C.N.T.E.E. Transelectrica

Capital/Financing Update Apr 9, 2024

2299_iss_2024-04-09_36826310-6651-4c76-975a-dab9c955b7f3.pdf

Capital/Financing Update

Open in Viewer

Opens in native device viewer

To: Bucharest Stock Exchange – Regulated Markets, Operations, Issuers Department Financial Supervision Authority – General Supervision Division – Issuers Division

Current report in accordance with the provisions of Law No 24/2017, BSE Code and Regulation no. 5/2018 of FSA Date of the current report: April 9, 2024 Name of issuer Company: National Power Transmission Grid Transelectrica, managed under two tier system Headquarters: Bucharest 3 rd district, Str. Olteni no. 2-4 Phone / fax numbers: 4021 3035 611 / 4021 3035 610 Single registration code: 13328043 RON Code: 254900OLXCOUQC90M036 Number in the Commercial Register: J40/8060/2000 Share capital subscribed and paid: 733,031,420 RON Regulated market where the issued securities are transacted: Bucharest Stock Exchange

Communication – contract financed by PNRR (national recovery and resilience plan) amounted to 56.2 million EURO

Following up the information spread through the current report sent through the capital market institutions on December 11, 2023, the National Power Transmission Co. Transelectrica informs the investing public on the fact that on April 9, 2024 it signed with the General Secretariat of the Government, as reform and/or investment coordinator for the national recovery and resilience plan (PNRR), the financing contract for the implementation of the investment "The efficiency, modernization and digitization of the national power transmission network", financed by the REPowerEU component of PNRR in the amount of 56.2 million euro. Three essential investment projects for the efficiency and modernization of the national power transmission network will be financed through this contract, two of them addressed to the subsidiaries SMART SA and Teletrans SA.

The investment aims at the installation of photovoltaic plants and storage facilities in 29 electrical energy stations, at the refurbishment of the SMART SA subsidiary and the optimization of the communications network managed by the Teletrans subsidiary and at creating a data centre.

We mention again that the implementation of these projects will bring significant contribution at strengthening the Electrical Energy Transmission Network of Romania. The objective of the REPower EU- funded investment is to increase flexibility and to address the jams in the electricity network in order to accelerate the integration of additional renewable energy capacity and increase grid resilience, while strengthening cyber security through better capacity response to cyber attacks.

Ștefăniță MUNTEANU Florin-Cristian TĂTARU

Executive Director General Chief Executive Officer

Directorate Member

LANGUAGE DISCLAIMER: This document represents the English version of the original official Romanian document filed with the Financial Supervisory Authority ASF. The English version has been created for English readers' convenience. Reasonable efforts have been made to provide an accurate translation, however, discrepancies may occur. The Romanian version of this document is the original official document. Any discrepancies or differences created in the translation are not binding. If any questions arise related to the accuracy of the information contained in the English version, please refer to the Romanian version of the document which is the official version.