Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

CENTAURUS METALS LIMITED Interim / Quarterly Report 2013

Jul 17, 2013

64715_rns_2013-07-17_e1066ccc-d3a0-4f26-96b3-8e6068386368.pdf

Interim / Quarterly Report

Open in viewer

Opens in your device viewer

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

JUNE 2013 QUARTERLY ACTIVITIES REPORT

18 JULY 2013

==> picture [125 x 57] intentionally omitted <==

==> picture [536 x 94] intentionally omitted <==

JUNE QUARTER HIGHLIGHTS

JAMBREIRO IRON ORE PROJECT

  • Installation Licence secured: construction cleared to proceed.

  • Project schedule adjusted to provide the time necessary to finalise negotiations on a potential life-of-mine sales contract and for process plant enhancements to be incorporated into the final engineering design.

  • Off-take negotiations continuing with key steel groups in Brazil.

  • Independent Technical Expert Report and Legal Due Diligence Report completed to support project financing.

  • Initial on-site development work commenced, with construction of a temporary coffer dam now complete.

  • Power-line route selected and land access work underway.

  • Positive results received from in-fill RC drilling program.

CANAVIAL IRON ORE PROJECT

  • Maiden Mineral Resource estimate of 27.6Mt at an average grade of 30.5% Fe.

CANDONGA IRON ORE PROJECT

  • Strong results received from RC drilling campaign with estimation of a maiden Mineral Resource underway.

CORPORATE

  • Cash reserves of $12.8M at Quarter-end.

==> picture [562 x 87] intentionally omitted <==

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

JAMBREIRO IRON ORE PROJECT (CTM 100%)

The Jambreiro Iron Ore Project is located in the State of Minas Gerais, south-east Brazil, approximately 200km north-east of the State capital of Belo Horizonte (Figure 1).

==> picture [443 x 224] intentionally omitted <==

Figure 1: Location of Jambreiro Iron Ore Project in Brazil

Centaurus achieved a number of important milestones during the Quarter as it continued to progress Jambreiro towards financing, construction and development.

Environmental Approval Process

At the beginning of the Quarter, the Company secured the key Installation Licence (“LI”) for the Jambreiro Project, clearing the way for on-site construction to commence. The granting of the LI, following approval of the Project’s Environmental Control Plan (“PCA”), was achieved ahead of schedule.

The LI approval enables Centaurus to build the Project with an installed capacity of 3Mtpa of final saleable product, even though it initially intends to commence operations at a rate of 2Mtpa. The LI includes all the water permits and vegetation clearing authorisations required to facilitate project development.

Project Schedule

As a result of positive developments with ongoing negotiations for product off-take during the Quarter, Centaurus revised its target schedule for development of the Jambreiro Project. This review was driven by negotiations with potential customers in the Brazilian domestic steel industry and the opportunity to establish a life-of-mine contract for its product. The revised schedule will also allow recently identified enhancements to the processing circuit to be incorporated into the plant design.

For any steel mill customer in south-eastern Brazil, a new life-of-mine off-take requires them to progressively alter their currently contracted feed sources. The implementation of this operational redirection by the steel mills – and the need for both parties to carefully establish the terms of the contract – has required additional time and resources to ensure that strong mutual benefits can be realised for both Centaurus and the steel mills.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Centaurus now expects to commission the Jambreiro Project in mid-2014, rather than by the end of calendar year 2013 as originally planned. The Company remains in regular contact with its preferred international Project Finance banks, to establish a debt financing package for the Jambreiro Project, subject to suitable offtake arrangements being put in place.

Pilot plant testing of Jambreiro ore in the Bankable Feasibility Study (BFS) process beneficiation circuit continued following completion of the November 2012 BFS Report, enabling further circuit enhancements to be identified. The new Project Schedule allows the Company to implement these enhancements and realize significant capital and operating cost savings.

In conjunction with its Management Support Contractor, MCA, and Detailed Engineering and Procurement (EP) Contractor, Tetra Tech, Centaurus has commenced work to incorporate spiral concentrator units into the beneficiation circuit, which represents the main improvement identified in the testwork conducted throughout the Quarter.

The introduction of spirals to the circuit has allowed a significant reduction in the size of the grinding mill. This reduction provides for a capital saving in the cost of the grinding mill itself as well as in overall grinding mill installation. Further, as the grinding mill is the main power consumer in the plant, its size reduction also results in a significant decrease in power demand and overall operating costs. The financial assessment of the basic engineering work on the spirals demonstrates a potential post-tax NPV benefit to the Project of A$12.7 million or 9% of the original BFS Net Present Value.

With commissioning of the Project now targeted for mid-2014, the revised Project Schedule will allow time to:

  • complete the full detailed engineering of the three-stage spirals circuit;

  • fully integrate it into the plant design;

  • complete the competitive tendering process for the additional equipment;

  • incorporate spirals construction into the overall Project Execution Plan; and

  • capture sufficient water in advance of the commencement of operations.

As a result of these initiatives, the Definitive Cost Estimate for the Project is now scheduled to be delivered in the September Quarter, when detailed engineering is expected to be over 70 per cent complete.

