CENTAURUS METALS LIMITED Investor Presentation 2019

Apr 4, 2019

64715_rns_2019-04-04_d4e9a43e-d272-42b4-9f8c-d938951c03ef.pdf

Investor Presentation

Open in viewer

Opens in your device viewer

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT & MEDIA RELEASE

==> picture [124 x 57] intentionally omitted <==

5 April 2019

CENTAURUS APRIL 2019 INVESTOR PRESENTATION
Centaurus Metals (ASX Code: CTM) is pleased to provide a copy of its latest April 2019 Investor Presentation,
which provides an update on ongoing activities at its three high quality mineral projects in Brazil.
Jambreiro Iron Ore Project, South‐eastern Brazil
The 100%‐owned Jambreiro Project is a fully‐permitted, shovel‐ready development project that is licensed for
3Mtpa of production. Following the recently completed capital raising, the Company has commenced planning
work to update the 2013 Feasibility Study for the Jambreiro Iron Ore Project (details of which are summarised in
the presentation).
In light of the current strength in the iron ore price, the premium being paid in the market for high grade (+65%
Fe), low‐impurity ore (4.5% silica, 0.8% alumina and 0.01% phosphorus) and renewed interest from prospective
partners, the Company believes that the already strong economics demonstrated in the 2013 Feasibility Study
could be further improved, given:

The lower availability of high‐grade iron ore in the Brazilian domestic market compared with 2013;

Improved domestic market pricing relative to 2013 as a result of the currency impact of a weaker Brazilian
Real against the US Dollar;

Significant premiums being realised for high grade 65% Fe product, in light of tighter environmental
conditions for steel mills across the globe which did not present themselves in the domestic market in
2013;

Greater access to open‐access ports, logistics and infrastructure compared with 2013, which should
provide an increased opportunity for the Company to consider supply into the export market;

A number of new potential customers and partners in the domestic market which were not available to
the Company in 2013; and

A new pro‐development government in Brazil which is expected to provide an increased level of support
to the domestic steel industry in Brazil over the coming years.
Salobo West Copper‐Gold Project, Northern Brazil
The 100%‐owned Salobo West Copper‐Gold Project is located just 15km along strike from Vale’s world‐class
Salobo Copper‐Gold Mine with similar geological, structural, geochemical and geophysical characteristics to
Salobo and a number of other known IOCG deposits in the Carajás. Since acquiring the Project, Centaurus has
completed an extensive review of all available geochemical, geophysical and drilling data for the 120km2Salobo
West tenement package, allowing the Company to plan an initial 35‐hole drill program.
The necessary vegetation inventory has been completed for the areas planned to be cleared ahead of drilling and
a site inspection of the planned holes is now required to be completed by the Environmental Agency, ICMBio, in
advance of the grant of the drilling and clearing licence. This site visit is awaiting a window in the heavy rainfall
currently being experienced in the region. The Company expects to receive the licence by the end of April 2019,
following the site inspection, which should be able to be completed in the next couple of weeks.
Australian Office
Brazilian Office
ASX: CTM
Centaurus Metals Limited
Centaurus Brasil Mineração Ltda
ACN 009 468 099
Level 3, 10 Outram St
Avenida Barão Homem de Melo, 4391
[email protected]
WEST PERTH WA 6005
Salas 606 e 607 ‐ Estoril
Telephone: +61 8 6424 8420
Belo Horizonte ‐ MG ‐ CEP: 30.494.275
BRAZIL

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT & MEDIA RELEASE

==> picture [52 x 33] intentionally omitted <==

The Company has had a number of proactive approaches from large third‐party mining groups to potentially joint venture into the Salobo West Project. Centaurus is currently evaluating the merits of these joint venture approaches.

Itapitanga Nickel‐Cobalt Project

The Itapitanga Nickel‐Cobalt Project was acquired by the Company in February 2018 and the Company was able to quickly advance the project with drilling during 2018. In November 2018, Centaurus entered into a farm‐out joint venture with battery metal specialist, Simulus Group. Under the farm‐out, Simulus can earn 80% of the project by free‐carrying Centaurus to a Decision to Mine.

Since entering the joint venture, Simulus has been undertaking Scoping Study work with this work anticipated to be completed by the end of April 2019. The 40‐tonne bulk sample that was collected in January and early February 2019 is expected to arrive in Australia in mid‐April. The bulk sample will be used for flowsheet optimisation work and to produce a suite of battery‐metal products for marketing purposes with potential off‐ takers.

‐ENDS‐

Released by: Nicholas Read Read Corporate M: +61 419 929 046

On behalf of: Darren Gordon Managing Director Centaurus Metals Limited T: +618 6424 8420

==> picture [842 x 159] intentionally omitted <==

  • Advanced iron ore and nickel-cobalt assets

  • Strategic development options under review

  • Leveraged to discovery success at large scale copper-gold project

Investor Presentation April 2019 Darren Gordon, Managing Director

Disclaimer

  • This presentation does not constitute investment advice. Neither this presentation nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sale of shares in any jurisdiction. This presentation does not take into account any person's particular investment objectives, financial resources or other relevant circumstances and the opinions and recommendations in this presentation are not intended to represent recommendations of particular investments to particular persons. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments.

