NEWS RELEASE
Release Time
IMMEDIATE
==> picture [144 x 119] intentionally omitted <==
Date
18 January 2012
Number
01/12
BHP BILLITON PRODUCTION REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2011
-
Western Australia Iron Ore production rose to a record annualised rate of 178 million tonnes per annum (100% basis) in the December 2011 quarter, a 25% increase over the previous corresponding period.
-
A strong recovery in production across the Base Metals portfolio delivered a 27% increase in copper volumes from the September 2011 quarter.
-
Half yearly production records were achieved at New South Wales Energy Coal (Australia) and Cerrejon Coal (Colombia), two of BHP Billiton’s high value, export oriented energy coal operations.
-
Petroleum production increased 36% from the December 2010 half year following the acquisition of the Fayetteville and Petrohawk Onshore US businesses and strong uptime performance from existing, operated assets.
Petroleum
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Crude oil, condensate and natural gas liquids (‘000 boe) | 44,066 | 22,228 | -10% | -5% | 2% |
| Natural gas (bcf) | 391.84 | 214.49 | 108% | 160% | 21% |
| Total petroleum products (million boe) | 109.38 | 57.98 | 36% | 56% | 13% |
Total petroleum production – Petroleum production increased 36 per cent from the December 2010 half year following the acquisition of the Fayetteville and Petrohawk Onshore US businesses and strong uptime performance from existing, operated assets.
Crude oil, condensate and natural gas liquids – Liquids volumes increased marginally from the September 2011 quarter as production from the Onshore US portfolio, development drilling at Shenzi and high uptime at Atlantis (all USA) offset anticipated field decline.
The contribution from the Onshore US portfolio resulted in an eight per cent increase in natural gas liquids production in the December 2011 half year, although anticipated field decline and the temporary shut down of the non-operated Mad Dog facility (USA) resulted in lower overall liquids production relative to the prior corresponding period. Mad Dog is forecast by the operator to remain shut down until the June 2012 quarter.
Natural gas – Natural gas production was higher than all comparable periods reflecting strong performance from the Onshore US and Angostura (Trinidad and Tobago) businesses. Gas production in eastern Australia was down against the September 2011 quarter due to lower seasonal demand.
Aluminium
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Alumina (‘000 tonnes) | 2,061 | 1,001 | 2% | -2% | -6% |
| Aluminium (‘000 tonnes) | 628 | 313 | 0% | 0% | -1% |
Alumina – Sales volumes increased when compared with all corresponding periods as the Alumar refinery (Brazil) continued to deliver into expanded capacity. While a planned calciner outage at Worsley (Australia) constrained production during the December 2011 quarter, volumes are expected to recover as the refinery processes stockpiled hydrate in future periods.
Aluminium – Production was in line with comparable periods with all operations running at, or close to, maximum technical capacity.
Despite our competitive position on the cost curve, our integrated Aluminium business continues to be challenged by underlying cost pressure and weaker prices.
Base Metals
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Copper (‘000 tonnes) | 500.6 | 280.3 | -16% | -7% | 27% |
| Lead (tonnes) | 122,651 | 66,992 | -9% | 3% | 20% |
| Zinc (tonnes) | 51,742 | 28,298 | -33% | -23% | 21% |
| Silver (‘000 ounces) | 20,054 | 10,903 | -15% | -6% | 19% |
| Uranium oxide concentrate (Uranium) (tonnes) | 1,909 | 909 | -3% | -5% | -9% |
Copper – A strong recovery in production across the Base Metals portfolio delivered a 27% increase in copper volumes from the September 2011 quarter. Escondida (Chile) average mill throughput per day steadily increased as operations recovered from the industrial action that affected production in the prior quarter. In addition, Olympic Dam (Australia) benefited from higher grades and improved smelter availability following the planned outage in the September 2011 quarter. The expansion of mining fleets at Antamina (Peru) and Pampa Norte (Chile) contributed to half yearly material mined records for both assets.
Consistent with prior guidance, Escondida production is forecast to be marginally lower in the 2012 financial year, with volumes weighted to the second half. Production is expected to improve beyond the 2012 financial year as mining activities progress towards higher grade ore with completion of the Escondida Ore Access project in the main pit.
At 31 December 2011, the Group had 219,718 tonnes of outstanding copper sales that were revalued at a weighted average price of US$3.45 per pound. The final price of these sales will be determined over the remainder of the 2012 financial year. In addition, 239,156 tonnes of copper sales from the 2011 financial year were subject to a finalisation adjustment in the current period. The finalisation adjustment and provisional pricing impact as at 31 December 2011 will decrease earnings before interest and tax by US$258 million for the period.
Lead/silver – Production at Cannington (Australia) decreased in the December 2011 half year reflecting lower average ore grades.
BHP Billiton Production Report for the half year ended 31 December 2011
2
Zinc – Production at Antamina decreased in the December 2011 half year as mining continued to progress through a copper rich ore zone.
Uranium – Production was broadly in line with all comparable periods.
Diamonds & Specialty Products
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Diamonds (‘000 carats) | 938 | 481 | -32% | -29% | 5% |
Diamonds – As anticipated, production in the December 2011 half year was lower than the prior corresponding period. EKATI (Canada) production is expected to remain constrained in the medium term as the operations extract lower grade material, consistent with the mine plan.
During the quarter, BHP Billiton announced a review of its diamonds business, including the Group’s interests in the EKATI Diamond Mine. The process is ongoing and could continue through the first half of the 2012 calendar year.
