ASX Announcement

11 March 2020

==> picture [143 x 48] intentionally omitted <==

TICK HILL GOLD PROJECT Compelling Scoping Study Results

==> picture [22 x 27] intentionally omitted <==

Carnaby Resources Limited (ASX: CNB) (‘Carnaby’ or ‘Company’) is pleased to announce the results from a Scoping Study into the potential commercialisation of the 100% owned Tick Hill Gold Project.

==> picture [22 x 28] intentionally omitted <==

Fast Facts

Shares on Issue 96M

Cautionary Statement

The Scoping Study (Study) referred to in this announcement has been undertaken to determine the potential viability of an open pit cutback mining operation and re-processing of tailings, processing the ore by toll treatment. It is a preliminary technical and economic study of the potential viability of the Project. It is based on low level technical and economic assessments that are not sufficient to support the estimation of Ore Reserves. Further exploration and evaluation work and appropriate studies are required before Carnaby will be in a position to estimate any Ore Reserves or to provide any assurance of an economic development case.

The Study is based on the material assumptions outlined below. While Carnaby considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the Study will be achieved.

The Study includes existing JORC 2012 Code Indicated and Inferred resources defined within the Project. Approximately 16% of the Production

Target referred to in the Study is based on Inferred Resources. Investors are cautioned that there is a low level of geological confidence in Inferred Resources and there is no certainty that this will result in the determination of Measured or Indicated Resources or that the Production Target will be realised.

Carnaby has concluded it has a reasonable basis for providing the forwardlooking statements included in this announcement and believes that it has a “reasonable basis” to expect it will be able to complete the development of the Project.

Key components of the Study and the material assumptions used are contained within this announcement. Information includes preliminary mine design studies, metallurgical recoveries from existing test work and indicative costs based on initial discussions with 3[rd] party toll treatment parties and by external consultants. Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Scoping Study.

Market Cap (@ 4.0 cents) $3.8M Cash $2.4M1

  • 1As of 31 December 2019 and inclusive of Restricted Cash

Board and Management

Peter Bowler, Non-Exec Chairman Rob Watkins, Managing Director Justin Tremain, Non-Exec Director Paul Payne, Non-Exec Director Ben Larkin, Company Secretary

Company Highlights

  • Proven and highly credentialled management team

  • 100% ownership of the Tick Hill Gold Project (granted ML’s) in Qld, historically one of Australia highest grade and most profitable gold mines

  • Past production of 511 koz at 22 g/t gold

  • 323 km2 surrounding exploration package containing numerous gold and copper targets

  • Tight capital structure and strong cash position

Registered Office

78 Churchill Avenue Subiaco Western Australia 6008

T: +61 8 9320 2320

www.carnabyresources.com.au

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 8] intentionally omitted <==

1

==> picture [595 x 95] intentionally omitted <==

Key Highlights of the Scoping Study

  • The Scoping Study contemplates a mining and toll treatment operation over a 12 month period processing a Mineral Resource Inventory of 348,000 t @ 2.47 g/t to recover approximately 25,000 ounces of gold at an All-In Sustaining Cost (‘AISC’) of A$1,247 per ounce.

  • With the current gold price in excess of A$2,500 per ounce , the results of the Scoping Study demonstrate compelling economics warranting the immediate advance to Pre-Feasibility Studies.

  • Re-processing of the high grade East Paddock tailings stockpile of 285,000 t @ 1.42 g/t for 13,000 ounces to provide a low risk project start up resulting in negligible pre-production capital requirement and immediate cash flow.

  • An optimised Open Pit cutback of the Tick Hill open pit contains a Mineral Resource Inventory of 63,000 t @ 7.24 g/t gold for 14,600 ounces.

  • Ongoing discussions are in progress with 3[rd] parties for toll treatment options and contract miners regarding a potential joint venture arrangement.

  • Newly identified high grade gold mineralisation in the lower north wall of the open pit with results up to 5.5 m @ 30.1 g/t gold BOH and 5.5 m @ 20.3 g/t BOH have enhanced the economics of the study (Figures 2 & 3).

  • Carnaby’s primary focus remains to explore for the fault offset of the Tick Hill orebody. The scoping study results released today clearly show a pathway to sole fund this exploration for many years to come through the development of the Tick Hill Gold Project.

The Company’s Managing Director, Rob Watkins commented:

“The Scoping Study results announced today are highly significant and we look forward to progressing the project rapidly and advancing discussions with regional operators in the district. Successful commencement of the Tick Hill Gold Project at a time of record gold prices, will allow self-funding of ongoing exploration at Tick Hill for many years to come.”

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

2

==> picture [595 x 95] intentionally omitted <==

MINING

A mining Mineral Resource Inventory for the Scoping Study is based on an optimised open pit cutback of the historical 70 m deep Tick Hill open pit and re-processing of the high grade East Paddock Tick Hill tailings Dam. The Mineral Inventory is summarised in the following table and detailed below.

