Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

ELEVRA LITHIUM LIMITED Audit Report / Information 2017

Aug 29, 2017

64838_rns_2017-08-29_629b0da4-7ea2-497f-95b0-6e5dbe7cbdfd.pdf

Audit Report / Information

Open in viewer

Opens in your device viewer

==> picture [596 x 144] intentionally omitted <==

30 AUGUST 2017

LITHIUM CARBONATE/HYDROXIDE CONCEPT STUDY DEMONSTRATES POSITIVE TECHNICAL AND ECONOMIC VIABILITY

  • Positive Concept Study confirms opportunity to unlock value at Authier processing concentrates into high-value products used in the lithium-ion battery industry

  • Potential to partly finance downstream operations by the sale of spodumene concentrate in the early years whilst the permitting and downstream feasibility study are completed

  • Significant competitive advantages in raw material supply, infrastructure, energy and reagent supply and costs, in Quebec

  • Competitive capital and operating costs compared to benchmark new projects

Sayona Mining Limited (ASX: SYA) ("Sayona" or the "Company") is pleased to report the positive results of a downstream processing Concept Study for the production of lithium carbonate and/or lithium hydroxide at the Authier lithium project in Quebec, Canada.

The Concept Study prepared by engineering consultants, Wave International (“Wave”), has demonstrated the potential technical and economic viability of constructing a lithium carbonate and/or hydroxide facility in Quebec.

The study evaluated the option of converting Authier’s annual spodumene concentrate into either 13,000 tonnes of lithium carbonate or 14,000 tonnes of lithium hydroxide, utilising conventional processing technology, and leveraging the world-class infrastructure, low energy and reagent costs. Lithium carbonate and hydroxide are both high-value products used in the lithium-ion battery industry.

The Concept Study demonstrates that the Authier downstream project has the potential to be competitive on both capital and operating costs compared to benchmarked projects. The Company will explore options to either acquire or partner with other companies that have deposits in Quebec, as significant economies of scale are achievable at larger scale.

The next step in the project development plan is to convert Authier concentrates into lithium carbonate, complete of a Pre-Feasibility Study, permitting and site selection. This process will run in parallel with the completion of the mining and concentrate processing Definitive Feasibility Study, and strategic partnering process.

Chief Executive Officer, Corey Nolan, commented: “The positive results from the Concept Study signals a new phase of value creation for the Authier project. In the short term, the Company is committed to developing a low capital expenditure concentrate sales operation and capitalising on the projected high price environment for concentrates near term. The cash flows could then be applied to funding the equity required to construct the downstream processing plant. This would unlock the inherent value in the project at a time when lithium carbonate/hydroxide prices are trading near at all time price highs based on the strong demand growth for lithium-ion batteries. Please also refer to the cautionary contained within”.

==> picture [596 x 71] intentionally omitted <==

==> picture [596 x 105] intentionally omitted <==

Cautionary Note

The Concept Study referred to in this announcement has been undertaken to determine the potential viability of downstream processing Authier concentrates into lithium carbonate and/or hydroxide. It is based on a low level technical and economic assessment and was based on the AACE International Recommended Practice No. 18R-97, as a Class 4 estimate (see Figure 1 below). The study has not been used as the basis for the estimation of Ore Reserves. Further technical and economic assessment including, metallurgical testing, Feasibility Study and permitting will be required to provide any assurance or certainty of an economic development case.

The Concept Study is based on the mine and concentrator assumptions (includes Ore Reserves) outlined in the February 2017 Authier Pre-Feasibility Study, Authier Updated JORC Resource report (14 June 2017), a report prepared by Wave International on the downstream capital and operating costs, Appendix – Project Design Criteria, and other material assumptions outlined elsewhere in this document. Whilst the Company considers all the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the outcomes indicated in the Concept Study will be achieved.

To achieve the potential downstream process plant development outcomes indicated in this Concept Study, additional funding will be required. Funding will be required to complete metallurgical testing ($100,000), feasibility studies and permitting (approximately $1,000,000) and development (approximately $223 to $240 million depending on whether it is a lithium carbonate or lithium hydroxide plant). Investors should note that there is no certainty that the Company will be able to raise the funding when needed. It is also possible that such funding may only be available at terms that may be too dilutive to or otherwise affect the value of Sayona shares. It is also possible that Sayona could pursue other ‘value realisation strategies such as sale, partial sale or joint venture of the project. If it does, this could materially reduce Sayona’s proportionate ownership of the project. Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Concept Study.

The Company has concluded it has reasonable basis for providing forward looking statements included in this announcement and believes that it has a reasonable basis to expect it will be able to continue funding the feasibility activities for the project.

Technical Study Overview

In February 2017, the Company completed a Pre-Feasibility Study (including a Maiden Ore Reserve statement) assessing the technical and economic viability of selling spodumene concentrates into the global seaborne traded market[1] ). In August 2017, the Company commissioned an evaluation of the technical and economic viability of building a lithium carbonate and/or hydroxide production conversion facility using Authier spodumene concentrates to enhance the project value, and improve the long-term competitive position of the project.

1 see ASX release, Authier Pre-Feasibility Study Demonstrates Excellent returns and significant Upside Potential, 16 February 2017 and ASX release, Authier Maiden JORC Ore Reserve, 16 February 2017

Page 2

==> picture [596 x 105] intentionally omitted <==

The downstream study was prepared by Wave International (Wave), a highly experienced resource industry development consulting group with over a decade of experience in the lithium industry. Wave are one of only a handful of consultants globally who have successfully studied, designed and delivered spodumene concentration plants, as well as having successfully delivered studies and detailed design for downstream lithium conversation plants. The experience of Wave and its key personnel includes projects such as James Bay (Canada), Greenbushes, Mt Cattlin and Bald Hill.

The study has assessed the alternative processing options, process flow sheet selection, operating and capital cost estimates, financial analysis, and recommendations for the next phase of development.

The Concept Study is based on a low level technical and economic assessment and was based on the AACE International Recommended Practice No. 18R-97, Class 4 estimate.

==> picture [486 x 390] intentionally omitted <==

Figure 1 : AACE International Recommended Practice No. 18R-97

Page 3

==> picture [596 x 105] intentionally omitted <==

Key Highlights from Concept Study

The Concept Study has confirmed the technical and financial viability of processing Authier spodumene concentrates into value added battery products including, lithium carbonate and lithium hydroxide. The positive Concept Study demonstrates the opportunity to create substantial long-term sustainable shareholder value at a competitive capital cost.

Table 1: Authier Downstream Processing Financial Highlights Table 1: Authier Downstream Processing Financial Highlights Table 1: Authier Downstream Processing Financial Highlights Table 1: Authier Downstream Processing Financial Highlights Table 1: Authier Downstream Processing Financial Highlights
(Approximate Values Derived from the Scoping Study)
Description Unit Lithium Carbonate
Lithium Hydroxide
Annual Production Capacity Tonnes 13,000 14,000
Ave Cash operating Costs* C$ per tonne 6,331 6,032
Ave Cash Operating Costs* US$ per tonne 4,812 4,585
Price forecast US$ per tonne 10,200 12,000
Initial Capital# C$ million 223 240
Total Capital# C$ million 284 301
Pre-tax NPV @ 9%DR C$ million 426 794
Pre-Tax IRR % 31 44
Exchange rate CAD$:US$ 0.76
* Cash Operating Costs includes mining, processing, administration, royalties, transport, and
downstream processing
# Capital expenditure includes all mine, concentrator and downstream process plant

Authier Project Strategy

In February 2017, the Company completed a Pre-Feasibility Study (see highlights in Table 2) and reported a maiden Ore Reserve (see Table 3) demonstrating the technical and economic viability of constructing a mine and concentrator to produce spodumene concentrate at Authier.

