Borr Drilling Management Reports 2019

Mar 5, 2019

6241_rns_2019-03-05_712599ce-c833-4d97-9815-305699f5373f.pdf

Management Reports

Open in viewer

Opens in your device viewer

Fleet Status Report

5 thMarch 2019

Operational HQ

+971 4 4487501

Borr Drilling Management DMCC 28th Floor, Reef Tower, Cluster O, Jumeirah Lake Towers, Post Box - 36913, Dubai – UAE

Financial HQ

Borr Drilling Management AS Klingenberggata 4 0160 Oslo - Norway +47 22 48 3000

Fleet Status Report - 05th March 2019

New Contracts / Extensions / Amendments

Letters of Intent / Negotiations

Prospector 5:

• LOI: April 2019 to October 2019, Operator Undisclosed, North Sea

Grid:

• Advanced Negotiations: mid 2019, Multi-year contract, Operator Undisclosed

Gersemi:

• Advanced Negotiations: mid 2019, Multi-year contract, Operator Undisclosed

Saga:

• Advanced Negotiations: early 2020, Multi-year contract, Operator Undisclosed

Skald:

• Advanced Negotiations: early 2020, Multi-year contract, Operator Undisclosed

This summary is provided as a courtesy and is not intended to replace a detailed review of the Fleet Status Report. This summary contains information on letters of intent/award and advanced negotiations. Letters of intent/award or advanced negotiations may not result in an actual drilling contract.

Forward Looking Statements:

The statements described in this status report that are not historical facts are "Forward Looking Statements".

Forward Looking Statements reflect management's current expectations and assumptions, and are subject to inherent uncertainties, risks and changes in circumstances that are difficult to predict. No assurance can be given that the expectations expressed in these Forward-Looking Statements will prove to be correct. Actual results could differ materially from expectations expressed in, or implied by, the Forward-Looking Statements if one or more of the underlying assumptions or expectations proves to be inaccurate or is unrealised. These include, but are not limited to, changes to commencement dates, contract duration, earned day rates, locations and other contractual terms; risks relating to the delivery of drilling rigs under construction; sale and purchase of drilling units; oil and gas prices; and risks associated with international operations generally.

No Forward-Looking Statement contained in herein or expressed elsewhere should be relied upon as predicting future events. We undertake no obligation to update or revise any Forward-Looking Statements to reflect events or circumstances that occur, or which we become aware of, after the date hereof, except as otherwise may be required by law.

