DART MINING NL — Investor Presentation 2013
Jul 31, 2013
64792_rns_2013-07-31_31ed32b5-054e-40b0-b927-ae0c12302dd8.pdf
Investor Presentation
Open in viewerOpens in your device viewer
==> picture [650 x 92] intentionally omitted <==
Managing Director
July 2013
1
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
DISCLAIMER
----- End of picture text -----
The information contained in this document is disclosed to you by Dart Mining NL (ACN 119 904 880) (the "Company").
Nothing in this document shall form the basis of any contract or commitment, or constitutes investment, financial product, legal, tax or other advice. The information in this document does not take into account your investment objectives, financial situation or particular needs.
The Company has prepared this document and is not aware of any errors in this document, but does not make any recommendations or warranty, express or implied concerning the accuracy of any forward looking statements or the likelihood of achievement or reasonableness of any assumptions, forecasts, prospects or returns contained in the information. Such assumptions, forecasts, prospects or returns are by their nature subject to significant uncertainties and contingencies.
This document is intended to provide background information only and does not purport to make any recommendation upon which you may reasonably rely without taking further and more specific advice. Potential investors should make their own decision whether to purchase any share in the Company based on their own enquiries. Potential investors are advised to seek appropriate independent advice, if necessary, to determine the suitability of the investment. An investment in the Company should be considered speculative.
This document is not a prospectus or other disclosure document.
2
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
DTM CASHED UP + MOVING FORWARD
----- End of picture text -----
Cash ~$6.2M[1] with burn rate ~$240,000 / month PLUS $4.7M 2[nd] Red Kite Tranche[2] PLUS FY13 R&D refund Vic. Govt re-affirming it’s commitment to resource development Single contact point, project facilitation, statutory timeframes
Strategy 1 – Progress Unicorn Prefeasibility
Strategy 2 – Growth DTM Tenements NE Vic – Gold + Porphyry's
Strategy 3 – Growth M&A – Gold and Base Metals
1 As at 7 July 2013 2 Refer ASX announcement 12 March 13. Second tranche subject to key milestones
3
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
DTM INVESTMENT HIGHLIGHTS
----- End of picture text -----
-
Unicorn deposit – potentially a long life Mo + Cu + Ag porphyry mine
-
Red Kite (US metal merchant) invests upto A$10M – detailed due diligence
-
Prefeasibility underway – fully funded, as is regional exploration
-
High grade from surface – very low strip ratio / available infrastructure
-
Very positive metallurgy – no known native title, flora or fauna issues
-
NPV $255M initial 14 years (100% equity) – +6yr life[1] adds $50 - 70M NPV
-
• 2.5 year payback – pretax IRR 27% (discount rate 10% / 100% equity) • $304M capital – all up cash cost @ $8/lb[2] Mo (onsite, logistics, smelting)
1 2 Still to be geologically defined and included in a JORC Resource, Net of credits
4
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
ABOUT RK MINE FINANCE – RED KITE
----- End of picture text -----
-
RK Mine Finance specializes in providing development, acquisition and bridge financing to miners of precious & non-ferrous metal ( www.RKMineFinance.com )
-
Red Kite Group – ~$3.5B under management[1] (~$1.7B mine finance exclusively)
-
Large global metal merchant – NY, London, Shanghai, HK, Sydney, Bermuda
-
Red Kite $10M DTM investment[2] – major confidence boost for Unicorn
-
–
-
Red Kite rewarded from production 3% NSR royalty @A$8.5M (2 tranches)[3]
-
–
-
Equity A$1.5M (2 tranches) invested[2] 10% premium to 20 day VWAP
-
Currently ~4.5% shareholding – will move to ~9% with 2[nd] tranche
-
Red Kite detailed due diligence – confidence in Unicorn & management
==> picture [114 x 53] intentionally omitted <==
==> picture [114 x 53] intentionally omitted <==
$8.6M (AUD) $50M Equity, Loan Equity and Off and Off take take Agreement Agreement (August 2012) (November 2012 )
==> picture [140 x 99] intentionally omitted <==
==> picture [114 x 54] intentionally omitted <==
==> picture [114 x 54] intentionally omitted <==
$20M Equity, $20M Royalty Royalty and Off Agreement take Agreement (February 2013) (November 2012 )
1 2 3 30 April 2013 Refer ASX announcement 12 March 13 Second tranche subject to meeting key milestones
5
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
HIGH GRADE ZONES CONTINUE AT DEPTH
----- End of picture text -----
==> picture [244 x 134] intentionally omitted <==
- Additional Rhyolitic Pulse showing UST - Pulse centre to the east of drilling.
