ASX ANNOUNCEMENT 4 MARCH 2021

==> picture [175 x 273] intentionally omitted <==

Butcherbird Pre-Commissioning Activities Commenced

  • Pre-commissioning activities have commenced at the Butcherbird mine site.

  • Electrical systems and instrument loop checking underway.

  • Power station installation and power up scheduled for later this week.

  • First ore processing planned for the second half of March 2021.

Element 25 Limited ( E25 or Company ) ( ASX:E25 ) is pleased to confirm that the delivery of the first stage of a planned multi-stage development at the Company’s 100% owned world class Butcherbird Project ( Project ) continues with completion on track and in line with the original target of Quarter 1, 2021.

Pre-commissioning activities have commenced on schedule with electrical systems and instrument loop checking underway utilising temporary power. Sequential rotational checking of drives is expected to commence today. The power station is due to arrive at site today, with installation and power up scheduled for later in the week.

This is the first stage of a multi-stage development strategy for the Project, which will be expanded to produce high purity manganese sulphate monohydrate ( HPMSM ) for electric vehicle ( EV ) batteries to power the global transition away from fossil fuel powered mobility.

Manganese is emerging as an increasingly important ingredient for EV batteries, with potential supply constraints for nickel and cobalt forcing battery manufacturers to look to high manganese cathodes to produce the vast amount of cathode material required by the EV industry in coming years.[1]

The Project is ideally placed to feed this potential demand, with advanced flowsheet development work undertaken in 2019 and 2020 confirming a simple, unique, ambient temperature and atmospheric pressure leach process for E25 ores which, when combined with offsets, will target the world’s first Zero Carbon Manganese[TM] for EV cathode manufacture[2] .

1 https://thenextavenue.com/2021/01/22/svolt-opens-orders-for-its-nmx-nickel-manganese-batteries/

2 Reference: Company ASX release dated 12 February 2019.

COMPANY SNAPSHOT

Market Summary Board of Directors: ASX code: E25 Seamus Cornelius Chairman Shares on issue: 133M Justin Brown MD Shares price: $1.92 John Ribbons NED

Element 25 Limited is developing the world class Butcherbird Manganese Project in Western Australia to produce high quality manganese concentrate and high purity manganese products for traditional and new energy markets.

Element 25 Limited

==> picture [595 x 69] intentionally omitted <==

==> picture [511 x 179] intentionally omitted <==

About the Butcherbird Manganese Project

The Butcherbird Manganese Project is a world class manganese resource with current JORC resources in excess of 263 Mt of manganese ore[3] . The Company completed a Pre-Feasibility Study (PFS) with respect to developing the deposit to produce manganese concentrate for export to generate early cashflow with a modest capital requirement[4] . The outstanding economics and low capital hurdle of less than A$17 million for the first stage of development will allow the Company to develop the project in a relatively short timeframe. The delivery of this first stage of production is fully funded and already underway.

The PFS also highlighted the Project has the potential for significant growth beyond the initial Stage 1 production volumes (the studies examined the potential for a 2X and 3X expansion to Stage 1 within 12 months of initial commissioning) and the Company expects to expedite the expansion of the Project once Stage 1 is fully operational. In addition to the concentrate export business, the Company has completed extensive research & development and laboratory test work into the production of high purity manganese products including battery grade manganese sulphate ( HPMSM ) and High Purity Electrolytic Manganese Metal ( HPEMM ). The work has highlighted that the Butcherbird ores are highly amenable to an ambient temperature, atmospheric pressure leach process, resulting in a very efficient extraction of the manganese into solution, the key requirement for the cost effective and sustainable production of HPMSM and HPEMM.

The Project straddles the Great Northern Highway and the Goldfields Gas Pipeline, providing turnkey logistics and energy solutions. The Company plans to integrate renewable energy into the power solution over time to target a zero-carbon

3 Reference: Company ASX release dated 17 April 2019.

4 Reference: Company ASX release dated 3 December 2020

Element 25 Limited

==> picture [595 x 69] intentionally omitted <==

footprint for the Project, which is expected to also reduce energy costs. A cleaner, lower carbon flowsheet and high penetration renewable energy will place Butcherbird at the forefront of sustainable high purity manganese production.

Mineral Resources

Category Tonnes (Mt) Mn (%) Si (%) Fe (%) Al (%)
Measured 16 11.6 20.6 11.7 5.7
Indicated 41 10.0 20.9 11.0 5.8
Inferred 206 9.8 20.8 11.4 5.9
Total 263 10.0 20.8 11.4 5.9

Notes:

• Reported at a 7% Mn cut-off for the Measured and Indicated categories and an 8% Mn cut-off for the Inferred categories. • All figures rounded to reflect the appropriate level of confidence (apparent differences may occur due to rounding)

Mining Reserve

Based on the results of the Pre-Feasibility Study completed in May 2020, E25 has published a Maiden Ore Reserve for the Project of 50.55Mt in the Proved and Probable categories[5] .

Classification Tonnes (Mt) Grade (Mn%) Contained Mn (Mt) Recovered Mn (Mt)
Proved 14.4 11.5 1.65 1.35
Probable 36.2 9.8 3.56 2.92
Total 50.6 10.3 5.21 4.27

Justin Brown

Managing Director

Company information, ASX announcements, investor presentations, corporate videos and other investor material in the Company’s projects can be viewed at: http://www.element25.com.au.

Competent Persons Statement

The company confirms that in the case of estimates of Mineral Resource or Ore Reserves, all material assumptions and technical parameters underpinning the estimates in the market announcements dated 17 April 2019 and 19 May 2020 continue to apply and have not materially changed. The company confirms that the form and context in which the competent person’s findings are presented has not been materially modified from the original market announcements.

The information in this report that relates to Exploration Results and Exploration Targets is based on information compiled by Mr Justin Brown who is a member of the Australasian Institute of Mining and Metallurgy. At the time that the Exploration Results and Exploration Targets were compiled, Mr Brown was an employee of Element 25 Limited. Mr Brown is a geologist and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Brown consents to the inclusion of this information in the form and context in which it appears in this report.

This announcement is authorised for market release by Element 25 Limited’s Board of Directors.

5 Reference: Element 25 Limited Reserve Statement lodged with ASX 19 May 2020.