The schedule extension has also provided the Company with capacity to incorporate other enhancements into the development of the Jambreiro Project such as a reduction in the size of the thickener which forms part of the tailings management system. It will also facilitate another capital cost saving, identified during the equipment manufacturer’s performance guarantee testwork, which was completed during the long lead-time equipment procurement process. The manufacturer’s testwork has demonstrated that faster tailings settling rates are possible than originally estimated in the BFS.

Initial Development Work

With Detailed Engineering continuing and with the Company having secured the key environmental Installation Licence for the Jambreiro Project, Centaurus commenced some initial on-site development work during the Quarter.

Water availability during construction and the operational phase is an important consideration for the Project. Accordingly, a local earthmoving contractor was engaged to construct a temporary coffer dam immediately upstream from site for the project tailings dam wall.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

This has the dual purpose of harvesting water for construction and de-watering the basement of the tailings dam wall to allow construction of the permanent dam ahead of the 2013/14 wet season. This will ensure availability of the extra water required for the plant first-fill, significantly de-risking the development and ramp-up once the Project development is fully implemented.

Figure 2 below shows construction of the temporary water dam just prior to completion at the end of June:

==> picture [237 x 176] intentionally omitted <==

==> picture [237 x 178] intentionally omitted <==

==> picture [235 x 176] intentionally omitted <==

==> picture [235 x 176] intentionally omitted <==

Figure 2 – Temporary Water Dam Construction at Jambreiro

Off-take Negotiations

In conjunction with the timely delivery of the necessary Government approvals for the Project, the Company continued negotiations with a number of potential customers in relation to off-take in order to facilitate a suitable debt financing package for project development.

The Company has gained wide interest and acceptance of the quality of the iron ore to be produced from the Jambreiro Project and is aiming to secure a suitable off-take arrangement during Q3 2013 which will then allow the financing of the Project to be completed.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Debt Finance

During the Quarter, the Company decided to defer entering into a mandate agreement with its preferred project finance banks until a suitable off-take arrangement is concluded (see above). The Company has continued to keep its preferred project financiers regularly updated on progress in relation to the ongoing offtake discussions and the development of the Project generally.

During the Quarter, the Independent Technical Expert’s Report, prepared for the benefit of the Project financiers, was completed by Coffey International as was the legal due diligence report. The completion of this work will allow the project financiers to complete their due diligence activities quickly once they are formally mandated.

Power Supply

During the Quarter, Centaurus selected the final route for the high voltage project connection to the existing State power transmission grid in conjunction with the State Energy provider, CEMIG. The 10km route will connect the Jambreiro Project to the existing grid (which runs parallel to the state highway MG 120) at a point between the existing cities of Guanhães and São João Evangelista.

Negotiations have commenced with the relevant landowners and access agreements for the power-line route are expected to be in place by the end of Q4 2013.

Diesel generators will supply construction power until the grid connection becomes available.

In-fill Drilling & Resource Upgrade

During the Quarter, the Company completed a small in-fill RC drill program at Jambeiro, mainly to enable some of the existing Inferred Resources falling within the current pit design to be converted to Measured and Indicated Resources.

The areas of drilling are set out on the map at Figure 3 and included:

Tigre In-fill – Three shallow holes were drilled at the south-eastern end of the Tigre pit. These holes were designed to allow the conversion of Inferred Resources to the Indicated category. Converting resources in this area will result in an improved mine schedule in the first and second years of operations and allow further reductions in early mine operating costs. Results from drilling in this area included:

  • 39.0m @ 38.8% Fe, 1.3% Al2O3 and 0.03% P from surface in hole JBR-RC-13-000166

Tigre Colluvium – 13 shallow holes were completed targeting the colluvium on the hangingwall side of the Tigre Pit. Outcrop existed in this area but no drilling had previously been undertaken. Recent clearing which exposed the colluvium indicated that the mineralisation may be a good early source of coarser plant feed. Approximately half of these colluvium holes intersected ferruginous colluvium or friable itabirite intervals between 4 and 10 metres, close to surface.

Coelho In-fill – A conceptual pit was designed for the Coelho mineralisation (500m south of the Tigre pit) and drilling was planned to convert Inferred Resources to the Indicated category within the conceptual pit limits. Seven holes were drilled to achieve this. Prior to drilling, Coelho had an estimated 7.2Mt of Inferred Resources. The Coelho drilling results were positive with six of the seven holes returning positive intersections of friable itabirite.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Results from drilling in this area included:

  • 31.0m @ 30.9% Fe, 1.8% Al2O3 and 0.01% P from 12.0 metres in Hole JBR-RC-13-000179

  • • 26.0m @ 29.6% Fe, 3.6% Al2O3 and 0.04% P from 29.0 metres in Hole JBR-RC-13-000174 • 14.0m @ 28.9% Fe, 2.1% Al2O3 and 0.02% P from 43.0 metres in Hole JBR-RC-13-000177 • 14.0m @ 28.4% Fe, 3.0% Al2O3 and 0.30% P from 12.0 metres in Hole JBR-RC-13-000178

==> picture [407 x 585] intentionally omitted <==

Figure 3 – RC Infill Drilling Locations at Jambreiro

A full list of results is set out in Table 4. An upgraded resource estimate will be completed during July 2013.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

CANAVIAL IRON ORE PROJECT (CTM 100%)

Exploration

Towards the end of the Quarter, Centaurus completed a maiden JORC Mineral Resource for the Canavial Project, a key satellite deposit located 10km to the south-west of Jambreiro (see Figure 4 ).