Tick Hill Diluted and Recovered
Indicated
Diluted and Recovered
Indicated
Diluted and Recovered
Indicated
Diluted and Recovered
Inferred
Diluted and Recovered
Inferred
Diluted and Recovered
Inferred
Diluted and Recovered
Total
Diluted and Recovered
Total
Diluted and Recovered
Total
cut-
off
tonnes g/t ounces tonnes g/t ounces tonnes g/t ounces g/t
Tick Hill Open Pit 44,000 7.29 10,200 19,000 7.11 4,400 63,000 7.24 14,600 1.05
Tick Hill East
Paddock Tailings
285,000 1.42 13,000 285,000 1.42 13,000
Tick Hill Total
Mineral Inventory
329,000 2.19 23,200 19,000 7.11 4,400 348,000 2.47 27,600

Table 1: Mineral Inventory used in the Tick Hill Scoping Study.

The Scoping Study Mineral Resource Inventory is after dilution and mining recovery factors of 10% dilution and 95% mining recovery of Open Pit Indicated Resources and 20% dilution and 50% mining recovery of Inferred Resources. Inferred Resources make up 16% of the inventory.

Tick Hill Tailings Stockpile

The Tick Hill tailings dam comprises 2 adjoined tailings paddocks that have remained on site since processing of Tick Hill ore was curtailed in 1994. The East Paddock has been selected to be incorporated into the Scoping Study due to its higher grade containing 285,000 t @ 1.42 g/t gold for 13,000 ounces.

The Tick Hill Tailings dams have been the subject of previous Scoping studies by previous owners at significantly lower gold prices. The Tailings Stockpiles have been drilled on approximately 40 m spacing and are classified as Indicated Resources.

The tailings stockpile is considered a low risk mining operation.

==> picture [467 x 161] intentionally omitted <==

Figure 1: Tick Hill East Paddock Tailings Dam Cross Section showing gold results

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

3

==> picture [595 x 95] intentionally omitted <==

Tick Hill Open Pit Cutback

==> picture [452 x 337] intentionally omitted <==

Figure 2: Tick Hill 3D view of optimised open pit facing east.

As part of the Scoping Study an open pit whittle optimisation was completed by external consultants Minesure Pty Ltd. The optimisation was based on a gold price assumption of $A2,300 per ounce.

The open pit optimisation was designed to test the potential viability of an open pit cut back of the historical Tick Hill open pit and assess against a possible re-establishment of existing underground development to extract the Mineral Resources.

The results indicate an open pit cut back of Tick Hill is potentially viable and an open pit whittle shell was selected for the Scoping Study containing an open pit Mineral Resource Inventory totalling 63,000 t @ 7.24 g/t for 14,600 ounces (see Table 1).

The cutback results in a deepening of the pit by approximately 40 metres. The Mineral Resource Inventory in the optimised pit shell includes the previously unmined southern extent of the Main Lode immediately beneath the historical open pit and the Hangingwall Lode. Significant high grade gold mineralisation is also captured in the cut back from the direct northern strike extent of the Main Lode into the lower north wall of the open pit (Figure 1).

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

4

==> picture [595 x 95] intentionally omitted <==

A parameters table for the pit optimisation is presented below and based on indicative costs.

Cut Off Grade Calculation
Gold Price $/oz 2,300
State / MIM Royalty(Au) % 5.8%
Metallurgical RecoveryAu % 97%
Treatment Cost Au $/t ore 45.0
Admin Cost $/t ore 1.00
Tech Services $/t ore 0.95
Dewatering $/t ore 0.50
Grade Control $/t ore 0.50
Contractor fixed $/t ore 1.42
Ore Haulage $/t ore 15
Total ProcessingCost $/t ore 65
COG g/t 0.96
MiningDilution % 10%
Miningrecovery % 95%
In Situ COG g/t 1.05
NPV discount rate % 5%
Annual Throughput Mtpa 0.5
East Wall Angle degrees 45
West Wall Angle degrees 50

Table 2: Open pit optimisation parameters

PROCESSING

The scoping study contemplates toll treatment of the Mineral Resource Inventory at 3[rd] party offsite processing facilities within the Mt Isa / Cloncurry district. Indicative pricing for toll treatment costs and haulage have been obtained and have been used in the Scoping Study.

Scheduled processing of the 347,000 t @ 2.47 g/t is planned to occur over a 12 month period to recover approximately 25,000 ounces of gold. Overall recoveries are anticipated to be 91%.

Metallurgical recoveries from the Mineral Resource Inventory are estimated to be 97% for hard rock ore from the open pit cutback at a grind size of approximately 110 micron, based on historical grind size and recoveries from the Tick Hill mine.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

5

==> picture [595 x 95] intentionally omitted <==

Metallurgical recoveries from the tailings dam are estimated to be 85% at approximately a 35 micron grind size based on detailed metallurgical studies previously completed. The Tailings Dam Mineral Resource Inventory is already crushed to approximately 110 micron. Additional metallurgical test work is being conducted by Carnaby.

