in hedge reserves (-€13.0 million) and the revaluation of post-employment benefit obligations (-€6.1 million).

| Elia Transmission key figures (in € million) | 1H 2025 | 1H 2024 | Difference (%) |
|---|---|---|---|
| Revenue, other income and net income (expense) from settlement mechanism |
763.0 | 779.3 | (2.1%) |
| Revenues | 802.1 | 610.1 | 31.5% |
| Other income | 61.9 | 80.6 | (23.2%) |
| Net income (expense) from settlement mechanism |
(101.0) | 88.6 | (213.9%) |
| Equity accounted investees | 1.8 | 1.5 | 20.8% |
| EBITDA* | 333.2 | 282.8 | 17.8% |
| EBIT | 204.0 | 162.2 | 25.8% |
| Adjusted items | 0.0 | 0.0 | n.r. |
| Adjusted EBIT | 204.0 | 162.2 | 25.8% |
| Net finance costs | (35.1) | (32.0) | 9.6% |
| Income tax expenses | (39.1) | (31.6) | 23.9% |
| Net profit | 129.8 | 98.6 | 31.7% |
| Adjusted items on net profit | 0.0 | 0.0 | n.r. |
| Adjusted net profit | 129.8 | 98.6 | 31.7% |
| Key figures of the financial position (in € million) | 1H 2025 | 2024 | Difference (%) |
| Total assets | 10,632.5 | 9,466.4 | 12.3% |
| Total equity | 4,194.0 | 3,130.7 | 34.0% |
| Net financial debt | 3,275.4 | 4,365.3 | (25.0%) |
| Free cash flow | 89.9 | (370.9) | (124.2%) |
* Changes in provisions are now included in EBITDA, with 1H 2024 restated accordingly
See the glossary for definitions
See Section 4 for information on adjusted items
Comparative figures for Total assets, Total equity and Net financial debt as at 31/12/2024
In the first half of 2025, Elia Transmission reported a revenue of €763.0 million, marking a 2.1% decrease compared to the same period in 2024 when the revenue totalled €779.3 million. The increase in tariffs and hence tariff sales was almost fully offset by regulatory movements. In 2025, Elia Transmission is having a negative net income from the regulatory settlement mechanism (tariff debt) mainly due to significantly lower system services costs, whereas in 2024 the revenue was increased by a reimbursement to the tariff from the previous years' debt.

This effect was partially offset by several factors, including a higher regulated net profit, increased depreciations tied to the expanding asset base, and elevated net financial costs related to last year's green bond issuance. Additionally, a one-off tariff compensation for the financial costs associated with the capital increase, specifically the portion allocated to ETB, contributed to the higher funding costs.
EBITDA rose to €333.2 million (+17.8%) due to a higher regulated net profit, higher depreciations linked to the growing asset base and higher net finance costs, all passed through into revenue. The EBIT also increased despite the increasing depreciations linked to the asset portfolio and the IFRS depreciations for intangible assets, capitalised borrowing costs and leasing. The contribution of equity-accounted investments slightly increased to €1.8 million, linked to the contribution from HGRT.
Net finance cost increased (+9.6%) compared to previous year. This was mainly driven by last year's debt issuance to supports ETB's organic growth and lower interest income from cash deposits due to decreased interest rates. This was partially counterbalanced by increased capitalisation of borrowing costs due to expansion of the asset base (+€7.6 million). With the EIB green loan facility fully utilized at year end 2024 and the capital raise proceeds, ETB is well financed and did not access the debt market in the first half of 2025. The average cost of debt remained flat at 2.5% (+10 bps) at end of June 2025. ETB maintains a well-balanced debt maturity profile, with all outstanding debt at fixed interest rates. The financial costs linked to Elia Group's capital increase were allocated to the Belgian regulated activities on a pro-rata basis according to the use of proceeds. Under IFRS, these costs (€9.7 million) are directly accounted through equity.
(Adjusted) net profit rose by 31.7% to €129.8 million, mainly due to the following:
These effects were partially offset by:
Total assets increased by €1,166.1 million to €10,632.5 million due to the realisation of the investment programme €518.7 million and enhanced liquidity from the proceeds of the capital raise allocated to ETB (€1,050 million) in April

Equity increased to €4,194.0 million (+€1,063.3 million) driven by the net proceeds from the equity injection (after cost) (€1,040.3 million) and the half-year profit (+€129.8 million). This was partially offset by the dividend payment to Elia Group (-€69.3 million), a higher allocation of equity towards Nemo Link (-€29.8 million), the revaluation of postemployment benefit obligations (-€6.1 million) and the change in fair value of an interest rate hedge (-€1.6 million).