The maiden Mineral Resource estimate, comprising 27.6 million tonnes at an average grade of 30.5% Fe, boosted the Company’s JORC compliant resource inventory in the Guanhães region of south-eastern Brazil to over 152 million tonnes and the Company’s total resource inventory in south-east Brazil to over 201 million tonnes ( see Table 2 ).

Importantly, the new Canavial Resource estimate included 15.8 million tonnes grading 33.2% Fe of friable itabirite mineralisation, of which 6.1 million tonnes grading 34.1% Fe are already classified as Indicated Resources.

With the addition of this friable itabirite Resource at Canavial to that of the Jambreiro Project, the friable component of the Company’s Guanhães regional footprint now stands at 81.5 million tonnes grading 28.8% Fe with over 70% of this resource base falling into the Measured and Indicated categories.

Mineral characterization and process testwork is focused on the friable itabirite mineralisation at Canavial. The Company expects to be able to achieve similar beneficiation results to those achieved at Jambreiro, confirming that a high-grade, low impurity concentrate can be produced.

The Canavial Project is advantageously located in an area predominantly covered by a eucalypt plantation, which means that environmental licensing for potential future project development will be relatively simple, as was the case with Jambreiro.

The maiden Canavial JORC Mineral Resource estimate is set out in Table 1 below, with additional technical details of the Resource provided in Appendix A:

Table 1 – Canavial Project JORC Mineral Resource Estimate by Resource Category – May 2013

Project
Canavial
JORC Category JORC Category Million Tonnes Million Tonnes Fe % Fe % SiO2 % SiO2 % Al2O3 % Al2O3 % P % LOI %
Indicated 6.5 33.6 33.6 7.1 0.10 7.9
Inferred 21.1 29.6 38.0 5.7 0.07 5.9
TOTAL 27.6 30.5 37.0 6.0 0.07 6.4
20% Fe Cut-off
Table 2 – Total Mineral Resource Inventory for Centaurus in South East Brazil
Project Million Tonnes Fe % **SiO2 % ** **Al2O3 % ** P % LOI %
Canavial* 27.6 30.5 37.0 6.0 0.07 6.4
Jambreiro* 125.2 26.7 50.2 4.4 0.05 1.5
Guanhães Region 152.7 27.4 47.8 4.7 0.05 2.4
Passabém** 39.0 31.0 53.6 0.8 0.07 0.1
Itambé*** 10.0 36.6 39.1 4.0 0.05 2.4
TOTAL 201.7 28.6 48.5 3.9 0.06 2.0
  • 20% Fe cut-off grade applied; ** 27% Fe cut-off grade applied; *** 25%Fe cut-off grade applied

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Table 3 below sets out the different mineralisation types at the Canavial Project, by resource category:

Table 3 – Canavial Mineral Resource Estimate by Mineralisation Type – May 2013

Material JORC Category Million Tonnes Fe % SiO2 % Al2O3 % P % LOI %
Friable Itabirite Indicated 6.1 34.1 32.6 7.2 0.10 8.0
Inferred 9.7 32.6 34.5 8.4 0.07 7.1
TOTAL 15.8 33.2 33.8 7.9 0.08 7.5
Compact Itabirite Indicated 0.4 26.3 47.1 6.0 0.13 6.5
Inferred 3.0 29.0 43.4 6.1 0.10 5.2
TOTAL 3.4 28.7 43.9 6.1 0.10 5.3
Amphibolitic Itabirite Indicated
Inferred 8.4 26.3 40.1 2.5 0.05 4.7
TOTAL 8.4 26.3 40.1 2.5 0.05 4.7
Grand Total Indicated 6.5 33.6 33.6 7.1 0.10 7.9
Inferred 21.1 29.6 38.0 5.7 0.07 5.9
TOTAL 27.6 30.5 37.0 6.0 0.07 6.4
20% Fe Cut-off

The mineralisation at Canavial is divided into two zones: the Central Zone and the Southern Zone ( see Figure 5 ). The Central Zone mineralisation strikes in a NW-SE orientation and has a strike extent of approximately 1,000 metres, dipping at between 20 and 45⁰ to the north-east.

The shallow zones of friable itabirite mineralisation are between 15 to 35 metres thick and extend over 100 metres down-dip between holes on section (s ee Sections 4 and 5 in Figures 6 and 7 ). The geometry and material characteristics of the Central Zone mineralisation is expected to lend itself to a low strip ratio and has the potential to support a low-cost open cut operation.

The Southern Zone is a NW-SE zone with a strike extent of around 700 metres where the mineralisation is subvertical ( see Section 10 in Figure 8 ). The change in dip angle is due to the proximity of the nose of a large-scale fold in the south eastern limit of the tenement area. The zones of friable itabirite mineralisation are between 10 to 20 metres thick and vertical to sub-vertical.

