CAPRICORN METALS LTD — Investor Presentation 2016
May 23, 2016
64670_rns_2016-05-23_ed94b622-b2a0-4829-b56f-dd017cdaa06b.pdf
Investor Presentation
Open in viewerOpens in your device viewer
ASX Code: CMM
KARLAWINDA GOLD PROJECT Resources Rising Stars Conference 24-25[th] May 2016
ABN
841
21
700
105
www.capmetals.com.au
Disclaimer & Competent Person Statement
This presentation contains only a brief overview of Capricorn Metals Limited and its associated entities (“CAPRICORN or CML") and their respective activities and operations. The contents of this presentation, including matters relating to the geology of CML’ projects, may rely on various assumptions and subjective interpretations which it is not possible to detail in this presentation and which have not been subject to any independent verification.
This presentation contains a number of forward-looking statements. Known and unknown risks and uncertainties, and factors outside of CML’ control, may cause the actual results, performance and achievements of CML to differ materially from those expressed or implied in this presentation. To the maximum extent permitted by law, CML does not warrant the accuracy, currency or completeness of the information in this presentation, nor the future performance of CML, and will not be responsible for any loss or damage arising from the use of the information. The information contained in this presentation is not a substitute for detailed investigation or analysis of any particular issue. Current and potential investors and shareholders should seek independent advice before making any investment decision in regard to CML or its activities.
The information in this presentation that relates to Mineral Resources is extracted from the Mineral Resource and Ore Reserve Statement released to the Australian Securities Exchange (ASX) on 25 October 2013 by IGO (Independence Group) and for which Competent Person’s consents were obtained. The Competent Person’s consents remain in place for subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by a subsequent report and accompanying consent.
The Company confirms that it is not aware of any new information or data that materially affects the information included in the original ASX announcement released on 25 October 2013 and, in the case of estimates or Mineral Resources, that all material assumptions and technical parameters underpinning the estimates in the original ASX announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original ASX announcement.
ASX announcements are available on the Company’s website at www.capmetals.com.au
Sole Focus on WA Gold
==> picture [10 x 9] intentionally omitted <==
==> picture [10 x 9] intentionally omitted <==
==> picture [10 x 9] intentionally omitted <==
==> picture [10 x 9] intentionally omitted <==
==> picture [10 x 9] intentionally omitted <==
==> picture [10 x 10] intentionally omitted <==
==> picture [10 x 10] intentionally omitted <==
==> picture [10 x 10] intentionally omitted <==
COMPANY SNAPSHOT
Karlawinda Gold Project is the single focus 650,000oz JORC compliant inferred resource at Bibra Clear, accelerated route to 2018 production $12m spent on scoping study activities Potential for camp-scale exploration success Assets in Madagascar being divested Strong cornerstone support from Regis Resources (9%) Building a simple and highly profitable gold company
==> picture [229 x 308] intentionally omitted <==
==> picture [294 x 117] intentionally omitted <==
Corporate Overview
| Corporate Informa3on | Board of Directors | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| ASX Code Shares on Issue Share Price as at |
19 May 2016 | CMM 487m 12..5c |
Guy Le Clezio Peter Thompson |
Non-Execu;ve Chairman (World Titanium Resources / Eyres Reed) Managing Director (St Barbara / Jubilee / Anaconda) |
||||||
| Market Capitalisa;on as at 19 May 2016 Cash as at 30 March 2016 Unlisted op;ons |
$61m $13m 18.8m |
Heath Hellewell Peter Langworthy |
Non-Execu;ve Director (Doray / IGO / Resolute) Technical Director (Jubilee / WMC / Pacmin) |
|||||||
| 6 Month Share Price | Shareholding Post $12.6m Placement | |||||||||
| $0.000 $0.050 $0.100 $0.150 $0.200 Nov 2015 Dec 2015 |
Jan 2016 Feb 2016 Mar 2016 |
Apr 2016 May 2016 |
44% | 9% 15% 20% Regis Resources 9% Escrowed - Centrepeak 15% Escrowed - Other Greenmount 20% Ins;tu;onal 12% |
||||||
| Source: IRESS | 12% | Free Float 44% |