  • To the fullest extent permitted by law, the Company does not make any representation or warranty, express or implied, as to the accuracy or completeness of any information, statements, opinions, estimates, forecasts or other representations contained in this presentation. No responsibility for any errors or omissions from this presentation arising out of negligence or otherwise is accepted.

  • This presentation may include forward looking statements. Forward looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of Centaurus Metals. These risks, uncertainties and assumptions include commodity prices, currency fluctuations, economic and financial market conditions in various countries and regions, environmental risks and legislative, fiscal or regulatory developments, political risks, project delay or advancement, approvals and cost estimates. Actual values, results or events may be materially different to those expressed or implied in this presentation. Given these uncertainties, readers are cautioned not to place reliance on forward looking statements. Any forward looking statements in this presentation speak only at the date of issue of this presentation. Subject to any continuing obligations under applicable law and the ASX Listing Rules, Centaurus Metals does not undertake any obligation to update or revise any information or any of the forward looking statements in this presentation or any changes in events, conditions or circumstances on which any such forward looking statement is based.

  • The information in this announcement that relates to Exploration Results and Mineral Resources is based on information compiled by Roger Fitzhardinge, a Competent Person who is a Member of the Australasian Institute of Mining and Metallurgy and Volodymyr Myadzel, a Competent Person who is a Member of Australian Institute of Geoscientists. Roger Fitzhardinge is a permanent employee of Centaurus Metals Limited and Volodymyr Myadzel is the Senior Resource Geologist of BNA Consultoria e Sistemas Limited, independent resource consultants engaged by Centaurus Metals. Roger Fitzhardinge and Volodymyr Myadzel have sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Roger Fitzhardinge and Volodymyr Myadzel consent to the inclusion in the announcement of the matters based on their information in the form and context in which it appears.

  • The information in this announcement that relates to Ore Reserves is based on information compiled by Beck Nader, a Competent Person who is a professional Mining Engineer and a Member of Australian Institute of Geoscientists. Beck Nader is the Managing Director of BNA Consultoria e Sistemas Ltda and is a consultant to Centaurus. Beck Nader has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Beck Nader consents to the inclusion in the announcement of the matters based on his information in the form and context in which it appears.

  • All information included in this presentation regarding Exploration Results, Mineral Resources and Ore Reserve estimates was prepared and first disclosed under the JORC Code 2004. The information in relation to the Jambreiro Ore Reserve has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. The information has been updated to the JORC 2012 Code for the Jambreiro Mineral Resource.

  • All information included in this presentation regarding the Canavial Mineral Resource was prepared and released to the market on 31 May 2013 under the JORC Code 2004.

  • Refer to the ASX announcements dated 20 December 2013 and 13 January 2014 for details of the material assumptions underpinning the production target and forecast financial information included in this presentation for the Jambreiro Iron Ore Project. The Company confirms that all the material assumptions underpinning the production target and forecast financial information derived from the production target continue to apply and have not materially changed.

  • This Jambreiro JORC Ore reserve was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. All information included in this presentation regarding the Ore Reserve estimate for the Jambreiro Iron Ore Project should be read in conjunction with the Company’s ASX announcement dated 5 November 2012.

  • All information contained in this presentation on the Salobo Mine of Vale has been taken from the “Vale Production in 4Q17” Report, its 20‐F Annual Report for 2017 and other public domain reports including their 2018 Vale Day presentation

  • All information contained in this presentation on the Jacaré Mineral Resource has been taken from Anglo American Presentations “O Depósito de Níquel Laterítico do Jacaré (PA), Brasil” – Simexmin 2010 and Ore Reserves and Mineral Resources Report 2016.

  • All information contained in this presentation on the Itapitanga Exploration Target was release to the market on 1 August 2018.

  • This presentation comments on and discusses some of Centaurus Metals Limited’s exploration in terms of target size and type. The information relating to the Itapitanga Exploration Target should not be misunderstood or misconstrued as an estimate of Mineral Resources or Ore Reserves. The potential quantity and quality of material discussed as an Exploration Target is conceptual in nature since there has been insufficient work completed to define them as Mineral Resources or Ore Reserves. It is uncertain if further exploration work will result in the determination of a Mineral Resource or Ore Reserve.

2

Delivering Value from a Diversified Asset Base in Brazil

Development‐ready iron ore project at Jambreiro ideally positioned to take advantage of changing market dynamics, with planning for updated Feasibility Study underway

High‐potential nickel‐cobalt and copper‐gold projects in Tier‐1 Carajás Mineral Province of northern Brazil

Large‐scale Itapitanga nickel‐cobalt discovery moving rapidly to development under innovative JV with battery metals specialist Simulus Group – CTM: free‐carried

Capital Structure
Shares on Issue 2,705m
Listed Options (EP $0.01, Exp 31/8/19) 623m
Unlisted Options (EP $0.008 to $0.015) 255m
Directors and Management Holding 5.3%
Market Capitalisation (at $0.006) A$16.2m
Cash as at 31 March 2018 A$3.0m

Extensive, well‐defined copper‐gold targets at Salobo West in Carajás Mineral Province – permitting well‐ advanced ahead of planned drilling

Centaurus offers highly leveraged exposure to a rich asset base in Brazil including exciting new greenfields nickel‐cobalt and copper‐gold projects and a retained high‐quality development iron ore asset.