Stainless Steel Materials
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Nickel (‘000 tonnes) | 73.5 | 38.4 | -10% | -11% | 9% |
Nickel – Production increased in the December 2011 quarter with the Line 1 furnace at Cerro Matoso (Colombia) operating at full production rates following its successful replacement in the prior quarter. In addition, higher nickel in matte production at the Nickel West Kalgoorlie smelter (Australia) compensated for a decline in metal production at the Nickel West Kwinana refinery that resulted from a planned outage at a third party hydrogen supplier. Nickel West Kwinana is expected to commission its new hydrogen plant in the March 2012 quarter.
The Nickel West Mt Keith Talc Redesign Project, which enables the processing of talc bearing ore, was successfully commissioned in December 2011.
Nickel West operating margins remain sensitive to persistent weakness in nickel prices and the continued strength of the Australian dollar.
BHP Billiton Production Report for the half year ended 31 December 2011
3
Iron Ore
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Iron ore (‘000 tonnes) | 80,644 | 41,072 | 23% | 22% | 4% |
Iron ore – Western Australia Iron Ore (WAIO) delivered another quarterly record as production rose to an annualised rate of 178 million tonnes per annum (100% basis). Consistently strong operating performance, the ramp up of Ore Handling Plant 3 at Yandi, dual tracking of the company’s rail infrastructure and additional ship loading capacity at Port Hedland all contributed to the record performance. While scheduled maintenance, tie-in activities and the wet season in the Pilbara are expected to affect WAIO production in the second half of the 2012 financial year, full year production is now forecast to marginally exceed prior guidance of 159 million tonnes per annum (100% basis).
Production at Samarco (Brazil) was in line with comparable periods with all three pellet plants continuing to run at full capacity.
Manganese
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Manganese ore (‘000 tonnes) | 3,825 | 1,806 | -3% | -1% | -11% |
| Manganese alloy (‘000 tonnes) | 389 | 195 | -1% | 2% | 1% |
Manganese ore – Production was lower than the September 2011 quarter as planned maintenance at Hotazel (South Africa) and a weather related reduction in plant availability at GEMCO (Australia) constrained performance.
Manganese alloy – Alloy production was in line with comparable periods.
Metallurgical Coal
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Metallurgical coal (‘000 tonnes) | 17,784 | 8,493 | -2% | 9% | -9% |
Metallurgical coal – Queensland Coal (Australia) volumes for the December 2011 quarter remained below capacity as a result of stoppages associated with the ongoing labour negotiations and the remnant effects of wet weather. In addition, geotechnical issues at the Gregory Crinum longwall adversely affected production in the period. While system capability is no longer constrained by the 2011 floods, the extent to which industrial action will continue to impact production, sales and unit costs is difficult to predict.
Illawarra Coal (Australia) production increased in the December 2011 half year following successful longwall moves at Dendrobium and Appin in the June 2011 quarter. Volumes were lower than the September 2011 quarter as a planned shutdown of the West Cliff Coal Handling Preparation Plant was undertaken in readiness for commissioning of a plant upgrade. A longwall move and plant shutdown at Dendrobium is scheduled for the March 2012 quarter.
BHP Billiton Production Report for the half year ended 31 December 2011
4
Energy Coal
| DEC | DEC | DEC H11 | DEC Q11 | DEC Q11 | |
|---|---|---|---|---|---|
| 2011 | 2011 | vs | vs | vs | |
| HALF | QTR | DEC H10 | DEC Q10 | SEP Q11 | |
| Energy coal (‘000 tonnes) | 35,379 | 16,919 | 5% | 2% | -8% |
Energy coal – Half yearly production records were achieved at New South Wales Energy Coal and Cerrejon Coal, two of BHP Billiton’s high value, export oriented energy coal operations. However, unfavourable mining conditions and an industrial dispute at South Africa Coal, together with the suspension of operations at San Juan Coal (USA), resulted in lower production relative to the September 2011 quarter.
Throughout this report, unless otherwise stated, production volumes refer to BHP Billiton’s share and exclude suspended and sold operations.
