Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

Bharat Heavy Electricals Ltd. Capital/Financing Update 2026

Feb 4, 2026

60809_rns_2026-02-04_29ef7080-e425-465e-a06b-3848765ef721.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

==> picture [71 x 59] intentionally omitted <==

==> picture [68 x 59] intentionally omitted <==

==> picture [269 x 75] intentionally omitted <==

Ref: CC/MISC/2025-26/56 Date: 04.02.2026

To

  1. BSE Limited, Mumbai

  2. National Stock Exchange of India Ltd., Mumbai

Subject: Receipt of LOI

Sir/Madam,

Bharat Heavy Electricals Limited (BHEL) has received a Letter of Intent (LOI) from HINDALCO Industries Limited. Details are enclosed at Annexure I.

Digitally signed by SAYED SAYED SALAHUDDIN SALAHUDDIN Date: 2026.02.04 12:49:03 +05'30'

(Sayed Salahuddin) Manager, Corporate Communication, BHEL

==> picture [500 x 52] intentionally omitted <==

==> picture [71 x 59] intentionally omitted <==

==> picture [68 x 59] intentionally omitted <==

==> picture [269 x 75] intentionally omitted <==

Annexure I

a) Name of the entity awarding the order(s)/contract(s);

Reply: HINDALCO Industries Limited (HIL).

b) Significant terms and conditions of order(s)/contract(s) awarded in brief;

Reply: Letter of Intent (LOI) received on 3[rd] February 2026 for Design, Engineering, Supply of equipment, Installation, Commissioning and Performance Acceptance Test (PAT) for 2 x 150 MW BTG Package for Aditya Expansion Project Phase II at Aditya Aluminium, Hindalco Industries Limited at Lapanga, Sambalpur in the state of Odisha, India.

c) Whether order(s) / contract(s) have been awarded by domestic/ international entity;

Reply: Domestic Entity

d) Nature of order(s) / contract(s);

Reply: Design, Engineering, manufacture, supply up to site, unloading & Storage, Erection, Commissioning and performance guarantee test for 2 x 150 MW BTG Package excluding civil work.

e) Whether domestic or international;

Reply: Domestic Tender

f) Time period by which the order(s)/contract(s) is to be executed;

Reply: Commissioning of BTG Package within 35 Months for Unit 1 & 37 Months for Unit 2 from the effective date of contract (Effective date of contract shall be the date of Letter of Intent)

g) Broad consideration or size of the order(s)/contract(s);

Reply: Approx. INR 1200-1500 Crores excluding GST

h) Whether the promoter/ promoter group / group companies have any interest in the entity that awarded the order(s)/contract(s)? If yes, nature of interest and details thereof;

Reply: No.

i) Whether the order(s)/contract(s) would fall within related party transactions? If yes, whether the same is done at “arms length”.

Reply: No.