Fleet Status Report - 05th March 2019

Rig Name Rig Design Rig Water
Depth (ft)
Year Built Customer / Status Contract Start Contract End Location Comments
Premium Jack-Ups
Idun KFELS Super B Bigfoot Class 350 ft 2013 Available Singapore Warm Stacked
Mist KFELS Super B Bigfoot Class 350 ft 2013 Available Singapore Warm Stacked
Galar PPL Pacific Class 400 400 ft 2017 Available Singapore Warm Stacked
Gunnlod PPL Pacific Class 400 400 ft 2018 Available Singapore Warm Stacked
Gyme PPL Pacific Class 400 400 ft 2018 Available Singapore Warm Stacked
Njord PPL Pacific Class 400 400 ft 2019 Available Singapore Warm Stacked
Gersemi PPL Pacific Class 400 400 ft 2018 Available Singapore Warm Stacked, Adv. Negotiations
Grid PPL Pacific Class 400 400 ft 2018 Available Singapore Warm Stacked, Adv. Negotiations
Saga KFELS Super B Bigfoot Class 400 ft 2018 Available Singapore Warm Stacked, Adv. Negotiations
Skald KFELS Super B Bigfoot Class 400 ft 2018 Available Singapore Warm Stacked, Adv. Negotiations
Available December - 2018 February - 2019 In Transit Mobilization
Odin KFELS Super B Bigfoot Class 350 ft 2013 PanAmerican March - 2019 November - 2019 Mexico Committed
Total January - 2019 March - 2019 Nigeria Operating
Frigg 1 KFELS Super A 400 ft 2013 Shell (via Assignment) April - 2019 October - 2019 Nigeria Committed with option to extend
Prospector 1 1 F&G, JU2000E 400 ft 2013 Tulip December - 2018 May - 2019 Netherlands Operating with option to extend
Available February - 2019 March - 2019 United Kingdom Warm Stacked
Prospector 5 1 F&G, JU2000E 400 ft 2014 Undisclosed April - 2019 October - 2019 Netherlands LOI
2018 Available September - 2018 March - 2019 Nigeria Mobilization
Gerd PPL Pacific Class 400 400 ft Exxon March - 2019 March - 2021 Nigeria Committed with option to extend
Available September - 2018 April - 2019 Singapore Activation and Mobilization
Groa PPL Pacific Class 400 400 ft 2018 Exxon April / May - 2019 April / May - 2021 Nigeria Committed with option to extend
KFELS Super A 400 ft Available September - 2018 April - 2019 Netherlands Activation and Mobilization
Ran 1 2013 Spirit Energy April - 2019 March - 2020 United Kingdom Committed
400 ft Perenco September - 2018 April - 2019 Gabon Operating
Norve PPL Pacific Class 400 2011 Available May - 2019 June - 2019 Gabon / Cameron Warm Stacked
BW Energy Dussafu July -2019 April - 2020 Gabon Committed
Natt PPL Pacific Class 400 400 ft 2018 Available October - 2018 March - 2019 In Transit Mobilization
First E&P March / April - 2019 March / April - 2021 Nigeria Committed with option to extend
Standard Jack-Ups
C20051 CFEM T-2005-C 360 ft 1982 Total September - 2018 March - 2019 Netherlands Operating
Dhabi II Baker Marine BMC-150 ILC 150 ft 1981 NDC (ADOC) April - 2017 July - 2019 United Arab Emirates Operating
B152 Baker Marine BMC-150 ILC 150 ft 1982 NDC (ADOC) April - 2017 November - 2019 United Arab Emirates Operating
B391 Baker Marine Europe Class 250 ft 1981 Spirit Energy March - 2018 December - 2019 United Kingdom Operating with option to extend
Semi-Submersible
MSS1 Offshore Company (IDC) SCP III M2 1500 ft 1979 TAQA March - 2018 November - 2019 United Kingdom Operating with option to extend

Fleet Status Report - 05th March 2019

Rig Name Rig Design Rig Water
Depth (ft)
Year Built Customer / Status Contract Start Contract End Location Comments
Jack-Ups Under Construction
Hild KFELS Super B Bigfoot Class 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in October - 2019
Heimdal KFELS Mod V 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in January - 2020
Hermod KFELS Mod V 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in April - 2020
Huldra KFELS Mod V 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in July - 2020
Tivar KFELS Super B Bigfoot Class 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in July - 2020
Heidrun KFELS Mod V 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in October - 2020
Vale KFELS Super B Bigfoot Class 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in October - 2020
Var KFELS Super B Bigfoot Class 400 ft Under Construction KFELS shipyard, Singapore Rig Delivery in December - 2020
Cold Stacked Jack-Ups
Atla F&G, JU 2000 400 ft 2003 United Arab Emirates
Balder F&G, JU 2000 400 ft 2003 Cameroon
Baug 1 F&G, Mod VI Universe Class 394 ft 1991 United Kingdom Not Marketed
Eir 1 F&G, Mod VI Universe Class 394 ft 1999 United Kingdom Not Marketed

Forward Looking Statements: 1 - HD/HE Capability.

The statements described in this status report that are not historical facts are "Forward Looking Statements".

Forward Looking Statements reflect management's current expectations and assumptions, and are subject to inherent uncertainties, risks and changes in circumstances that are difficult to predict. No assurance can be given that the expectations expressed in these Forward-Looking Statements will prove to be correct. Actual results could differ materially from expectations expressed in, or implied by, the Forward-Looking Statements if one or more of the underlying assumptions or expectations proves to be inaccurate or is unrealised. These include, but are not limited to, changes to commencement dates, contract duration, earned day rates, locations and other contractual terms; risks relating to the delivery of drilling rigs under construction; sale and purchase of drilling units; oil and gas prices; and risks associated with international operations generally.

No Forward-Looking Statement contained in herein or expressed elsewhere should be relied upon as predicting future events. We undertake no obligation to update or revise any Forward-Looking Statements to reflect events or circumstances that occur, or which we become aware of, after the date hereof, except as otherwise may be required by law.

