ABOUT KOPORE METALS
Kopore Metals Limited is a public company listed on the Australian Securities Exchange (ASX) and is actively exploring its copper-silver prospects on the emerging world class Kalahari Copper Belt, Republic of Botswana.
DIRECTORS & MANAGEMENT
TIM GOLDSMITH Non-Executive Chairman
GRANT FERGUSON Managing Director
SHANNON COATES Non-Executive Director
ANDREW METCALFE Company Secretary DAVID CATTERALL Exploration Manager
REGISTERED OFFICE
for the period ending 31 December 2017
HIGHLIGHTS
Technical
-
Ground magnetic and EM survey completed over GW1 and GW2 historical soil anomalies, with the identification of multiple bedrock conductors. Drill testing planned for late Q1/early Q2 2018.
-
NRG Geophysics completed maiden airborne magnetic and electromagnetic (EM) survey over the GWD1 domal target covering an area of 1,091.7km[2] . Estimated completion of processing & reporting of results in early February 2018.
-
Soil sampling programs across the GW3, GWD2 and Senyetse S1 Prospects identified multiple copper soil anomalies, to be drill tested in early 2018.
Level 2, 470 Collins Street Melbourne Vic 3000
Corporate
KOPORE METALS LIMITED ABN 73 149 230 811 EMAIL [email protected] TEL +61 3 9867 7199 FAX +61 3 9867 8587
-
Acquisition of Global Exploration Technologies Pty Ltd (GET) and its Kalahari Copper Belt copper-silver project prospecting portfolio completed on 8 November 2017, following shareholder approval.
-
Metallum Limited’s name changed to Kopore Metals Limited and ASX Code changed to KMT in November 2017.
-
Appointment of Managing Director Mr Grant Ferguson and Non-Executive Chairman Mr Tim Goldsmith. Appointment of Exploration Manager Mr David Catterall. Resignation of Mr Winton Willesee and Ms Erlyn Dale from the Kopore Board.
-
Capital structure post GET transaction of 434,151,400 fully paid ordinary shares, 55 million unlisted options (exercisable at $0.06 each on or before 8 November 2020) and a minor parcel of historical unlisted options (Table 1).
REGISTERED OFFICE
30 January 2018
Kopore Metals Limited (“Kopore” or “Company”) is pleased to provide the following activities report that outlines progress achieved during the December 2017 quarter. The Company has undergone a significant change in focus and direction with the Company’s Botswana copper project acquisition and a focussed exploration and mining experienced board and senior management team, in addition to its existing Western Australian base metals and Philippine copper/gold projects.
Exploration activities have commenced with successful outcomes from the recently completed ground magnetic and soil sampling programs, providing the Company with a strong platform moving forward in 2018. Completion of airborne geophysical survey over the GWD1 potential domal target is expected to provide geological clarity in the test area and further exploration targets in 2018.
==> picture [506 x 322] intentionally omitted <==
Figure 1 - Kopore Metals Limited Regional Licence Map and Key Identified Targets
Page | 2
30 January 2018
==> picture [502 x 381] intentionally omitted <==
Figure 2 - Ghanzi West Project Area with Airborne Magnetic and EM Survey Area Outline
Prospecting Licences Activities
BOTSWANA
Award of Additional Licences
Kopore, through its Botswana subsidiaries Icon Trading Company (Proprietary) Limited and Alvis-Crest (Proprietary) Limited, was awarded four additional Kalahari Copper Belt prospecting licences for copper and silver during the quarter, adjacent to their existing prospecting licences. The four newly granted licences PL207/2017, PL208/2017, PL209/2017 and PL210/2017 provide an additional 2,730 km[2] to Kopore’s prospecting portfolio for a total of 7,891km[2] . This provides Kopore with significant coverage of the Kalahari Copper Belt.