The mineral assemblage of the Canavial friable itabirite mineralisation is similar to that of the Jambreiro Project with hematite and magnetite being the dominant iron oxides with quartz and some clay minerals. The main difference to the Jambreiro ore is the higher percentage of goethite and limonite present in the mineralisation. Locally, some shallow mineralised intervals have elevated levels of Al2O3 and P due to the clay minerals.

It is expected that these gangue minerals will clean up in the beneficiation process to produce a high iron, low impurity iron product, similar to that which is to be produced at Jambreiro.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

CANDONGA IRON ORE PROJECT (CTM 100%)

Exploration

During the Quarter, the Company reported fresh, high-grade results from the latest drilling at its 100%-owned Candonga Iron Ore Project, located 33km from Jambreiro ( see Figure 4 ). The results will be included in the maiden JORC Mineral Resource estimate for Candonga, which is on track to be delivered in July 2013.

The latest results included significant intersections of high-grade, near-surface mineralisation, demonstrating that Candonga has the potential to provide a source of high-grade coarse grained friable itabirite to the Jambreiro Project.

Highlights of the RC drilling results from Candonga included the following continuous intersections of friable itabirite (see Table 5 attached for a full list of the drilling intersections):

  • 32.0m @ 48.5% Fe, 1.4% Al2O3 and 0.08% P from surface in Hole CDG-RC-13-00024

  • 27.0m @ 38.6% Fe, 1.3% Al2O3 and 0.05% P from surface in Hole CDG-RC-13-00020

  • 23.0m @ 39.4% Fe, 4.9% Al2O3 and 0.09% P from surface in Hole CDG-RC-13-00018

  • 18.0m @ 46.9% Fe, 0.8% Al2O3 and 0.05% P from 7.0 metres in Hole CDG-RC-13-00017, including 5.0m @ 59.1% Fe, 0.6% Al2O3 and 0.07% P from 17.0m

  • 13.0m @ 47.8% Fe, 4.1% Al2O3 and 0.04% P from surface in Hole CDG-RC-13-00013

  • 12.0m @ 45.3% Fe, 1.3% Al2O3 and 0.07% P from 44.0 metres in Hole CDG-RC-13-00015

These intersections were consistent with the drill results announced earlier in the Quarter and the results from a drill program completed in 2010, which included the following intersections:

  • 85.6m @ 40.0% Fe, 1.1% Al2O3 and 0.07% P from 3.0 metres in diamond drill hole CDG-DD-001

  • 53.0m @ 45.6% Fe, 1.5% Al2O3 and 0.12% P from surface in RC drill hole CDG-RC-003

  • • 47.0m @ 36.9% Fe, 2.2% Al2O3 and 0.12% P from surface in diamond drill hole BAR-003

  • 58.0m @ 45.6% Fe, 2.6% Al2O3 and 0.11% P from surface in RC drill hole CDG-RC-13-00003

  • • 37.0m @ 56.5% Fe, 2.0% Al2O3 and 0.06% P from surface in RC drill hole CDG-RC-13-00008, including 20.0m @ 63.4% Fe, 0.6% Al2O3 and 0.06% P from 13.0m

  • • 12.0m @ 60.6% Fe, 4.2% Al2O3 and 0.02% P from surface in RC drill hole CDG-RC-002

It is expected that the Candonga mineralisation will be able to be upgraded to a high grade, low impurity product using a similar process flowsheet to the one that will be utilised at Jambreiro.

Candonga is predominantly located on farm land which should lend itself to relatively simple environmental licensing for drilling and future project development, as was the case with Jambreiro.

The friable itabirite mineralisation at the Candonga Project is identified in two distinct zones, the Western and the Eastern Zones, separated by a north-south striking fault (see Figure 9 ). The two zones have a combined strike length of 1.6 km of mineralisation.

The mineral assemblage of the Candonga friable itabirite mineralisation is slightly different to that of the Jambreiro Project. Magnetite and hematite are the dominant iron oxides with some goethite, limonite and quartz. The iron oxides are coarse to medium grained especially in the enriched zone near to surface.

Structural controls have generated zones of high grade iron mineralisation which have then been further enriched through supergene processes near to surface.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

CORPORATE

Annual General Meeting Results

The Annual General Meeting of Centaurus Metals Limited was held on Friday 31 May 2013. All resolutions were passed on a show of hands.

Cash Position

At 30 June 2013, the Company held cash reserves of approximately A$12.8 million.

Shareholder Information

At 30 June 2013, the Company had 195,747,919 shares on issue with the Top 20 holding 60.3% of the total issued capital. Directors and Senior Management held 5.2% of the total issued capital.

DARREN GORDON MANAGING DIRECTOR

Competent Person’s Statement

The information in this report that relates to Exploration Results and Mineral Resources is based on information compiled by Roger Fitzhardinge who is a Member of the Australasia Institute of Mining and Metallurgy and Volodymyr Myadzel who is a Member of Australian Institute of Geoscientists. Roger Fitzhardinge is a permanent employee of Centaurus Metals Limited and Volodymyr Myadzel is the Senior Resource Geologist of BNA Consultoria e Sistemas Limited, independent resource consultants engaged by Centaurus Metals.

Roger Fitzhardinge and Volodymyr Myadzel have sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as a Competent Person as defined in the 2004 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserve’. Roger Fitzhardinge and Volodymyr Myadzel consent to the inclusion in the report of the matters based on their information in the form and context in which it appears.