| 50Hertz Transmission key figures (in € million) | 1H 2025 | 1H 2024 | Difference (%) |
|---|---|---|---|
| Revenue, other income and net income (expense) from settlement mechanism |
1,337.8 | 1,132.1 | 18.2% |
| Revenues | 1,363.7 | 1,194.2 | 14.2% |
| Other income | 116.7 | 88.5 | 31.9% |
| Net income (expense) from settlement mechanism |
(142.5) | (150.7) | (5.4%) |
| EBITDA* | 555.4 | 376.4 | 47.5% |
| EBIT | 352.2 | 204.5 | 72.2% |
| Net finance costs | (49.4) | (39.1) | 26.4% |
| Income tax expenses | (95.2) | (53.1) | 79.4% |
| Net profit | 207.5 | 112.3 | 84.7% |
| Of which attributable to the Elia group | 166.0 | 89.9 | 84.7% |
| Adjusted items on net profit | 0.0 | 0.0 | n.r. |
| Adjusted net profit | 207.5 | 112.3 | 84.7% |
| Key figures of the financial position (in € million) | 1H 2025 | 2024 | Difference (%) |
| Total assets | 15,710.9 | 14,155.3 | 11.0% |
| Total equity | 3,080.5 | 3,097.2 | (0.5%) |
| Net financial debt | 7,967.3 | 7,224.0 | 10.3% |
| Net financial debt, excl. EEG and similar mechanisms | 8,359.4 | 7,584.5 | 10.2% |
| Free cash flow | (540.2) | (649.3) | (16.8%) |
*Changes in provisions are now included in EBITDA, with 1H 2024 restated accordingly
Income, expenses, assets and liabilities are reported in the table at 100%
See the glossary for definitions
See Section 4 for information on adjusted items
Comparative figures for Total assets, Total equity, Net financial debt, Net financial debt excl. EEG and other mechanisms as at 31/12/2024
50Hertz Transmission's total revenue and other income increased compared with 2024 (+18.2%). The growth was primarily driven by increased remuneration for 50Hertz's expanding on- & offshore asset base as well as increased charges of energy costs.
EBITDA increased to €555.4 million (+47.5%). The expanding onshore and offshore asset base benefitted the investment remuneration (+€135.6 million). Additionally, EBITDA was affected by a change in regulatory accounting: intra-year onshore investment remuneration now reflects a pro-rata share of the full-year expected CAPEX, rather

than actual CAPEX spend, aligning with the approach in Belgium. This adjustment, ensures more balanced revenue recognition throughout the year, given that a substantial portion of CAPEX is spent in the second half. The effect of this change amounts to €40.2 million (if the same method had been applied in 1H 2024). Moreover, the operating expenses (e.g. for personnel and IT) rose in line with the business growth and were only partly compensated by higher base year revenues (in total -€4.5 million). 50Hertz's non pass-through energy costs (e.g. for Balancing Groups) decreased compared to last year (+€7.6 million). EBIT increased as well (+72.2%) despite the higher depreciation costs (-€31.2 million) arising from the execution of the investment program.
The net financial costs increased to -€49.4 million (-€10.3 million), primarily due to increased funding costs associated with Eurogrid's green bond issuances (-€47.0 million). However, this was partially offset by higher capitalized interest during construction (+€23.8 million) as a result of numerous investment projects being in the construction phase. Furthermore, initial interest income (+€20.5 million) was recognized under a pre-financing agreement with the developer for the Gennaker offshore platform. The largest share of this amount consists of accrued interest from prior years and therefore it is not expected to continue at this magnitude in the future.
(Adjusted) net profit increased to €207.5 million (+84.7%) as a result of:
These effects were partially offset by:
Total assets rose by €1,555.6 million compared to 2024 largely due to the significant progress made on the investment programme over the last months (€969.9 million). In addition, the liquidity as per end of June increased (€729.2 million) due to Eurogrid's funding activities over the first half of the year. The free cash flow totalled -€540.2 million and was significantly impacted by the execution of the investment programme and the net cash inflow from EEG and similar mechanisms (+€31.7 million). It should be noted that 50Hertz functions as a trustee for these mechanisms.
The net financial debt, excl. EEG and similar mechanisms increased by €774.9 million compared to 2024, reaching a total of €8,359.4 million. The execution of the investment programme was partially financed from operating cash flow, but also through funds obtained from accessing the debt market. Taking into account EEG and similar mechanisms, the net financial debt rose by €743.2 million due to the increase in the cash balance for EEG and