Karlawinda Gold Project
Major Growth Project
==> picture [9 x 9] intentionally omitted <==
==> picture [9 x 9] intentionally omitted <==
New gold province
Unexplored Archaean Greenstone Belt Gold first discovered in 2005 (WMC) Large “Camp-Scale” exploration potential
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
Advanced resource status
Bibra Gold Deposit:
==> picture [8 x 8] intentionally omitted <==
Defined 650,000oz JORC inferred resource $12m spent by Independence Group (IGO) Resource and exploration drilling Metallurgy
==> picture [8 x 8] intentionally omitted <==
Mining and engineering studies Mining Lease pegged; application underway
==> picture [8 x 8] intentionally omitted <==
==> picture [375 x 418] intentionally omitted <==
----- Start of picture text -----
120°0'0"E 122°0'0"E
Telfer Group
NULLAGINE
3
AUSKI
3
NEWMAN JIGALONG MISSION
Sylvania Dome 3 3
Karlawinda Project
Plutonic Group 0 50
PEAK HILL Kilometers [¯]
3
120°0'0"E 122°0'0"E
22°0'0"S 22°0'0"S
24°0'0"S 24°0'0"S
----- End of picture text -----
Karlawinda Gold Project Major Growth Project
Resource growth
==> picture [10 x 10] intentionally omitted <==
9,642m RC drilling program (47 holes) by CMM Mineralisation in every hole Strong results first 37 holes reported Matching anticipated widths and grades New zones identified Major opportunity to increase resources Updated resource by June 2016 Reviewing and building on Scoping Study
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [375 x 418] intentionally omitted <==
----- Start of picture text -----
120°0'0"E 122°0'0"E
Telfer Group
NULLAGINE
3
AUSKI
3
NEWMAN JIGALONG MISSION
Sylvania Dome 3 3
Karlawinda Project
Plutonic Group 0 50
PEAK HILL Kilometers [¯]
3
120°0'0"E 122°0'0"E
22°0'0"S 22°0'0"S
24°0'0"S 24°0'0"S
----- End of picture text -----
Karlawinda Gold Project
Major Growth Project
==> picture [9 x 9] intentionally omitted <==
==> picture [9 x 9] intentionally omitted <==
Strategic Operational Advantages
60km from premier WA mining centre
==> picture [8 x 8] intentionally omitted <==
Major infrastructure
==> picture [8 x 8] intentionally omitted <==
Sealed roads, airport (daily flights), mining services
==> picture [8 x 8] intentionally omitted <==
Single Native Title Claimant Group
==> picture [8 x 8] intentionally omitted <==
Low CAPEX environment
==> picture [8 x 8] intentionally omitted <==
Commercial
Residual payment: $1.5m due August 2016 (IGO)
==> picture [8 x 8] intentionally omitted <==
- Royalty: 2% Net Smelter Royalty (South32)
==> picture [8 x 8] intentionally omitted <==
- Claw-back right: >5Moz gold and/or 120kt nickel
==> picture [8 x 8] intentionally omitted <==
Buy back 70% interest at 3x costs (BHPB)
==> picture [375 x 419] intentionally omitted <==
----- Start of picture text -----
120°0'0"E 122°0'0"E
Telfer Group
NULLAGINE
3
AUSKI
3
Geology
map
showing
Pilbara
Gold
deposits
and
plutonic
NEWMAN JIGALONG MISSION
Sylvania Dome 3 3
Karlawinda Project
Plutonic Group 0 50
PEAK HILL Kilometers [¯]
3
120°0'0"E 122°0'0"E
22°0'0"S 22°0'0"S
24°0'0"S 24°0'0"S
----- End of picture text -----
Karlawinda Gold Project Major Growth Project
==> picture [9 x 9] intentionally omitted <==
==> picture [9 x 9] intentionally omitted <==
Exploration
Near mine expansion opportunities Dedicated budget – targeting new deposits Large-scale, high-grade potential
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
Funding Recent $12.6 million placement Cash $13m Ongoing sale of assets in Madagascar Funding to end of Feasibility Study
==> picture [328 x 436] intentionally omitted <==
Bibra Gold Deposit Quality, large-scale open pit opportunity
==> picture [8 x 8] intentionally omitted <==
==> picture [9 x 9] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
JORC Compliant Inferred Resource:
18 million tonnes @ 1.1g/t Au for 650,880oz
==> picture [6 x 6] intentionally omitted <==
“Virgin” resource with no legacy issues Mineralisation starts near surface:
- Laterite and oxide resource at surface
==> picture [7 x 6] intentionally omitted <==
Shallow dipping geometry
==> picture [7 x 6] intentionally omitted <==
Low stripping ratio (4:1)
==> picture [7 x 6] intentionally omitted <==
Thick, continuous, tabular gold mineralisation Development of hanging wall lode structures High ounces per vertical metre CIL processing:
Metallurgical testwork: free milling / good recoveries Opportunity for major resource growth!