Further information on BHP Billiton can be found at: www.bhpbilliton.com
Media Relations
Investor Relations
Australia
Samantha Stevens Tel: +61 3 9609 2898 Mobile: +61 400 693 915 email: [email protected]
Kelly Quirke Tel: +61 3 9609 2896 Mobile: +61 429 966 312 email: [email protected]
Fiona Martin Tel: +61 3 9609 2211 Mobile: +61 427 777 908 email: [email protected]
United Kingdom and Americas
Ruban Yogarajah Tel: US +1 713 966 2907 or UK +44 20 7802 4033 Mobile: UK +44 7827 082 022 email: [email protected]
Australia
James Agar Tel: +61 3 9609 2222 Mobile: +61 467 807 064 email: [email protected]
Andrew Gunn Tel: +61 3 9609 3575 Mobile: +61 439 558 454 email: [email protected]
United Kingdom and South Africa
Brendan Harris Tel: +44 20 7802 4131 Mobile: +44 7990 527 726 email: [email protected]
Tara Dines Tel : +44 20 7802 7113 Mobile : +44 7825 342 232 Email : [email protected]
Americas
Scott Espenshade Tel: +1 713 599 6431 Mobile: +1 713 208 8565 email: [email protected]
BHP Billiton Limited ABN 49 004 028 077 Registered in Australia Registered Office: 180 Lonsdale Street Melbourne Victoria 3000 Australia Tel +61 1300 55 4757 Fax +61 3 9609 3015
BHP Billiton Plc Registration number 3196209 Registered in England and Wales Registered Office: Neathouse Place London SW1V 1BH United Kingdom Tel +44 20 7802 4000 Fax +44 20 7802 4111
Members of the BHP Billiton Group which is headquartered in Australia
BHP Billiton Production Report for the half year ended 31 December 2011
5
BHP BILLITON PRODUCTION SUMMARY - CONTINUING OPERATIONS
| QUARTER ENDED DEC SEP DEC 2010 2011 2011 |
YEAR TO DATE DEC DEC 2011 2010 |
% CHANGE | |
|---|---|---|---|
| DEC YTD11 DEC Q11 DEC Q11 vs vs vs DEC YTD10 DEC Q10 SEP Q11 |
|||
| PETROLEUM | 20,652 18,482 18,866 82.54 177.35 214.49 2,842 3,356 3,362 37.25 51.40 57.98 1,025 1,060 1,001 314 315 313 302.3 220.3 280.3 64,925 55,659 66,992 36,945 23,444 28,298 51,626 39,439 44,007 11,571 9,151 10,903 957 1,000 909 485 595 766 676 457 481 43.0 35.1 38.4 33,666 39,572 41,072 1,829 2,019 1,806 192 194 195 7,787 9,291 8,493 16,513 18,460 16,919 |
37,348 42,739 391.84 188.37 6,718 6,205 109.38 80.34 2,061 2,025 628 628 500.6 593.5 122,651 134,066 51,742 77,142 83,446 100,987 20,054 23,723 1,909 1,967 1,361 693 938 1,379 73.5 81.5 80,644 65,649 3,825 3,951 389 391 17,784 18,086 35,379 33,619 |
-13% -9% 2% 108% 160% 21% 8% 18% 0% 36% 56% 13% 2% -2% -6% 0% 0% -1% -16% -7% 27% -9% 3% 20% -33% -23% 21% -17% -15% 12% -15% -6% 19% -3% -5% -9% 96% 58% 29% -32% -29% 5% -10% -11% 9% 23% 22% 4% -3% -1% -11% -1% 2% 1% -2% 9% -9% 5% 2% -8% |
| Crude oil & condensate ('000 bbl) Natural gas (bcf) Natural gas liquids ('000 boe) Total petroleum products (million boe) |
|||
| ALUMINIUM | |||
| Alumina ('000 tonnes) Aluminium ('000 tonnes) |
|||
| BASE METALS | |||
| Copper ('000 tonnes) Lead (tonnes) Zinc (tonnes) Gold (ounces) Silver ('000 ounces) Uranium oxide concentrate (tonnes) Molybdenum (tonnes) |
|||
| DIAMONDS AND SPECIALTY PRODUCTS | |||
| Diamonds ('000 carats) |
|||
| STAINLESS STEEL MATERIALS | |||
| Nickel ('000 tonnes) |
|||
| IRON ORE | |||
| Iron ore ('000 tonnes) |
|||
| MANGANESE | |||
| Manganese ore ('000 tonnes) Manganese alloy ('000 tonnes) |
|||
| METALLURGICAL COAL | |||
| Metallurgical coal ('000 tonnes) |
|||
| ENERGY COAL | |||
| Energy coal ('000 tonnes) |
Throughout this report figures in italics indicate that this figure has been adjusted since it was previously reported.
BHP Billiton Production Report for the half year ended 31 December 2011
Page 1
BHP BILLITON ATTRIBUTABLE PRODUCTION
| BHP BILLITON ATTRIBUTABLE PRODUCTION | ||
|---|---|---|
| BHP Billiton Interest |
QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE |
| DEC DEC 2011 2010 |
||
| PETROLEUM | 20,652 19,200 18,652 18,482 18,866 82.54 84.90 131.79 177.35 214.49 2,842 2,442 2,636 3,356 3,362 37.25 35.79 43.25 51.40 57.98 |
37,348 42,739 391.84 188.37 6,718 6,205 |
| Production Crude oil & condensate ('000 bbl) Natural gas (bcf) NGL ('000 boe) (a) Total petroleum products (million boe) |
||
| 109.38 80.34 |
||
| ALUMINIUM | 758 663 725 752 694 267 296 301 308 307 1,025 959 1,026 1,060 1,001 |
1,446 1,514 615 511 |
| ALUMINA Production ('000 tonnes) Worsley 86% Alumar 36% Total |
||
| 2,061 2,025 |
||
| ALUMINIUM Production ('000 tonnes) Hillside 100% Bayside 100% Alumar 40% Mozal 47% Total |
179 173 179 180 180 25 24 24 25 24 43 44 43 44 42 67 64 67 66 67 314 305 313 315 313 |
360 359 49 49 86 87 133 133 |
| 628 628 |
||
| BASE METALS (b) | 112.7 87.7 79.4 49.9 80.4 27.2 24.9 22.5 30.3 30.9 139.9 112.6 101.9 80.2 111.3 47.1 44.4 42.6 32.9 43.0 66.0 64.1 75.7 65.4 70.0 1.5 1.4 1.4 1.4 1.4 47.8 51.1 50.7 40.4 54.6 162.4 161.0 170.4 140.1 169.0 |
130.3 223.4 61.2 50.4 |
| COPPER Payable metal in concentrate ('000 tonnes) Escondida 57.5% Antamina 33.8% Total Cathode ('000 tonnes) Escondida 57.5% Pampa Norte (c) 100% Pinto Valley 100% Olympic Dam 100% Total |
||
| 191.5 273.8 |
||
| 75.9 92.1 135.4 132.4 2.8 2.9 95.0 92.3 |
||
| 309.1 319.7 |
||
| LEAD Payable metal in concentrate (tonnes) Cannington 100% Antamina 33.8% Total |
64,748 51,673 58,414 55,557 66,787 177 237 164 102 205 64,925 51,910 58,578 55,659 66,992 |
122,344 133,277 307 789 |
| 122,651 134,066 |
||
| ZINC Payable metal in concentrate (tonnes) Cannington 100% Antamina 33.8% Total |
14,920 16,129 14,348 14,488 14,745 22,025 24,123 20,385 8,956 13,553 36,945 40,252 34,733 23,444 28,298 |
29,233 30,180 22,509 46,962 |
| 51,742 77,142 |
Refer footnotes on page 4.