Outstanding leverage to exploration success with value underpinned by large asset base

3

Board and Key Management

BOARD OF DIRECTORS

==> picture [81 x 95] intentionally omitted <==

DIDIER MURCIA AM, B.Juris, LL.B

Non‐Executive Chairman

==> picture [83 x 98] intentionally omitted <==

==> picture [81 x 97] intentionally omitted <==

MARK CHRIS HANCOCK BANASIK B.Bus, CA, FFin

MSc Mineral Economics, BApp Sc, MAusIMM

Non‐Executive Director Non‐Executive Director

==> picture [84 x 97] intentionally omitted <==

DARREN GORDON B.Bus, FCA, AGIA, MAICD

Managing Director

==> picture [83 x 99] intentionally omitted <==

==> picture [83 x 100] intentionally omitted <==

BRUNO ROGER SCARPELLI FITZHARDINGE M.Sc, PMP B.Sc (Geology), MAusIMM

Brazil Country Manager Exploration Manager & Executive Director

==> picture [83 x 100] intentionally omitted <==

PAUL BRIDSON

B.Comm, CA, AGIA

Company Secretary & CFO

MANAGEMENT TEAM

Chartered Accountant, 25 years experience

Geologist, +30 years experience

Chartered Accountant, +20 years experience

Lawyer, +30 years experience

Non‐executive Chairman – Alicanto Minerals and Current Chief Commercial Strandline Resources Officer and former Executive Director of Atlas Former Non‐Executive Iron

Founding Director of Exploration and Geology at Silver Lake Resources (ASX: SLR).

Extensive resource financing and operations exposure in both gold and iron ore

Former Non‐Executive Iron SLR). iron ore Director of Gryphon Minerals and Cradle Resources Has previously held senior Extensive experience in Former Non‐Executive financial roles with nickel exploration, Director of Genesis Honorary Australian Consul to Woodside Petroleum, development and Minerals Tanzania Premier Oil & Lend Lease operations (WMC, GMM, Beta Hunt) Previously CFO at Gindalbie Metals

Chartered Accountant, 20 years experience

Engineer, +15 years Geologist, 20 years experience experience

Former Manager of Co Sec & CFO Syndicated Technical Services and Metals Senior Mine Geologist at Mirabela Nickel in Brazil Former Co Sec & CFO,

Former Environmental Coordinator at Vale’s Carajas Iron Ore Operations in State of Para, Brazil

Former Co Sec & CFO, Avalon Minerals

Previous Manager Former geologist with roles with Brandt Meio Homestake’s gold Previously Financial Ambiente and Golder exploration team and Controller, Gindalbie Associates in Brazil BHP’s Pilbara iron ore Metals

4

Brazil – A Mining‐Friendly Destination

Latin America’s largest economy Growing population (currently ~208 million)

Low interest rates (by historical standards), low inflation and rising economic growth

Pro‐mining President encouraging foreign investment in mining and infrastructure projects

Wide‐ranging economic reforms underway – labour laws, pension scheme, tax and government royalties Strong tenement control system, established Mining Code – Up to 8 years for Exploration Licences, which can be converted to Mining Leases

No Government ownership in mining projects – Government revenue generated from royalties

==> picture [371 x 172] intentionally omitted <==

==> picture [371 x 172] intentionally omitted <==

Minas Gerais and Pará are key mining States – strong mining culture, experienced workforce

5

Iron Ore – New Opportunities Emerging at Jambreiro

==> picture [842 x 377] intentionally omitted <==

----- Start of picture text -----

Jambreiro Iron Ore Project – fully licensed for 3Mtpa of product
Mining Leases granted
Extensive project design and engineering in place
Well located relative to Brazilian steel industry
Strategic development options under review in light of changed
market dynamics
----- End of picture text -----

6

Jambreiro – Well Located for Domestic and Global Markets

  • 110km from Ipatinga steel‐making region

  • JORC Resource of 127.2Mt 350km

  • • Initial Ore Reserve of 48.5Mt 110km

  • • Over 19,000 metres of diamond and RC drilling to support 140km JORC resource and reserve

  • Over US$25 million spent on exploration, feasibility and engineering work

  • Extensive data set (including drill core) available to support project funding

7

Iron Ore – High Quality JORC Resource Inventory

Project JORC Category Million Tonnes Fe (%) SiO2 (%) Al2O3 (%) P (%) LOI (%)
Jambreiro* (1) Measured 44.3 29.2 50.5 3.9 0.04 1.6
Indicated 37.7 27.5 51.1 3.7 0.04 1.7
Measured + Indicated 82.1 28.4 50.8 3.8 0.04 1.3
Inferred 45.1 27.3 52.7 3.3 0.05 1.3
TOTAL 127.2 28.0 51.4 3.7 0.05 1.5
Canavial* (2) Indicated 6.5 33.6 33.6 7.1 0.10 7.9
Inferred 21.1 29.6 38.0 5.7 0.07 5.9
TOTAL 27.6 30.5 37.0 6.0 0.07 6.4
Guanhães
Region*
Measured 44.3 29.2 50.5 3.9 0.04 1.6
Indicated 44.2 28.4 48.5 4.2 0.05 2.6
Measured + Indicated 88.6 28.8 49.5 4.1 0.05 2.1
Inferred 66.2 28.0 48.0 4.1 0.06 2.8
TOTAL 154.7 28.5 48.9 4.1 0.05 2.4
  • 20% Fe cut‐off grade applied; Rounding may generate differences in last decimal place.