Table 2 - Authier Lithium Project PFS Highlights Table 2 - Authier Lithium Project PFS Highlights
Description Unit Results
Average Annual Ore Feed to the Plant tonnes 700,000
Annual Average Spodumene Production tonnes 99,000
Life-of-Mine andprocessingoperations years 13/15
Life-of-Mine StripRatio waste to ore 6:1
Average Spodumene Price based on 5.75% Li20 US$/tonne 515
Development Capital Costs C$ million 66
Total Life of Mine Capital Costs C$ million 113
Total Net Revenue(real terms) C$ million 978

Page 4

==> picture [596 x 105] intentionally omitted <==

Total Project EBITDA(real terms) C$ million 449
Average Life of Mine Cash Costs(Montreal Port FOB basis) C$/tonne 367
Net Present Value(real terms @ 8% discount rate) C$ million 140
Pre-Tax Internal Rate of Return % 39
Project Payback Period years 2.2
Exchange Rate CAD:USD 0.76
Source: Authier Pre-FeasibilityASX release, 16thFebruary2017
Table 3 - Authier JORC Ore Reserve Estimate (0.45% Li20 Table 3 - Authier JORC Ore Reserve Estimate (0.45% Li20 Table 3 - Authier JORC Ore Reserve Estimate (0.45% Li20 cut-off grade)
Category Tonnes (Mt) Grades (%Li20) **Contained Li20 **
Proven Reserve 4.9 0.97% 47,821
Probable Reserve 5.3 1.06% 55,904
Total Reserves 10.2 1.02% 103,725
Note:The Ore Reserve estimate is based on the details published in a separate ASX release “Authier JORC
Reserve Estimate”, 16 February 2017.

Note: The Ore Reserve estimate is based on the details published in a separate ASX release “Authier JORC Reserve Estimate”, 16 February 2017.

However, the Company believes an opportunity exists to potentially enhance the value of the Authier project by further processing of the Authier concentrates into valuable products for the lithium-ion battery supply chain.

The rationale for considering downstream processing, includes:

  • There is a significant price premium paid for value-added lithium products. Currently, lithium carbonate and lithium hydroxide prices in the Chinese market are US$18,100/t and US$21,000/t[2] , respectively; and

  • Spodumene concentrates are low grade (typically containing between 5 and 6% Li20) and it is less economically efficient to transport a concentrate that contains a high proportion of waste material.

In addition, Quebec is uniquely positioned with a number of significant commercial and market advantages for value-adding concentrates, including:

  • High quality infrastructure, including roads, rail, and port access;

  • Globally competitive, low-cost gas and electricity prices. Electricity is sourced from renewable energy;

  • Skilled, competitive cost labour force;

  • Sulphuric acid, a key reagent for processing, is available from a copper smelter at Rouyn Noranda, 80 kilometres west of the Authier project site;

2 Curran & Co

Page 5

==> picture [596 x 105] intentionally omitted <==

  • Road and rail transport networks connecting to export ports;

  • Supportive government that invests directly into mineral development projects (e.g. Nemaska and North American Lithium); and

  • Located in close proximity to the US markets including, the Tesla Giga factory in Nevada, and other planned battery factories in the United States.

In addition, currently all the world’s hard-rock lithium concentrates are imported and processed into value-added products in China. China’s policy incentives for investment into battery manufacturing for electric vehicles and storage systems, and export tax regime for lithium products, is restricting supply of battery raw materials to western battery manufacturers like Korea, Japan and Europe. The Company believes it can be an alternative, stable source of lithium new supply outside China.

Next steps

Based on the positive outcomes of the study, the next steps for the downstream project, include:

  • Progress to the Pre-Feasibility Stage. This process is expected to take 3-4 months. Target accuracy of operating and capital cost estimates is +/-25%;

  • Detailed study of the lithium carbonate and lithium hydroxide supply and demand market dynamics to ascertain proposed production mix for the Authier project;

  • Further metallurgical test work including bench scale production of lithium carbonate and hydroxide;

  • Site selection assessment;

  • Off-take and strategic partnering process to facilitate securing development finance. This would include both debt and equity options, and forward product sales;

  • Consultation with the stakeholders in the Abitibi district; and

  • Establish the permitting regime for the project with the Environmental authorities.

The Company is currently finalising the Updated PFS for Authier mine and concentrate project and planning the next phase of assessment for the downstream operations.

Page 6

==> picture [596 x 105] intentionally omitted <==

==> picture [494 x 289] intentionally omitted <==

Figure 2: Current schedule for the mine and concentrator, and downstream feasibility study

Market Opportunity

Lithium concentrate produced from Authier will be classed as Chemical Grade specification. The principal markets for Chemical Grade concentrates are battery, lubricants, aluminum smelting and pharmaceuticals applications. The lithium market is currently experiencing a major demand shift driven by the increasingly critical role of the lithium-ion battery technology for storage applications in the automotive, consumer electronics and electricity storage/distribution sectors. The electrochemistry of lithium based batteries provide higher voltage, higher power density and lower discharge rates with no memory effect, when compared to competing technologies.

The lithium-ion battery or rechargeable market represented 42% of total lithium consumption or 81,300 tonnes of Lithium Carbonate Equivalent (“LCE”) in 2016, a year-on-year increase of 38%3. Most industry commentators are forecasting the consumption of lithium in volume terms will continue to be driven heavily by the rechargeable battery sector. In a recent presentation, Roskill estimated that the total consumption of lithium could approximately 5 times from 200,000 tonnes in 2016 to 1,000,000 tonnes LCE by 2026[4] - see Figure 3. Key macro demand drivers include, carbon emissions legislation aimed at reducing the reliance on fossil

3 UBS, Lithium & Graphite: Driving Disruption, 15 June 2017

4 Source: Robert Baylis, Roskill, 9th Lithium Supply and Markets Conference, 31st May 2017

Page 7

==> picture [596 x 105] intentionally omitted <==

fuels, government incentives, environmental concerns, technological advancements, and the improved product offerings utilising lithium-ion batteries.

==> picture [484 x 227] intentionally omitted <==

Figure 3 : Forecast demand for lithium by use to 2026 (t LCE)

According to Deutsche Bank[5] , within the battery segment, key drivers include:

  • Electric vehicles (“EV”) – the adoption of electric vehicles is poised to rapidly expand over the next decade. Forecast global EV penetration (including hybrids and plug-inhybrids) to increase from 4% of 2015 global auto sales (of which EV accounted for 0.6%) to 14% market share by 2025, of which EV makes up 2.6% of sales. This implied the EV market would grow from 0.5 million units in 2014 to 3 million global sales within ten years. This represents growth in lithium demand from 25Kt LCE in 2015 to 205kt in 2025 (23% CAGR over the next ten years);

  • Grid scale battery storage – whilst at an early-stage, lithium-ion batteries have the capability to increase energy reliability in undeveloped grids, balance short term grid fluctuations, reduce grid congestion and load shift power requirements from peak periods. The introduction of the Tesla power wall has the potential to revolutionise this market as pricing becomes more affordable. Forecasts battery use in energy storage will grow to 50GWhpa by 2025, a 46% CAGR over 10 years. As a result, lithium demand will increase from virtually nil in 2015 to 34kt LCE in 2025; and

  • Consumer electronics – lithium-ion batteries remain the dominant technology for consumer electronic applications. This segment could raise annual consumption from 42kt in 2014 to 63kt LCE by 2020, representing a CAGR of 3.5%. This will be driven by the increased power intensity of mobile headsets as the developing world transitions to smart phones.

