Progress Report - WBEXT 1B fault block Sandstone Development 23 November 2012

Highlights

  • Development programme for WBEXT 1B fault block is on schedule

  • Target production rate is 800 BOPD (gross)

  • Drilling of 2012 production wells now completed on time and budget

  • Water injection program to commence in December 2012

  • Well workover activities are continuing

The drilling of the WBEXT-1H was completed on 22nd November 2012. This well was the 7[th] and final well in the 2012 phase of the WBEXT 1B fault block development program.

These seven new wells drilled since July 2012 will be combined with three previous wells for the first stage of development of the WBEXT 1B fault block sandstone development program. The results from the drilling program are tabulated below and depicted in the attached map.

Standard operations for wells in this development area involve the suspension of the well at the completion of drilling to enable the drilling rig to be mobilised to the next drilling location and the workover rig is then used to complete the operations.

At the conclusion of the WBEXT sandstone drilling activities, well logs are analysed and the results compared to other wells in the development area to determine perforation intervals and development details. The wells are then completed using a workover rig. The process for examination of logs and completion of perforation is around 7-10 days depending on the workover rig schedule.

Thereafter, individual well zones are tested to determine the optimum development scheme to take into account positioning of water injection and matching of injection and production wells. Further refinement of open intervals has been ongoing with continual workovers to test multiple zones in each well.

It is anticipated that well testing will be completed and water injection pumps installed in December 2012 and then the WBEXT 1B development will be placed online. It is expected that production from this fault block will be in the order of 800 bopd.

Depending on production results, a further 5 wells are contingent for this fault block for early 2013.

==> picture [510 x 5] intentionally omitted <==

==> picture [510 x 73] intentionally omitted <==

==> picture [449 x 464] intentionally omitted <==

Figure 1: The WBEXT 1B fault block development area

==> picture [510 x 5] intentionally omitted <==

==> picture [510 x 73] intentionally omitted <==

WBEXT-5C

Permit L44/43
Location Easting:
730,519 m E
Northing:
1,731,222 m N
CVN Interest 40%
Target Formation WBEXT sandstone reservoirs
Spud Date 25thJuly 2012
Days on Location 12
Total Depth 1010 m
Approximate Cost USD $ 1.35 million
Hydrocarbon Indications Oil and gas shows, wireline logs indicate presence of
hydrocarbons
Completed Intervals 815 - 817.6 & 823.3 – 826.3mMD
Forward Operations Continue testing; production enhancement
anticipated at commencement of WBEXT-1G water
injection

WBEXT-5B

Permit L44/43
Location Easting:
730,495 m E
Northing:
1,731,258 m N
CVN Interest 40%
Target Formation WBEXT sandstone reservoirs
Spud Date 15thAugust 2012
Days on Location 8
Total Depth 872 m
Approximate Cost USD $ 1.05 million
Hydrocarbon Indications Oil and gas shows, wireline logs indicate presence of
hydrocarbons
Completed Intervals 578 – 580 & 676 – 677mMD
Forward Operations Continue testing, assess recompletion opportunities.
Analyse test rates to determine necessity for
additional water injection well at WBEXT-5D
(contingent well).

==> picture [510 x 5] intentionally omitted <==

==> picture [510 x 73] intentionally omitted <==

WBEXT-1DST3

Permit
L44/43
Location
Easting:
730,349 m E
Northing:
1,732,118 m N
CVN Interest
40%
Target Formation
WBEXT sandstone reservoirs
Spud Date
16thSeptember 2012
Days on Location
10
Total Depth
1015 m
Approximate Cost
USD $850,000
Hydrocarbon Indications
Oil and gas shows, wireline logs indicate presence of
hydrocarbons
Completed Intervals
Currently under recompletion
Forward Operations
Workover underway to isolate two gas producing
intervals with a bridge plug (586 – 590 & 633.8 –
636.6mMD) and continue testing from sand at
576.4 – 582mMD.


WBEXT-1G

Permit
L44/43
Location
Easting:
730,311 m E
Northing:
1,732,106 m N
CVN Interest
40%
Target Formation
WBEXT sandstone reservoirs
Spud Date
16thOctober 2012
Days on Location
10
Total Depth
959 m
Approximate Cost
USD $975,000
Hydrocarbon Indications
Oil and gas shows, wireline logs indicate presence
of hydrocarbons
Completed Intervals
765 – 768mMD
Forward Operations
Additional intervals will be perforated and tested
for productivity and injectivity before conversion
into water injection well.

==> picture [510 x 5] intentionally omitted <==

==> picture [510 x 73] intentionally omitted <==

WBEXT-6D

Permit L44/43
Location Easting: 730,347 m E
Northing: 1,732,493 m N
CVN Interest 40%
Target Formation WBEXT sandstone reservoirs
Spud Date 25thOctober 2012
Days on Location 11
Total Depth 1165 m
Approximate Cost USD $1.15 million
Hydrocarbon
Indications
Oil and gas shows, wireline logs indicate presence of
hydrocarbons
Completed Intervals 1064.5 – 1067mMD
Forward Operations Continue testing and assess recompletion
opportunities. Analyse test rates to determine timing
to convert previously drilled WBEXT-1C into injection
well.

WBEXT-1AST2

Permit L44/43
Location Easting: 730,421 m E
Northing: 1,732,105 m N
CVN Interest 40%
Target Formation WBEXT sandstone reservoirs
Spud Date 5thNovember 2012
Days on Location 8
Approximate Cost USD $780,000
Total Depth 844 m
Hydrocarbon
Indications
Oil and gas shows, wireline logs indicate presence of
hydrocarbons
Completed Intervals 762 – 763, 771.4 – 773.4 & 781.6 – 784.2mMD
Forward Operations Commissioning underway. Analyse test rates to
determine timing to convert previously drilled
WBEXT-1C into injection well.

==> picture [510 x 5] intentionally omitted <==

==> picture [510 x 73] intentionally omitted <==

WBEXT-1H

Permit
L44/43
Location
Easting:
730,282 m E
Northing:
1,732,127 m N
CVN Interest
40%
Target Formation
WBEXT sandstone reservoirs
Spud Date
14thNovember 2012
Days on Location
6
Total Depth
842 m
Approximate Cost
USD $ 850,000
Hydrocarbon Indications
Oil and gas shows, wireline logs indicate presence of
hydrocarbons
Completed Intervals
n/a
Forward Operations
Rig recently released, awaiting analysis of well logs
before completing and testing well. Production
anticipated commencing upon recompletion of
WBEXT-1G into water injection well.