(1) JORC 2012, (2) JORC 2004. Refer Centaurus’ 2018 Annual Report released 28 March 2019

8

Jambreiro ‐ JORC Ore Reserves & Product Quality

Project Ore Reserve Classification Million Tonnes Fe (%) SiO2 (%) Al2O3 (%) P (%) LOI (%)
Jambreiro* Proved 35.4 28.5 49.6 4.3 0.04 1.7
Probable 13.1 27.2 49.0 5.3 0.04 2.4
TOTAL 48.5 28.1 49.4 4.6 0.04 1.9

JORC Ore Reserve produces 18Mt of High Grade (+65% Fe), Low Impurity Product RESERVE CURRENTLY ONLY CONSIDERS FRIABLE COMPONENT OF RESOURCE.

*This information was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. All information included in this presentation regarding the Ore Reserve estimate for the Jambreiro Iron Ore Project should be read in conjunction with the Company’s ASX announcement dated 5 November 2012.

9

Jambreiro – Process Flowsheet

==> picture [842 x 238] intentionally omitted <==

Integrated Beneficiation Circuit to accommodate a long life mining business in Brazil.

10

Jambreiro – Fully Permitted

Environmental Approvals (3.0Mtpa project)

==> picture [346 x 166] intentionally omitted <==

==> picture [347 x 186] intentionally omitted <==

Environmental Impact Assessment (EIA/RIMA) – Approved Key Environmental Approvals in place

==> picture [7 x 8] intentionally omitted <==

LP – Issued; LI – Issued;

LO – On Completion of Construction;

Strong community support for Project

Mines Department and Ministry of Mines & Energy Plan of Economic Evaluation (PAE) – Approved Mining Leases – Granted

Land Access

10‐year land access and co‐operation signed with land owner CENIBRA

One of the only fully licensed yet undeveloped iron ore projects in Brazil.

11

Jambreiro – Extensive Engineering Completed

==> picture [455 x 182] intentionally omitted <==

Engineering Activities

Extensive basic engineering completed for both 2Mtpa (2012) operation and revised 1Mtpa operation (2013)

Modularised plant designed and costed with CDE out of Northern Ireland for production of 1Mtpa

Cofferdam previously constructed but stored water released in 2014

==> picture [339 x 181] intentionally omitted <==

==> picture [339 x 180] intentionally omitted <==

Site Layout for Modularised 1Mtpa operation

12

Jambreiro – 2013 Project Economics

Key Financial Outcomes – 2013 Feasibility Study
Total A$
Total R$
Production Rate
1Mtpa
1Mtpa
Mine Life
18 years
18 years
Total Revenue
A$750 million
R$1,505 million
EBITDA
A$350 million
R$699 million
Capital Costs
A$53 million
R$109 million
Annual Average Operating Cash Flow
A$19.4 million
R$37.4 million
LOM Average Sales Price
A$41.3/dmt
R$82.7/dmt
Operating Cash Cost (per tonne Product ‐ LoM)
A$22.0/dmt
R$44.0/dmt
ASX Release – FS Dec
2013
Current – Apr 19
Average FX ‐ AUD to BRL
2.00
2.73
Average FX ‐ AUD to USD
0.91
0.71
Average FX ‐ USD to BRL
2.20
3.85
Ave Sales Price ‐ Mine Gate R$/wmt Product
82.7
See Below
Mine gate sales of 62% Fe ore are occurring in close proximity to the Jambreiro Project which, based on information available to the
Company, indicates that a price of R$100‐R$120 tonne is presently being achieved for that ore.

Potential partners have expressed an interest in the project. While there is no guarantee that a transaction of this nature will be finalised, the discussions to date provide the Company with confidence that Jambreiro can be funded at a Project level with equity, should the review of the previous Feasibility Study work deliver the results expected by the Company.

13

Jambreiro – 2013 Capital and Operating Costs for 1Mtpa Operation

Capital Cost Breakdown* A$ million
At 2013 FX Rates
R$ million
Direct Costs
Processing Plant & Equipment 32.1 65.9
Site Infrastructure/Civils/Pre Strip 6.5 13.5
Water Supply & Tailings Mgt 4.4 9.1
Detailed Engineering/Project Management 5.4 11.1
Contingency 4.6 9.5
TOTAL CAPEX 53.0 109.1
Operating Cost Breakdown* A$ per Tonne
Product At 2013
FX Rates
R$ per Tonne
Product
Mining 9.2 18.4
Processing & Beneficiation 8.6 17.2
Administration 2.2 4.4
SITE OPERATING CASH COST (C1) 20.0 40.0
Royalties – Government and Landowner 2.0 4.0
TOTAL OPERATING CASH COSTS (C1 + Royalties) 22.0 44.0