similar mechanisms. As of June 2025, the cash position for these schemes saw an increase, amounting to €392.2 million.
In 2025, Eurogrid continued to access the debt market to strengthen its liquidity to supports its investment plan. Early 2025, it tapped €200 million from an existing bond issued in 2024. This was followed by the issuance of €800 million green bond (12 year term, 4.06% interest rate), while reimbursing as well a €500 million bond reaching maturity. Finally, end of June, Eurogrid fully draw on the €1 billion green loan (3.0% interest rate) it secured earlier this year as part of the KfW's climate protection programme and syndicated with 12 banks to fund offshore projects. As a result, the average cost of debt rose slightly to 3.0% (up 10 bps) at the end of June 2025.
All back-up facilities (€3.9 billion) remain undrawn. Additionally, Eurogrid has secured a new €750 million commercial paper programme, enhancing flexibility in funding its grid investment plan. Eurogrid maintains a BBB rating with a stable outlook from Standard & Poor's.
The total equity decreased slightly by €16.8 million to €3,080.5 million, mainly due to changes in (hedge) reserves (- €14.3 million). The half-year result's contribution to equity was offset by dividends paid on the 2024 results.

| Non-regulated segment and Nemo Link Key figures (in € million) |
1H 2025 | 1H 2024 | Difference (%) |
|---|---|---|---|
| Total revenues and other income | 36.9 | 35.4 | 4.2% |
| Equity accounted investees | 14.0 | 22.0 | (36.4%) |
| EBITDA* | 4.6 | 19.6 | (76.7%) |
| EBIT | 3.3 | 19.1 | (82.5%) |
| Adjusted items | 0.0 | 0.0 | 0.0% |
| Adjusted EBIT | 3.3 | 19.1 | (82.5%) |
| Net finance costs | (14.6) | (9.3) | n.r. |
| Income tax expenses | (0.6) | (1.9) | n.r. |
| Net (loss)/profit | (11.8) | 7.9 | n.r. |
| Of which attributable to the Elia Group | (11.8) | 7.7 | n.r. |
| Adjusted items on net profit | 0.0 | 0.0 | n.r. |
| Adjusted net (loss)/profit | (11.8) | 7.9 | n.r. |
| Key figures of the financial position (in € million) | 1H 2025 | 2024 | Difference (%) |
| Total assets | 4,881.0 | 2,621.9 | 86.2% |
| Total equity | 3,476.6 | 1,206.1 | 188.2% |
| Net financial debt | 2.0 | 1,208.9 | (99.8%) |
* Changes in provisions are now included in EBITDA, with 1H 2024 restated accordingly
See the glossary for definitions
See Section 4 for information on adjusted items
Comparative figures for Total assets, Total equity and Net financial debt as at 31/12/2024
Non-regulated revenue slightly increased by 4.2% to €36.9 million compared to half-year 2024. Transactions between segments increased, particularly involving Elia Group SA, Elia Transmission Belgium, and 50Hertz. The implications of these intersegment activities can be found in 'Note 2.2. Segment Reconciliation'. This was partly offset by a slight decline in the revenues of Elia Grid International ('EGI') (-€0.2 million) due to lower international consulting services.
Equity-accounted investments, including Nemo Link and energyRe Giga, contributed €14.0 million to the Group's result (-€8.0 million). Nemo Link contributed €15.5 million to result, while energyRe Giga reported a loss of -€1.6 million.

Nemo Link's strong operational performance benefited from higher revenues due to an increased spread compared to 2024. Long-term revenues were bolstered by the unexpected unavailability of other interconnectors and a rise in renewable production. During the first half of 2025, the interconnector maintained an impressive availability rate of 99.96%. Despite higher revenues compared to the first half of 2024, Nemo Link's contribution was limited by its cumulative cap, resulting in a reduced net contribution of €9.2 million compared to last year.
The development of US activities by energyRe Giga continues, with strict cost control measures leading to a decrease in operating loss compared to last year. This resulted in a negative contribution of -€1.6 million to the Group.
EBIT dropped to €3.3 million (-€15.7 million). This decrease was primarily driven by a lower contribution from the associates Nemo Link and energyRe Giga (-€8.0 million), lower contribution of re.alto (-€1.4 million) and EGI (-€0.9 million). Finally, the EBIT was also negatively impacted by regulatory settlements following the saldi 2024 review (- €4.3 million) and higher other non-regulated costs.
The net finance cost increased to -€14.6 million. This increase was primarily driven by the full-year impact on interest expenses related to the €600 million bond issued in June 2024 (-€10.6 million) and a foreign exchange loss against USD (-€1.6 million) linked to WindGrid US. This was partially offset by higher interest income on cash deposits (+€6.7 million) while prior year was marked by important funding costs linked to the investment in energyRe Giga (+€2.7 million) and other items (-€2.5 million). The pro-rata costs linked to the capital increase of Elia Group and allocated to respectively Elia Group SA and Eurogrid International are directly recognized in equity under IFRS (€10.7 million). The pro-rata costs linked the equity injection in ETB are borne by ETB and covered by the tariffs.
(Adjusted) net (loss)/profit totalled -€11.8 million (-€19.7 million), mainly as a result of:
Net financial debt decreased by €1,206.9 million to €2.0 million. This decrease is primarily attributed to the net proceeds from the capital increase, which remain on the holding balance sheet (€1,139 million). In April, €1,050 million was allocated to ETB. The allocation pertaining to Eurogrid GmbH, approximately €1,000 million, is planned to be evenly distributed over the period of 2025-2026. The holding's liquidity was enhanced by a €100 million commercial paper programme, which remained fully undrawn.
Total assets saw a more significant increase (+86.2%), amounting to €4,881.0 million (+€2,259.1 million), mainly driven by the capital increase of €2.2 billion.