Planned exploration activities will commence in early 2018, with continued historical data collation, review, ground reconnaissance mapping, ground geophysical survey and a potential regional soil sampling program. Kopore aims to identify targeted zones for subsequent geophysics and drilling programs.
Page | 3
30 January 2018
GWD1 Airborne Magnetic and Electromagnetic (EM) Survey
The Company completed its initial airborne magnetic and electromagnetic survey on 30 December 2017, over the Ghanzi West GWD1 copper-silver domal prospect. The airborne survey covered an area of 1,091.7km[2] , covering an interpreted regional ‘domal’ structure which forms a primary base metals target in the Kalahari Copper Belt.
The geophysical survey was conducted by South African based NRG Exploration CC using a helicopter borne electromagnetic and magnetic survey (HTDEM) system. Survey lines were flown at 200 m line spacing, with potential depth penetration from near ground level to >300m below surface. Recent airborne geophysical surveys by other companies across the Kalahari Copper Belt have highlighted the potential success for delineating copper mineralisation utilising these techniques. Initial processing of the data has commenced on site, with corrected data to undergo specialist modelling during January. The Company anticipates results of the airborne survey in early February 2018.
Ground Magnetic and Electromagnetic (EM) Survey – GW1 and GW2 Prospects
During the December 2017 Quarter, Kopore conducted a successful Ground Magnetic and Electromagnetic (EM) Survey over its Ghanzi West GW1 and GW2 prospects, identifying potential bedrock sulphide conductors. The GW1 and GW2 Prospects are located within a regionally interpreted structural corridor (Figure 3) and were originally identified by historical soil sampling program, conducted by a previous explorer. The recent ground geophysical survey over the GW2 Prospect, has provided Kopore an area of potential bedrock conductors (Figure 2) along with a better understanding of lithological and structural geology.
==> picture [452 x 159] intentionally omitted <==
Figure 3 - GW1 Prospect with Ground EM Survey Results and GW2 Prospect Ground EM Survey Results
Soil Sampling Program
Over the December 2017 Quarter, Kopore received the soil sample program results from the September 2017 Quarter field activities. Upon review of the soil sample results, the Company conducted further extensive ground reconnaissance field mapping and historical data compilation, aiming to consolidate the field information with these soil results. This information has provided the Company with a basis for better future exploration program targeting.
Page | 4
30 January 2018
GW3 Prospect
A total of 291 samples were taken at the GW3 prospect at 1km line spacing, 25m sample spacing and assayed at 50m intervals. The results of the program identified three zones of anomalous copper (Figure 4):
-
Anomaly A has been interpreted to overlay a highly magnetic regional zone of the D’Kar formation
-
Anomaly B lies across the interpreted contact position of the D’Kar and Mamuno Formations.
Both Anomalies A and B have coincident zinc anomalies.
- Anomaly C is interpreted to cover a historically mapped thin dolomitic limestone bands interbedded with siltstones and sandstones.
==> picture [518 x 182] intentionally omitted <==
Figure 4 - GW3 Soil Results and GWD2 Domal Prospect Soil Anomaly Map
GWD2 Prospect
The GWD2 soil sampling program was designed to test a new geological interpretation across the northern limb of the GWD2 dome prospect (Figure 4). The program comprised a total of 4 x 3.5km long soil sample lines, at an approximate line spacing of 1km, sampled every 25m and assayed every 50m, for a total of 286 samples.
Three copper soil anomalies were identified:
-
Anomaly A is interpreted to overlay the geological contact of the Ngwako Pan and D’Kar Formations. This contact position is known on the Kalahari Copper Belt to be the key zone for potential copper mineralisation.
-
oAnomaly B is located within 1km of the main soil anomaly and over an interpreted cross cutting structure. -
Anomaly C has been interpreted to overlay a regional low/high magnetic boundary within the D’Kar Formation.
The three identified copper soil anomalies occur with coincident zinc anomalies, providing Kopore with a further impetus to conduct an introductory RAB/RC reconnaissance drilling program over these anomalies.