5 Deutsche Bank, Welcome to the Lithium-ion Age, Industry Report, 9 May 2016

Page 8

==> picture [596 x 105] intentionally omitted <==

Both high purity ‘battery grade’ lithium hydroxide and lithium carbonate are used in the production of cathode materials for lithium-ion batteries. Historically, the cathode chemistry employed in lithium-ion battery manufacturing predominately used lithium carbonate (45%[6] ). This was primarily due to the cost of producing lithium hydroxide from lithium carbonate which was typically sourced from brine or mineral converters. However, there is a growing preference for lithium hydroxide for use in the lithium-ion battery due to the superior energy storage characteristics, energy density and higher concentration of electrolyte in the battery.

Figure 4 outlines Roskill’s forecast for the cathode chemistry in a passenger vehicle battery. Nickel-manganese-cobalt (NMC) and nickel-cobalt-alumina (NCA) is emerging as the materials of choice of many car manufacturers. LFP is in widespread use in commercial vehicles and some passenger EVs, especially in China where a ban on other materials has now been lifted. Higher energy density cathode materials with mid/high nickel content are at the forefront of extended range EVs, and will require increasing amount of lithium hydroxide.

==> picture [287 x 313] intentionally omitted <==

Figure 4 : Roskill’s baseline forecast for changes in cathode chemistry for passenger vehicles. Source: Source: Robert Baylis, Roskill, 9th Lithium Supply and Markets Conference, 31st May 2017

6 Canaccord Genuity, Start Me Up – Electric Vehicle and grid storage to drive lithium demand, 17 May 2016

Page 9

==> picture [596 x 105] intentionally omitted <==

Due to these characteristics, lithium-ion batteries using lithium hydroxide cathodes are preferred for use in high performance applications such as electric vehicles. Given that the lithium-ion battery demand is expected to be dominated by electric vehicle uptake, it is expected that lithium hydroxide will display the highest relative demand growth of the various lithium compounds.

Through the Company’s ongoing discussions with potential offtake parties, recent feedback from consumers of lithium products has indicated a preference for the source material to be from a primary lithium source (either brine or spodumene). As Authier is a pure spodumene project, it anticipates its lithium chemicals will well regarded in the marketplace.

Pricing Assumptions

Current Chinese pricing according to Curran & Co is US$18,100/t for lithium carbonate and US$21,000/t for lithium hydroxide, well above the price assumptions used in the Concept Study (see Figure 5). The financial analysis assumed real long-term prices of US$10,200/t for highpurity ‘battery grade’ lithium carbonate and US$12,000/t for lithium hydroxide. The long-run pricing analysis reflects current estimates from a number of broking and investment firms – see Figure 6.

==> picture [472 x 283] intentionally omitted <==

Figure 5 : Chinese lithium carbonate and hydroxide prices over the last two years. Source: Curran & Co

Page 10

==> picture [596 x 105] intentionally omitted <==

==> picture [482 x 307] intentionally omitted <==

Figure 6 : Various independent price forecasts for lithium carbonate and hydroxide

Thermal Conversion of Authier Spodumene Concentrates

The Company recently completed a testing program, performed by SGS Lakefield in Canada, demonstrating the conversion of Authier lithium concentrate into traditionally extractable beta spodumene (a form of spodumene amenable to further processing) was achievable, at high conversion rates (see ASX release, Thermal Conversion of Authier Concentrates, 3 July). This provides confidence that lithium products could be produced from Authier concentrates.

Three flotation concentrate samples were transformed from alpha to beta spodumene in a decrepitating kiln. The lithium was the extracted from lithium sulphate through sulphuric acid roasting and then leached with water to be transformed into aqueous lithium sulphate - further purification is required to produce a lithium carbonate end product. Up to 96.8% of the lithium was recovered in the process from a 5.98% Li20 concentrate.

Processing Options

Lithium is sold in a number of forms. Lithium carbonate (Li2CO3) and lithium hydroxide (LIOH) are the largest lithium product markets based on volume, representing approximately 50% and 20% respectively (see Figure 7).

Page 11

==> picture [596 x 105] intentionally omitted <==

==> picture [429 x 348] intentionally omitted <==

Figure 7 : Distribution of Lithium sales per type of lithium form. Source: Canaccord

Spodumene concentrate from Authier needs to be refined into high purity lithium products before they can be used in the battery supply chain. The concentrate product is converted to lithium carbonate through an intensive thermal and hydrometallurgical process involving roasting, leaching, purifying and ion exchange.

Most conventional flow sheets to produce lithium carbonate or lithium hydroxide involve the production of lithium sulphate (see Figure 8). The process involves the comminution of the spodumene concentrate to reduce the particle size and then decrepitation and/or roasting (at 1080 degrees Celsius) using sulphuric acid, and leaching to produce lithium sulphate (or chloride depending on process). The lithium sulphate is then purified to remove impurities like aluminium, iron, calcium, etc.

The process route then varies depending on the end product being produced:

  • Lithium carbonate – the purified lithium sulphate liquor is evaporated to upgrade the lithium grade, and then soda ash is added to crystallise out the lithium carbonate. The lithium product is dried and micronized prior to bagging; and

  • Lithium hydroxide – lithium sulphate liquor is reacted with sodium hydroxide to form lithium hydroxide.

Page 12

==> picture [596 x 105] intentionally omitted <==

==> picture [469 x 342] intentionally omitted <==

Figure 8 : Conventional sulphate process routes for the production of lithium carbonate and lithium hydroxide. Source: Wave International

For this study, the Company has elected to pursue the traditional sulphation process route on the basis that:

  • The sulphation route has been proven, resources exist with knowledge of the process, and there are no IP barriers;

  • Existing producers utilise this process route, enabling Sayona to potentially partner with an established producer;

  • Major process package vendors exist who can guarantee process performance for key areas of the plant, de-risking process performance; and

  • Authier is ideally positioned to respond quickly to the increasing supply side of the market, therefore a lengthy technology development process does not align with this unique strategic positioning.

Further consideration to technological variations will be completed as part of a Pre-Feasibility Study.

Page 13

==> picture [596 x 105] intentionally omitted <==

Downstream Plant Site Selection

The selection of the downstream plant site is a critical decision, and one based on a multiple of factors, including:

  • Proximity to power;

  • Proximity to labour skilled in the operation of heavy industrial or chemical plants;

  • Proximity of the mine;

  • Proximity to infrastructure including roads, rail and ports;

  • Locally available reagents (e.g. sulphuric acid);

  • Environmental considerations; and

  • Designated use of the proposed site (i.e. land already zoned for heavy industrial use, or an existing industrial precinct).

At this stage, a site has not been selected but is likely to be within the Abitibi district given the close proximity to infrastructure, skilled labour, and key raw materials (see Figure 9). The district already has a fully permitted lithium mine, concentrator and lithium carbonate production facility (Quebec Lithium). The mine which was previously on care and maintenance due to financial troubles is now being re-commissioned (see www. na-lithium.com).