| Consolidated results (in € million) − period ended 30 June |
2025 | 2025 | 2025 | 2025 | 2025 |
|---|---|---|---|---|---|
| Elia Transmission |
50Hertz Transmission |
Non regulated segment and Nemo Link |
Consolidation entries & intersegment transactions |
Elia Group | |
| ( a ) | ( b ) | ( c ) | ( d ) | ( a ) + ( b ) + ( c ) + ( d ) |
|
| Revenue | 802.1 | 1,363.7 | 36.9 | (30.3) | 2,172.4 |
| Other income | 61.9 | 116.7 | 0.0 | (14.4) | 164.2 |
| Net income (expense) from settlement mechanism | (101.0) | (142.5) | 0.0 | 0.0 | (243.5) |
| Depreciation, amortisation and impairment | (129.2) | (203.2) | (1.2) | 0.1 | (333.6) |
| Results from operating activities | 202.2 | 352.2 | (10.7) | 10.2 | 553.9 |
| Share of profit of equity accounted investees, net of tax |
1.8 | 0.0 | 14.0 | 0.0 | 15.8 |
| Earnings before interest and tax (EBIT) | 204.0 | 352.2 | 3.3 | 10.2 | 569.7 |
| Earnings before depreciation, amortisation, interest and tax (EBITDA)* |
333.2 | 555.4 | 4.6 | 10.1 | 903.3 |
| Finance income | 12.9 | 33.2 | 32.5 | 0.0 | 78.6 |
| Finance costs | (47.9) | (82.6) | (47.1) | (10.2) | (187.8) |
| Income tax expenses | (39.1) | (95.2) | (0.6) | 0.0 | (134.9) |
| Net profit | 129.8 | 207.5 | (11.8) | (0.0) | 325.6 |
| Profit attributable to the owners of the company Consolidated statement of financial position (in € million) |
129.8 30/06/2025 |
166.0 30/06/2025 |
(11.8) 30/06/2025 |
(0.0) 30/06/2025 |
284.1 30/06/2025 |
| Total assets | 10,632.5 | 15,710.9 | 4,881.0 | (2,353.9) | 28,870.5 |
| Capital expenditures | 507.0 | 1,161.5 | 0.0 | 0.0 | 1,668.5 |
| Net financial debt | 3,275.4 | 7,967.3 | 2.0 | 0.0 | 11,244.7 |
*Changes in provisions are now included in EBITDA, with 1H 2024 restated accordingly

For 2025, Elia Group expects to deliver a net profit Elia Group share, in a range between €490 million and €540 million.
The guidance does not consider any potential M&A transactions.
2 The following statements are forward-looking and actual results may differ materially.

| (in € million) - Period ended 30 June 2025 | Ella Transmission | 50Hertz Non-regulated Transmission segment and Nemo Link |
Consolidation entries |
Ella Group | |
|---|---|---|---|---|---|
| Adjusted items | |||||
| Nihil | 0.0 | 0.0 | 0.0 | 0.0 | 00 |
| Adjusted EBIT | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
| Tax Impact | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
| Net profit - adjusted items | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
| (in € million) - Period ended 30 June 2024 | Elia Transmission | 50Hertz Non-regulated Transmission segment and Nemo Link |
Consolidation entries |
Elia Group | |
| Adjusted items | |||||
| Transaction costs (acquisition of a minority stake in energyRe Giga - US) |
0.0 | 0.0 | 0.0 | 0.0 | 0 0 |
| Adjusted EBIT | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 |
| Tax Imoact | 00 | 00 | 00 | 00 | 00 |
| Publication of half-year results 2025 | 25 July 2025 |
|---|---|
| Quarterly statement Q3 2025 | 28 November 2025 |
| Publication of full-year results 2025 | 6 March 2026 |
| Publication of 2025 Annual report | 17 April 2026 |
| General Meeting of Shareholders | 19 May 2026 |
| Quarterly Statement Q1 2026 | 20 May 2026 |
| Ex-dividend date | 29 May 2026 |
| Record date | 1 June 2026 |
| Payment of dividend for 2025 | 2 June 2026 |