Page | 5
30 January 2018
SENYETSE – S1 Prospect
A confirmatory soil sampling program was designed to provide further confidence over an area of historical soil sampling. Kopore conducted a small soil sampling program over one of the Bamangwato Concessions Ltd (BCL) historically significant copper soil anomalies.
A total of five lines spaced at 1km apart were sampled at 25m and assayed every 50m for a total of 323 soil samples (Figure 5).
-
A copper, lead and zinc anomaly has been confirmed at Anomaly A, covering a previously identified copper and zinc anomaly on the S1 Prospect and overlying an interpreted geological contact with cross-cutting geological structure. Kopore believes this area to be highly prospective for potential copper mineralisation.
-
Anomaly B is located above an interpreted cross-cutting geological structure that forms part of an elongated anomalous copper zone parallel to interpreted D’Kar Formation lithologies.
==> picture [507 x 362] intentionally omitted <==
Figure 5 - Senyetse Soil Anomaly Map
Planned Activities for March 2018 Quarter
Kopore is one of the first exploration companies to aggressively explore the Ghanzi West region on the Kalahari Copper Belt, Botswana (Figure 1). The Company’s desktop and field activities during the September and December 2017
Page | 6
30 January 2018
Quarters have prompted a significant geological reinterpretation across of our Ghanzi West and Senyetse licence areas and further increasing our view of prospectivity.
Ghanzi West GW1 and GW2 Prospects
Kopore has planned an initial stratigraphic drilling program over the GW1 and GW2 Prospects, anticipated to commence in Q1/Q2 2018, with the key objectives of the RAB and RC drilling program to further strengthen the knowledge of the geological stratigraphy in these immediate areas and to test the identified potential bedrock conductors.
A series of short RAB holes are proposed to test this assumption and to identify any mineralised trap sites associated with either the D’Kar Formation lithologies, containing the two potential conductors and the Sharpe’s Post thrust. The vertical RAB holes will be drilled in a fence line to identify the bedrock lithologies and assist in the estimate of dip and dip direction of the units across the thrust. An RC hole will then be sited to transect the interpreted conductors and to test for mineralisation above the thrust contact or within the structure.
Soil Sampling Program
Further soil sampling programs are planned across the GWD2 domal target newly granted PL210/2017 and across the GWD1 Domal Prospect, upon review of the airborne geophysical results.
Kopore has planned an initial RAB and RC drilling campaign, consisting of 800m RAB and 1500m RC, to investigate the potential bedrock EM conductors and interpreted geological contacts. The drilling campaign is scheduled to commence and reach completion in Q1/Q2 2018, subject to landowner access agreements and Botswana Department of Environmental Affairs (DEA) approval.
Proposed Drilling Activities
Subject to approval by the Botswana Department of Environmental Affairs (DEA) and land owner agreements, Kopore intends to conduct an initial 200m of RAB and 300m of RC reconnaissance drilling program in the 2[nd] Quarter 2018 over the geophysical and soil anomaly areas.
The RAB drilling is expected to assist to accurately define the targeted D’Kar and Ngwako Pan Formation contact position, known as the Kalahari Copper Belt targeted horizon.
AUSTRALIA
Teutonic Project
The Company is currently reprocessing the 2017 Moving Loop Electromagnetic Survey (MLEM) raw data, with the objective of further refinement of drill targets. The reprocessing is expected to be completed by early February 2018.
PHILIPPINES
Comval Project
Kopore is currently assessing its options for the optimal path forward with the Philippines Comval Project.
Page | 7
30 January 2018
Corporate
At 31 December 2017, the Company has a cash position of $2,552,348 and a capital structure as shown in Table 1 below.