==> picture [489 x 312] intentionally omitted <==

Figure 9 : Location of the Authier mine relative to other critical infrastructure in the Abitibi district

Page 14

==> picture [596 x 105] intentionally omitted <==

Estimated Production

The study has evaluated the option of converting Authier’s annual spodumene concentrate production of nominally 100,000 tonnes per annum[7] (grading 5.75%), based on an 88% processing recovery, into:

  • 13,000 tonnes per year of lithium carbonate; or

  • 14,000 tonnes per year of lithium hydroxide.

The annual production estimates are derived from the Company’s JORC Mineral Resource estimate (see ASX release, Authier JORC Resource Expanded, 14 June 2017) tabulated below. The Mineral Resource Estimates declared on the June 14th 2017 has been used as the basis for the production target. This estimate was prepared by a Competent Person in the accordance with the 2012 JORC Code & Guidelines.

Table 4 - Authier JORC Mineral Resources Estimate (0.45% Li20 cut-off grade) Table 4 - Authier JORC Mineral Resources Estimate (0.45% Li20 cut-off grade) Table 4 - Authier JORC Mineral Resources Estimate (0.45% Li20 cut-off grade) Table 4 - Authier JORC Mineral Resources Estimate (0.45% Li20 cut-off grade)
Category Tonnes (Mt) **Grades %Li20 ** **Contained Li20 **
Measured 5.62 1.01% 56,762
Indicated 9.57 1.03% 98,571
Inferred 2.21 0.99% 21,879
Total 17.40 1.02% 177,212

For this Concept Study, the mine plan assumes that a Mineral Resource amount of 14.4 Mt grading 0.96 %Li2O is processed which represents 41% and 59% of the Measured and Indicated Resources, respectively. No Inferred Resources have been used in the mine plan.

The production target and financial information in this release are based on a Concept Study. The Concept Study referred to in this announcement is based on low-level technical and economic assessments, and is insufficient to support, or to update, an estimate of Ore Reserves or to provide assurances of an economic development case at this stage, or to provide certainty that the conclusions of the Concept Study will be realised.

Capital Cost Estimate

As part of the economic evaluation of the downstream project, a nominal capital cost estimate has been produced for both the lithium carbonate and lithium hydroxide options (note capital costs for the mine and concentrator operations are outlined in the February 2017 ASX Release, Authier PFS Demonstrates excellent returns and upside potential).

The basis of these estimates is Wave International standard Lithium Carbonate flowsheet, with database vendor equipment costs applied, which are then factored up to arrive at a total capital cost estimate. The flowsheet and equipment cost have then been adjusted to estimate the capital cost to produce Lithium Hydroxide.

7 See ASX release, Authier Pre-Feasibility Study, 17 February 2017

Page 15

==> picture [596 x 105] intentionally omitted <==

These estimates have then been benchmarked against nominal capital cost data which Wave has seen through its experience for other (larger capacity plants), and factored for comparative purposes to validate the concept study outcomes.

Table 5 – Capital Cost Estimate for the Lithium Carbonate and Hydroxide Plants (Approximate Values Derived from Scoping Study)

Table 5 – Capital Cost Estimate for the Lithium Carbonate and Hydroxide Plants
(Approximate Values Derived from Scoping Study)
Table 5 – Capital Cost Estimate for the Lithium Carbonate and Hydroxide Plants
(Approximate Values Derived from Scoping Study)
Plant Area
Lithium Carbonate
Lithium Hydroxide
In-directs
1.2
1.4
Mechanical equipment
49.0
54.0
Plant infrastructure
6.1
6.8
Earthworks
2.4
2.7
Concrete
9.8
10.8
Steelwork
12.2
13.5
Platework
2.4
2.3
Pipework
8.6
9.5
Electrics
12.2
13.5
EPCM
18.4
20.3
Total
122.5
135.0
Site infrastructure (allowance)
12.2
13.5
Variation and growth allowances
(concept study)
30.6
33.8
Total (C$)
165.3
182.3
Total (US$)
125.6
138.5

The capital cost has also been benchmarked on the basis of capital intensity compared to other proposed new lithium development projects around the world – see Figure 10.

Page 16

==> picture [596 x 105] intentionally omitted <==

==> picture [488 x 294] intentionally omitted <==

Figure 10 : Capital intensity of new lithium development projects. Source: Various public reports

Operating Cost Estimate

The operating cost estimate is based on a mass balance for a typical sulphation plant using Canadian cost estimates (see Table 6). At this stage, no laboratory testing, process modelling or flowsheets have been developed for the Authier project (note operating costs for the mine and concentrator operations are outlined in the February 2017 ASX Release, Authier PFS Demonstrates excellent returns and upside potential). This work will be completed during a Pre-Feasibility level study.

Changes to the flowsheet due to capital cost constraints, nature of the feed concentrate or other factors such as winter proofing, environmental requirements, and site location can all significantly affect operating costs and could impact the viability and direction of the project.

Page 17

==> picture [596 x 105] intentionally omitted <==

Table 6 outlines the key operating cost items expected for the Authier project.

Table 6 – Key Operating Cost (Source: WAVE International) 6 – Key Operating Cost (Source: WAVE International)
(Approximate Values Derived from Scoping Study)
Cost Item Consumption Notes
Concentrate 100kt/yr 5.75% 2017 Authier Pre-Feasibility Study
Gas 5 Gj/t concentrate Sourced locally from Gaz Metro
Sodium carbonate 2 t/t Li2CO3 Sourced locally
Sulphuric acid 0.25 t/t concentrate Available from Glencore Horne smelter
Limestone 0.1 t/t concentrate Sourced from Graymont
Sodium hydroxide 0.1 t/t Li2CO3 / 2 t/t LiOH Sourced from Univar
Electricity 7,500 Kw Readily available at 5c kWh
Direct employees 100 Local skilled available

==> picture [478 x 288] intentionally omitted <==

Figure 11 : Cash Operating Costs of new lithium development projects. Includes costs of concentrate. Source: Various public reports

Financial Analysis

The summary financial analysis is tabulated below and key non-operating and capital assumptions outlined below.

Page 18

==> picture [596 x 105] intentionally omitted <==

Table 7: Authier Downstream Processing Financial Highlights Table 7: Authier Downstream Processing Financial Highlights Table 7: Authier Downstream Processing Financial Highlights Table 7: Authier Downstream Processing Financial Highlights
(Approximate Values Derived from the Scoping Study)
Description Unit Lithium Carbonate
Lithium Hydroxide
Annual Production Capacity Tonnes 13,000 14,000
Ave Cash operating Costs* C$ per tonne 6,331 6,032
Ave Cash Operating Costs* US$ per tonne 4,812 4,585
Price forecast US$ per tonne 10,200 12,000
Initial Capital# C$ million 223 240
Total Capital# C$ million 284 301
Pre-tax NPV @ 9%DR C$ million 426 793
Pre-Tax IRR % 31 44
Exchange rate CAD$:US$ 0.76
* Cash Operating Costs include all costs including mining, processing, administration, royalties,
transport, and downstream processing Costs
# Capital expenditure includes all mine, concentrator and downstream processing costs

Summary of the main assumptions:

  1. Exchange rates - An exchange rate of 0.76 USD per CAD was used to convert the USD market price projections into Canadian currency. The sensitivity of the base case financial results to variations in the exchange rate was examined. Those cost components which include U.S. content originally converted to Canadian currency using the base case exchange rate were adjusted accordingly;