*Refer ASX announcement of 20 December 2013 and 13 January 2014 for cost details

14

Jambreiro – Project and Mine Life Upside

Potential to double the mine life to 36 years based on 1Mtpa operation

Compact Ore

Comprises 63.6Mt @ 26% Fe within overall resource of 127.2Mt @ 28.0% Fe

Mass PRODUCT QUALITY Fe% SiO2% Al2O3% P% Recovery % – COMPACT MINERALISATION BENCH SCALE (Wet Magnetic Separation) Head Grade 25.0 55.9 2.2 0.07 Beneficiated Product 66.2 3.7 0.9 0.01 35.2

Successful test work has delivered

beneficiated product grading 66.2% Fe

Pit optimisation incorporating this material has defined an In Pit Resource:

  • 102.6Mt @ 26.7% Fe (+80% of global resource)

Potential product of 36.3Mt of +65% Fe at strip ratio of 1.05 to 1

==> picture [411 x 120] intentionally omitted <==

15

Jambreiro – Potential Feed Sources

  • Just 10km from the Jambreiro Project

  • JORC Itabirite Resource of 27.6Mt @ 30.5% Fe

  • Friable Itabirite Resource of 15.8Mt @ 33.2 % Fe

  • DNPM Final Exploration Report lodged – May 2014

Material JORC
Category
Million
Tonnes
Fe % SiO2 % Al2O3 % P % LOI %
Friable Itabirite Indicated 6.1 34.1 32.6 7.2 0.10 8.0
Inferred 9.7 32.6 34.5 8.4 0.07 7.1
TOTAL 15.8 33.2 33.8 7.9 0.08 7.5
Compact Itabirite Indicated 0.4 26.3 47.1 6.0 0.13 6.5
Inferred 3.0 29.0 43.4 6.1 0.10 5.2
TOTAL 3.4 28.7 43.9 6.1 0.10 5.3
Amphibolitic Indicated
Itabirite Inferred 8.4 26.3 40.1 2.5 0.05 4.7
TOTAL 8.4 26.3 40.1 2.5 0.05 4.7
Grand Total Indicated 6.5 33.6 33.6 7.1 0.10 7.9
Inferred 21.1 29.6 38.0 5.7 0.07 5.9
TOTAL 27.6 30.5 37.0 6.0 0.07 6.4

20% Fe cut-off

==> picture [342 x 198] intentionally omitted <==

==> picture [342 x 197] intentionally omitted <==

The Carajás Mineral Province – Land of the Giants

==> picture [510 x 110] intentionally omitted <==

10 IOCG deposits with resources of +100Mt Cu‐Au, including six >300Mt for +4.0Bt of Cu‐Au

resources

Includes Vale’s giant Salobo Mine:

‒ Reserves of 1.2Bt @ 0.61% Cu, 0.3g/t Au Produced ~195kt Cu and ~346koz Au in 2017

==> picture [510 x 110] intentionally omitted <==

Also hosts the largest high‐grade iron ore deposits on the planet, plus multiple large nickel deposits CTM holds + 250km[2] tenement portfolio located within the world‐class Carajás Mineral Province Includes Itapitanga Ni‐Co Project, the Salobo West Cu‐Au Project and the Pebas Cu‐Au Project Vale planning to roll out “Mini Mines” partnership model in base metals in the Carajás

The Carajás contains one of the world’s largest known concentrations of large‐tonnage mineral deposits

17

Salobo West Copper‐Gold Project

==> picture [822 x 377] intentionally omitted <==

18

Salobo West – High‐Potential Cu‐Au Exploration

==> picture [658 x 396] intentionally omitted <==

The Carajás contains one of the world’s largest concentrations of large tonnage iron oxide copper‐ gold (IOCG) deposits: +4.0Bt of Cu‐Au resources OZ Minerals entered Carajás in 2018 Vale plans to roll out “mini mines” model 19

The Carajás Mineral Province – The Land of the Giants

==> picture [467 x 162] intentionally omitted <==

==> picture [467 x 162] intentionally omitted <==

The Carajás Mineral Province has been explored by Vale since the 1970’s – has controlled 90% of the province for past 50 years

Most of the IOCG deposits in the Carajás were discovered in the 1970s and 1980s using conventional mapping and soil geochemistry programs

All IOCG deposits hosted in the Itacaiúnas Supergroup and most come to surface Modern infrastructure now makes most of the Carajás accessible year‐round

Centaurus has secured a unique opportunity at Salobo West in one of the world’s most prospective IOCG provinces.

20

The Carajás Mineral Province – The Cinzento Shear Zone

==> picture [842 x 119] intentionally omitted <==

==> picture [842 x 120] intentionally omitted <==

IOCG deposits in the Cinzento occur along fault splays and intersections of major lineaments. The Salobo West Project hosts multiple prospects that fit precisely this scenario within the favourable geological context of the Itacaiúnas Supergroup.