==> picture [529 x 142] intentionally omitted <==
==> picture [528 x 256] intentionally omitted <==
Bibra Gold Deposit Quality, large-scale open pit opportunity
==> picture [10 x 9] intentionally omitted <==
JORC Compliant Inferred Resource*
18mt @ 1.1g/t Au for 650,880oz gold to a depth of 230m 240,300oz of near surface laterite and saprolite resource (top 65 metres) Resource lies within much larger mineralised envelope Early drilling sets basis for a significantly expanded in-pit resource
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
| Mineralisa3on Type |
Tonnes (Mt) | Au (g/t) Cut | Ounces |
Resource Es3ma3on based on: 43 diamond drill holes: 5,373 metres 266 RC drill holes: 42,564 metres Drill spacing: Inferred boundary 50 x 50 metres Top cut: 10g/t laterite / 16g/t main ore body Lower cut: 0.5g/t Pit Constraint: A$1600/oz op;mal pit shell Review and audit: Op;ro |
Resource Es3ma3on based on: |
|---|---|---|---|---|---|
Laterite |
2.1 | 1.2 | 82,900 | 43 diamond drill holes: 5,373 metres | |
| Upper Saprolite | 0.8 | 0.9 | 21,700 | 266 RC drill holes: 42,564 metres | |
| Lower Saprolite | 2.3 | 1.2 | 88,900 | Drill spacing: Inferred boundary 50 x 50 metres | |
| Transi;onal | 1.3 | 1.1 | 46,800 | Top cut: 10g/t laterite / 16g/t main ore body | |
| Sub Total | 6.5 | 1.1 | 240,300 | Lower cut: 0.5g/t | |
| Fresh | 11.5 | 1.1 | 410,500 | Pit Constraint: A$1600/oz op;mal pit shell | |
| Total Inferred | 18.0 | 1.1 | 650,800 | Review and audit: Op;ro |
See
ASX
announcement
dated
6[th] October
2015
for
JORC
Table
1
details
and
drilling
details**
Bibra Resource – New drilling
Recently
announced
drilling
results: (see
ASX
announcements:
13[th] and
22[nd] April
2016) KBRC
285: 9
metres
@
5.10g/t
Au from
169m 21
metres
@
1.33g/t
Au from
190m KBRC
284: 12
metres
@
1.00g/t
Au from
162m 13
metres
@
1.02g/t
Au from
176m KBRC
286: 15
metres
@
1.07g/t
Au from
203m KBRC
290: 19
metres
@
1.37g/t
Au from
200m 9
metres
@
3.32
g/t
Au from
126m KBRC
294: 23
metres
@
1.13g/t
Au from
160m KBRC
295: 6
metres
@
1.36g/t
Au from
111m 14
metres
@
0.66g/t
Au from
167m 17
metres
@
1.14g/t
Au from
183m KBRC
296: 5
metres
@
3.71g/t
Au from
89m 16
metres
@
0.87g/t
Au from
138m 19
metres
@
1.35g/t
Au from
160 KBRC
297: 10
metres
@
1.09g/t
Au from
160m 22
metres
@
1.58g/t
Au from
171m
==> picture [659 x 318] intentionally omitted <==
Bibra Resource – New drilling
**Recently
announced
drilling
results:**
KBRC
299: 18
metres
@
1.10g/t
Au from
129m 3
metres
@
1.33g/t
Au from
163m KBRC
300: 11
metres
@
1.12g/t
Au from
152m 2
metres
@
7.45g/t
Au from
177m KBRC
305: 18
metres
@
1.06g/t
Au from
133m KBRC
306: 15
metres
@
1.01g/t
Au from
146m KBRC
307: 16
metres
@
1.15g/t
Au from
157m KBRC
311: 24
metres
@
1.01g/t
Au from
52m KBRC
315: 11
metres
@
1.21g/t
Au from
212m KBRC
317: 23
metres
@
1.08g/t
Au from
213m KBRC
319: 12
metres
@
1.64g/t
Au from
206m KBRC
320: 18
metres
@
1.01g/t
Au from
183m*
(see
ASX
announcement:
13[th] May
2016)
==> picture [659 x 319] intentionally omitted <==
Bibra Resource – Hanging Wall Lodes
==> picture [885 x 429] intentionally omitted <==
Bibra Resource Three main resource domains
Current Inferred Resource
18,000,000 @ 1.1g/t Au for 650,800oz
==> picture [8 x 8] intentionally omitted <==
Defined by RC and diamond drilling – typically 50 x 50m Optimised pit utilises non-classified mineral envelope ONLY inferred resource within the pit reported Resource size within the pit limited by drilling Infill drilling required to classify as Measured & Indicated Down-dip resource expansion opportunity