The joint statutory auditors, EY Bedrijfsrevisoren BV/Réviseurs d'Entreprises SRL represented by Mr Frédéric De Mee and BDO Bedrijfsrevisoren BV/Réviseurs d'Enterprises SRL represented by Mr Michaël Delbeke, have confirmed that their audit procedures, have not revealed any material adjustments which would have to be made to the accounting information included in this press release.
Certain statements in this press release are not historical facts and are forward-looking statements. From time to time, the Company may make written or oral forward-looking statements in reports to shareholders and in other communications. Forward-looking statements include, but is not limited to, the estimates of revenues, operating margins, capital expenditures, cash, future liquidity, working capital, and capital requirements, the Company's ability to raise capital and debt, other financial information, expected legal, political or regulatory evolutions, in Belgium and in and outside Europe, and other such estimates and evolutions, including amongst others the uncertainty with respect to the necessary regulatory approvals of costs and terms and conditions related to the operation of the grid, the expected development of the Company's business, projects, joint ventures and other co-operations, the execution of the Company's vision and growth strategy, including with respect to future M&A activity and global growth. Words such as "believe", "anticipate", "estimate", "expect", "intend", "predict", "project", "could", "may", "will", "plan", "remain confident" and similar expressions are intended to identify forward-looking statements, but are not the exclusive means of identifying such statements. By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that the predictions, forecasts, projections and other forwardlooking statements will not be achieved. Investors should be aware that a number of important factors could cause actual results to differ materially from the plans, objectives, expectations, estimates and intentions expressed in such forward-looking statements. When relying on forward-looking statements, investors should carefully consider the foregoing factors and other uncertainties and events, especially in light of the political, economic, social, industry and legal environment in which the Company operates. Such forward-looking statements speak only as of the date on which they are made. Accordingly, the Company does not undertake any obligation to update or revise any of them, whether as a result of new information, future events or otherwise, other than as required by applicable laws, rules or regulations. The Company makes no representation, warranty or prediction that the results anticipated by such

forward-looking statements will be achieved, and such forward-looking statements represent, in each case, only one of many possible scenarios and should not be viewed as the most likely or standard scenario.
Please refer to the following link for the glossary: 2025 half-year financial report.

Elia Group is a key player in electricity transmission. We ensure that production and consumption are balanced around the clock, supplying 30 million end users with electricity. Through our subsidiaries in Belgium (Elia) and the north and east of Germany (50Hertz), we operate 19,741 km of high-voltage connections, meaning that we are one of Europe's top 5 transmission system operators. With a reliability level above 99%, we provide society with a robust power grid, which is important for socioeconomic prosperity. We also aspire to be a catalyst for a successful energy transition, helping to establish a reliable, sustainable and affordable energy system.
By expanding international high-voltage connections and incorporating ever-increasing amounts of renewable energy into our grid, we are promoting both the integration of the European energy market and the decarbonisation of society. We also continuously optimise our operational systems and develop new market products so that new technologies and market parties can access our grid, thus further facilitating the energy transition.
As a key player in the energy system, Elia Group is committed to working in the interest of society. We are responding to the rapid increase in renewable energy by constantly adapting our transmission grid. We also ensure that investments are made on time and within budget, with a maximum focus on safety. In carrying out our projects, we manage stakeholders proactively by establishing two-way communication channels between all relevant parties very early on in the development process. We also offer our expertise to different players across the sector in order to build the energy system of the future.
In In addition to its activities as a transmission system operator, Elia Group provides consulting services to international customers through its subsidiary Elia Grid International. In recent years, the Group has launched new non-regulated activities such as re.alto - the first European marketplace for the exchange of energy data via standardised energy APIs - and WindGrid, a subsidiary which will continue to expand the Group's overseas activities, contributing to the development of offshore electricity grids in Europe and beyond.
The legal entity Elia Group is a listed company whose core shareholder is NextGrid Holding.
.
Investor Relations Yannick Dekoninck | M +32 478 90 13 16 | [email protected] Stéphanie Luyten | M +32 467 05 44 95 | [email protected] Corporate Communication Marleen Vanhecke | M +32 486 49 01 09 | [email protected]