==> picture [244 x 144] intentionally omitted <==
Coarse visible Mo within radial veins showing strong Potassic alteration halos.
==> picture [392 x 409] intentionally omitted <==
6
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
SCOPING STUDY PRODUCTION PARAMETERS
----- End of picture text -----
-
Initially open cut mine – potential to move to underground
-
Residential mine within Corryong Community – not fly in fly out
-
–
-
High grade from surface and outcrops very low strip ratio
-
Clear / Mine / Crush / Float / Tailings – simple separation process
-
~
-
Targeting 20 year mine life – 10Mtpa ore / 30Ktpa concentrate
-
51% Mo Con (~3ktpa[1] Mo) – 23% Cu/Ag Con (~6Ktpa[1] Cu,~0.8Moz Ag[1] )
-
Export in containers – truck to Albury / train to Melbourne Port
-
Buy local - employ local - live local – community support is key
1Average First 10 Years of Production from Scoping Study
7
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
PRE-FEASIBILITY STUDY PARTNERS
----- End of picture text -----
==> picture [86 x 30] intentionally omitted <==
Ecology & Cultural Heritage - Biosis
are expert consultants in the field of Environmental, Ecology (fauna & flora) and Cultural Heritage Management throughout Australia
==> picture [92 x 78] intentionally omitted <==
Environmental and Approvals -
GHD are a longstanding Global consultancy firm specialising in Environmental Management
==> picture [86 x 25] intentionally omitted <==
Metallurgical Test Work -AMML Pty Ltd, an established minerals testing laboratory specialising in flotation test work
==> picture [92 x 31] intentionally omitted <==
Water Management - URS is an Industry leader in sustainable water resource practices and technologies
==> picture [86 x 71] intentionally omitted <==
Mine Design - Mining Plus are global mining consultants with a proven track record of delivering innovative & practical results
==> picture [91 x 51] intentionally omitted <==
Tailings Storage & Management -
ATC Williams are specialist consultants for the design, transport, storage & management of mine tailings
==> picture [86 x 32] intentionally omitted <==
Plant Design and Prefeasibility Study - Lycopodium is a leading Australian engineering & project management group, developing & commissioning major resource projects worldwide
==> picture [91 x 48] intentionally omitted <==
Power Supply - Parsons
Brinkerhoff is a Leading Provider of engineering & project management services to the global power/energy Market
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
INDICATIVE PATHWAY TO PRODUCTION
----- End of picture text -----
==> picture [720 x 437] intentionally omitted <==
1Unicorn is not in production and there is no certainty that the pathway to production will occur
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
EMPLOYMENT OPPORTUNITIES
----- End of picture text -----
-
Approximately 85 full time jobs when in operation
-
Trades, equipment & plant operators, supervisors and warehousing
-
Geology, mining, processing, metallurgy, surveying, accounting
-
Only essential employees onsite - other staff based in Corryong
-
Not fly in fly out - full residential mine
-
Many support roles in supplying services to the mine
-
Transport, consumables, fuel, light vehicle maintenance, services
-
Employ and train people from the community
-
Specialist positions to relocate with families to Corryong or nearby towns
-
Construction of the mine and plant will take about 18 months
-
Over this time there will be up to 100 contractors working on site
-
Some will be specialist contractors from out of town
-
Town will benefit from the supply of accommodation, food & transport
10
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
ENVIRONMENTAL EFFECTS STATEMENT
----- End of picture text -----
-
In Victoria, environmental assessment of the potential environmental impacts or effects of a proposed development may be required under the Environmental Effects Act 1978
-
When a proposed project could potentially have significant environmental effects, a written referral is sent to the Minister for Planning requesting a decision on whether an Environmental Effects Statement (EES) is required
-
Dart will submit the referral document on 2[nd] August
-
The Minister for Planning will make a decision within 20 business days on whether the project requires an EES
-
If the Minister decides that an EES is required, the project proponent is responsible for preparing the EES and undertaking the necessary investigations
==> picture [52 x 36] intentionally omitted <==
11
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
WHAT IS INCLUDED IN AN EES?