PRODUCTION TARGET AND COST ESTIMATE

Production Target

Table 3 below provides a summary Life of Mine (‘LOM’) and gold production schedule that comprises the Tick Hill Open Pit and East Paddock Tailings Dam Project at the time of this Scoping Study.

Production Targets LOM
Site Establishment
months
3
Mine life
months
12
Ore mined
t
348,000
Grade
g/t
2.47
Containedgold
oz
27,600
Ore milled
t
348,000
Grade
g/t
2.47
Contained gold
oz
27,600
Recovery
%
91%
Goldproduced
oz
25,211

Table 3: Production Target

Capital Costs Estimate

The estimated capital cost for the establishment of the site to allow recommencement of mining activities has been estimated at a scoping study level (i.e. +/- 35%) is $295,000. Table 4 provides a summary of the capital costs estimate.

Capital Costs Estimate LOM
$'000's
LOM
$/oz
Site establishment 150 6
Facilities 62 2
Site works 45 2
Sub-total 257 10
Contingency15% 39 2
Total capital cost estimate 295 12

Table 4: Capital Costs estimate in Australian Dollars

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

6

==> picture [595 x 95] intentionally omitted <==

A 15% contingency has been applied to the capital costs estimate. The contingency is not intended to cover additional capital cost items, rather it is intended to cover uncertainty in relation to assumptions made and cost inputs for which pricing is not firm.

All-In Sustaining Costs

Table 5 provides a summary of the operating costs estimate showing the LOM all-in sustaining costs (‘AISC’) on a LOM and per ounce basis. The estimated costs have been derived from independent consultants, mining contractors and potential toll treatment plant operators. Uncertainty in relation to the cost inputs exists as pricing used is indicative only and is not considered firm.

All-In Sustaining Cost Estimate LOM
$'000's
LOM
$/oz
G&A 377 15
Mining & ore haulage costs 14,002 555
Toll treatment cost 13,886 551
Gold transport and refining 38 1
Royalties 3,135 124
Total AISC estimate 31,438 1,247

Table 5: Operating Costs Estimate in Australian Dollars

Key Cost Assumptions

The following key assumptions have been made in relation to the capital cost and AISC estimates:

  • Toll treatment of the gold ore at a nearby processing facility;

  • Use of existing site infrastructure, including haul roads and ROM pad;

  • Use of a mining contractor assumed; and

  • Accommodation of workforce at nearby offsite mine camp.

PERMITTING

The Tick Hill Gold Project is located on granted mining leases ML7094, ML7096 and ML7097. An Environmental Authority over the mining leases is in place along with environmental bonds. The mining leases are currently classified as on Care and Maintenance and Exploration.

Permitting to convert the mining leases back to mining activities associated with the Scoping Study are anticipated to take 6 months to complete, however there are no guarantees that this time frame can be achieved.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

7

==> picture [595 x 95] intentionally omitted <==

MINERAL RESOURCE ESTIMATE

A non material revision to the Tick Hill Mineral Resource has resulted in the addition of remaining Crown Pillar Inferred Resource and re-classification of Resources in the North Pit Wall. Refer to ASX release on 29 January 2020 for a description and summary of parameters used in the Mineral Resource Estimate.

The availability of a survey pickup of the pit floor post extraction of the crown pillar resulted in the revision of the Tick Hill resource to include the crown pillar remnants. A portion of the resource extracted by the pit in the vicinity of the crown pillar was removed and new crown pillar remnants were added in. This resulted in the removal of 5,400 t @ 6.20 g/t for 1,100oz of Indicated Resource and addition of 4,200 t @ 18.4 for 2,500 oz of Crown Pillar Inferred resource representing a net addition of 1,400 oz to the total resource.

==> picture [452 x 386] intentionally omitted <==

Figure 3: Tick Hill Cross Section Showing Location of historic GC results at the base of the north wall of the open pit.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

8

==> picture [595 x 95] intentionally omitted <==

A review of the historic grade control drilling has resulted in the reclassification of a strip of inferred material in the north wall of the existing Tick Hill Pit. Originally classed as Indicated by the estimation, this was down-graded to Inferred over doubts about the continuity of mineralisation further north. Part of this resource has since been manually reverted to an Indicated classification in light of high grade historic grade control drill results against and within the north wall of the pit. The reclassification has resulted in a conversion from Inferred to Indicated of 6,600 t @ 19.1 g/t for 4,000 oz.