| (in € million) - Period ended 30 June | 2025 | 2024 |
|---|---|---|
| Revenue | 2.172.4 | 1.786.9 |
| Raw materials, consumables and goods for resale | (10.0) | (15.0) |
| Other Income | 164.2 | 189.5 |
| Net income (expense) from settlement mechanism | (243.5) | (62.0) |
| Services and other goods | (891.3) | (996.6) |
| Personnel expenses | (270.9) | (227.7) |
| Depreciation, amortisation and impairment | (333.6) | (293.1) |
| Changes in provisions | (3.3) | 08 |
| Other expenses | (30.1) | (20.4) |
| Results from operating activities | 553.9 | 362.3 |
| Share of profit of equity accounted investees (net of tax) | 15.8 | 23.5 |
| Earnings before Interest and tax (EBIT) | 569.7 | 385.8 |
| Net finance costs | (109.2) | (80.5) |
| Finance Income | 78.6 | 51.9 |
| Finance costs | (187.8) | (132.4) |
| Profit before income tax | 460.5 | 305.3 |
| Income tax expense | (134.9) | (86,5) |
| Profit for the period | 325.6 | 218.8 |
| Profit attributable to: | ||
| Equity holders of the parent - equity holders of ordinary shares | 269.6 | 181.6 |
| Equity holders of the parent - hybrid securities | 14.5 | 14.5 |
| Non-controlling interest | 41.5 | 22.6 |
| Profit for the period | 325.6 | 218.8 |
| Earnings per share (in €) | ||
| Basic earnings per share* | 2 90 | 2 35 |
| Diluted earnings per share* | 2.90 | 2.35 |
* Includes the bonus adjustment related to the 2025 rights issue (bonus factor of 0.95)
Rounding – In general, all figures are rounded. Variances are calculated from the source data before rounding, meaning that some variances may not add up.

| (in € million) - Period ended 30 June | 2025 | 2024 | |
|---|---|---|---|
| Profit for the period | 325.6 | 218.8 | |
| Other comprehensive income (OCI) | |||
| Items that may be reclassified subsequently to profit or loss: | |||
| Net changes in fair value of cash flow hedges | (22.5) | 108.6 | |
| Foreign currency translation differences of foreign operations | (0.4) | (1.3) | |
| Related tax | 6.7 | (32.4) | |
| Items that will not be reclassified to profit or loss: | |||
| Remeasurements of post-employment benefit obligations | (8.2) | 135 | |
| Net changes in fair value of investments | 0.0 | 65.9 | |
| Related tax | 2.0 | (5.2) | |
| Other comprehensive income for the period, net of tax | (22.4) | 149.1 | |
| Total comprehensive income for the period | 303.2 | 367.9 | |
| Total comprehensive income attributable to: | |||
| Equity holders of the parent - ordinary shareholders | 250.0 | 303.0 | |
| Equity holders of the parent - hybrid securities holders | 14.5 | 14.5 | |
| Non-controlling interest | 38.7 | 50.4 | |
| Total comprehensive income for the period | 303.2 | 367.9 |
Rounding – In general, all figures are rounded. Variances are calculated from the source data before rounding, meaning that some variances may not add up.

| (in € million) - As at | 30 June 2025 | 31 December 2024 | ||
|---|---|---|---|---|
| Assets | ||||
| Non-current assets | 22,593.1 | 21,425.9 | ||
| Property, plant and equipment | 18,838.6 | 17,692.6 | ||
| Goodwill | 2.411.1 | 2,411.1 | ||
| Intangible assets | 613.9 | 565.2 | ||
| Equity-accounted investees | 499 2 | 512.7 | ||
| Other financial assets | 187.0 | 186.3 | ||
| Derivatives | 0.0 | 23 | ||
| Trade and other receivables non-current | 42.3 | 55.0 | ||
| Deferred tax assets | 1.1 | 0.7 | ||
| Current assets | 6,277.4 | 3,501.7 | ||
| Inventories | 298.3 | 224.6 | ||
| Trade and other receivables | 840.0 | 1,098.4 | ||
| Current tax assets | 52.1 | 94.3 | ||
| Derivatives | 21.8 | 10.0 | ||
| Cash and cash equivalents | 4,974,2 | 2,030.3 | ||
| Deferred charges and accrued revenues | 91.1 | 44.1 | ||
| Total assets | 28.870.5 | 24,927.6 | ||
| Equity and liabilities | ||||
| Equity | 8,443.0 | 6,177.4 | ||
| Equity attributable to owners of the Company | 7.825.2 | 5,556,2 | ||
| Equity attributable to ordinary shares: | 7.324.0 | 5,040.3 | ||
| Equity attributable to hybrid securities holders | 501.2 | 515.9 | ||
| Non-controlling interest | 617.8 | 6212 | ||
| Non-current liabilities | 16,260.7 | 14,899.2 | ||
| Loans and borrowings | 15,355.3 | 13,968.8 | ||
| Employee benefits | 75.4 | 61.4 | ||
| Derivatives | 6.2 | 4.5 | ||
| Provisions | 176.8 | 172.1 | ||
| Deferred tax liabilities | 300.7 | 301.9 | ||
| Other liabilities | 346.3 | 390 5 | ||
| Current liabilities | 4,166.8 | 3,851.0 | ||
| Loans and borrowings | 863.5 | 859.7 | ||
| Provisions | 10.8 | 8.9 | ||
| Trade and other payables | 2,212.7 | 2,158.0 | ||
| Current tax liabilities | 30.3 | 10.2 | ||
| Derivatives | 7.5 | 2.3 | ||
| Other liabilities | 0.5 | 0.6 | ||
| Accruals and deferred income | 1,041.5 | 811.2 | ||
| Total equity and liabilities | 28.870.5 | 24.927.6 |