----- End of picture text -----
-
A description of the proposed development
-
An outline of public and stakeholder consultation
-
A description of the existing environment that may be affected
-
Predictions of significant environmental effects of the project
-
Proposed measures to avoid, minimise or manage adverse environmental affects
-
A proposed program for monitoring and managing environmental effects during the project implementation
12
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
STUDIES LIKELY TO BE COMPLETED
----- End of picture text -----
-
Risk assessment
-
Cultural heritage
-
Soils and geochemistry
-
Air quality
-
Surface water, flooding and drainage
-
Noise and vibration
-
Visual
-
Biodiversity and habitat
-
Social and economic
-
Groundwater
-
Road, traffic and transport
-
Water use
- Rehabilitation and closure
-
Greenhouse gases and
-
energy consumption
-
Land use
==> picture [52 x 36] intentionally omitted <==
13
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
COMMUNITY INVOLVEMENT
----- End of picture text -----
- Dart Mining is committed to involving the community in the EES
process
-
Dart Mining will further develop their Consultation Plan to inform individuals and groups who could be affected and provide opportunities for input
-
Consultation will help Dart Mining to identify issues of concern and potential effects, as well as get feedback from stakeholders on project options or potential mitigation measures
-
Members of the public can also participate in the EES process by providing written comments on the draft scoping requirements and the final EES
14
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
ECOLOGICAL ASSESSMENT - BIOSIS
----- End of picture text -----
-
Biosis Wangaratta office is managing the Ecological and Cultural Heritage aspects of the Prefeasibility Study for Dart Mining
-
Biosis provide expert consulting services in ecology and cultural heritage. They are industry leaders and have 30 years experience throughout Victoria and south eastern Australia
-
Victorian Desalination Project
-
Peninsula Link
-
Chiltern Quarry
-
Northern Victoria Irrigation Renewal Project
-
Wind farms in western
-
Barnawartha LOGIC Hub
Victoria
==> picture [91 x 26] intentionally omitted <==
15
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
KEY LEGISLATION & GOVERNMENT POLICY
----- End of picture text -----
-
Commonwealth Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)
-
Victorian Flora and Fauna Guarantee Act 1988 (FFG Act)
-
Victorian Environmental Effects Act 1978
-
Victorian Planning and Environment Act 1987 (including regulations for permitted removal of native vegetation)
Biosis determines which species and communities are within the investigation area, as well as the potential for any listed species and communities listed under the EPBC and FFG Acts. Biosis then works with Dart Mining to design the project to avoid or mitigate impacts in line with legislation and policy
==> picture [91 x 26] intentionally omitted <==
16
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
SURVEY AIMS AND METHODOLOGY
----- End of picture text -----
-
Database searches to determine potential for listed species and communities
-
General field survey (collecting lists of species, assessing vegetation, habitat type and quality)
-
Map suitable habitat for listed flora species (survey during spring flowering season)
==> picture [217 x 182] intentionally omitted <==
Australian Owlet-nightjar
-
Assess aquatic habitat values
-
Use remote camera technology and hair tubes to target detection of Spot-tailed Quoll and Smoky Mouse (both listed under the EPBC Act)
-
Call playback to detect large forest owls
-
Spotlighting for nocturnal species
==> picture [91 x 26] intentionally omitted <==
17
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
FIELD SURVEY RESULTS - FAUNA
----- End of picture text -----
-
Majority of fauna habitat types within the study area are common and widespread in the region (drier forests and woodlands)
-
Most of the fauna species detected during survey are common, and typical of the habitat types present
-
White-footed Dunnart was recorded (listed under the FFG Act)
-
Some fauna species on the DEPI Advisory list were recorded (eg. Lace Goanna)
-
The EPBC and FFG-listed species Spot-tailed Quoll and Smoky Mouse were not recorded, and are now considered to have a low likelihood of occurrence in the investigation area
-
The aquatic habitats near the mine, plant and tailings storage facility are unlikely to support listed aquatic species
==> picture [91 x 26] intentionally omitted <==
18
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
SOME FAUNA SPECIES IDENTIFIED
----- End of picture text -----
Black Wallaby
==> picture [225 x 127] intentionally omitted <==
==> picture [225 x 127] intentionally omitted <==
----- Start of picture text -----
DRILL RIG
----- End of picture text -----
Feral Cat
Long-nosed Bandicoot
==> picture [225 x 127] intentionally omitted <==
WhiteWinged Chough
==> picture [225 x 127] intentionally omitted <==
Eastern Yellow Robin
==> picture [95 x 23] intentionally omitted <==
==> picture [225 x 127] intentionally omitted <==
Superb Lyrebird
==> picture [225 x 127] intentionally omitted <==
19
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
FIELD SURVEY RESULTS - FLORA
----- End of picture text -----
==> picture [301 x 346] intentionally omitted <==
Eyebright Euphrasia sp.
-
The majority of the vegetation types within the investigation area are common widespread, and have a conservation status of ‘least concern’
-
The investigation area may contain two species listed under the EPBC and FFG Acts (Purple Eyebright and Austral Toad-flax).