The information in this report that relates to Ore Reserves is based on information compiled by Beck Nader who is a professional Mining Engineer and a Member of Australian Institute of Geoscientists. Beck Nader is the Managing Director of BNA Consultoria e Sistemas Ltda and is a consultant to Centaurus.

Beck Nader has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration and to the activity, which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserve’. Beck Nader consents to the inclusion in the report of the matters based on their information in the form and context in which it appears.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~

~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~ ~~Table 4 – Jambreiro Iron Ore Project RC Drill Results - June 2013~~
Hole ID Target **SAD East ** SAD North mRL Dip Azi Final
Depth(m)
From (m) To (m) Downhole
width (m)
Rock Type Fe% SiO2% Al2O3% P% 1.20
1.20
0.73
0.73
2.845
3.50
1.16
2.04
2.53
2.97
2.97
0.629
1.80
1.991
1.07
2.21
2.21
2.39
2.39
2.59
1.14
1.83
2.42
1.43
1.53
1.57
0.40
0.72
0.62
0.62
0.76
0.76
2.47
0.60
1.48
0.87
1.00
1.00
10.61
10.61
LOI%
JBR-RC-13-000158
JBR-RC-13-000158 Tigre - Colluvium 722314 7945031 938 -90 0 16.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000159
JBR-RC-13-000159 Tigre - Colluvium 722274 7944965 930 -90 0 16.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000160 1.00 9.00 8.00 Itabirite 28.09 55.39 3.24 0.02
JBR-RC-13-000160 Tigre - Colluvium 722242 7944896 921 -90 0 15.00 Downhole composite 8.00 28.09 55.39 3.24 0.02
JBR-RC-13-000161 9.00 13.00 4.00 Itabirite 32.65 49.97 2.36 0.04
JBR-RC-13-000161 Tigre - Colluvium 722203 7944817 908 -90 0 19.00 Downhole composite 4.00 32.65 49.97 2.36 0.04
JBR-RC-13-000162
JBR-RC-13-000162 Tigre - Colluvium 722148 7944737 888 -90 0 15.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000163
JBR-RC-13-000163
JBR-RC-13-000163
JBR-RC-13-000163
0.00
4.00
18.00
24.00
4.00
10.00
21.00
30.00
4.00
6.00
3.00
6.00
Colluvium
QMXF
Itabirite
Itabirite
24.35
22.07
27.67
24.9
57.02
57.80
55.53
54.93
5.21
7.05
3.20
6.46
0.00
0.00
0.02
0.02
JBR-RC-13-000163 Tigre - Colluvium 722118 7944872 893 -90 0 31.00 Downhole composite 19.00 24.33 56.37 5.87 0.01
JBR-RC-13-000164
JBR-RC-13-000164 Tigre - Colluvium 722060 7944757 879 -90 0 15.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000165 1.00 11.00 10.00 Itabirite 23.23 57.41 6.16 0.04
JBR-RC-13-000165 Tigre - Colluvium 722089 7944812 886 -90 0 30.00 Downhole composite 10.00 23.23 57.41 6.16 0.04
JBR-RC-13-000166 0.0 39.0 39.0 Itabirite 38.81 37.70 1.30 0.03
JBR-RC-13-000166
JBR-RC-13-000166
39.0
50.0
50.0
60.0
11.0
10.0
Amphibolitic itabirite
Itabirite
24.01
29.67
41.01
41.04
1.16
0.824
0.04
0.03
JBR-RC-13-000166 Tigre - Infill 722881 7944186 956 -90 0 60.00 Downhole composite 60.00 34.57 38.86 1.20 0.03
JBR-RC-13-000167 21 24 4.00 Itabirite 28.32 49.90 6.01 0.05
JBR-RC-13-000167 Tigre - Infill 722242 7944717 913 -90 0 15.00 Downhole composite 4.00 28.32 49.90 6.01 0.05
JBR-RC-13-000168 4 14 10.00 QMXF 20.52 61.99 5.83 0.04
JBR-RC-13-000168 Tigre - Colluvium 722242 7944717 913 -90 0 15.00 Downhole composite 10.00 20.52 61.99 5.83 0.04
JBR-RC-13-000169
JBR-RC-13-000169 Tigre - Colluvium 722314 7944843 936 -90 0 15.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000170
JBR-RC-13-000170 Tigre - Colluvium 722250 7944634 912 -90 0 20.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000171
JBR-RC-13-000171 Tigre - Colluvium 722304 7944696 929 -90 0 15.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000172
JBR-RC-13-000172 Tigre - Colluvium 722328 7944543 944 -90 0 30.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000173
JBR-RC-13-000173
0.0
34.0
9.0
44.0
9.00
10.00
Colluvium
Itabirite
26.55
25.41
54.33
58.59
4.65
3.71
0.03
0.03
JBR-RC-13-000173 Coelho 722058 7944493 856 -60 80 52.00 Downhole composite 19.00 25.95 56.57 4.15 0.03
JBR-RC-13-000174 14
29.0
17
55.0
3.00
26.00
Itabirite
Itabirite
27.59
29.63
52.93
51.84
5.12
3.64
0.04
0.04
JBR-RC-13-000174 Coelho 722171 7944292 864 -60 240 58.00 Downhole composite 29.00 29.42 51.96 3.79 0.04
JBR-RC-13-000175
JBR-RC-13-000175 Coelho 722058 7944493 856 -60 240 73.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000176 9.0 12.0 3.00 31.82 48.50 3.64 0.02
JBR-RC-13-000176 54.0 62.0 8.00 Itabirite 28.92 56.11 1.93 0.02
JBR-RC-13-000176 Coelho 722281 7944025 903.711 -60 45 70.00 Downhole composite 11.00 29.71 54.03 2.40 0.02
JBR-RC-13-000177 43.0 57.0 14.00 Itabirite 28.89 55.73 2.09 0.02
JBR-RC-13-000177 Coelho 722384 7943920 912 -60 45 75.00 Downhole composite 14.00 28.89 55.73 2.09 0.02
JBR-RC-13-000178 12.0 26.0 14.00 Itabirite 28.38 55.09 3.04 0.30
JBR-RC-13-000178 Coelho 722450 7943872 896 -60 40 42.00 Downhole composite 14.00 28.38 55.09 3.04 0.30
JBR-RC-13-000179
JBR-RC-13-000179
JBR-RC-13-000179
0.0
12.0
51.0
3.0
43.0
57.0
3.0
31.0
6.00
Itabirite
Itabirite
Itabirite
25.10
30.85
29.29
54.73
53.39
53.38
6.47
1.84
2.76
0.03
0.01
0.04
JBR-RC-13-000179 Coelho 722494 7943822 884 -60 40 70.00 Downhole composite 40.00 30.18 53.49 2.33 0.02
JBR-RC-13-000180
JBR-RC-13-000180 Coelho 722298 7944804 927 -90 0 15.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000181 10.0 15.0 5.00 Itabirite 28.54 54.24 3.35 0.04
JBR-RC-13-000181 Tigre - Infill 722965 7944223 961 -90 0 20.00 Downhole composite 5.00 28.54 54.24 3.35 0.04
JBR-RC-13-000182
JBR-RC-13-000182 Exploration 720785 7943927 885 -60 25 120.00 NO SIGNIFICANT INTERSECTION
JBR-RC-13-000183 29 33 4.00 QMXF 20.56 34.48 20.95 0.27
JBR-RC-13-000183 Exploration 721717 7945786 904 -60 47 120.00 Downhole composite 4.00 20.56 34.48 20.95 0.27