The compilation of historical open pit grade control results shows high grade gold mineralisation from the Main Lode over significant widths entering the lower north wall of the open pit (Figures 2 & 3). Significant grade control results from the base and immediately below the north wall include;

595.22 5.5 m @ 6.18 g/t gold including 2.75 m @ 10.5 g/t gold BOH 596.22 5.5 m @ 30.1 g/t gold including 2.75 m @ 55 g/t gold BOH 597.22 5.5 m @ 20.29 g/t gold including 2.75 m @ 37.6 g/t gold 604.22 2.75 m @ 2.18 g/t gold BOH 605.22 5.5 m @ 4.36 g/t gold including 2.75 m @ 8 g/t gold BOH 606.22 5.5 m @ 9.09 g/t gold BOH 607.22 5.5 m @ 2.95 g/t gold BOH 637.2 2.75 m @ 5.6 g/t gold BOH 539.24 5.5 m @ 8.25 g/t gold including 2.75 m @ 12.2 g/t gold BOH 540.24 2.75 m @ 7.1 g/t gold BOH 5.26 2.75 m @ 37.8 g/t gold BOH

Total Indicated and Inferred Mineral Resources at Tick Hill from the Main and Hangingwall Lodes and including the existing Tailings Dam Resource (refer ASX announcement 12 March 2019) are presented in the following table with supporting detailed information provided in the attached JORC table 1.

==> picture [595 x 95] intentionally omitted <==

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

9

==> picture [595 x 95] intentionally omitted <==

Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Inferred
Total
cut-
off
tonnes
g/t
ounces
tonnes
g/t
ounces
g/t
92,000
7.31
21,700
153,000
7.15
35,100
0.5
21,000
7.07
4,900
53,000
5.46
9,400
0.5
114,000
7.27
26,600
207,000
6.71
44,600
0.5
345,000
0.8
8,800
0.5
285,000
1.42
13,000
0.5
630,000
1.08
21,800
0.5
114,000
7.27
26,600
837,000
2.47
66,400
0.5
Tick Hill Indicated Inferred Total cut-
off
tonnes g/t ounces tonnes g/t ounces tonnes g/t ounces g/t
Tick Hill Main Lode 61,000 6.90 13,400 92,000 7.31 21,700 153,000 7.15 35,100 0.5
Tick Hill
Hangingwall Lode
32,000 4.40 4,500 21,000 7.07 4,900 53,000 5.46 9,400 0.5
Tick Hill Deposit
Total
93,000 6.04 18,000 114,000 7.27 26,600 207,000 6.71 44,600 0.5
Tailings Dam West
Paddock
345,000 0.8 8,800 345,000 0.8 8,800 0.5
Tailings Dam East
Paddock
285,000 1.42 13,000 285,000 1.42 13,000 0.5
Tailings Dam Total 630,000 1.08 21,800 630,000 1.08 21,800 0.5
Tick Hill Total 723,000 1.72 39,800 114,000 7.27 26,600 837,000 2.47 66,400 0.5

Table 6: Tick Hill Mineral Resource Table

TIMELINE TO PRODUCTION

A Pre-feasibility study is immediately commencing as a result of the positive Scoping Study results and additional metallurgy, geotechnical review and pit design work will be completed.

In conjunction, ongoing discussions with 3[rd] party operators will continue.

It is anticipated that the Pre-feasibility studies will be completed in May 2020.

Assuming a positive outcome of the Pre-feasibility study, a 6 month permitting period will ensue, targeting first gold production towards the end of 2020.

NEXT STEPS

The Tick Hill Scoping Study has successfully outlined a potentially robust project of an open pit cutback of the Tick Hill open pit and re-processing of high grade tailings.

Toll treatment options in the Mt Isa / Cloncurry district will be advanced, including early stage discussions relating to potential contract mining and joint venture arrangements to negate funding requirement of the pre-production capital.

In order to advance the project to Pre-Feasibility status the following additional work programs are required:

  • Engineering and cost optimisation work to confirm that the open pit cut back is a more profitable option than re-establishing underground access to extract the Mineral Resource Inventory;

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

10

==> picture [595 x 95] intentionally omitted <==

  • Additional metallurgical test work relating to the tailings including grind size, residence time and oxygen injection. Samples have been collected from recent drilling;

  • Geotechnical review of historical data and diamond drilling completed by Carnaby;

  • Detailed ground water studies; and

  • Updating of mining and rehabilitation plan for submission to government authorities.

==> picture [458 x 458] intentionally omitted <==

Figure 4: Tick Hill regional location plan.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

11

==> picture [595 x 95] intentionally omitted <==

For further information please contact: Robert Watkins, Managing Director (08) 9320 2320

Competent Persons Statement

The information in this document that relates to the Tick Deposit Mineral Resources is based upon information compiled by Mr Paul Tan. Mr Tan is a full time employee and security holder of the Company and a Member of the AUSIMM. Mr Tan consents to the inclusion in the report of the matters based upon the information in the form and context in which it appears. Mr Tan has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which is undertaken to qualify as a Competent Person as defined in the December 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (JORC Code).

The information in this document that relates to the Tailings Dam Mineral Resources is based upon information compiled by Mr Robert Watkins. Mr Watkins is a Director and security holder of the Company and a Member of the AUSIMM. Mr Watkins consents to the inclusion in the report of the matters based upon the information in the form and context in which it appears. Mr Watkins has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which is undertaken to qualify as a Competent Person as defined in the December 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (JORC Code).

