AI Terminal

MODULE: AI_ANALYST
Interactive Q&A, Risk Assessment, Summarization
MODULE: DATA_EXTRACT
Excel Export, XBRL Parsing, Table Digitization
MODULE: PEER_COMP
Sector Benchmarking, Sentiment Analysis
SYSTEM ACCESS LOCKED
Authenticate / Register Log In

C.N.T.E.E. Transelectrica

Regulatory Filings Nov 12, 2019

2299_iss_2019-11-12_f67791b0-67d7-4f45-82ce-d88d3b9bad87.pdf

Regulatory Filings

Open in Viewer

Opens in native device viewer

To the: Bucharest Stock Exchange – Department of Operations Issuers Regulated Markets

Financial Supervision Authority - General Directorate Supervision - Issuers Division

Date of the report: November 12, 2019

Name of Issuer Company: CNTEE TRANSELECTRICA SA, managed under two-tier system Headquarters: Boulevard Gheorghe Magheru 33, Bucharest 1 Working location: Str. Olteni 2-4, Bucharest 3 Phone / fax numbers: 021 30 35 611 / 021 30 35 610 Single registration Code: 13328043 LEI code: 254900OLXCOUQC90M036 Number in the Trade Register: J40/8060/2000 Share capital subscribed and paid: 733.031.420 RON Regulated market where the issued securities are transacted: Bucharest Stock Exchange

COMMUNIQUÉ

The National Power Grid Company Transelectrica SA informs the shareholders and investors about its signing the execution contracts for the project of common interest "Internal line between Cernavoda and Stalpu" financed from European funds under the "Europe Interconnection Mechanism".

After the procurement procedure Transelectrica signed execution contracts for 3 of the 4 project components, namely for the 400 kV OHL Cernavoda - Stalpu (contract 919/30.10.2019 amounting to 287 million Lei), the 400 kV substation Stalpu (contract 920/31.10.2019 amounting to 58.4 million Lei) and extending the 400 kV substation Cernavoda (contract 168/11.02.2019 amounting to 11.5 million Lei). The execution term is 24 months from the date provided in the work beginning order.

The Cernavoda - Stalpu internal line aims at consolidating the cross section between the western Black Sea coast (eastern part of Romania) and the rest of the European system, while also contributing to enhancing the Romanian electricity transmission grid, to greater interconnection capacity between Romania and Bulgaria and to integrating the wind output from Dobrogea region. The new 400 kV line will be 160 km long, and to commission it we need building the 400 kV substation Stalpu and extending the 400 kV substations Cernavoda and Gura Ialomitei.

The "Internal line between Cernavoda and Stalpu" is the first project of common interest carried out by CNTEE Transelectrica SA, which received European financing in sum of maximum 27 million Euro under the CEF mechanism. It has the following components:

  • The 400 kV double circuit overhead line (OHL) Cernavoda Stalpu;
  • The 400 kV substation Stalpu;
  • Extending the 400 kV substation Cernavoda;
  • Extending the 400 kV substation Gura Ialomitei.

Claudia – Gina ANASTASE Adrian SAVU

Executive Director General Directorate Chairperson

Directorate Member

LANGUAGE DISCLAIMER: This document represents the English version of the original official Romanian document filed with the Financial Supervisory Authority ASF. The English version has been created for English readers' convenience. Reasonable efforts have been made to provide an accurate translation, however, discrepancies may occur. The Romanian version of this document is the original official document. Any discrepancies or differences created in the translation are not binding. If any questions arise related to the accuracy of the information contained in the English version, please refer to the Romanian version of the document which is the official version.