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Figure 4 – Canavial & Candonga Iron Ore Projects Location Map

==> picture [508 x 636] intentionally omitted <==

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Figure 5 – Canavial Iron Ore Project Map – Analytical Signal Magnetic Image and Drill Results

==> picture [468 x 685] intentionally omitted <==

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Figure 6 – Canavial Iron Ore Project Schematic Cross Section 4

==> picture [501 x 330] intentionally omitted <==

Figure 7 – Canavial Iron Ore Project Schematic Cross Section 5

==> picture [497 x 328] intentionally omitted <==

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Figure 8 – Canavial Iron Ore Project Schematic Cross Section 10

==> picture [496 x 326] intentionally omitted <==

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Figure 9 – Candonga Iron Ore Project Map – Analytical Signal Magnetic Image and Drill Results – June 2013

==> picture [523 x 431] intentionally omitted <==

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Table 5 – Candonga Iron Ore Project RC Drill Hole Results – June 2013

Hole ID SAD East **SAD North ** mRL Dip Azi Final
Depth(m)
From (m) To (m) Downhole
width (m)
Rock Type Fe% SiO2% Al2O3% P% LOI%
CDG-RC-13-000001
CDG-RC-13-000001
0.00
24.00
5.00
27.00
5.00
3.00
Friable Itabirite
Friable Itabirite
36.29
32.06
27.88
26.33
11.55
14.55
0.09
0.07
8.32
7.35
CDG-RC-13-000001 721712 7912332 855 -90 0 95.00 Downhole composite 8.00 34.71 27.30 12.68 0.08 7.96
CDG-RC-13-000002 0.00 12.00 12.00 Friable Itabirite 41.97 22.44 8.49 0.07 5.47
CDG-RC-13-000002 721744 7912438 857 -90 0 80.00 Downhole composite 12.00 41.97 22.44 8.49 0.07 5.47
CDG-RC-13-000003 0.00 58.00 58.00 Friable Itabirite 45.59 27.41 2.58 0.11 4.08
CDG-RC-13-000003 721810 7912312 867 -90 0 80.00 Downhole composite 58.00 45.59 27.41 2.58 0.11 4.08
CDG-RC-13-000004
CDG-RC-13-000004
CDG-RC-13-000004
0.00
14.00
37.00
11.00
29.00
42.00
11.00
15.00
5.00
Friable Itabirite
Friable Itabirite
Friable Itabirite
37.40
41.70
22.82
34.15
27.79
29.66
7.40
6.64
22.36
0.04
0.10
0.21
4.45
3.80
10.47
CDG-RC-13-000004 721828 7912376 874 -90 0 52.00 Downhole composite 31.00 37.13 30.35 9.45 0.10 5.11
CDG-RC-13-000005 26.00 45.00 19.00 Friable Itabirite 43.85 28.42 4.06 0.13 3.75
CDG-RC-13-000005 721929 7912416 886 -90 0 65.00 Downhole composite 19.00 43.85 28.42 4.06 0.13 3.75
CDG-RC-13-000006 0.00 14.00 14.00 Friable Itabirite 43.90 25.35 6.02 0.09 4.73
CDG-RC-13-000006 721872 7912329 874 -90 0 58.00 Downhole composite 14.00 43.90 25.35 6.02 0.09 4.73
CDG-RC-13-000007 30.00 54.00 24.00 Friable Itabirite 37.46 39.47 1.67 0.10 0.01
CDG-RC-13-000007 722012 7912261 850 -90 0 58.00 Downhole composite 24.00 37.46 39.47 1.67 0.10 0.01
CDG-RC-13-000008 0.00 37.00 37.00 Friable Itabirite 56.53 14.17 2.01 0.06 1.85
