AI assistant
BEACH ENERGY LIMITED — Capital/Financing Update 2013
May 12, 2013
64558_rns_2013-05-12_bf1dd9a0-e21d-4c2c-8eb2-46f8d2322044.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
==> picture [127 x 86] intentionally omitted <==
For Immediate Release – 13 May 2013 Ref. #028/13
ASX Ltd/SGX Singapore Exchange Ltd Companies Announcement Office Electronic Lodgement System
==> picture [127 x 247] intentionally omitted <==
Dear Sir,
COMPLETION OF INITIAL FARM-IN BY CHEVRON
All conditions precedent for the transfer to Chevron of initial Beach interests in PEL 218 and ATP 855 have been satisfied. Cash payments by Chevron to Beach relating to the initial farmin have been made
On 25 February 2013, Beach Energy Limited (ASX: BPT, “Beach”) and Beach group subsidiaries, signed documents with Chevron Australia Exploration 1 Pty Ltd and Chevron Australia Holdings Pty Ltd (“Chevron”) for Chevron to farm-in to PEL 218 (South Australia) and ATP 855 (Queensland) joint ventures (“Nappamerri Trough Gas Ventures”).
Settlement for the first stage of the transaction, being the transfer to Chevron of the initial equity interest of 30% in PEL 218 and 18% in ATP 855, has now occurred following the receipt of FIRB and other government approvals and third party consents. The first stage transfers to Chevron remain subject to formal South Australian and Queensland government approval, with indicative approval having been granted in Queensland and the farm-in agreement having been approved and registered in South Australia to date.
Beach’s Managing Director, Reg Nelson, said: “The indicative approval by the relevant authorities, to transfer the initial Beach equity interest in the Nappamerri Trough Gas Ventures to Chevron, is the start of what we anticipate will be a value adding relationship in more ways than one. As we have mentioned on a number of occasions and for some time now, there is a gas shortage looming in Eastern Australia. The Nappamerri Trough Gas Ventures, and the substantial gas resource within the acreage, has the potential to be a material source of gas for both the Eastern Australian domestic and international markets in the coming years.”
As a result of the payments made by Chevron at settlement, Beach now has approximately $400 million of cash on hand.
Page 1
ASX Release
==> picture [94 x 64] intentionally omitted <==
Details of the stages of the Chevron farm-in are as follows:
| PEL 218 ATP 855 Stage 1 Initial equity interest of 30% acquired through: US$36 million cash US$95 million carry On completion of Stage 1 work program, Chevron election to proceed to Stage 2 Initial equity interest of 18% acquired through: US$59 million cash Chevron election to proceed to acquire Stage 2 in the period from 1 September 2014 to 31 March 2015 Stage 2 Acquire an additional 30% interest through: US$41 million cash US$47 million carry On completion of Stage 2 work program, Chevron election to proceed Acquire an additional 18% interest through: US$36 million cash Chevron election, from 1 October 2016 to 31 December 2016, to proceed Post Stage 2 Commitment bonus payment of US$35 million |
PEL 218 ATP 855 Stage 1 Initial equity interest of 30% acquired through: US$36 million cash US$95 million carry On completion of Stage 1 work program, Chevron election to proceed to Stage 2 Initial equity interest of 18% acquired through: US$59 million cash Chevron election to proceed to acquire Stage 2 in the period from 1 September 2014 to 31 March 2015 Stage 2 Acquire an additional 30% interest through: US$41 million cash US$47 million carry On completion of Stage 2 work program, Chevron election to proceed Acquire an additional 18% interest through: US$36 million cash Chevron election, from 1 October 2016 to 31 December 2016, to proceed Post Stage 2 Commitment bonus payment of US$35 million |
|---|---|
| Stage 1 Stage 2 Post Stage 2 |
Initial equity interest of 18% acquired through: US$59 million cash Chevron election to proceed to acquire Stage 2 in the period from 1 September 2014 to 31 March 2015 Acquire an additional 18% interest through: US$36 million cash Chevron election, from 1 October 2016 to 31 December 2016, to proceed |
Note 1: Stage 1 has already commenced and includes wells after Encounter-1 and Holdfast-1 for PEL 218 Note 2: Timing of the stages for PEL 218 are expected to be in line with that of ATP 855
If after Stage 1, Chevron elects not to proceed to acquire Stage 2, the interest held by Chevron will be re-assigned to Beach for no consideration. If after Stage 2, Chevron elects not to proceed, Beach may elect to receive a re-assignment of the interests held by Chevron.
Yours sincerely,
==> picture [64 x 58] intentionally omitted <==
Reg Nelson Managing Director, FAusIMM
For more information contact
Corporate
Reg Nelson Beach Energy Ltd 08 8338 2833 Investor Relations Chris Jamieson Beach Energy Ltd 08 8338 2833
==> picture [419 x 16] intentionally omitted <==
Page 2