21

The Carajás Mineral Province – Vale is Expanding

Vale is currently producing ~290ktpa of copper from the Carajás and is looking to raise this to 450‐500ktpa by 2024 ¹ by:

  • Increasing Salobo capacity to 250ktpa via installation of a third concentrator (Salobo III) – US$1.1B investment, with start‐up in 2022

  • Implementing the Carajás mini‐mines program , to add 50‐100ktpa from smaller deposits operated by third parties, in the short‐medium term

  • Bringing Cristalino deposit online (80ktpa) to maintain Sossego’s full plant capacity, with start‐up in 2023

  • Restart to Alemão Cu‐Au mine, 60‐70ktpa, high gold credits, with start‐up in 2024

==> picture [413 x 156] intentionally omitted <==

----- Start of picture text -----

Salobo West 2 Salobo West 1
(12km WNW) (15km NW)
----- End of picture text -----

==> picture [413 x 155] intentionally omitted <==

----- Start of picture text -----

Salobo Mine
----- End of picture text -----

Vale announced a US$1.1 billion expansion of its Salobo mine, adding a third concentrator, lifting the mine’s capacity to ~250ktpa of copper.

22

1: Vale Data sourced from “Vale Production in 4Q17” Report, its 20-F Annual Report for 2017, Vale Day 2018 - Presentation and other public reports.

Salobo West Copper‐Gold Project

==> picture [444 x 381] intentionally omitted <==

Two tenements – SW1 and SW2 (120km[2] of tenure):

==> picture [12 x 13] intentionally omitted <==

Tenements hosts at least five quality Cu‐Au Prospects ‐ SW1‐A, SW1‐B, Serendipidade, Dom & Gov Prospects.

Expansive high‐quality exploration dataset:

  • Stream sediment and soils geochem database (more then 3,500 samples);

  • Airborne VTEM and Magnetic data, 200m spacing;

  • Ground Induced Polarization (16 lines)

  • Diamond drilling, 10 drill holes for a total of 1,787 m

Environmental Licence secured from ICMBio for non‐ ground disturbing exploration

Vegetation inventory work now complete. ICMBio site inspection to be completed in advance of issue of drilling and clearing license. Current anticipated issue date – April 2019

23

Salobo West Copper‐Gold Project – SW1

==> picture [445 x 169] intentionally omitted <==

==> picture [445 x 168] intentionally omitted <==

SW1‐B: The Cruzamento Zone:

Located at the intersection of the east‐west BIF (Itacaiúnas) and the north‐west trending BIF unit of the SW1‐A Prospect

Discrete EM conductor plates modelled coincidently with IP chargeability anomalies, magnetic plates and Cu‐Au(‐Co) signatures – Priority 1 targets;

SW1‐B: The Central Zone:

Continuous +2.5km distinct magnetic signature coincident with the strongest and consistent Cu‐Au(‐Co) signature

Clear relationship between the modelled EM conductor plates and magnetic anomalies

SW1‐A:

+3.5km long Cu‐Au(‐Co) soil anomaly hosted in the same stratigraphic sequence as Salobo with favourable structural orientation (NW)

Distinct 2.0km EM conductor plate that is coincident with magnetic anomaly

SW1‐B ‐ 6.5km Cu‐Au(‐Co) anomaly that features three distinct zones, all of which display similar geological, structural, geochemical and geophysical characteristics to known IOCG deposits in the Carajás

24

Salobo West Copper‐Gold Project – SW1

==> picture [552 x 322] intentionally omitted <==

SW1‐B: Positive Historical Drill Hole

==> picture [12 x 13] intentionally omitted <==

Anglo American drilled only one hole into SW1‐B Prospect (IOCG target) FD0010 intersected 4m @ 0.8g/t Au (incl. 1m @ 2.0g/t Au) with 55% Fe from 116m‐120m Preceded by an interval from 110m‐115m with copper values between 0.07‐0.2% Cu FD0010 intersected the highly prospective meta‐volcanic sedimentary package of the Itacaiúnas Supergroup FD0010 finished at 130.8m depth, +50m short of the magnetics and IP targets

With multiple positive IOCG indicators – THE BEST COPPER‐GOLD TARGETS REMAIN UNTESTED!

25

Salobo West Copper‐Gold Project – SW2

Salobo West 2 (SW2) covers an WNW lineament that extends from the Salobo Mine

This WNW structure is through to be the mineralisation conduit for the 1.8Ga mineralising event at Salobo; where it hits the reactive Itacaiúnas unit (mag highs) there is Cu‐Au mineralisation

The Dom Prospect is delineated by an extensive +4.5km long Cu‐Au‐in‐soils anomaly that is up to 800m wide locally with soil values of up to 650ppm Cu and 137ppb Au

The Gov Prospect is delineated by a 2.0km long copper‐in‐soils anomaly that is up to 400m wide with soil values of up to 502ppm Cu

==> picture [432 x 319] intentionally omitted <==

This anomalous belt represents an association of several EM anomalies with distinct magnetic anomalies and a geological environment favourable to mineralisation, with many characteristics that resemble those observed in the Salobo Cu-Au deposit.” – translated from Vale Exploration Report, December 2000.

26

Salobo West Copper‐Gold Project

THE ROAD TO DISCOVERY

==> picture [15 x 15] intentionally omitted <==

Target generation work undertaken with industry leading independent consultants:

Clearing permit for drill camp facilities, access roads and initial 35 drill hole platforms lodged in Q4 2018

Clearing and drilling licence grant expected in April 2019 after ICMBio site inspection completed Maiden RC/DD drilling program planned for Q3 2019

The Company has had a number of proactive approaches by large third party mining groups to potentially joint venture into the Project with the concept of joint venturing the Project being assessed by the Company.