CDG-RC-13-000008 722062 7912374 861 -90 0 60.00 Downhole composite 37.00 56.53 14.17 2.01 0.06 1.85
CDG-RC-13-000009
CDG-RC-13-000009
0.00
34.00
7.00
56.00
7.00
22.00
Friable Itabirite
Friable Itabirite
31.99
39.37
27.50
34.45
15.24
3.49
0.23
0.10
7.96
2.93
CDG-RC-13-000009 722136 7912216 898 -90 0 75.00 Downhole composite 29.00 37.59 32.77 6.32 0.13 4.14
CDG-RC-13-000010 0.00 25.00 25.00 Friable Itabirite 45.88 21.38 7.67 0.10 3.38
CDG-RC-13-000010 722178 7912286 901 -90 0 60.00 Downhole composite 25.00 45.88 21.38 7.67 0.10 3.38
CDG-RC-13-000011 0.00 5.00 5.00 Friable Itabirite 41.13 25.43 8.50 0.19 5.03
CDG-RC-13-000011 722241 7912200 909 -90 0 70.00 Downhole composite 5.00 41.13 25.43 8.50 0.19 5.03
CDG-RC-13-000012 1.00 27.00 26.00 Friable Itabirite 45.31 13.42 8.63 0.03 6.89
CDG-RC-13-000012 721580 7912429 817 -90 0 60.00 Downhole composite 26.00 45.31 13.42 8.63 0.03 6.89
CDG-RC-13-000013 0.00 4.00 4.00 Colluvium 48.86 18.23 7.63 0.04 0.27
CDG-RC-13-000013 4.00 13.00 9.00 Friable Itabirite 47.26 28.47 2.51 0.04 0.21
CDG-RC-13-000013 722266 7912237 905 -90 0 57.00 Downhole composite 13.00 47.75 25.32 4.09 0.04 0.23
CDG-RC-13-000014
CDG-RC-13-000014 722498 7911895 943 -90 0 76.00 NO SIGNIFICANT INTERSECTION
CDG-RC-13-000015 44.00 56.00 12.00 Friable Itabirite 45.28 31.93 1.27 0.07 0.21
CDG-RC-13-000015 56.00 60.00 4.00 Amphibolitic itabirite 29.52 42.00 0.98 0.07 0.09
CDG-RC-13-000015 722619 7911913 962 -90 0 67.00 Downhole composite 16.00 41.34 34.44 1.20 0.07 0.18
CDG-RC-13-000016
CDG-RC-13-000016 722866 7911808 989 -90 0 54.00 NO SIGNIFICANT INTERSECTION
CDG-RC-13-000017 0.00 4.00 4.00 Colluvium 34.69 38.13 7.55 0.05 0.48
CDG-RC-13-000017 7.00 25.00 18.00 Friable Itabirite 46.87 28.89 0.81 0.05 0.25
CDG-RC-13-000017 722764 7911797 962 -90 0 53.00 Downhole composite 22.00 44.65 30.57 2.04 0.05 0.29
CDG-RC-13-000018 0.00 23.00 23.00 Friable Itabirite 39.36 31.87 4.96 0.09 2.55
CDG-RC-13-000018 722744 7911737 936 -90 0 51.00 Downhole composite 23.00 39.36 31.87 4.96 0.09 2.55
CDG-RC-13-000019
CDG-RC-13-000019 722696 7911633 914 -90 0 50.00 NO SIGNIFICANT INTERSECTION
CDG-RC-13-000020 0.00 27.00 27.00 Friable Itabirite 38.57 38.09 1.31 0.05 1.09
CDG-RC-13-000020 722821 7911698 929 -90 0 40.00 Downhole composite 27.00 38.57 38.09 1.31 0.05 1.09
CDG-RC-13-000021 0.00 4.00 4.00 Colluvium 33.62 35.90 10.55 0.03 0.58
CDG-RC-13-000021 722999 7911546 930 -90 0 50.00 Downhole composite 4.00 33.62 35.90 10.55 0.03 0.58
CDG-RC-13-000022 6.00 16.00 10.00 Friable Itabirite 37.89 31.79 7.98 0.06 1.36
CDG-RC-13-000022 723066 7911632 914 -90 0 55.00 Downhole composite 10.00 37.89 31.79 7.98 0.06 1.36
CDG-RC-13-000023
CDG-RC-13-000023 722923 7911506 911 -90 0 52.00 NO SIGNIFICANT INTERSECTION
CDG-RC-13-000024 0.00 32.00 32.00 Friable Itabirite 48.42 25.48 1.44 0.08 2.21
CDG-RC-13-000024 723030 7911280 886 -90 0 52.00 Downhole composite 32.00 48.42 25.48 1.44 0.08 2.21