Forward Looking Statements

Some statements in this announcement regarding estimates or future events are forward looking statements. They include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Forward looking statements include, but are not limited to, statements preceded by words such as “planned”, “expected”, “projected”, “estimated”, “may”, “scheduled”, “intends”, “anticipates”, “believes”, “potential”, “could”, “nominal”, “conceptual” and similar expressions. Forward looking statements, opinions and estimates included in this announcement are based on assumptions and contingencies which are subject to change without notice, as are statements about market and industry trends, which are based on interpretations of current market conditions. Forward looking statements are provided as a general guide only and should not be relied on as a guarantee of future performance. Forward looking statements may be affected by a range of variables that could cause actual results to differ from estimated results, and may cause the Company’s actual performance and financial results in future periods to materially differ from any projections of future performance or results expressed or implied by such forward looking statements. These risks and uncertainties include but are not limited to liabilities inherent in mine development and production, geological, mining and processing technical problems, the inability to obtain any additional mine licenses, permits and other regulatory approvals required in connection with mining and third party processing operations, competition for among other things, capital, acquisition of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of acquisitions, changes in commodity prices and exchange rate, currency and interest fluctuations, various events which could disrupt operations and/or the transportation of mineral products, including labour stoppages and severe weather conditions, the demand for and availability of transportation services, the ability to secure adequate financing and management’s ability to anticipate and manage the foregoing factors and risks. There can be no assurance that forward looking statements will prove to be correct.

This announcement has been prepared in compliance with the JORC Code (2012) and the ASX Listing Rules.

The Company has concluded it has a reasonable basis for providing the forward looking statements included in this announcement, including with respect to any production targets and financial estimates, based on the information contained in this announcement.

This announcement has been prepared by Carnaby Resources Limited. This document contains background information current at the date of this announcement. The announcement is in summary form and does not purport to be all-inclusive or complete.

Recipients should conduct their own investigations and perform their own analysis in order to satisfy themselves as to the accuracy and completeness of the information, statements and opinions contained in this announcement.

The announcement is for information purposes only. Neither this announcement nor the information contained in it constitutes an offer, invitation, solicitation or recommendation in relation to the purchase or sales of shares in any jurisdiction. The announcement may not be distributed in any jurisdiction except in accordance with the legal requirements applicable in such jurisdiction. Recipients should inform themselves of the restrictions that apply to their own jurisdiction as a failure to do so may result in a violation of securities laws in such jurisdiction.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

12

==> picture [595 x 95] intentionally omitted <==

This announcement does not constitute investment advice and has been prepared without considering the recipients investment objectives, financial circumstances or particular needs and the opinions and recommendations in this announcement are not intended to represent recommendations of particular investments to particular persons.

Recipients should seek professional advice when deciding if an investment is appropriate. All securities transactions involve risks, which include (among others) the risk of adverse or unanticipated market, financial or political developments. To the fullest extent of the law, the Company, its officers, employees, agents and advisors do not make any representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of any information, statements, opinion, estimates, forecasts or other representations contained in this announcement. No responsibility for any errors or omissions from the announcement arising out of negligence or otherwise is accepted.

Disclaimer

References have been made in this announcement to certain ASX announcements, including references regarding exploration results and mineral resources. For full details, refer to said announcement on said date. The Company is not aware of any new information or data that materially affects this information. Other than as specified in this announcement and the mentioned announcements, the Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and, in the case of estimates of Mineral Resources, Exploration Target(s) or Ore Reserves that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.

Detailed information on all aspects of the Company’s projects can be found on the Company’s website www.carnabyresources.com.au.

Appendix 1 | Historical Open Pit Grade Control RC Drill Results

Hole ID Location East
(MGA94/54)
North
(MGA94/54)
RL Dip Azimuth From Thickness Au g/t
595.22 Pit 388836 7605982 291.3 ‐65 109.58 0 5.5 6.18
inc 2.75 2.75 10.5
596.22 Pit 388838 7605981 291.3 ‐65 109.58 0 5.5 30.1
inc 2.75 2.75 55
597.22 Pit 388840 7605981 291.3 ‐65 109.58 0 5.5 20.29
inc 0 2.75 37.6
604.22 Pit 388835 7605986 291.3 ‐65 109.58 2.75 2.75 2.18
605.22 Pit 388838 7605985 291.3 ‐65 109.58 0 5.5 4.36
inc 2.75 2.75 8
606.22 Pit 388840 7605984 291.3 ‐65 109.58 0 5.5 9.09
607.22 Pit 388842 7605983 291.3 ‐65 109.58 0 5.5 2.95
637.2 Pit 388842 7605986 296.3 ‐65 109.58 2.75 2.75 5.6
539.24 Pit 388831 7605981 286.3 ‐65 109.58 0 5.5 8.25
inc 2.75 2.75 12.2
540.24 Pit 388833 7605980 286.3 ‐65 109.58 2.75 2.75 7.1
5.26 Pit 388829 7605978 281.3 ‐65 109.58 2.75 2.75 37.8