BHP Billiton Production Report for the half year ended 31 December 2011
Page 2
BHP BILLITON ATTRIBUTABLE PRODUCTION
| BHP BILLITON ATTRIBUTABLE PRODUCTION | ||
|---|---|---|
| BHP Billiton Interest |
QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE |
| DEC DEC 2011 2010 |
||
| BASE METALS (continued) | 23,133 19,667 17,116 11,063 14,242 28,493 29,892 28,429 28,376 29,765 51,626 49,559 45,545 39,439 44,007 |
25,305 47,940 58,141 53,047 |
| GOLD Payable metal in concentrate (ounces) Escondida 57.5% Olympic Dam (refined gold) 100% Total |
||
| 83,446 100,987 |
||
| SILVER Payable metal in concentrate ('000 ounces) Escondida 57.5% Antamina 33.8% Cannington 100% Olympic Dam (refined silver) 100% Total |
796 670 580 403 549 1,025 813 773 972 1,087 9,509 7,315 8,242 7,559 9,056 241 258 282 217 211 11,571 9,056 9,877 9,151 10,903 |
952 1,599 2,059 2,014 16,615 19,668 428 442 |
| 20,054 23,723 |
||
| URANIUM OXIDE CONCENTRATE Payable metal in concentrate (tonnes) Olympic Dam 100% Total |
957 1,063 1,015 1,000 909 957 1,063 1,015 1,000 909 |
1,909 1,967 |
| 1,909 1,967 |
||
| MOLYBDENUM Payable metal in concentrate (tonnes) Antamina 33.8% Total |
485 334 418 595 766 485 334 418 595 766 |
1,361 693 |
| 1,361 693 |
||
| DIAMONDS AND SPECIALTY PRODUCTS | 676 551 576 457 481 |
938 1,379 |
| DIAMONDS Production ('000 carats) EKATI™ 80% |
||
| STAINLESS STEEL MATERIALS | 12.4 7.8 7.4 10.4 12.3 30.6 25.2 30.8 24.7 26.1 43.0 33.0 38.2 35.1 38.4 |
22.7 24.8 50.8 56.7 |
| NICKEL Production ('000 tonnes) CMSA 99.9% Nickel West 100% Total |
||
| 73.5 81.5 |
Refer footnotes on page 4.
BHP Billiton Production Report for the half year ended 31 December 2011
Page 3
| BHP BILLITON ATTRIBUTABLE PRODUCTION | QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
|
|---|---|---|
| BHP Billiton Interest |
||
| YEAR TO DATE | ||
| DEC DEC 2011 2010 |
||
| IRON ORE | 11,213 11,912 12,480 13,158 13,247 225 305 284 254 334 10,154 9,510 10,044 10,479 10,437 9,078 8,799 9,796 12,708 14,170 2,996 2,705 2,922 2,973 2,884 33,666 33,231 35,526 39,572 41,072 |
26,405 20,853 588 609 20,916 20,240 26,878 17,865 5,857 6,082 |
| Production ('000 tonnes) (d) Newman (e) 85% Goldsworthy Joint Venture 85% Area C Joint Venture 85% Yandi Joint Venture 85% Samarco 50% Total |
||
| 80,644 65,649 |
||
| MANGANESE | 779 514 776 911 808 1,050 838 1,014 1,108 998 1,829 1,352 1,790 2,019 1,806 |
1,719 1,717 2,106 2,234 |
| MANGANESE ORES Saleable production ('000 tonnes) South Africa (f) 60% Australia (f) 60% Total |
||
| 3,825 3,951 |
||
| MANGANESE ALLOYS Saleable production ('000 tonnes) South Africa (f) (g) 60% Australia (f) 60% Total |
123 111 120 124 124 69 61 70 70 71 192 172 190 194 195 |
248 255 141 136 |
| 389 391 |
||
| METALLURGICAL COAL | 4,534 3,955 4,874 5,274 5,006 1,421 1,133 1,426 1,803 1,580 1,832 1,582 1,622 2,214 1,907 7,787 6,670 7,922 9,291 8,493 |
10,280 11,072 3,383 3,334 4,121 3,680 |
| Production ('000 tonnes) (h) BMA 50% BHP Mitsui Coal (i) 80% Illawarra 100% Total |
||
| 17,784 18,086 |
||
| ENERGY COAL | 8,507 8,596 8,228 9,095 7,976 2,296 2,360 3,779 2,467 2,163 3,394 3,978 3,793 4,046 4,027 2,316 2,609 2,538 2,852 2,753 16,513 17,543 18,338 18,460 16,919 |
17,071 17,504 4,630 5,473 8,073 5,900 5,605 4,742 |
| Production ('000 tonnes) South Africa 100% USA 100% Australia 100% Colombia 33% Total |
||
| 35,379 33,619 |
(a) LPG and ethane are reported as Natural Gas Liquid (NGL). Product-specific conversions are made and NGL is reported in barrels of oil equivalent (boe).