  2. Corporate tax - The current Canadian tax system applicable to Mineral Resource Income is used to assess the project’s annual tax liabilities. This consists of federal and provincial corporate taxes as well as provincial mining taxes. The federal and provincial corporate tax rates currently applicable over the project’s operating life are 15.0% and 11.9% of taxable income, respectively. The marginal tax rates applicable under the recently adopted mining tax regulations in Quebec (originally proposed as Bill 55, December 2013) are 16%, 22% and 28% of taxable income and depend on the profit margin. The analysis for the Concept Study and Mine/Concentrator PFS is done on a pre-tax basis;

  3. Discount rate – a discount rate of 9% has been applied to the NPV calculations;

  4. Inflation – All the forecasts within the financial analysis are on a real basis, i.e. with no inflation adjustments; and

  5. Royalties – The Quebec Government does not impose any royalties on mineral production. However, Authier is subject to a number of vendor royalty payments and a 2% Gross revenue royalty was assumed in the cut-off grade calculations and financial modelling undertaken for the PFS mine sales.

Page 19

==> picture [596 x 105] intentionally omitted <==

Sensitivity Analysis

Key sensitivities of the variables for the lithium carbonate and hydroxide plants are tabulated below.

Lithium Carbonate

Lithium Carbonate
Price Assumptions Sensitivities Table
Price sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV @ 9% - before tax 38,061,893
$
167,514,884
$
296,967,875
$
426,420,866
$
555,873,857
$
685,326,848
$
814,779,839
$
IRR - before tax 11% 18% 24% 31% 37% 42% 48%
Li2CO3 salesprice$USD 6,300
$
7,200
$
8,100
$
9,000
$
9,900
$
10,800
$
11,700
$
Reagents Assumptions Sensitivities Table
Reagents sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 462,779,888
$
450,660,214
$
438,540,540
$
426,420,866
$
414,301,192
$
402,181,518
$
390,061,844
$
IRR - before tax 32% 32% 31% 31% 30% 30% 29%
Total reagents cost CAD$/T Li2CO3 879
$
1,005
$
1,130
$
1,256.00
$
1,382
$
1,507
$
1,633
$
Energy Assumptions Sensitivities Table
Energy sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 442,087,961
$
436,865,596
$
431,643,231
$
426,420,866
$
421,198,501
$
415,976,136
$
410,753,771
$
IRR - before tax 31% 31% 31% 31% 30% 30% 30%
Total energycost CAD$/T Li2CO3 378
$
432
$
486
$
540.00
$
594
$
648
$
702
$
Downstream Opex (exc Reagents and energy) Sensitivities Table
Downstream Opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 469,145,003
$
454,903,624
$
440,662,245
$
426,420,866
$
412,179,487
$
397,938,108
$
383,696,728
$
IRR - before tax 33% 32% 31% 31% 30% 29% 29%
Opex cost CAD$/T Li2CO3 2,111
$
2,412
$
2,714
$
3,015.00
$
3,317
$
3,618
$
3,920
$
Mining and Concentration Opex Assumptions Sensitivities Table
Mine opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 517,336,487
$
487,031,280
$
456,726,073
$
426,420,866
$
396,115,659
$
365,810,452
$
335,505,245
$
IRR - before tax 35% 33% 32% 31% 29% 28% 26%
Mine and concentration opex CAD$/T conc 251
$
287
$
323
$
359.00
$
395
$
431
$
467
$
Concentrate Grade Assumptions Sensitivities Table
Con grade sensitivity 87.0% 91.3% 95.7% 100.0% 104.3% 108.7% 113.0%
NPV@9% - before tax 416,076,095
$
419,823,885
$
423,310,200
$
426,420,866
$
429,275,043
$
431,961,845
$
434,385,424
$
IRR - before tax 30% 30% 31% 31% 31% 31% 31%
Congrade 5.00% 5.25% 5.50% 5.75% 6.00% 6.25% 6.50%
Beneficiation Recovery Assumptions Sensitivities Table
Bene recovery sensitivity 90% 94% 98% 100.0% 103% 106% 110%
NPV@9% - before tax 319,895,316
$
362,499,888
$
405,112,063
$
426,420,866
$
458,387,322
$
490,357,539
$
532,990,093
$
IRR - before tax 26% 28% 30% 31% 32% 34% 36%
Recovery 72% 75% 78% 80% 82% 85% 88%
Development Capex Assumptions Sensitivities Table
Development Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 489,199,086
$
468,273,013
$
447,346,939
$
426,420,866
$
405,494,793
$
384,568,719
$
363,642,646
$
IRR - before tax 43% 38% 34% 31% 28% 26% 24%
Development capex CAD$ 182,127,860
$
208,146,126
$
234,164,392
$
260,182,657
$
286,200,923
$
312,219,189
$
338,237,455
$
Other Capex Assumptions Sensitivities Table
Other Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 434,544,166
$
431,836,399
$
429,128,632
$
426,420,866
$
423,713,099
$
421,005,333
$
418,297,566
$
IRR - before tax 31% 31% 31% 31% 31% 30% 30%
Development capex CAD$ 42,789,986
$
48,902,841
$
55,015,696
$
61,128,551
$
67,241,406
$
73,354,261
$
79,467,117
$

Page 20

==> picture [596 x 105] intentionally omitted <==

Lithium Hydroxide

Lithium Hydroxide
Price Assumptions Sensitivities Table
Price sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV @ 9% - before tax 274,915,447
$
447,793,846
$
620,672,244
$
793,550,642
$
966,429,040
$
1,139,307,438
$
1,312,185,836
$
IRR - before tax 22% 30% 37% 44% 50% 56% 62%
LiOH salesprice$USD 8,400
$
9,600
$
10,800
$
12,000
$
13,200
$
14,400
$
15,600
$
Reagents Assumptions Sensitivities Table
Reagents sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 841,506,182
$
825,521,002
$
809,535,822
$
793,550,642
$
777,565,462
$
761,580,282
$
745,595,102
$
IRR - before tax 46% 45% 44% 44% 43% 42% 42%
Total reagents cost CAD$/T LiOH 1,022
$
1,168
$
1,314
$
1,460.00
$
1,606
$
1,752
$
1,898
$
Energy Assumptions Sensitivities Table
Energy sensitivity
NPV@9% - before tax 809,682,614
$
804,305,290
$
798,927,966
$
793,550,642
$
788,173,318
$
782,795,994
$
777,418,670
$
IRR - before tax 44% 44% 44% 44% 43% 43% 43%
Total energycost CAD$/T LiOH 343
$
392
$
441
$
490.00
$
539
$
588
$
637
$
Downstream Opex (exc Reagents and energy) Sensitivities Table
Downstream Opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 838,730,476
$
823,670,531
$
808,610,587
$
793,550,642
$
778,490,697
$
763,430,753
$
748,370,808
$
IRR - before tax 45% 45% 44% 44% 43% 43% 42%
Opex cost CAD$/T LiOH 1,845
$
2,108
$
2,372
$
2,635.00
$
2,899
$
3,162
$
3,426
$
Mining and Concentration Opex Assumptions Sensitivities Table
Mine opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 884,466,263
$
854,161,056
$
823,855,849
$
793,550,642
$
763,245,435
$
732,940,228
$
702,635,021
$
IRR - before tax 47% 46% 45% 44% 43% 42% 40%
Mine and concentration opex CAD$/T conc 251
$
287
$
323
$
359.00
$
395
$
431
$
467
$
Concentrate Grade Assumptions Sensitivities Table
Con grade sensitivity 87.0% 91.3% 95.7% 100.0% 104.3% 108.7% 113.0%
NPV@9% - before tax 783,205,871
$
786,953,661
$
790,439,977
$
793,550,642
$
796,404,819
$
799,091,621
$
801,515,200
$
IRR - before tax 43% 43% 44% 44% 44% 44% 44%
Congrade 5.00% 5.25% 5.50% 5.75% 6.00% 6.25% 6.50%
Beneficiation Recovery Assumptions Sensitivities Table
Bene recovery sensitivity 90% 94% 98% 100.0% 103% 106% 110%
NPV@9% - before tax 648,371,602
$
706,437,124
$
764,510,850
$
793,550,642
$
837,113,839
$
880,681,096
$
938,776,810
$
IRR - before tax 38% 40% 43% 44% 45% 47% 49%
Recovery 72% 75% 78% 80% 82% 85% 88%
Development Capex Assumptions Sensitivities Table
Development Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 861,518,862
$
838,862,789
$
816,206,715
$
793,550,642
$
770,894,569
$
748,238,495
$
725,582,422
$
IRR - before tax 60% 53% 48% 44% 40% 37% 34%
Development capex CAD$ 168,098,000
$
192,112,000
$
216,126,000
$
240,140,000
$
264,154,000
$
288,168,000
$
312,182,000
$
Other Capex Assumptions Sensitivities Table
Other Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 802,054,365
$
799,219,790
$
796,385,216
$
793,550,642
$
790,716,068
$
787,881,493
$
785,046,919
$
IRR - before tax 44% 44% 44% 44% 44% 43% 43%
Development capex CAD$ 42,789,986
$
48,902,841
$
55,015,696
$
61,128,551
$
67,241,406
$
73,354,261
$
79,467,117
$