==> picture [842 x 134] intentionally omitted <==

27

Itapitanga Nickel‐Cobalt Project

==> picture [842 x 238] intentionally omitted <==

28

Itapitanga Nickel‐Cobalt Project – Alligator by the Tail?

==> picture [299 x 167] intentionally omitted <==

==> picture [299 x 166] intentionally omitted <==

The Itapitanga Ni‐Co Project is located at the southern extent of Anglo American’s world‐class Jacaré Nickel‐Cobalt Project Resources: 307Mt at 1.3% Ni and 0.13% Co, including a high‐grade cobalt resource of 185Mt at 1.2% Ni and 0.18% Co.

Project acquired in February 2018

Forms part of the southern extension of the ultramafic‐mafic intrusive complex (2.8Ga) that hosts Jacaré

Vale also holds multiple large tonnage (+100Mt) Ni‐Co resources along the 15km of ground between Itapitanga and Jacaré

==> picture [13 x 14] intentionally omitted <==

Innovative JV with battery metal specialist Simulus (November 2018)

The Itapitanga JV aims to be the first mover in one of the worlds largest undeveloped high‐ grade nickel‐cobalt provinces.

29

First‐Mover Advantage in High‐grade Nickel Province

90.0m @ 1.00 % Ni and 0.27% Co in trench ITAP‐BS00001

==> picture [12 x 13] intentionally omitted <==

~240‐hole Auger program completed for 1,200m

155‐hole maiden RC program completed for 4,309m

High‐grade nickel‐cobalt results include:

  • 10.0m @ 1.03% nickel and 0.21% cobalt (1.95% Nieq) from surface in ITAP‐RC‐18‐025;

  • 30.0m @ 1.48% nickel and 0.09% cobalt (1.79% Nieq) from 10.0m in ITAP‐RC‐18‐128;

==> picture [315 x 167] intentionally omitted <==

The nickel equivalent (“Nieq”) calculation assumes a nickel price of US$12,000/t and a cobalt price of US$50,000/t and assumes recoveries of 98% for nickel and 94% for cobalt (refer to Itapitanga Metallurgical Results, ASX Announcement 6 July 2018).

  • 13.0m @ 1.08% nickel and 0.17% cobalt (1.71% Nieq) from 2.0m in ITAP‐RC‐18‐001; 12.0m @ 0.94% nickel and 0.19% cobalt (1.68% Nieq) from 2.0m in ITAP‐RC‐18‐002; and 32.0m @ 1.02% nickel and 0.13% cobalt (1.50% Nieq) from surface in ITAP‐RC‐18‐127.

Initial leaching testwork delivered excellent results – extraction of 98% of Ni, 94% of Co and 99% of Sc

Exploration Target[1] of 35‐45Mt at 0.80% to 1.10% nickel, 0.07% to 0.12% cobalt and 18g/t to 30g/t scandium.

Centaurus cautions that the potential quantity and grade of the Exploration Target is conceptual in nature and there has been insufficient exploration to define a JORC compliant Mineral Resource. It is also uncertain if further exploration and resource development work will result in the estimation of a Mineral Resource.

40‐tonne bulk sample collected and shipped to Simulus’ state‐of‐the‐art facilities in Perth for flowsheet optimisation

1 For further detail of the Exploration Target please see ASX Announcement of 1 August 2018

30

Fast‐Track Development Pathway – Simulus JV

The Simulus Group – Australia’s premier hydrometallurgy and mineral processing service group and ideal JV partner for Centaurus to fast‐track development of the Itapitanga Project

Simulus has the right to earn up to 80%, in stages, by free‐ carrying Centaurus through the entire exploration and evaluation to a Decision to Mine and process arranging project finance

Industry leaders in process development for battery metals

Simulus to leverage off its in‐house capabilities for process design on nickel‐cobalt projects, with the ultimate aim of delivering a low capital intensity process design

Australia’s largest operating High‐Pressure Acid Leach (HPAL) testing facility and battery metal demonstration plant is owned and operated by Simulus at their laboratory in Western Australia

31

Moving Rapidly to Development

ON THE DEVELOPMENT FAST‐TRACK – FUNDED BY SIMULUS

==> picture [842 x 293] intentionally omitted <==

----- Start of picture text -----

Q1 Q2 Q3 Q4 2020
40t Bulk Sample Resource infill and extension JORC Resource update Pilot plant and testwork as Detailed engineering design
Site topographical survey drilling Mine Schedule update required Final CAPEX and OPEX estimation
Maiden JORC Resource Hydrology/Geotech studies Maiden JORC Reserve FS Engineering design and Lodge Mining Lease application
costing
Flow sheet optimisation
Variability process testwork Pilot plant and testwork as Securing project finance
Lodge Environmental Impact
First Pilot Plant run required
Flow sheet optimisation Statement and Project License
Initiate off‐take discussions PFS engineering design and Application (EIA/RIMA)
Preliminary Mine schedule
costing Definitive
Environmental surveys
Lodge Final Exploration Report Feasibility Study
Pre-Feasibility and
Scoping Study
Study Decision to Mine
2019 2020
----- End of picture text -----