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

13

==> picture [595 x 95] intentionally omitted <==

Appendix 2 | JORC Code, 2012 Edition | ‘Table 1’ Report

Section 1 Material Assumptions Used in Tick Hill Scoping Study

(Criteria in this section apply to all succeeding sections)

Item Criteria Commentary
1 Mineral
Resource
estimate
used
for
assessment of potential Production Target
• No Ore Reserves are estimated as part of the Tick Hill Scoping
Study.
• For the purposes of this Scoping Study, the Mineral Resource
Estimate (MRE) as published in this ASX announcement has been
used. This estimate was prepared by a Competent Person in
accordance with the JORC Code, 2012 Edition.
2 Parties participating in the Scoping Study and
site visits
• The following parties have provided input to this Scoping
Study:
• Nigel Spicer (Minesure Pty Ltd) coordinated the mining study
work and Ben Larkin (Carnaby Resources Ltd) the compilation of
the economic model for theproject.
3 Study status • The type and level of study is a Scoping Study as defined in
Section 38 of the JORC Code, 2012 Edition.
• The Scoping Study has not been used to convert Mineral
Resources to Ore Reserves. Modifying Factors based on
information currently available have been applied to the Scoping
Study.
4 Cut-off parameters used in potential mine
analysis
• The portion of the MRE above 1.05 g/t gold was evaluated in
the Scoping Study.
• Cut-off grades (COGs), expressed as grams per tonne of gold
(g/t Au) were determined by dividing the estimated operating
cost per tonne of ore treated by the revenue per gram of gold
produced.
• The following inputs were used to estimate revenue per gram
of gold produced:
• Gold price: A$2,300 per troy ounce
• Metallurgical recovery:85-97% by CIL treatment
• Qld state royalty: 5% of revenue
• The following inputs were used to estimate operating cost per
tonne of ore treated, for potential open pit and underground
mines:
• Mining cost
• Processing cost
• Other royalty charges
• General & administration costs
5 Mining factors or assumptions used in the
Scoping Study
• No conversion of the Mineral Resource to Ore Reserves.
Mining Resource Inventory estimation: Pit shells were optimised
in Whittle using Indicated and Inferred classified blocks (There
are no Measured classified blocks are in the resource).
• Operating model: Mining contractor.
• Geotechnical considerations: The following pit wall angles were
considered for the optimisation;
East Wall: 45 degrees
West Wall: 50 degrees