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [338 x 431] intentionally omitted <==
----- Start of picture text -----
Inferred
resource
Op3mised
open
pit
outline
----- End of picture text -----
Bibra Resource Three main resource domains
Domain (1): Laterite and saprolite (oxide): 6,500,000 @ 1.1g/t Au for 240,300oz
Over 1000m long and up to 500m wide From surface to a depth of approximately 65m Well defined by aircore and RC drilling Infill drilling required to classify as Measured and Indicated
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [348 x 440] intentionally omitted <==
Bibra Resource
Three main resource domains
Domains (2 & 3): Main & Hanging Wall Lodes (fresh)
==> picture [8 x 8] intentionally omitted <==
11,500,000 @ 1.1g/t Au for 410,000oz
==> picture [8 x 8] intentionally omitted <==
MAIN LODES
Resource currently defined over 700m of strike length and approximately 400m down dip
==> picture [8 x 8] intentionally omitted <==
Completed 47 hole (9,642m) RC drilling program aimed at extending resource up to 300m further down dip and with potential to extend to the south Mineralisation remains open with higher grade targets defined
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
Potential to expand open pit to the west
==> picture [8 x 8] intentionally omitted <==
New
drilling
(CMM)
Bibra Resource
Three main resource domains
Domains (2 & 3): Main & Hanging Wall Lodes (fresh)
11,500,000 @ 1.1g/t Au for 410,500oz
==> picture [8 x 8] intentionally omitted <==
MAIN LODES
==> picture [8 x 8] intentionally omitted <==
Resource currently defined over 700m of strike length and approximately 400m down dip
==> picture [8 x 8] intentionally omitted <==
Completed 47 hole (9,642m) RC drilling program aimed at extending resource up to 300m further down dip and with potential to extend to the south
==> picture [8 x 8] intentionally omitted <==
Mineralisation remains open with higher grade targets defined
==> picture [8 x 8] intentionally omitted <==
Potential to expand open pit to the west
==> picture [8 x 8] intentionally omitted <==
==> picture [352 x 446] intentionally omitted <==
Bibra Resource
Three main resource domains
Domains (2 & 3): Main & Hanging Wall Lodes (fresh) 11,500,000 @ 1.1g/t Au for 410,000oz
HANGING WALL LODES
==> picture [8 x 8] intentionally omitted <==
Resource currently defined over 500m of strike length and approximately 400m down dip
==> picture [8 x 8] intentionally omitted <==
Current RC drilling program has intersected the Hanging Wall zone at least 150 metres north of the resource boundary:
==> picture [8 x 8] intentionally omitted <==
KBRC 285: 9 metres @ 5.10g/t Au KBRC 296: 5 metres @ 3.71g/t Au Mineralisation remains open with higher grade targets defined Potential to expand open pit to the west
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [353 x 451] intentionally omitted <==
Bibra Resource
Three main resource domains
Domains (2 & 3): Main & Hanging Wall Lodes (fresh) 11,500,000 @ 1.1g/t Au for 410,000oz
HANGING WALL LODES
==> picture [8 x 8] intentionally omitted <==
Resource currently defined over 500m of strike length and approximately 400m down dip
==> picture [8 x 8] intentionally omitted <==
Current RC drilling program has intersected the Hanging Wall zone at least 150 metres north of the resource boundary:
==> picture [8 x 8] intentionally omitted <==
9 metres @ 5.10g/t Au
KBRC 285:
KBRC 296: 5 metres @ 3.71g/t Au
Mineralisation remains open with higher grade targets defined
==> picture [8 x 8] intentionally omitted <==
Potential to expand open pit to the west
==> picture [8 x 8] intentionally omitted <==