Permitting, Social and Environmental Considerations

A detailed environmental study was completed at the proposed Authier mine and concentrator site in 2013 by Dessau. An update of the environmental study commenced in June 2017 to gather relevant information about the fauna and the flora with the aim of mitigating the environment risks attributable to the operation which could be considered low. The program, coordinated by SNC-Lavalin, will continue over the next five months.

At this stage, no site has been selected for the proposed downstream plant site. The Company envisages building the downstream operation within an industrial or chemical park (not similar to the strategy of Nemaska Lithium which is building its downstream processing facilities in an old factory) and transport the concentrates from the mine to the plant. Once a site is selected the Company will begin its permitting, environmental and social activities.

Page 21

==> picture [596 x 105] intentionally omitted <==

Appendix – Project Design Criteria

Mineral Resource
Estimate
The Mineral Resource Estimates declared on June 14th2017 has been
used as a basis for the production target. This estimate was prepared
by a Competent Person in the accordance with the 2012 JORC
Code & Guidelines.
From this resource, the Concept Study assumes processing an
amount of 14.4 Mt grading at 0.96 %Li2O, composed of 41 % and 59 %
of Measured and Indicated material respectively.
Site Visit Mr. Gustavo Delendatti, the Competent Person for the Mineral
Resource Estimates as part of this study has been on a site visit. Mr
Delendatti has been involved with more than 8,000 metres of
diamond drilling at Authier and compiled a number of Mineral
Resource estimates for theproject.
Study Status The production target and financial information in this release are
based on a Concept Study. The Concept Study referred to in this
announcement is based on low-level technical and economic
assessments, and is insufficient to support, or to update, an estimate
of Ore Reserves or to provide assurances of an economic
development case at this stage, or to provide certainty that the
conclusions of the scopingstudywill be realized.
Capital Costs The following Table provides a summary of the pre-production
capital as estimated for the scoping study.
Estimation Margin of
Error
It is not possible to ascribe a single margin of error assessment over
the numbers in the Scoping Study. However, Capital and operating
cost have an estimate accuracy level of Class 4 per table on page
3.

Page 22

==> picture [596 x 105] intentionally omitted <==

Mining Factors or
Assumptions
The mining Scoping Study has been prepared based on a
conventional truck and hydraulic excavator operation, with an
average total material movement of 5.06 Mtpa over the mine life to
achieved the required 0.7 Mtpa mill feed rate. The main mining fleet
would compromise of 63 tonnes trucks loaded by a 140 tonne
excavator.
Mining cut-off grades were set to 0.60 %Li2O (years 1 to 3), 0.70 % Li2O
(year 4) and 0.30 %Li2O (years 5 and over). A mining dilution of 5.0 %
and no ore loss were considered. Mill feed is planned to be 14.4 Mt
grading at 0.96 %Li2O with a waste to ore stripping ratio of 6.4.
The mine plan, using a 5x5x5 meters block model, was based on
Whittle optimized pit shell combined with 3 internal cutbacks. Slope
angles of 55 degrees and 45 degrees were used for the North and
South walls respectively. Bench heights of 5.0 meters were also
assumed to calculate the mining operating costs.
The percentage of Measured and Indicated resources relate to the
production schedule is given in the Table below. Note that Inferred
material was not considered for the Concept Study.
-
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21
Mill Feed
Period
Mill Tonnage by Resource Category
Measured (South Pit)
Indicated (South Pit)
Indicated (North Pit)
Metallurgical Factors or
Assumptions
A recently completed a testing program, performed by SGS
Lakefield in Canada, demonstrating the conversion of Authier lithium
concentrate into traditionally extractable beta spodumene (a form
of spodumene amenable to further processing) was achievable, at
high conversion rates. This provides confidence that lithium
carbonate could be produced from Authier concentrates. Up to
96.8% of the lithium was recovered in the process from a 5.98% Li20
concentrate.

Page 23

==> picture [596 x 105] intentionally omitted <==

The study has evaluated the option of converting Authier’s annual
spodumene concentrate production of nominally 100,000 tonnes per
annum (grading 5.75%), based on an 88% processing recovery, into:

13,000 tonnes per year of lithium carbonate; or

14,000 tonnes per year of lithium hydroxide.
Environmental A detailed environmental study was completed at the proposed
Authier mine and concentrator site in 2013 by Dessau. An update of
the environmental study commenced in June 2017 to gather
relevant information about the fauna and the flora with the aim of
mitigating the environment risks attributable to the operation which
could be considered low. The program, coordinated by SNC-Lavalin,
will continue over the next five months.
Infrastructure The concentration plant will be located directly at the mine site.
Other standard infrastructure, such as administration office,
maintenance garage, etc., will also be erected at the mine site.
At this stage, no site has been selected for the proposed downstream
plant site. The Company envisages building the downstream
operation within an industrial or chemical park. Once a site is
selected, Sayona will begin its permitting, environmental and social
activities.
Costs The Tables below detail the key operating cost items as well of the
resulting average cash operating cost per tonne of lithium
compound produced over the life of the mine.