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

14

==> picture [595 x 95] intentionally omitted <==

Commentary
The following Mining Recovery and Dilution Parameters were
used in the Mining Resource Inventory Estimation;
Indicated Resources; 95% Mining Recovery, 10% Dilution
Inferred Resources; 50% Mining Recovery, 20% Dilution.
A lower mining recovery and higher dilution was applied to
Inferred resources owing to potential mining issues against the
old stope voids.
• Development excavations will be mined by conventional open
pit drill and blast methods, excavator, front end loaders and 50t
trucks.
• Further geotechnical investigation and assessment will be
completed as the study work progresses.
• Geological drilling: Grade control drilling will be required as the
pit advances to better define the mineralisation prior to mining.
Some holes will be used as resource infill and to probe the areas
with old voids. This drilling will generally be RC located on the
cut back benches.
• All Mineral Resource categories have been included in the
mining study work.
• Both Indicated and Inferred Mineral Resources were used in the
possible production schedule used in the Scoping Study. Inferred
resources account for 30% of the total pit resource ounces used
in the production schedule.
• Infrastructure: The Scoping Study considers the provision of all
necessary infrastructure to facilitate the mining activities
proposed including mining, power, office and workshop
infrastructure.
• Ore will be Toll treated. The metallurgical process proposed is a
conventional carbon-in-leach (CIL) process plant, inclusive of
single stage crushing ball mill comminution circuit and gravity
concentrator as typically used in the Australian gold mining
industry.
• The metallurgical process proposed is a well-tested and proven
technology, dating back to the 1980s and used extensively in the
Australian gold mining industry and internationally.
• A 97% metallurgical recovery has been applied for mined open
pit ore based on historical recovery data at Tick Hill.
• A 85% metallurgical recovery has been applied for the
treatment of gold tailings. This has been determined from test
work undertaken.
• No deleterious elements are present.
• The Tick Hill project area has been previously mined and
rehabilitated and as such there is not expected to be any
environmental impacts of significance as a result of the proposed
mining. Ore extracted from site will be toll treated off site.
Previously disturbed areas will be preferentially used for
establishing infrastructure where possible.
• All proposed mining areas lie within granted Mining Leases
which offer ample area for infrastructure establishment.
• Carnaby Resources Ltd has established ground water
piezometers and is involved in ongoing ground water and
environmental monitoring work.
• Statutory approval and permitting applications will include
DMIRS Mining Proposal and DWER Works Approval and there
will be a requirement to update DWER Groundwater Operating
Item Criteria Commentary
The following Mining Recovery and Dilution Parameters were
used in the Mining Resource Inventory Estimation;
Indicated Resources; 95% Mining Recovery, 10% Dilution
Inferred Resources; 50% Mining Recovery, 20% Dilution.
A lower mining recovery and higher dilution was applied to
Inferred resources owing to potential mining issues against the
old stope voids.
• Development excavations will be mined by conventional open
pit drill and blast methods, excavator, front end loaders and 50t
trucks.
• Further geotechnical investigation and assessment will be
completed as the study work progresses.
• Geological drilling: Grade control drilling will be required as the
pit advances to better define the mineralisation prior to mining.
Some holes will be used as resource infill and to probe the areas
with old voids. This drilling will generally be RC located on the
cut back benches.
• All Mineral Resource categories have been included in the
mining study work.
• Both Indicated and Inferred Mineral Resources were used in the
possible production schedule used in the Scoping Study. Inferred
resources account for 30% of the total pit resource ounces used
in the production schedule.
• Infrastructure: The Scoping Study considers the provision of all
necessary infrastructure to facilitate the mining activities
proposed including mining, power, office and workshop
infrastructure.
6 Metallurgical factors or assumptions used in
the Scoping Study
• Ore will be Toll treated. The metallurgical process proposed is a
conventional carbon-in-leach (CIL) process plant, inclusive of
single stage crushing ball mill comminution circuit and gravity
concentrator as typically used in the Australian gold mining
industry.
• The metallurgical process proposed is a well-tested and proven
technology, dating back to the 1980s and used extensively in the
Australian gold mining industry and internationally.
• A 97% metallurgical recovery has been applied for mined open
pit ore based on historical recovery data at Tick Hill.
• A 85% metallurgical recovery has been applied for the
treatment of gold tailings. This has been determined from test
work undertaken.
• No deleterious elements are present.
7 Environmental • The Tick Hill project area has been previously mined and
rehabilitated and as such there is not expected to be any
environmental impacts of significance as a result of the proposed
mining. Ore extracted from site will be toll treated off site.
Previously disturbed areas will be preferentially used for
establishing infrastructure where possible.
• All proposed mining areas lie within granted Mining Leases
which offer ample area for infrastructure establishment.
• Carnaby Resources Ltd has established ground water
piezometers and is involved in ongoing ground water and
environmental monitoring work.
• Statutory approval and permitting applications will include
DMIRS Mining Proposal and DWER Works Approval and there
will be a requirement to update DWER Groundwater Operating