==> picture [357 x 451] intentionally omitted <==
Scoping Study to Feasibility Study
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
Quality Scoping Study activities well advanced
Results reported end-July 2016
==> picture [6 x 7] intentionally omitted <==
Approximately $12m spent historically Current work updates and expands Industry recognised consultants
Resource estimation and audit
==> picture [6 x 7] intentionally omitted <==
Mining studies
==> picture [6 x 7] intentionally omitted <==
Metallurgy
==> picture [6 x 7] intentionally omitted <==
Geotechnical
==> picture [6 x 7] intentionally omitted <==
Process plant design
==> picture [6 x 7] intentionally omitted <==
Hydrology
==> picture [6 x 7] intentionally omitted <==
Archaeological and ethnographic
==> picture [6 x 7] intentionally omitted <==
Environment
==> picture [6 x 7] intentionally omitted <==
Transition into Feasibility Study Funding in place for both scoping and feasibility study
==> picture [500 x 357] intentionally omitted <==
Exploration Near Pit and Regional
==> picture [857 x 229] intentionally omitted <==
==> picture [172 x 189] intentionally omitted <==
NEAR TERM UPSIDE! IS THIS A NEW GOLD PROVINCE ?
==> picture [172 x 189] intentionally omitted <==
Exploration Near Pit and Regional
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
-
Simple, consolidated, low-cost tenement package
-
Large areas of Archaean greenstone under cover:
-
Shallow recent transported sediments
==> picture [8 x 8] intentionally omitted <==
- Bangemall Basin
==> picture [8 x 8] intentionally omitted <==
-
Comprehensive database for drill targeting: 36,000m aircore drilling
-
Numerous high priority prospects: Bibra extensions
-
Francopan Prospect
==> picture [8 x 8] intentionally omitted <==
- K3 Prospect
==> picture [8 x 8] intentionally omitted <==
==> picture [527 x 247] intentionally omitted <==
==> picture [527 x 146] intentionally omitted <==
----- Start of picture text -----
NEWMAN JIGALONG MISSION
Sylvania Dome 3 3
Karlawinda Project
24°0'0"S 24°0'0"S
----- End of picture text -----
Exploration Near Pit and Regional
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
- Large-scale exploration potential within 8km of Bibra
==> picture [540 x 365] intentionally omitted <==
At least 13km of prospective geology
-
Demonstrated endowment across the project area
-
Excellent, but still limited database
-
Wide spaced aircore drilling
==> picture [8 x 8] intentionally omitted <==
- Area largely under transported cover
==> picture [8 x 8] intentionally omitted <==
-
Understanding the data
-
Old saying: “There is a mine hidden in your data”
==> picture [8 x 8] intentionally omitted <==
- Systematic, effective exploration to run in parallel to the ongoing resource work at Bibra
Exploration Near Pit and Regional
==> picture [569 x 384] intentionally omitted <==
Bibra Satellite Targets
Current focus on the immediate west of Bibra Early drilling targets
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
“T2” Target Potential next “stacked lode” KBRC377: 8 metres @ 1.15g/t Au KBRC150: 17 metres @ 1.00g/t Au KBRC160: 12 metres @ 1.02g/t Au
==> picture [8 x 8] intentionally omitted <==
Exploration Near Pit and Regional
==> picture [569 x 384] intentionally omitted <==
Bibra Satellite Targets Current focus on the immediate west of Bibra Early drilling targets “T2” Target Potential next “stacked lode” KBRC377: 8 metres @ 1.15g/t Au KBRC150: 17 metres @ 1.00g/t Au KBRC160: 12 metres @ 1.02g/t Au
Exploration Near Pit and Regional