(b) Metal production is reported on the basis of payable metal.
(c) Includes Cerro Colorado and Spence.
(d) Iron ore production is reported on a wet tonnes basis.
(e) Newman includes Mt Newman Joint Venture and Jimblebar.
(f) Shown on 100% basis. BHP Billiton interest in saleable production is 60%.
(g) Production includes Medium Carbon Ferro Manganese.
(h) Metallurgical coal production is reported on the basis of saleable product. Production figures include some thermal coal.
(i) Shown on 100% basis. BHP Billiton interest in saleable production is 80%.
BHP Billiton Production Report for the half year ended 31 December 2011
Page 4
PRODUCTION AND SHIPMENT REPORT
| PRODUCTION AND SHIPMENT REPORT | ||
|---|---|---|
| QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE | |
| DEC DEC 2011 2010 |
||
| PETROLEUM | 4,717 5,264 3,086 4,425 2,007 909 7,108 10,878 26 25 4,471 5,919 - 1,949 7,967 7,775 2,303 - 932 285 747 789 880 1,090 2,935 3,273 169 158 |
|
| 37,348 42,739 |
||
| 55.53 59.75 65.53 72.96 9.01 9.83 1.31 2.40 - 0.31 1.19 1.52 199.22 - 19.03 - 2.17 2.72 9.42 12.45 29.43 26.43 |
||
| 391.84 188.37 |
||
| 3,230 3,442 857 913 243 365 - 84 589 532 1,359 - 75 96 63 134 302 639 |
||
| 6,718 6,205 |
||
| 109.38 80.34 |
||
(a) Other Australia includes Minerva.
(b) Gulf of Mexico volumes are net of royalties.
(c) The Genghis Khan operation is reported in Shenzi.
(d) Fayetteville shale acquisition completed on 31 March 2011. Petrohawk Energy Corporation acquisition completed on 20 August 2011. Onshore US volumes are net of mineral holder royalties.
(e) Other Americas includes Neptune, West Cameron 76, Genesis and Starlifter.
(f) Total barrels of oil equivalent (boe) conversions are based on 6,000 scf of natural gas equals 1 boe.
BHP Billiton Production Report for the half year ended 31 December 2011
Page 5
| PRODUCTION AND SHIPMENT REPORT | QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
|
|---|---|---|
| YEAR TO DATE | ||
| DEC DEC 2011 2010 |
||
| ALUMINIUM | 1,446 1,514 615 511 |
|
| 2,061 2,025 |
||
| 1,465 1,502 629 510 |
||
| 2,093 2,012 |
||
| ALUMINIUM Production Hillside, South Africa Bayside, South Africa Alumar, Brazil Mozal, Mozambique Total Sales Hillside, South Africa Bayside, South Africa Alumar, Brazil Mozal, Mozambique Total |
179 173 179 180 180 25 24 24 25 24 43 44 43 44 42 67 64 67 66 67 314 305 313 315 313 160 163 181 163 186 31 38 29 24 25 43 43 44 44 43 76 66 80 60 85 310 310 334 291 339 |
360 359 49 49 86 87 133 133 |
| 628 628 |
||
| 349 308 49 60 87 87 145 131 |
||
| 630 586 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 6
PRODUCTION AND SHIPMENT REPORT
| QUARTER ENDED | QUARTER ENDED | YEAR TO | DATE | |||||
|---|---|---|---|---|---|---|---|---|
| DEC | MAR | JUN | SEP | DEC | DEC | DEC | ||
| 2010 | 2011 | 2011 | 2011 | 2011 | 2011 | 2010 | ||
| BASE METALS | ||||||||
| BHP Billiton attributable production and sales unless otherwise stated. | Metals production is payable | metal unless | otherwise stated. | |||||
| Escondida, Chile | ||||||||
| Material mined (100%) | ('000 tonnes) | 98,167 | 100,966 | 97,705 | 69,006 | 96,152 | 165,158 | 202,008 |
| Sulphide ore milled (100%) | ('000 tonnes) | 18,789 | 15,993 | 16,399 | 12,029 | 18,663 | 30,692 | 38,486 |
| Average copper grade | (%) | 1.26% | 1.15% | 1.06% | 0.97% | 0.97% | 0.97% | 1.25% |
| Production ex mill (100%) | ('000 tonnes) | 194.6 | 153.1 | 141.2 | 91.9 | 144.3 | 236.2 | 392.3 |
| Production | ||||||||
| Payable copper | ('000 tonnes) | 112.7 | 87.7 | 79.4 | 49.9 | 80.4 | 130.3 | 223.4 |
| Payable gold concentrate | (fine ounces) | 23,133 | 19,667 | 17,116 | 11,063 | 14,242 | 25,305 | 47,940 |
| Copper cathode (EW) | ('000 tonnes) | 47.1 | 44.4 | 42.6 | 32.9 | 43.0 | 75.9 | 92.1 |
| Payable silver concentrate | ('000 ounces) | 796 | 670 | 580 | 403 | 549 | 952 | 1,599 |