Table 1 - Kopore Capital Structure at 31 December 2017
| Number | Description | Exercise Price | Date of Expiry |
|---|---|---|---|
| 434,151,400 | FullyPaid OrdinaryShares | ||
| 55,000,000 | Unlisted Options | $0.06 each | 8 November 2020 |
| 21,750 | Unlisted Options | $2.92 each | 16 July2018 |
| 7,500 | Unlisted Options | $7.60 each | 9 March 2019 |
Expiry of Options
On the 17 November 2017, a total of 34,500 unlisted options exercisable at $7.44 each, expired unexercised.
Change of Company Name and ASX Code
As announced on 20 November 2017, the Company officially changed its name from Metallum Limited to Kopore Metals Limited. The ASX code has changed from MNE to KMT.
Directors’ Appointments and Resignations
Upon completion of the GET acquisition, Mr Winton Willesee and Ms Erlyn Dale resigned from the Board and Managing Director Mr Grant Ferguson and Non-Executive Chairman Mr Tim Goldsmith were appointed.
Marketing
During the December 2017 Quarter, Kopore conducted roadshows across Perth, Brisbane, Sydney and Melbourne.
Competent Persons Statement
The information in this announcement that relates to exploration results is based on information compiled by Mr David Catterall, a Competent Person and a member of a Recognised Professional Organisations (ROPO). David has been engaged by Kopore as a consultant Exploration Manager. David has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. David consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
- END -
FOR FURTHER INFORMATION PLEASE CONTACT:
GRANT FERGUSON Managing Director [email protected]
Page | 8
ASX RELEASE | 30 January 2018
Kopore Metals Limited Prospecting Tenement Schedule - Botswana
| Kopore Metals Limited Prospecting Tenement Schedule - Botswana | |||||||||||||
| Pr | ABO Kopor ospecting Licence |
UT KOPORE METALS e Metals Limited is a public Holder |
Date Granted |
Expiry Date |
Project Area |
Annual Rent |
Annual Rent |
Minimum Expenditure | |||||
| (Year 1) | (Year 2) | (Yea | r 3) | ||||||||||
| **(km2) ** | (BWP) | (A$) | BWP) | (A$) | BWP) | (A$) | BWP) | (A$) | |||||
| P | ~~comp~~ Secur active L203/2016 |
~~any listed on the Australian~~ ities Exchange (ASX) and is ly exploring its copper-silver ~~t th i ld~~ Icon-Trading Company (Proprietary) Limited CO2016/9359 |
1/10/2016 | 30/09/2019 | 928.6 | 4,643 | 605 | 200,000 | 26,076 | 250,000 | 32,595 | 300,000 | 39,114 |
| P | ~~prosp~~ class Repu KOP L204/2016 |
~~cs on e emergng wor~~ Kalahari Copper Belt, blic of Botswana. ORE METALS LIMITED Icon-Trading Company (Proprietary) Limited CO2016/9359 |
1/10/2016 | 30/09/2019 | 925 | 4,625 | 603 | 200,000 | 26,076 | 250,000 | 32,595 | 300,000 | 39,114 |
| P | DIRE ABN EMAI TEL L205/2016 |
CTORS & MANAGEMENT 73 149 230 811 L [email protected] +61 3 9867 7199 Icon-Trading Company (Proprietary) Limited CO2016/9359 |
1/10/2016 | 30/09/2019 | 870.6 | 4,353 | 568 | 200,000 | 26,076 | 250,000 | 32,595 | 300,000 | 39,114 |