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

15

==> picture [595 x 95] intentionally omitted <==

Commentary
Strategy documents and related licences.
• Waste rock is typically non-acid forming.
• Tailings will be stored off site.
• The Tick Hill Project is located ~120km SSE of Mt Isa, Qld.
• Air services operate out of Phosphate Hill with a sealed airstrip
~30km south of the project area by road. The nearest town is
Duchess ~40km to the north by road.
• Current infrastructure at site is minimal and consists of access
roads, tracks, water tank and bore field pipeline. New
infrastructure required for the proposed operation includes:
• Mining
• Power
• Office and workshop
• Accommodation and flights will use established facilities at
Phosphate Hill.
• All proposed mining areas lie within granted Mining Leases
which offer ample area for infrastructure establishment which is
easily accessed by existing roads and tracks.
• Capital cost estimates have been derived by Carnaby Resources
for mine related capital costs.
• Cost estimates are based on conceptual designs for mines, site
non-process infrastructure and a combination of budget
quotations, factored estimates and cost data from similar
operations/projects. The derivation of cost estimates is
considered reasonable for Scoping Study purposes.
• Operating cost estimates have been derived by Carnaby
Resources for mining costs and for general and administration
costs based on indicative pricing provided by consultants and
nearby operators.
• Toll treatment and haulage costs have been estimated by
Carnaby Resources Ltd via application of quoted cost estimates
from operating process plants and mining operators.
• The total operating cost estimate has been consolidated by
Carnaby Resources Ltd.
• There are no costs relating to deleterious elements.
• All costs have been denominated in A$ and will not be
impacted by movements in exchange rates.
• Haulage costs: No specific allowance has been made for
transportation of gold bullion.
• Refining costs: Gold refining charges have been estimated by
independent consultant Minesure.
• The following royalties are applicable to the project and have
been allowed for in the Scoping Study:
• A 5% royalty on revenue applicable to gold mining operations
is payable to the Queensland government.
• An estimated 0.8% Net Smelter Return royalty is to MIM
Holdings.
• A gold price of A$2,300 per ounce has been used for Scoping
Study economic modelling.
• There is a transparent, quoted market for the sale of gold.
• There has been no NPV or IRR calculated for the Scoping Study.
• All proposed mining and infrastructure areas lie within a
granted MiningLease.
Item Criteria Commentary
Strategy documents and related licences.
• Waste rock is typically non-acid forming.
• Tailings will be stored off site.
8 Infrastructure • The Tick Hill Project is located ~120km SSE of Mt Isa, Qld.
• Air services operate out of Phosphate Hill with a sealed airstrip
~30km south of the project area by road. The nearest town is
Duchess ~40km to the north by road.
• Current infrastructure at site is minimal and consists of access
roads, tracks, water tank and bore field pipeline. New
infrastructure required for the proposed operation includes:
• Mining
• Power
• Office and workshop
• Accommodation and flights will use established facilities at
Phosphate Hill.
• All proposed mining areas lie within granted Mining Leases
which offer ample area for infrastructure establishment which is
easily accessed by existing roads and tracks.
9 Capital and operating costs • Capital cost estimates have been derived by Carnaby Resources
for mine related capital costs.
• Cost estimates are based on conceptual designs for mines, site
non-process infrastructure and a combination of budget
quotations, factored estimates and cost data from similar
operations/projects. The derivation of cost estimates is
considered reasonable for Scoping Study purposes.
• Operating cost estimates have been derived by Carnaby
Resources for mining costs and for general and administration
costs based on indicative pricing provided by consultants and
nearby operators.
• Toll treatment and haulage costs have been estimated by
Carnaby Resources Ltd via application of quoted cost estimates
from operating process plants and mining operators.
• The total operating cost estimate has been consolidated by
Carnaby Resources Ltd.
• There are no costs relating to deleterious elements.
• All costs have been denominated in A$ and will not be
impacted by movements in exchange rates.
• Haulage costs: No specific allowance has been made for
transportation of gold bullion.
• Refining costs: Gold refining charges have been estimated by
independent consultant Minesure.
• The following royalties are applicable to the project and have
been allowed for in the Scoping Study:
• A 5% royalty on revenue applicable to gold mining operations
is payable to the Queensland government.
• An estimated 0.8% Net Smelter Return royalty is to MIM
Holdings.
Revenue factors • A gold price of A$2,300 per ounce has been used for Scoping
Study economic modelling.
Market assessment of gold price • There is a transparent, quoted market for the sale of gold.
Economic evaluation • There has been no NPV or IRR calculated for the Scoping Study.
Social • All proposed mining and infrastructure areas lie within a
granted MiningLease.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

16

==> picture [595 x 95] intentionally omitted <==

Commentary
• There are no Native Title claims pending over the Tick Hill
project area.
• The project area is located within the boundary of the
Stanbroke and Chattsworth Pastoral Leases.
• As the Tick Hill project area is a brownfields site with historical
mining dating back to 1993, there are reasonable grounds to
expect that Government approvals will be received when
required upon successful completion of a Pre-Feasibility Study.
• Government approvals required to advance the project include
converting the Mining Leases from Care & Maintenance back to
active mining. Given that such approvals have been granted to
previous operators in recent history, there is no reason to
suggest that approvals will not be granted once again.
• There are currently no unresolved matters relating to a third
party that would prohibit project development, should that be
the decision resulting from completion of further study work.
• Not applicable as no Ore Reserves are being reported as the
project is at Scoping Study level.
• Not applicable as no Ore Reserve estimate reported.
• No Ore Reserve estimate has been completed as a result of the
Scoping Study.
• Metallurgical recoveries have been based on historical plant
data.
• Costs have been estimated by independent consultants
generally from budget quotations, factored estimates or cost
data from similar operations/projects.
• Cost estimate accuracy for the Scoping Study is considered to
be in the order of ±35%.
Item Criteria Commentary
• There are no Native Title claims pending over the Tick Hill
project area.
• The project area is located within the boundary of the
Stanbroke and Chattsworth Pastoral Leases.
Other • As the Tick Hill project area is a brownfields site with historical
mining dating back to 1993, there are reasonable grounds to
expect that Government approvals will be received when
required upon successful completion of a Pre-Feasibility Study.
• Government approvals required to advance the project include
converting the Mining Leases from Care & Maintenance back to
active mining. Given that such approvals have been granted to
previous operators in recent history, there is no reason to
suggest that approvals will not be granted once again.
• There are currently no unresolved matters relating to a third
party that would prohibit project development, should that be
the decision resulting from completion of further study work.
Classification of Ore Reserves • Not applicable as no Ore Reserves are being reported as the
project is at Scoping Study level.
Ore Reserve Audits or reviews • Not applicable as no Ore Reserve estimate reported.
Discussion of relative accuracy/confidence • No Ore Reserve estimate has been completed as a result of the
Scoping Study.
• Metallurgical recoveries have been based on historical plant
data.
• Costs have been estimated by independent consultants
generally from budget quotations, factored estimates or cost
data from similar operations/projects.
• Cost estimate accuracy for the Scoping Study is considered to
be in the order of ±35%.

==> picture [596 x 11] intentionally omitted <==

==> picture [596 x 10] intentionally omitted <==

17