Operating / Committed Available Cold Stack Under Construction
Premium Jack-Ups 29 9 10 2 8
Standard Jack-Ups 6 4 2
Total Jack-Ups 35
Semi - Submersible 1 1
Total Fleet 36 14 10 4 8

Fleet Status Report - 05th March 2019

Rig Name Location 2018 2019 2020 2021
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Premium Jack-Ups
Idun Singapore Warm Stacked
Mist Singapore Kris Energy Warm Stacked
Galar Singapore Warm Stacked
Gunnlod Singapore Warm Stacked
Gyme Singapore Warm Stacked
Njord Singapore Warm Stacked
Gersemi Singapore Warm Stacked, Advanced Negotiations
Grid Singapore Warm Stacked, Advanced Negotiations
Saga Singapore Warm Stacked, Advanced Negotiations
Skald Singapore Warm Stacked, Advanced Negotiations
Odin In Transit / Mexico Mobilization PanAmerican
Frigg 1 Nigeria Total Total
Shell (via Assignment)
Option
Prospector 1 1 Netherlands Tulip
Prospector 5 1 United Kingdom / Netherlands Nexen LOI - Undisclosed
Gerd Nigeria Un
Mobilization
der
Exxon 2 x 1 Year Optional Period
Groa Singapore / Nigeria Activation & Mobilization cked
Exxon
2 x 1 Year Optional Period
Ran 1 Netherlands / United Kingdom Activation & Mobilization Spirit Energy
Norve Gabon / Cameron BW Energy Dussafu
Perenco
BW Energy Dussafu
Warm Sta
Natt In Transit / Nigeria Mobilization First E&P 1 Year Optional Period
Standard Jack-Ups
C20051 Netherlands Perenco
Total
Dhabi II United Arab Emirates NDC (ADOC)
B152 United Arab Emirates NDC (ADOC)
B391 United Kingdom Spirit Energy Up to 13 option wells (425 days)
Semi-Submersible
MSS1 United Kingdom TAQA Up to 5 option wells (375 days)
Contract Option Available Under Construction
1 - HD/HE Capability.

Fleet Status Report - 05th March 2019

Location 2018 2019 2020 2021
Rig Name Q1
Q2
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Jack-Ups Under Construction
Hild KFELS shipyard, Singapore Rig Delivery in October - 2019
Heimdal KFELS shipyard, Singapore Rig Delivery in January - 2020
Hermod KFELS shipyard, Singapore Rig Delivery in April - 2020
Huldra KFELS shipyard, Singapore Rig Delivery in July - 2020
Tivar KFELS shipyard, Singapore Rig Delivery in July - 2020
Heidrun KFELS shipyard, Singapore Rig Delivery in October - 2020
Vale KFELS shipyard, Singapore Rig Delivery in October - 2020
Var KFELS shipyard, Singapore Rig Delivery in December - 2020
Cold Stacked Jack-Ups
Atla United Arab Emirates
Balder Cameron
Baug 1 United Kingdom Not Marketed
Eir 1 United Kingdom Not Marketed
Contract Option Available Under Construction

1 - HD/HE Capability.

Forward Looking Statements:

The statements described in this status report that are not historical facts are "Forward Looking Statements".

Forward Looking Statements reflect management's current expectations and assumptions, and are subject to inherent uncertainties, risks and changes in circumstances that are difficult to predict. No assurance can be given that the expectations expressed in these Forward Looking Statements will prove to be correct. Actual results could differ materially from expectations expressed in, or implied by, the Forward Looking Statements if one or more of the underlying assumptions or expectations proves to be inaccurate or is unrealised. These include, but are not limited to, changes to commencement dates, contract duration, earned day rates, locations and other contractual terms; risks relating to the delivery of drilling rigs under construction; sale and purchase of drilling units; oil and gas prices; and risks associated with international operations generally.

No Forward Looking Statement contained in herein or expressed elsewhere should be relied upon as predicting future events. We undertake no obligation to update or revise any Forward Looking Statements to reflect events or circumstances that occur, or which we become aware of, after the date hereof, except as otherwise may be required by law.