-
Targeted survey will be undertaken for these species in spring
==> picture [91 x 26] intentionally omitted <==
20
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
ECOLOGICAL ASSESSMENT - SUMMARY
----- End of picture text -----
-
Preliminary flora and fauna findings are being reviewed by the regulatory authorities
-
Further survey’s will be undertaken in spring
-
Cultural heritage studies will be undertaken in 2014
-
Biosis will provide ongoing objective advice to ensure compliance with legislation and to minimise impacts to biodiversity during the construction and mine operation
-
The community will have the opportunity for input through the EES process
==> picture [91 x 26] intentionally omitted <==
21
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
TAILINGS STORAGE OPTIONS
----- End of picture text -----
-
ATC Williams (specialist tailings engineers) retained to develop a tailings and water management solution for Unicorn
-
Five tailings storage options investigated
-
Teapot Creek - adjacent to Mt Unicorn
-
Bunroy Creek - located south-east of Mt Unicorn in a heavily forested valley close to Bunroy Station
-
Biggara Creek - situated on privately owned farm land immediately to the north of Mt Unicorn
-
Bullocky Creek - situated to the west of Mt Unicorn on a tributary of Thowgla Creek
-
Bull Paddock Creek - immediately south-west of Mt Unicorn, also a tributary of Thowgla Creek
==> picture [76 x 35] intentionally omitted <==
22
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
TAILINGS SITE SELECTION PARAMETERS
----- End of picture text -----
-
Potential to store life of mine tailings production (200Mt)
-
High storage efficiency - ratio of storage volume to wall height
-
Community, cultural heritage and societal considerations
-
Site vegetation and current land use
-
Tailings discharge and return water management
-
Sources of embankment construction materials
==> picture [76 x 35] intentionally omitted <==
23
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
TAILINGS STORAGE OPTIONS
----- End of picture text -----
==> picture [682 x 416] intentionally omitted <==
24
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
PROPOSED TAILINGS STORAGE SITE
----- End of picture text -----
==> picture [692 x 411] intentionally omitted <==
25
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
BULL PADDOCK CREEK - PREFERRED SITE
----- End of picture text -----
-
Efficient site in terms of ratio of wall height to storage volume
-
Relatively isolated location with minimal visual impact
-
Low grade regrowth forest rather than prime agricultural land
-
No known cultural heritage constraints – detailed survey still to be completed
-
Least impact from a community, societal and environmental impact
-
Viable sources of rock fill material for embankment construction
==> picture [76 x 35] intentionally omitted <==
26
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
BULL PADDOCK CREEK - PREFERRED SITE
----- End of picture text -----
-
Tailings dam will block run off from Bull Paddock creek
-
It will be a NIL DISCHARGE Tailings dam ie no runoff from tailings into Thowgla creek
-
Investigating the viability of diverting part of the southern Bull Paddock creek catchment to maintain environmental flow
-
Bull Paddock creek catchment will provide make up water to mine
-
More detailed studies are underway with a focus on understanding impacts on Thowgla creek
-
Thowgla creek and Bull Paddock creek will be monitored for both flow rate and water quality
27
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
SUMMARY AND KEY TAKE AWAYS
----- End of picture text -----
-
Unicorn deposit – potentially a long life Mo + Cu + Ag porphyry mine
-
Red Kite investing up to A$10M into Unicorn – detailed due diligence
-
Prefeasibility underway – fully funded, with cash at bank $6.2M[1 ]
-
Approvals process has commenced – EES referral to be submitted
-
Community will have concerns – tailings / water / traffic / habitat
-
Dart committed to working with the community – further meetings
-
Environmental effects statement – ensures extensive community input
-
Residential mine not fly in fly out – 85 direct employment opportunities
1 As at 7 July 2013
28
==> picture [720 x 78] intentionally omitted <==
----- Start of picture text -----
FURTHER DISCLAIMER
----- End of picture text -----
Economic Potential
The Unicorn project remains at an early stage of planning and assessment and there are risks associated with the estimates of key parameters (including but not limited to further metallurgical test work to advance mineral processing design and the need to accurately cost the required tailings storage solution for the project). However, the data is sufficient to allow assessment to a scoping study level of accuracy and no technical issues have been identified at this stage that would prevent the project from advancing to a Pre-Feasibility study.
A key conclusion of the scoping study is that the project is considered to have positive economic potential.
Further Studies
Further studies are now required to increase confidence in the projects parameters and economics. In the coming months, Dart Mining will look to initiate a pre-feasibility study and to assess opportunities to extend the mine life, improve project economics and look at the potential of underground mining.
29
9
~~in the report of the matters based on his information in the form and context in which it appears.~~
30