| PHOTO ANTAB | STATE CRANETE | Herstail read | Cara | 151/9 nry |
123 00 11 nogamini 17 |
Betaled carrings | iliares 11 ANTES |
rytos 0 Edity all clubs |
150 Equity attributable to |
HIFT-COLLICITY FORCESSO | Total makery | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Cataller at 5 Jamesry 7004 | LETT 2 | 121 | 体育 利 | 1841 | 1741 | 1311 | 1222 | 4.18 9 | 0.088 # | 123 4 | 1373 | |
| Profit for the parlod | 190 I | 104-2 | 100 I | 22 € | 218.8 | |||||||
| Office comprehettshae income | 81.2 | 11.21 | 814 | 1213 | 121.8 | 27.8 | 140.1 | |||||
| Total comprehensive greative for the pattist | 01.1 | 11.11 | 237.0 | 11/2 | 917.9 | 03.4 | M3 | |||||
| Transactions with owners, recorded directly in oquilty | ||||||||||||
| Contributions by and distributions to Owners | ||||||||||||
| Corroll Saled | ||||||||||||
| 18800 004817431 | ||||||||||||
| Share-based payment experises | 18 - 1 | |||||||||||
| seeming portugue frankliked in provention programs. Direct | ||||||||||||
| Hybrid: set up fee & agio | ||||||||||||
| Hybrid: Sividend account | 54.7 | 14.7 | 144.77 | SETTER F | ||||||||
| Hybrid: coupon paid | (24.3) | (2000) | 124.30 | (20.8) | ||||||||
| Hybrid. Jax effect on dividend scolulal | 17 | 17 | 37 | 1.7 | ||||||||
| Acquisition of treasury shares | 10.32 | (0.30) | 14.31 | 00:00 | ||||||||
| Dividently to non-coming ling interests. | 28.00 | (20.01 | ||||||||||
| Divide not | (148,3) | (140.30 | (148.3) | [140,3] | ||||||||
| Ofter | 0.4 | 3.4 | 13.34 | (0.20 | 12:25 | (0.1) | ||||||
| moderedities blus assucts distritismes ato? | 贝库 | 0.0 | 19 | 12.71 | C158.47 | 1102700 | 114.11 | 117227 | 24.04 | 11:04 - 21 | ||
| Total transactions with owners | 11.9 | 0.0 | 0.0 | 3.9 | 19.31 | A.K. | (180.4) | (157.6) | £14.Th | (172.3) | 120.00 | (300.3) |
| Fills Bunf OC Jexssuries | 18213 | TWI | ור ובו | 183.4 | 12.71 | (1.7) | 14181 | 4,722.9 | 0012 | 1,211.0 | 4378 | LETE A |
| Salance at ? Jamany 2025 | 1.831.2 | 121 | 18.8 | 111.4 | 12-11 | 11,1 | 13811 | 1.841.3 | \$11.8 | 1.111.J | 1111 | LTTTA |
| Profit for the pariod | 244.4 | 254-1 | 244.1 | 41.8 | 326.0 | |||||||
| Other comprahamalva income | -12.0 | -0.4 | ના | -12-5 | 40.2 | 21 | 22 € | |||||
| THE Except storations in accome for the portual | -19.00 | 11 4 | 211.0 | 1994 00 | 754 0 | 14.7 | 301, Will | |||||
| Thansactions with owners, recorded directly in orgality Contributions by and distributions to Owners |
||||||||||||
| 191916 MAURO | 489.7 | 1.315 2 | 2.186.0 | 2.199.9 | 1.100.8 | |||||||
| 15500 00481551 townshipped frastylights and starts - starty |
(20.4) | 204) | (22-4) | (20.4) | ||||||||
| Hybrid assuance epayment of hytrid securities Hyorid set-oplee & ago |
||||||||||||
| AND CONSTITUTION OF DOOD BY | 14.7 | 14.7 | (14.79 | |||||||||
| Ayand: serieso part | 124.30 | (28.8) | 29 20 | (28.91 | ||||||||
| Hysrid. Jax effect on dividend poorual | 87 | 37 | 31 | 17 | ||||||||
| Antonia Arrana of the encreations | 0.7 | 2.7 | 0.7 | 0.7 | ||||||||
| Divide has to non-controlling interests. | (42.0) | 142.01 | ||||||||||
| Distdents | (184:7) | (188-T) | 1184:71 | 1160.71 | ||||||||
| Char | 14 | (2.9) | 86 | 0.8 | 06 | |||||||
| many and the proven and the chulters | 114.5 | 7,311.3 | 1,5 | 14 | ರ, | 11 | (1644) | 2,210,5 | 114.0 | 9,0004 | (47.0 | 1/463.3 |
| Total transactions with owners | 889.3 | 1,313.2 | 8.0 | 14 | 0.7 | ਸ ਤੋਂ | (184.4) | 2,018.3 | (14.7) | 2,0044 | 143.00 | 1,003-4 |
| Salance at 30 June 2025 | 1.2.899 1 | 9,252.3 | 18.4 | 1887 | 12 81 | 12 11 | 1383.1 | 2,238.0 | 2012 | 1 3853 | 817.8 | 8.413.0 |