==> picture [576 x 389] intentionally omitted <==
Bibra Satellite Targets
Current focus on the immediate west of Bibra Early drilling targets
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
“T1” Target KBRC019: 12 metres @ 1.5g/t Au Untested near surface along strike
==> picture [8 x 8] intentionally omitted <==
Exploration Near Pit and Regional
==> picture [576 x 389] intentionally omitted <==
Bibra Satellite Targets
Current focus on the immediate west of Bibra
==> picture [8 x 8] intentionally omitted <==
Early drilling targets
==> picture [8 x 8] intentionally omitted <==
“T1” Target
==> picture [8 x 8] intentionally omitted <==
KBRC019: 12 metres @ 1.5g/t Au Untested near surface along strike
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
Exploration Near Pit and Regional
Bibra Satellite Targets
- Southern Extension ~1.5km of Bibra stratigraphy south of the resource
==> picture [8 x 8] intentionally omitted <==
- Limited drilling has intersected gold in most holes
==> picture [8 x 8] intentionally omitted <==
KBRC056: 11 metres @ 1.0g/t Au KBRC040: 6 metres @ 3.5g/t Au KBRC280D: 5 metres @ 3.5g/t Au
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [8 x 8] intentionally omitted <==
==> picture [549 x 371] intentionally omitted <==
Exploration Near Pit and Regional
Regional Targets
B1 Trend 8km extension of the Bibra stratigraphy Wide spaced, shallow aircore drilling
==> picture [8 x 8] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
Area largely under transported cover Numerous significant results in fresh rock and regolith
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
Results include:
==> picture [7 x 7] intentionally omitted <==
KBAC1135 2 metres @ 2.75g/t Au KBAC1036 6 metres @ 2.40g/t Au KBAC0958 5 metres @ 3.55g/t Au KBD035 5 metres @ 2.34g/t Au KBAC0199 4 metres @ 2.32g/t Au
==> picture [5 x 5] intentionally omitted <==
==> picture [5 x 5] intentionally omitted <==
==> picture [5 x 5] intentionally omitted <==
==> picture [5 x 5] intentionally omitted <==
==> picture [5 x 5] intentionally omitted <==
==> picture [551 x 372] intentionally omitted <==
Exploration Near Pit and Regional
==> picture [563 x 380] intentionally omitted <==
Regional Targets
Francopan-K3 Prospects Confirmation: large-scale Archaean gold system! Gold mineralisation intersected over 5km! Major fault zone Limited drilling Bangemall cover sequence Results include:
==> picture [8 x 8] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
KBD025: 81m @ 1.2g/t Au. Includes: 7m @ 3.5g/t Au (1m @ 20.3g/t Au) 15m @ 3.0g/t Au 6m @ 3.1g/t Au
==> picture [7 x 7] intentionally omitted <==
KBD009: 33m @ 1.0g/t Au. Includes: 6m @ 4.5g/t Au (1m @ 18.3g/t Au) KBD001: 37m @ 1.9g/t Au 8m @ 5.1g/t Au (1m @ 21.8g/t Au)
==> picture [7 x 7] intentionally omitted <==
==> picture [7 x 7] intentionally omitted <==
Summary – 8 reasons to invest in CMM
Rapid pathway to gold production Ore body is simple and predictable Pipeline of positive news flow Resource upgrade – June 2016 Rapid completion of Scoping Study then moving into Feasibility Study
==> picture [12 x 12] intentionally omitted <==
==> picture [12 x 12] intentionally omitted <==
==> picture [12 x 12] intentionally omitted <==
==> picture [12 x 12] intentionally omitted <==
==> picture [12 x 11] intentionally omitted <==
Excellent leverage to Australian gold price Massive potential for new discoveries in 2016-17 Follow the money (look at our share register)
==> picture [12 x 11] intentionally omitted <==
==> picture [12 x 11] intentionally omitted <==
==> picture [12 x 11] intentionally omitted <==