Page 24

==> picture [596 x 105] intentionally omitted <==

These costs were based on a combination of results from Sayona Pre-
FeasibilityStudyand currentpricingfor similarprojects.
Revenue Factors The financial analysis assumed real long-term prices of US$10,200/t
for high-purity ‘battery grade’ lithium carbonate and US$12,000/t for
lithium hydroxide. The long-run pricing analysis reflects current
estimates from a number of broking and investment firms. Current
Chinese pricing according to Curran & Co is US$18,100/t for lithium
carbonate and US$21,000/t for lithium hydroxide.
Market Assessment Lithium concentrate produced from Authier will be classed as
Chemical Grade specification. The principal markets for Chemical
Grade concentrates are battery, lubricants, aluminum smelting and
pharmaceuticals applications. The lithium market is currently
experiencing a major demand shift driven by the increasingly critical
role of the lithium-ion battery technology for storage applications in
the
automotive,
consumer
electronics
and
electricity
storage/distribution sectors. The electrochemistry of lithium based
batteries provide higher voltage, higher power density and lower
discharge rates with no memory effect, when compared to
competing technologies.
The lithium-ion battery or rechargeable market represented 42% of
total lithium consumption or 81,300 tonnes of Lithium Carbonate
Equivalent (“LCE”) in 2016, a year-on-year increase of 38%8. Most
industry commentators are forecasting the consumption of lithium in
volume terms will continue to be driven heavily by the rechargeable
battery sector. In a recent presentation, Roskill estimated that the
total consumption of lithium could approximately 5 times from
200,000 tonnes in 2016 to 1,000,000 tonnes LCE by 20269. Key macro
demand drivers include, carbon emissions legislation aimed at
reducing the reliance on fossil fuels, government incentives,
environmental concerns, technological advancements, and the
improvedproduct offerings utilisinglithium-ion batteries.

8 UBS, Lithium & Graphite: Driving Disruption, 15 June 2017

9 Source: Robert Baylis, Roskill, 9th Lithium Supply and Markets Conference, 31st May 2017

Page 25

==> picture [596 x 105] intentionally omitted <==

Economic The Concept Study has confirmed the technical and financial
viability of processing Authier spodumene concentrates into value
added battery products including, lithium carbonate and lithium
hydroxide.
The economic returns, modelled in real Canadian $ as at Q3 2017,
are driven by the following key assumptions:

Production to begin in 2020

DFS and engineering to be completed by 2019

Execution phase would last approximately 24 months

Commissioning period of 6 months
The Concept Study resulted in the following economic returns.
A discount rate of 9.0 % has been assumed for the model.
A sensitivity analysis, presented in the following figures, was produced
on the following main items:

Page 26

==> picture [596 x 105] intentionally omitted <==

Lithium Carbonate Scenario Lithium Carbonate Scenario Sensitivities Controls Sensitivities Controls Sensitivities Controls Sensitivities Controls Sensitivities Controls Sensitivities Controls Sensitivities Controls
Price Assumptions Sensitivities Table 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
Price sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV @ 9% - before tax M$ 38.06
$
167.51
$
296.97
$
426.42
$
555.87
$
685.33
$
814.78
$
IRR - before tax % 11% 18% 24% 31% 37% 42% 48%
Li2CO3 sales price $USD $ 6,300
$
7,200
$
8,100
$
9,000
$
9,900
$
10,800
$
11,700
$
Reagents sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax M$ 462.78
$
450.66
$
438.54
$
426.42
$
414.30
$
402.18
$
390.06
$
IRR - before tax % 32% 32% 31% 31% 30% 30% 29%
Total reagents cost CAD$/T Li2CO3 $ 879
$
1,005
$
1,130
$
1,256.00
$
1,382
$
1,507
$
1,633
$
Energy sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax M$ 442.09
$
436.87
$
431.64
$
426.42
$
421.20
$
415.98
$
410.75
$
IRR - before tax % 31% 31% 31% 31% 30% 30% 30%
Total energy cost CAD$/T Li2CO3 $ 378
$
432
$
486
$
540.00
$
594
$
648
$
702
$
Downstream Opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax M$ 469.15
$
454.90
$
440.66
$
426.42
$
412.18
$
397.94
$
383.70
$
IRR - before tax % 33% 32% 31% 31% 30% 29% 29%
Opex cost CAD$/T Li2CO3 $ 2,111
$
2,412
$
2,714
$
3,015.00
$
3,317
$
3,618
$
3,920
$
Mine opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax M$ 517.34
$
487.03
$
456.73
$
426.42
$
396.12
$
365.81
$
335.51
$
IRR - before tax % 35% 33% 32% 31% 29% 28% 26%
Mine and concentration opex CAD$/T conc $ 251
$
287
$
323
$
359.00
$
395
$
431
$
467
$
Con grade sensitivity 87.0% 91.3% 95.7% 100.0% 104.3% 108.7% 113.0%
NPV@9% - before tax M$ 416.08
$
419.82
$
423.31
$
426.42
$
429.28
$
431.96
$
434.39
$
IRR - before tax % 30% 30% 31% 31% 31% 31% 31%
Con grade % 5.00% 5.25% 5.50% 5.75% 6.00% 6.25% 6.50%
Bene recovery sensitivity 90% 94% 98% 100.0% 103% 106% 110%
NPV@9% - before tax M$ 319.90
$
362.50
$
405.11
$
426.42
$
458.39
$
490.36
$
532.99
$
IRR - before tax % 26% 28% 30% 31% 32% 34% 36%
Recovery $ 72% 75% 78% 80% 82% 85% 88%
Development Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax M$ 489.20
$
468.27
$
447.35
$
426.42
$
405.49
$
384.57
$
363.64
$
IRR - before tax % 43% 38% 34% 31% 28% 26% 24%
Development capex CAD$ M$ 182.13
$
208.15
$
234.16
$
260.18
$
286.20
$
312.22
$
338.24
$
Other Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax M$ 434.54
$
431.84
$
429.13
$
426.42
$
423.71
$
421.01
$
418.30
$
IRR - before tax % 31% 31% 31% 31% 31% 30% 30%
Development capex CAD$ M$ 182.13
$
208.15
$
234.16
$
260.18
$
286.20
$
312.22
$
338.24
$