Completed on schedule Underway

32

Centaurus – Key Investment Takeaways

==> picture [315 x 300] intentionally omitted <==

Outstanding package of iron ore, nickel‐cobalt and copper‐ gold development and exploration projects

Development‐ready Jambreiro Project ideally positioned to capitalize on the rapidly changing iron ore market dynamics – planning for updated Feasibility Study underway

World‐class IOCG discovery opportunity at Salobo West neighbouring Vale’s flagship copper mine in the Carajás Innovative JV with leading battery metals process group to free‐carry Centaurus to Decision to Mine at Itapitanga Aggressive development time‐line with aim to be first‐mover in significant undeveloped nickel‐cobalt province

Centaurus offers highly leveraged exposure to a rich asset base in Brazil including exciting new greenfields ajás nickel‐cobalt and copper‐gold projects with the potential to deliver significant value in the short‐term.

33

==> picture [842 x 120] intentionally omitted <==

==> picture [842 x 238] intentionally omitted <==

----- Start of picture text -----

Delivering value from a
diversified asset base in
Brazil’s world‐class
mineral provinces
----- End of picture text -----

Investor Presentation April 2019 Darren Gordon, Managing Director

The Carajás Mineral Province – The Land of the Giants

Company Deposits Commodity Mineral Reserves Mineral Resources Annual Production Distance from CTM
Projects (Km)
BHP1 Olympic Dam Copper‐Gold [email protected]% Cu,0.72g/t Au [email protected]% Cu,0.34g/t Au 166kt Cu cathode & 100koz Au Australia
Vale2 Salobo Copper‐Gold 1,[email protected]% Cu,0.3g/t Au 1,[email protected]% Cu,0.40g/t Au 176kt Cu & 317koz Au 12
Vale Sossego Copper‐Gold [email protected]% Cu,0.20g/t Au [email protected]% Cu,0.28g/t Au 93kt Cu & 67koz Au 70
Vale Furnas Copper‐Gold [email protected]%Cu;0.30g/t Au 70
Vale Alemao Copper‐Gold [email protected]%Cu,0.83g/t Au 12
Vale Cristalino Copper‐Gold [email protected]%Cu,0.13g/t Au 90
Vale Gameleira Copper‐Gold [email protected]% Cu,0.12g/t Au 70
Vale Paulo Afonso Copper‐Gold [email protected]% Cu,0.04g/t Au 35
Oz Minerals3 Prominent Hill Copper‐Gold [email protected]% Cu,0.60g/t Au [email protected]% Cu,0.50g/t Au 100kt Cu & 120koz Au Australia
Vale Pojuca Group Copper‐Gold [email protected]% Cu,0.04g/t Au 4
Oz Minerals Carrapateena Copper‐Gold [email protected]%Cu,0.70g/t Au [email protected]%Cu,0.60g/t Au Australia
Vale Estrela Copper‐Gold [email protected]%Cu,0.01g/t Au 80
Glencore4 Ernest Henery Copper‐Gold [email protected]%Cu,0.54g/t Au [email protected]%Cu,0.63g/t Au 70kt Cu & 100koz Au Australia
Vale Breves Copper‐Gold [email protected]%Cu,0.75g/t Au 2
Vale 118 Copper‐Gold [email protected]% Cu,0.20g/t Au 75
Ero Copper5 Boa Esperanca Copper‐Gold [email protected]% Cu [email protected]% Cu 80
Oz Minerals(Avanco)6 Antas Norte Copper‐Gold [email protected]% Cu,0.55g/t Au [email protected]% Cu,0.20g/t Au 14kt Cu & 11koz Au 30
Oz Minerals(Avanco) Pedra Branco Copper‐Gold [email protected]% Cu,0.60g/t Au 50
Vale Onca Puma Nickel [email protected]% Ni [email protected]% Ni 24kt Ni 80
Anglo American7 Jacaré Nickel‐Cobalt [email protected]%Ni,0.13%Co 15
Glencore Murrin Murrin Nickel‐Cobalt [email protected]%Ni,0.08% Co [email protected]% Ni,0.08% Co 34kt Ni & 3kt Co Australia
Clean Teq8 Sunrise Nickel‐Cobalt [email protected]% Ni,0.10% Co [email protected]% Ni,0.10% Co Australia
Vale Carajas Iron Ore 2.4Bt@66%Fe 150 Mtpa Fe 30
Vale S11D Iron Ore 4.2Bt@66% Fe 40‐90Mtpa Fe 45
  • 1 – Mineral Resource, Reserve and Production figures from BHP 2017 Operations and Annual Reports;

  • 2 – Reserve and Production figures from Vale 2017 Annual Report (20‐F); Resource estimates from multiple sources (mainly technical reports and presentations)

  • 3 – Mineral Resource, Reserve and Production figures from Oz Minerals 2017 Annual Report and Resource and Reserves statements;

  • 4 – Mineral Resource, Reserve and Production figures from Glencore 2017 Results and Annual Reports;

  • 5 – Mineral Resource and Reserve figures from Ero Copper website;

  • 6 – Mineral Resource, Reserve and Production figures from Avanco website

  • 7 – Mineral Resource from Anglo American 2016 Mineral Resources Report

  • 8 – Mineral Resource and Reserve from Clean Teq website

35