| P | ~~TIM G~~ Non-E ~~FAX~~ L128/2013 |
~~OLDSMITH~~ xecutive Chairman ~~+61 3 9867 8587~~ Alvis Crest (Proprietary) Limited CO2016/8899 |
1/07/2016 | 30/06/2018 | 412.2 | 2,061 | 269 | 300,000 | 39,114 | 500,000 | 65,190 | ||
| P | GRAN Manag L129/2013 |
T FERGUSON ing Director Alvis Crest (Proprietary) Limited CO2016/8899 |
1/07/2016 | 30/06/2018 | 418.3 | 2,092 | 273 | 300,000 | 39,114 | 500,000 | 65,190 | ||
| P | SHAN Non-E L127/2017 |
NON COATES xecutive Director Ashmead Holdings (Pty) Ltd CO2016/9358 |
1/07/2017 | 30/06/2020 | 991 | 4,955 | 646 | 200,000 | 26,076 | 250,000 | 32,595 | 300,000 | 39,114 |
| P | ANDR L128/2017 |
EW METCALFE Ashmead Holdings (Pty) Ltd CO2016/9359 |
1/07/2017 | 30/06/2020 | 452 | 2,260 | 295 | 200,000 | 26,076 | 250,000 | 32,595 | 300,000 | 39,114 |
| P | Compa L129/2017 |
ny Secretary Ashmead Holdings (Pty) Ltd CO2016/9360 |
1/07/2017 | 30/06/2020 | 163 | 1,000 | 130 | 200,000 | 26,076 | 250,000 | 32,595 | 300,000 | 39,114 |
| P | ~~DAVID~~ Explor L207/2017 |
~~CATTERALL~~ ation Manager Icon-Trading Company (Proprietary) Limited CO2016/9359 |
1/01/2018 | 31/12/2020 | 985 | 4,925 | 642 | 80,000 | 10,430 | 100,000 | 13,038 | 120,000 | 15,646 |
| P | REGI Level ~~Melbo~~ L208/2017 |
STERED OFFICE 2, 470 Collins Street ~~urne Vic 3000~~ Icon-Trading Company (Proprietary) Limited CO2016/9360 |
1/01/2018 | 31/12/2020 | 581 | 2,905 | 379 | 80,000 | 10,430 | 100,000 | 13,038 | 120,000 | 15,646 |
| P | L209/2017 |
Icon-Trading Company (Proprietary) Limited CO2016/9361 |
1/01/2018 | 31/12/2020 | 164 | 1000 | 130 | 40,000 | 5,215 | 50,000 | 6,519 | 60,000 | 7,823 |
| P | L210/2017 | Alvis Crest (Proprietary) Limited CO2016/8899 | 1/01/2018 | 31/12/2020 | 1000 | 5000 | 652 | 100,000 | 13,038 | 125,000 | 16,298 | 130,000 | 16,949 |
| Total | 7,891 | 39,819 | 5,192 | 2,100,000 | 273,798 | 2,875,000 | 374,843 | 2,230,000 | 290,747 | ||||
| Applying AUD / BWP (Botswana Pula) exchange rate of AU$1 equals BWP 0.13038 as at 31 December 2017 | |||||||||||||
| REGISTERED OFFICE Level 2, 470 Collins Street MELBOURNE VIC 3000 |
REGISTERED OFFICE
30 January 2018
Kopore Metals Limited Exploration Tenement Schedule – Teutonic Project, WA, Australia
| Tenement Id | Holder | Current Area Graticules |
Grant Date | Expiry Date | Ownership |
|---|---|---|---|---|---|
| E37/1037 | SAMR JV | 9 | 23/07/2010 | 22/07/2020 | 70% |
| E37/1281 | PHIL (100% Kopore) |
4 | 21/03/2017 | 20/03/2022 | 100% |
| E37/1282 | PHIL (100% Kopore) |
9 | 21/03/2017 | 20/03/2022 | 100% |
Kopore Metals Limited Exploration Tenement Schedule – Comval Project, Philippines
| Tenement Id | Holder | Current Area (Ha) |
Grant Date | Expiry Date | Ownership |
|---|---|---|---|---|---|
| EP-000001-00-XI | Agusan Metals Corporation |
2,171 | 30/01/2009 | 29/01/2011 | 36% |
| EP-00002-09-XI | Agusan Metals Corporation |
2,139 | 15/08/2015 | 14/08/2017 | 36% |
Comval Projects currently under review