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Appendix A – Details of the Canavial Resource Estimate – May 2013

General Information
Project Name Canavial Iron Ore Project
Located approximately 170 Km NE of Belo Horizonte and 17Km North of
Guanhães in Minas Gerais, Brazil. Located 10km south west of the
Jambreiro Iron Ore Project.
Location
The Canavial Project is located within the Guanhães Group of the
Mantiqueira Complex. The region is structurally complex with duplex
fault systems and complex folding ranging from micro folding in outcrop
to large scale regional deformation.
The Itabirite unit is part of an iron formation including ferruginous
quartzites and quartzites hosted within a metasedimentry sequence.
This sequence is emplaced in regionalgneissic basement.
Geological Description
The Itabirite mineralisation comprises concentrations of medium -
coarse grained friable and compact material that have undergone
enrichment. The mineralisation is composed of quartz, hematite,
magnetite, goethite, limonite, with minor amphibole (Grunerite), Mica
(muscovite)and clayminerals.
Itabirite thicknesses vary from 5m to up to 35m thick within the Central
Zone. Itabirite has been intersected at depths upto 120m.
Spatial
Limits
of
Resource:
Total
Resource Area
714362.5mE to 717387.5mE
7935317.5mN 7938057.5mN
670.0mRL to 952.5mRL(surface)
Resource Base Max depth of 100m from base of drilling.
Responsibilities
Data Collection Centaurus Metals
Data Management Centaurus Metals and BNA Micromine Consultoria
Data Validation Centaurus Metals and BNA Micromine Consultoria
Geological
Interpretation
Centaurus Metals
Resource Modelling BNA Micromine Consultoria
Geological Interpretation
Geological Software Micromine 12.5
Lithological Boundaries Boundaries defined through Geological loggingand chemical analysis
Mineralisation
Boundaries
Boundaries defined through Geological logging and chemical analysis
Material
Type
Boundaries
Material types defined through Geotechnical logging. In particular,
friability tests.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Bulk DensityMeasurements Bulk DensityMeasurements Bulk DensityMeasurements
Method The bulk density for the resource estimation is assumed based on the
knowledge of the regional geology and the similarity to the mineralisation
seen at the Jambreiro Project. No bulk density measurements were taken as
all drillingwas RC.
Bulk DensityValues( t/m3)
Material Type Itabirite Itabirite Amphibolitic
Compact 3.0 3.0
Friable 2.3 2.3
Semi Friable 2.6 2.6
Colluvium 2.3
Drilling
Holes Metres
RC 35 3,195
Total 35 3,195
Survey
Grid System SAD_69 23S
Collar Survey Total surveycollars for all drill holes
DH Survey No down hole surveys have been completed
Sampling
Type and Method 1m samples for RC
RC One metre samples. Samples homogenised after leavingcyclone and split.
Sample Preparation and Chemical Analysis
Laboratory Samplepreparation carried out at Intertek's samplepreparation lab in BH
Analysis ofpulps carried out in Intertek's analysis lab in Sao Paulo
Physical
Sample
Prep
RC Drying,Crushing,Pulverising,Splitting
Analytical Method Metal Oxide determination through X-RAY Florescence (XR21L) Oxide and
elemental analyses including Fe, SiO2, Al2O3,P, Mn, TiO2, CaO, MgO, K2O,
Na2O and Cr2O3. FeO by a Volumetric Determination (VL3) and LOI using Loss
Determination by Gravity
Elements Fe,SiO2,Al2O3,P,Mn,TiO2,CaO,MgO,K2O,Na2O,Cr2O3and FeO
QAQC At total of 190 control samples were used including 106 Duplicate, 84
Standards. Standards inserted every 50 samples, duplicates every 20.

AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT

==> picture [55 x 31] intentionally omitted <==

Block Model Parameters Block Model Parameters
Estimation Method Inverse distance squared(ID2)
Y X Z
Parent Block Sizes 50m 50m 10m
Sub Block Sizes 5m 5m 5m
Attributes:
Rock_code (Itb_F,Itb_C and Waste)
OB Model Name
Fe% Fe Grade,ID2
SiO2% SiO2% Grade,ID2
Al2O3% Al2O3% Grade,ID2
P% P% Grade,ID2
Mn% Mn% Grade,ID2
TiO2% TiO2% Grade,ID2
CaO% CaO% Grade,ID2
MgO% MgO% Grade,ID2
K2O% K2O% Grade,ID2
Cr2O3% Cr2O3% Grade,ID2
LOI% LOI,ID2
FeO% FeO% Grade,ID2
CLASS Resource Classification Class
Density Bulk Densityof Itb_C,Itb_F and waste