| Sales | ||||||||
| Payable copper | ('000 tonnes) | 113.9 | 74.3 | 90.9 | 49.2 | 82.1 | 131.3 | 228.7 |
| Payable gold concentrate | (fine ounces) | 23,357 | 16,754 | 20,251 | 10,974 | 14,435 | 25,409 | 49,018 |
| Copper cathode (EW) | ('000 tonnes) | 46.1 | 47.7 | 48.0 | 25.7 | 45.3 | 71.0 | 86.1 |
| Payable silver concentrate | ('000 ounces) | 804 | 569 | 673 | 404 | 558 | 962 | 1,635 |
| Pampa Norte, Chile | ||||||||
| Cerro Colorado | ||||||||
| Material mined | ('000 tonnes) | 18,290 | 16,320 | 17,840 | 14,736 | 16,792 | 31,528 | 33,934 |
| Ore milled | ('000 tonnes) | 4,631 | 4,251 | 4,771 | 4,608 | 4,601 | 9,209 | 9,215 |
| Average copper grade | (%) | 0.76% | 0.75% | 0.74% | 0.72% | 0.71% | 0.72% | 0.75% |
| Production | ||||||||
| Copper cathode (EW) | ('000 tonnes) | 22.4 | 22.6 | 25.7 | 22.5 | 23.5 | 46.0 | 44.1 |
| Sales | ||||||||
| Copper cathode (EW) | ('000 tonnes) | 24.7 | 22.5 | 25.7 | 22.4 | 23.8 | 46.2 | 46.1 |
| Spence | ||||||||
| Material mined | ('000 tonnes) | 18,389 | 19,046 | 19,487 | 19,816 | 26,511 | 46,327 | 35,537 |
| Ore milled | ('000 tonnes) | 4,567 | 4,892 | 4,545 | 3,862 | 4,909 | 8,771 | 8,994 |
| Average copper grade | (%) | 1.28% | 1.23% | 1.22% | 1.30% | 1.46% | 1.39% | 1.27% |
| Production | ||||||||
| Copper cathode (EW) | ('000 tonnes) | 43.6 | 41.5 | 50.0 | 42.9 | 46.5 | 89.4 | 88.3 |
| Sales | ||||||||
| Copper cathode (EW) | ('000 tonnes) | 48.2 | 45.7 | 54.5 | 43.2 | 46.6 | 89.8 | 85.2 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 7
PRODUCTION AND SHIPMENT REPORT
| QUARTER ENDED | QUARTER ENDED | YEAR TO | DATE | |||||
|---|---|---|---|---|---|---|---|---|
| DEC | MAR | JUN | SEP | DEC | DEC | DEC | ||
| 2010 | 2011 | 2011 | 2011 | 2011 | 2011 | 2010 | ||
| BASE METALS | ||||||||
| BHP Billiton attributable production and sales unless otherwise stated. | Metals production is payable | metal unless | otherwise stated. | |||||
| Antamina, Peru | ||||||||
| Material mined (100%) | ('000 tonnes) | 32,722 | 33,154 | 41,669 | 44,212 | 38,759 | 82,971 | 63,321 |
| Sulphide ore milled (100%) | ('000 tonnes) | 9,347 | 9,288 | 9,253 | 9,396 | 9,656 | 19,052 | 18,388 |
| Average head grades | ||||||||
| - Copper | (%) | 1.06% | 0.99% | 0.90% | 1.11% | 1.15% | 1.13% | 1.00% |
| - Zinc | (%) | 1.11% | 1.15% | 1.03% | 0.68% | 0.72% | 0.70% | 1.23% |
| Production | ||||||||
| Payable copper | ('000 tonnes) | 27.2 | 24.9 | 22.5 | 30.3 | 30.9 | 61.2 | 50.4 |
| Payable zinc | (tonnes) | 22,025 | 24,123 | 20,385 | 8,956 | 13,553 | 22,509 | 46,962 |
| Payable silver | ('000 ounces) | 1,025 | 813 | 773 | 972 | 1,087 | 2,059 | 2,014 |
| Payable lead | (tonnes) | 177 | 237 | 164 | 102 | 205 | 307 | 789 |
| Payable molybdenum | (tonnes) | 485 | 334 | 418 | 595 | 766 | 1,361 | 693 |
| Sales | ||||||||
| Payable copper | ('000 tonnes) | 21.8 | 26.1 | 23.5 | 28.2 | 31.7 | 59.9 | 49.5 |
| Payable zinc | (tonnes) | 24,912 | 25,571 | 18,479 | 9,586 | 12,654 | 22,240 | 48,849 |
| Payable silver | ('000 ounces) | 882 | 839 | 658 | 833 | 940 | 1,773 | 2,124 |
| Payable lead | (tonnes) | 503 | 180 | 92 | 91 | 139 | 230 | 1,251 |
| Payable molybdenum | (tonnes) | 292 | 394 | 346 | 549 | 591 | 1,140 | 730 |
| Cannington, Australia | ||||||||
| Material mined | ('000 tonnes) | 824 | 703 | 841 | 819 | 778 | 1,597 | 1,566 |
| Ore milled | ('000 tonnes) | 760 | 713 | 786 | 826 | 888 | 1,714 | 1,591 |
| Average head grades | ||||||||
| - Silver | (g/t) | 459 | 377 | 381 | 332 | 370 | 352 | 453 |
| - Lead | (%) | 9.9% | 8.6% | 8.6% | 7.9% | 8.8% | 8.4% | 9.7% |
| - Zinc | (%) | 3.3% | 3.6% | 2.9% | 2.9% | 2.9% | 2.9% | 3.1% |
| Production | ||||||||
| Payable silver | ('000 ounces) | 9,509 | 7,315 | 8,242 | 7,559 | 9,056 | 16,615 | 19,668 |
| Payable lead | (tonnes) | 64,748 | 51,673 | 58,414 | 55,557 | 66,787 | 122,344 | 133,277 |