Page 27

==> picture [596 x 105] intentionally omitted <==

Price Assumptions Sensitivities Table
Price sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV @ 9% - before tax 38,061,893
$
167,514,884
$
296,967,875
$
426,420,866
$
555,873,857
$
685,326,848
$
814,779,839
$
IRR - before tax 11% 18% 24% 31% 37% 42% 48%
Li2CO3 salesprice$USD 6,300
$
7,200
$
8,100
$
9,000
$
9,900
$
10,800
$
11,700
$
Reagents Assumptions Sensitivities Table
Reagents sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 462,779,888
$
450,660,214
$
438,540,540
$
426,420,866
$
414,301,192
$
402,181,518
$
390,061,844
$
IRR - before tax 32% 32% 31% 31% 30% 30% 29%
Total reagents cost CAD$/T Li2CO3 879
$
1,005
$
1,130
$
1,256.00
$
1,382
$
1,507
$
1,633
$
Energy Assumptions Sensitivities Table
Energy sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 442,087,961
$
436,865,596
$
431,643,231
$
426,420,866
$
421,198,501
$
415,976,136
$
410,753,771
$
IRR - before tax 31% 31% 31% 31% 30% 30% 30%
Total energycost CAD$/T Li2CO3 378
$
432
$
486
$
540.00
$
594
$
648
$
702
$
Downstream Opex (exc Reagents and energy) Sensitivities Table
Downstream Opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 469,145,003
$
454,903,624
$
440,662,245
$
426,420,866
$
412,179,487
$
397,938,108
$
383,696,728
$
IRR - before tax 33% 32% 31% 31% 30% 29% 29%
Opex cost CAD$/T Li2CO3 2,111
$
2,412
$
2,714
$
3,015.00
$
3,317
$
3,618
$
3,920
$
Mining and Concentration Opex Assumptions Sensitivities Table
Mine opex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 517,336,487
$
487,031,280
$
456,726,073
$
426,420,866
$
396,115,659
$
365,810,452
$
335,505,245
$
IRR - before tax 35% 33% 32% 31% 29% 28% 26%
Mine and concentration opex CAD$/T conc 251
$
287
$
323
$
359.00
$
395
$
431
$
467
$
Concentrate Grade Assumptions Sensitivities Table
Con grade sensitivity 87.0% 91.3% 95.7% 100.0% 104.3% 108.7% 113.0%
NPV@9% - before tax 416,076,095
$
419,823,885
$
423,310,200
$
426,420,866
$
429,275,043
$
431,961,845
$
434,385,424
$
IRR - before tax 30% 30% 31% 31% 31% 31% 31%
Congrade 5.00% 5.25% 5.50% 5.75% 6.00% 6.25% 6.50%
Beneficiation Recovery Assumptions Sensitivities Table
Bene recovery sensitivity 90% 94% 98% 100.0% 103% 106% 110%
NPV@9% - before tax 319,895,316
$
362,499,888
$
405,112,063
$
426,420,866
$
458,387,322
$
490,357,539
$
532,990,093
$
IRR - before tax 26% 28% 30% 31% 32% 34% 36%
Recovery 72% 75% 78% 80% 82% 85% 88%
Development Capex Assumptions Sensitivities Table
Development Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 489,199,086
$
468,273,013
$
447,346,939
$
426,420,866
$
405,494,793
$
384,568,719
$
363,642,646
$
IRR - before tax 43% 38% 34% 31% 28% 26% 24%
Development capex CAD$ 182,127,860
$
208,146,126
$
234,164,392
$
260,182,657
$
286,200,923
$
312,219,189
$
338,237,455
$
Other Capex Assumptions Sensitivities Table
Other Capex sensitivity 70.0% 80.0% 90.0% 100.0% 110.0% 120.0% 130.0%
NPV@9% - before tax 434,544,166
$
431,836,399
$
429,128,632
$
426,420,866
$
423,713,099
$
421,005,333
$
418,297,566
$
IRR - before tax 31% 31% 31% 31% 31% 30% 30%
Development capex CAD$ 42,789,986
$
48,902,841
$
55,015,696
$
61,128,551
$
67,241,406
$
73,354,261
$
79,467,117
$
Social At the social level, a stakeholder survey has been completed and a
communication strategy to present the project to the local
community and First Nations has been developed.
The community relations program will begin to be implemented in
the upcoming weeks. The preliminary program will address
governmental
consultation
obligations
and
make
sure
environmental, social and economic issues to be raised by
stakeholders are integrated into the project development. A list of
potential constraints to the mining development, both from an
objective perspective and based on the consultant’s experience in
the area will be prepared. Finally, a working sequence will also be
developed in order to start building relationships with relevant
stakeholders
and
rights
holders
(municipalities,
municipality,
Abitibiwinni First Nation, neighbours, and land users).
Classification Resources were classified in accordance with the Australian Code
for the Reporting of Explorations Results, Mineral Resources and Ore
Reserves (JORC Code, 2012 Edition). The classification of Mineral
Resources was completed based on the geological complexity,
estimation performance, number of drill samples, drill hole spacing

Page 28

==> picture [596 x 105] intentionally omitted <==

and sample distribution. The Competent Person is satisfied that the
results appropriately reflect his view of the deposit.
Audit or Review The content of the desktop study, prepared by Wave international,
was review internally. No material issues were identified during the
process.

Page 29

==> picture [596 x 105] intentionally omitted <==

For more information, please contact:

Corey Nolan

Chief Executive Officer

Phone: +61 (7) 3369 7058

Email: [email protected]

Sayona Mining Limited is an Australian, ASX-listed (SYA), company focused on sourcing and developing the raw materials required to construct lithium-ion batteries for use in the rapidly growing new and green technology sectors.

The Company’s primary focus is the development of the advanced stage Authier lithium project in Quebec, Canada. Authier mineralisation is hosted in a spodumene-bearing pegmatite intrusion with more than 22,000 metres of drilling in 139 holes.

The Authier JORC (2012) compliant Ore Reserve and Mineral Resource estimates are tabulated below at a 0.45% Li20 cut-off grade.

Authier JORC Ore Reserve Authier JORC Ore Reserve Estimate (0.45% Li20 cut-off grade) Estimate (0.45% Li20 cut-off grade)
Category Tonnes(Mt) Grades(%Li20) **Contained Li20 **
Proven Reserve 4.9 0.97% 47,821
Probable Reserve
5.3
1.06% 55,904
Total Reserves 10.2 1.02% 103,725
Note: The Ore Reserve is based on the February 2017 Mineral Resource estimate and February 2017
FeasibilityStudy
Authier JORC Mineral Resources Estimate(0.45% Li20 cut-offgrade) Estimate(0.45% Li20 cut-offgrade)
Category Tonnes(Mt) Grades(% Li20) **Contained Li20 **
Measured 5.62 1.01% 56,762
Indicated 9.57 1.03% 98,571
Inferred 2.21 0.99% 21,879
Total Resources 17.4 1.02% 177,212

Authier is amenable to simple open-cut mining and processing methods, and is situated in close proximity to development infrastructure. The Company is currently completing an updated Pre-feasibility Study, due for completion in 3Q0217, prior to the commencement of a Definitive Feasibility Study which is planned to be completed in early 2018.

In addition, the Company controls a portfolio of lithium and graphite exploration projects in Western Australia.

Reference to Previous ASX Releases

This document refers to the following previous ASX releases:

  • Expanded Authier JORC Resource, 14 June 2017

  • Authier maiden JORC Ore Reserve estimate, 17 February 2017

  • Authier Pre-Feasibility Study” 17 February 2017

Page 30

==> picture [596 x 105] intentionally omitted <==

The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and all material assumptions and technical parameters continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcements.

FORWARD LOOKING STATEMENTS

This announcement contains certain forward looking statements. Such statements are only predictions, based on certain assumptions and involve known and unknown risks, uncertainties and other factors, many of which are beyond Sayona Limited’s control.

Actual events or results may differ materially from the events or results expected or implied in any forward looking statement in this announcement. The inclusion of such statements should not be regarded as a representation, warranty or prediction with respect to the accuracy of the underlying assumptions or that any forward looking statements will be or are likely to be fulfilled. Sayona Limited undertakes no obligation to update any forward-looking statement to reflect events or circumstances after the date of this presentation (subject to securities exchange disclosure requirements). The announcement has been prepared by Sayona Mining Limited. The document contains background information about Sayona Mining and is current at the date of this announcement. The announcement is in summary form and does not purport to be all inclusive or complete.

The information in this presentation does not take into account the objectives, financial situation or particular needs of any person. Nothing contained in this presentation constitutes investment, legal, tax or other advice. Recipients should seek professional advice when deciding if an investment is appropriate. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments. To the full extent of the law, Sayona Mining Ltd, its officers, employees, agents and advisors do make any representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of any information, statements, opinion, estimates, forecasts or other representations contained in the announcement. No responsibility for any errors or omissions from the announcement arising out of negligence or otherwise is accepted.

Page 31