| enmy 00 period ended 30 June | 2022 | 2024 |
|---|---|---|
| Cash flows from operating activities | ||
| Profit for the period | 325.6 | 218.8 |
| Adjustments for: | ||
| Net finance costs | 109.2 | 80.2 |
| Other non-cash items | 1.0 | (0.8) |
| Current Income tax expense | 111.0 | 67.6 |
| Profit or loss of equity accounted investees, net of tax | 15.8) | (23.5) |
| Depreciation of property, plant and equipment and amoritsason of intangible assets | 335.0 | 293:0 |
| Loss I proceeds on sale of property, plant and equipment and intangible assets | 14.5 | 38 |
| Impairment losses of current assets | 1.4 | 0.4 |
| Change in provisions | 83 | (5.3) |
| Change in loans and borrowings | ||
| Change in deferred taxes | 23.9 | 19.0 |
| Changes in fair value of financial assets through profit or loss | (0.1) | (0.2) |
| Cash flow from operating activities | 913.9 | 653.0 |
| Change in inventories | (75.0) | (67.7) |
| Change in trade and other receivables | 249 4 | 128.0 |
| Change in other current assets | (52.2) | (48.5) |
| Change in trade and other payables | 276.0 | 278.8 |
| Change in other current liabilities | 182.0 | 73.7 |
| 580.1 | 363.3 | |
| Changes in working capital | (288 a) | (201.3) |
| Interest paid | 30.0 | 55.3 |
| Interest received Income tax receivedi(paid) |
(47.0) | (71.9) |
| Not cash from operating activities | 1,178.1 | 788.4 |
| Cash flows from investing activities | ||
| Acquisition of intangible assets | (169.6) | (91.1) |
| Acquisition of property, plant and equipment Investment in subsidiary |
(1,498.9) 0.0 |
(1 737.9) 0.0 |
| Acquisition of equity-accounted investees | 00 | (230.2) |
| Acquisition of equity and debt instruments | (0.5) | 0.0 |
| Acquisition of investment | 0.0 | 0.0 |
| Acquired cash from acquisition of equilty-accounted investees | 0.0 | 0.0 |
| Proceeds from sale of property, plant and equipment | 0.7 | 1.0 |
| Proceeds from sales of investments | 0.0 | 0.0 |
| Proceeds from capital decrease from equity accounted investees | 0.0 | 0.0 |
| Dividend received | 1.5 | 4.1 |
| Loans and long term receivables | 0.0 | 0.0 |
| Net cash used in Investing activities | 1,666,8) | (2,054.0) |
| Cash flow from financing activities | ||
| Proceeds from the issue of share capital | 2.199.9 0.0 |
0.0 0.0 |
| Proceeds from the capital increase - NCI Expenses related to the issue of share capital |
(20.4) | 0.0 |
| 0.0 | 0.0 | |
| Proceeds from the issue of hybrid securities Repayment of hybrid securities |
0.0 | 0.0 |
| Expenses related to financing activities | 00 | |
| Purchase of own shares | 13 | 00 |
| Dividend paid | (0.6) | |
| (129.2) | (146.3) | |
| Hybrid coupon paid | (29.3) | (29.3) |
| Dividends to non-controlling parties | (42.0) | (36.0) |
| Repayment of borrowings | (550.6) 2.002.9 |
(632.0) |
| Proceeds from withdrawal of borrowings | 3,190.5 (0.0) |
|
| Non-controlling Interests | (0.0) | |
| Other cash flows from financing activities | 0.0 | 0.0 |
| Net cash flow from (used in) financing activities | 3.432.6 | 2.348.4 |
| Effects of changes in exchange rates | (0.1) | (3.6) |
| Net Increase (decrease) In cash and cash equivalents | 5,043 B | 1,017,2 |
| Cash & Cash equivalents at 1 January | 2.030.3 | 1,368,1 |
| Cash & Cash equivalents at 30 June | 4.974.2 | 2,455.3 |
| Not variations in cash & cash equivalents | 2.943.9 | 1.017.2 |

For more information, please refer to 2025 half-year financial report available at: Reports for Elia Group
Building tools?
Free accounts include 100 API calls/year for testing.
Have a question? We'll get back to you promptly.