| Payable zinc | (tonnes) | 14,920 | 16,129 | 14,348 | 14,488 | 14,745 | 29,233 | 30,180 |
| Sales | ||||||||
| Payable silver | ('000 ounces) | 9,973 | 7,263 | 8,235 | 6,434 | 8,960 | 15,394 | 19,192 |
| Payable lead | (tonnes) | 67,815 | 52,199 | 58,868 | 48,258 | 66,657 | 114,915 | 130,906 |
| Payable zinc | (tonnes) | 16,621 | 12,986 | 14,530 | 15,734 | 14,078 | 29,812 | 29,098 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 8
PRODUCTION AND SHIPMENT REPORT
| QUARTER ENDED | QUARTER ENDED | YEAR TO | DATE | |||||
|---|---|---|---|---|---|---|---|---|
| DEC | MAR | JUN | SEP | DEC | DEC | DEC | ||
| 2010 | 2011 | 2011 | 2011 | 2011 | 2011 | 2010 | ||
| BASE METALS | ||||||||
| BHP Billiton attributable production and sales unless otherwise stated. | Metals production is payable | metal unless | otherwise stated. | |||||
| Olympic Dam, Australia | ||||||||
| Material mined (a) | ('000 tonnes) | 2,513 | 2,433 | 2,675 | 2,543 | 2,440 | 4,983 | 5,223 |
| Ore milled | ('000 tonnes) | 2,622 | 2,670 | 2,533 | 2,471 | 2,440 | 4,911 | 5,127 |
| Average copper grade | (%) | 1.78% | 1.84% | 1.92% | 1.98% | 2.08% | 2.03% | 1.84% |
| Average uranium grade | kg/t | 0.50 | 0.54 | 0.54 | 0.54 | 0.50 | 0.52 | 0.52 |
| Production | ||||||||
| Copper cathode (ER) | ('000 tonnes) | 45.0 | 47.8 | 47.0 | 37.6 | 51.5 | 89.1 | 86.6 |
| Copper cathode (EW) | ('000 tonnes) | 2.8 | 3.3 | 3.7 | 2.8 | 3.1 | 5.9 | 5.7 |
| Uranium oxide concentrate | (tonnes) | 957 | 1,063 | 1,015 | 1,000 | 909 | 1,909 | 1,967 |
| Refined gold | (fine ounces) | 28,493 | 29,892 | 28,429 | 28,376 | 29,765 | 58,141 | 53,047 |
| Refined silver | ('000 ounces) | 241 | 258 | 282 | 217 | 211 | 428 | 442 |
| Sales | ||||||||
| Copper cathode (ER) | ('000 tonnes) | 45.3 | 48.7 | 46.5 | 36.4 | 51.7 | 88.1 | 87.5 |
| Copper cathode (EW) | ('000 tonnes) | 2.9 | 2.7 | 4.1 | 3.5 | 2.5 | 6.0 | 5.7 |
| Uranium oxide concentrate | (tonnes) | 1,121 | 930 | 1,143 | 910 | 1,126 | 2,036 | 1,872 |
| Refined gold | (fine ounces) | 29,757 | 31,742 | 30,323 | 28,979 | 24,327 | 53,306 | 48,671 |
| Refined silver | ('000 ounces) | 150 | 334 | 269 | 289 | 155 | 444 | 351 |
(a) Material mined refers to run of mine ore mined and hoisted.
| Pinto Valley, USA | ||||||||
|---|---|---|---|---|---|---|---|---|
| Production | ||||||||
| Copper cathode (EW) | ('000 tonnes) | 1.5 | 1.4 | 1.4 | 1.4 | 1.4 | 2.8 | 2.9 |
| Sales | ||||||||
| Copper cathode (EW) | ('000 tonnes) | 1.0 | 1.9 | 1.2 | 1.7 | 1.2 | 2.9 | 2.8 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 9
PRODUCTION AND SHIPMENT REPORT
| PRODUCTION AND SHIPMENT REPORT | ||
|---|---|---|
| QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE | |
| DEC DEC 2011 2010 |
||
| DIAMONDS AND SPECIALTY PRODUCTS | 2,267 2,358 938 1,379 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 10
PRODUCTION AND SHIPMENT REPORT
| PRODUCTION AND SHIPMENT REPORT | ||
|---|---|---|
| QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE | |
| DEC DEC 2011 2010 |
||
| STAINLESS STEEL MATERIALS | 22.7 24.8 20.8 24.8 |
|
| Nickel West, Australia Production Nickel contained in concentrate Nickel contained in finished matte Nickel metal Nickel production Sales Nickel contained in concentrate Nickel contained in finished matte Nickel metal Nickel sales |
1.7 1.6 3.3 2.6 1.8 21.8 12.4 16.1 9.0 15.2 7.1 11.2 11.4 13.1 9.1 30.6 25.2 30.8 24.7 26.1 0.8 2.2 3.9 1.2 2.6 19.9 14.7 14.9 10.1 13.9 9.6 9.2 12.4 9.4 10.9 30.3 26.1 31.2 20.7 27.4 |
4.4 2.6 24.2 35.4 22.2 18.7 |
| 50.8 56.7 |
||
| 3.8 2.4 24.0 34.5 20.3 21.8 |
||
| 48.1 58.7 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 11
PRODUCTION AND SHIPMENT REPORT
| PRODUCTION AND SHIPMENT REPORT | ||
|---|---|---|
| QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE | |
| DEC DEC 2011 2010 |
||
| IRON ORE | 26,405 20,853 588 609 20,916 20,240 26,878 17,865 |
|
| 74,787 59,567 |
||
| 87,985 70,078 16,444 15,652 57,717 44,919 |
||
| 74,161 60,571 |
||
| 87,248 71,260 |
||
| Samarco, Brazil Production 2,996 2,705 2,922 2,973 2,884 Shipments 3,460 2,598 2,736 2,926 2,961 |
5,857 6,082 5,887 6,094 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 12
| PRODUCTION AND SHIPMENT REPORT | QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
|
|---|---|---|
| YEAR TO DATE | ||
| DEC DEC 2011 2010 |
||
| MANGANESE | 1,719 1,717 1,714 1,604 |
|
| Australia (a) Saleable production 1,050 838 1,014 1,108 998 Sales 1,173 1,127 1,108 1,094 876 |
2,106 2,234 1,970 1,725 |
|
| MANGANESE ALLOY South Africa (a) (b) Saleable production 123 111 120 124 124 Sales 153 145 123 95 138 |
248 255 233 248 |
|
| Australia (a) Saleable production 69 61 70 70 71 Sales 68 62 75 91 58 |
141 136 149 121 |
(a) Shown on 100% basis. BHP Billiton interest in saleable production is 60%, except Hotazel Manganese Mines which is 44.4%.
(b) Production includes Medium Carbon Ferro Manganese.
BHP Billiton Production Report for the half year ended 31 December 2011
Page 13
PRODUCTION AND SHIPMENT REPORT
| QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE |
|---|---|
| DEC DEC 2011 2010 |
METALLURGICAL COAL
BHP Billiton attributable production and sales unless otherwise stated. ('000 tonnes)
| METALLURGICAL COAL (a) Queensland, Australia Production BMA Blackwater Goonyella Peak Downs Saraji Norwich Park Gregory Joint Venture BMA total BHP Mitsui Coal (b) South Walker Creek Poitrel BHP Mitsui Coal total Queensland total Shipments Coking coal Weak coking coal Thermal coal Total |
1,134 870 1,127 1,367 1,122 1,086 993 1,417 1,463 1,375 984 758 543 971 992 819 532 556 802 900 73 128 386 365 369 438 674 845 306 248 4,534 3,955 4,874 5,274 5,006 765 623 690 1,106 901 656 510 736 697 679 1,421 1,133 1,426 1,803 1,580 5,955 5,088 6,300 7,077 6,586 5,243 3,475 4,865 5,066 4,845 1,886 970 1,411 1,691 1,747 206 125 285 176 20 7,335 4,570 6,561 6,933 6,612 |
2,489 2,592 2,838 2,949 1,963 2,101 1,702 1,691 734 541 554 1,198 |
|---|---|---|
| 10,280 11,072 |
||
| 2,007 1,821 1,376 1,513 |
||
| 3,383 3,334 |
||
| 13,663 14,406 |
||
| 9,911 11,884 3,438 3,539 196 574 |
||
| 13,545 15,997 |
(a) Metallurgical coal production is reported on the basis of saleable product. Production figures include some thermal coal. (b) Shown on 100% basis. BHP Billiton interest in saleable production is 80%.
| Illawarra, Australia Production Shipments Coking coal Thermal coal Total |
1,832 1,582 1,622 2,214 1,907 1,495 1,374 1,407 1,673 1,255 536 211 216 159 441 2,031 1,585 1,623 1,832 1,696 |
4,121 3,680 2,928 2,883 600 898 |
|---|---|---|
| 3,528 3,781 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 14
PRODUCTION AND SHIPMENT REPORT
| PRODUCTION AND SHIPMENT REPORT | ||
|---|---|---|
| QUARTER ENDED DEC MAR JUN SEP DEC 2010 2011 2011 2011 2011 |
YEAR TO DATE | |
| DEC DEC 2011 2010 |
||
| ENERGY COAL | 17,071 17,504 6,985 6,412 10,204 10,691 250 206 |
|
| 17,439 17,309 |
||
| New Mexico, USA Production Navajo Coal San Juan Coal Total Sales - local utility |
1,818 1,629 2,271 1,178 2,060 478 731 1,508 1,289 103 2,296 2,360 3,779 2,467 2,163 3,339 3,385 3,106 3,630 3,108 |
3,238 3,572 1,392 1,901 |
| 4,630 5,473 |
||
| 6,738 6,700 |
||
| NSW Energy Coal, Australia Production Sales Export Inland Total |
3,394 3,978 3,793 4,046 4,027 3,253 3,824 3,522 3,523 3,566 180 339 364 625 333 3,433 4,163 3,886 4,148 3,899 |
8,073 5,900 7,089 5,879 958 584 |
| 8,047 6,463 |
||
| Cerrejon Coal, Colombia Production Sales - export |
2,316 2,609 2,538 2,852 2,753 2,672 2,149 2,853 2,901 2,784 |
5,605 4,742 5,685 5,448 |
BHP Billiton Production Report for the half year ended 31 December 2011
Page 15