Skip to main content

AI assistant

Sign in to chat with this filing

The assistant answers questions, extracts KPIs, and summarises risk factors directly from the filing text.

AUKING MINING LIMITED Capital/Financing Update 2023

May 31, 2023

64355_rns_2023-05-31_7bd34ccb-1a17-4b8a-a529-5b318dc4f063.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

ASX ANNOUNCEMENT 01 June 2023

AuKing Completes Scoping Study on Halls Creek Copper Project

Cazaly Resources Limited (ASX: CAZ, “Cazaly” or the “Company”) is pleased to announce that AuKing Mining Limited (ASX: “AKN” or “AuKing”) has today released the positive results of their Scoping Study into the Koongie Park copper-zinc project which includes the Company’s Halls Creek Copper deposits. Please refer to AKN’s announcement dated 1 June 2023 entitled, “Koongie Park copper mine development to progress after positive Scoping Study results” (copy attached).

The Company has previously executed a Memorandum of Understanding (MoU) with AKN to include the Company’s Halls Creek Copper deposits into the Scoping Study (ASX:CAZ release 20 December 2022).

Managing Director, Tara French said: “ We are very pleased with the AuKing Scoping Study outcomes that now moves the combined Halls Creek and Koongie Park Copper deposits towards potential development. The positive results of the Scoping Study indicate the potential viability of open pit and underground operations centred around AuKing’s Sandiego Cu-Zn-Ag deposit. We note that the AuKing Board has approved the commencement of further studies for the project, and we look forward to continuing our collaborative working relationship with them.”

ENDS

For and on behalf of the Cazaly Board

For further information please contact:

Tara French (Managing Director) / Mike Robbins (Company Secretary)

Cazaly Resources Limited ABN 23 101 049 334

Tel: +61 8 9322 6283 E: [email protected] Website: www.cazalyresources.com.au

Media Enquiries

David Tasker – Chapter One Advisors [email protected] +61 433 112 936

Forward Looking Statement

This ASX announcement may include forward-looking statements. Forward-looking statements include, but are not limited to, statements concerning Cazaly’s planned exploration program(s) and other statements that are not historical facts. When used in this document, the words such as "could," "plan," "estimate," "expect," "intend," "may”, "potential," "should," and similar expressions are forward looking statements. Although Cazaly Resources believes that its expectations reflected in these forward-looking statements are reasonable, such statements involve risks and uncertainties and no assurance can be given that actual results will be consistent with these forward-looking statements. The forward-looking statements in this announcement reflect views held only as at the date of this announcement.

Level 3, 30 Richardson Street, West Perth WA 6005. PO BOX 396 West Perth WA 6872.

www.cazalyresources.com.au [email protected]

Ph: +61 8 9322 6283

ASX:AKN ABN 29 070 859 522 Phone 07 3535 1208 www.aukingmining.com

Auking Mining Limited Suite 2208, Level 22 127 Creek Street Brisbane Queensland 4000

==> picture [190 x 50] intentionally omitted <==

1 June 2023

ASX RELEASE

Koongie Park copper mine development to progress after positive Scoping Study results

AuKing Mining Limited (ASX: AKN) will progress its Koongie Park copper/zinc Project in Western Australia’s Hall’s Creek region to more advanced development studies after a Scoping Study completed this month confirmed the potential for a financially robust, globally competitive operation.

The Study showed the mine would source mineralisation from four open pit mines and an underground mine for an estimated total production of 110kt Cu, 38kt Zn and 355koz Ag over an 11 year mine life.

CAUTIONARY STATEMENTS

The Scoping Study referred to in this announcement is a preliminary technical and economic study of the potential viability of developing the Koongie Park Copper/Zinc Project by establishing a mine at Sandiego and constructing a processing facility onsite. The proposed development includes the nearby Onedin deposit together with the Mt Angelo North and Bommie deposits owned by Cazaly Resources Ltd (ASX:CAZ). The Scoping Study referred to in this announcement is based on low-level technical and preliminary economic assessments and is insufficient to support estimation of Ore Reserves or to provide assurance of an economic development case at this stage, or certainty that the conclusions of the Scoping Study will be realised.

The Study is based on the material assumptions outlined below. These include assumptions about the availability of funding. While AKN considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or the range of outcomes indicated by the Study will be achieved.

To achieve the range of outcomes indicated in the Scoping Study, development funding in the order of A$135M will likely be required. Investors should note that there is no certainty that the Company will be able to raise that amount of funding when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of AKN’s existing shares.

1

==> picture [33 x 31] intentionally omitted <==

It is also possible that AKN could pursue other “value realization” strategies such as a sale, partial sale or joint venture of the project. If it does, this could materially reduce the Company’s proportionate ownership of the project. Given the uncertainties involved, investors should not make any investment decision based solely on the results of the Scoping Study.

For the first 8 years of production (from the Sandiego, Mt Angelo North and Onedin deposits) 89%, 100% and 58% respectively is in the Indicated Mineral Resource category and the balance is in the Inferred Mineral Resource Category across the different deposits. The Company has therefore concluded it has reasonable grounds for disclosing a Production Target, given that the Scoping Study assumes that in the first 8 years of operation, an average of 86% of the production is from the Indicated Resource category. The inferred mineral resource is not considered to be a determining factor in determining the viability of the Koongie Park Project.

There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of further Measured or Indicated Mineral Resources or that the Production Target or preliminary economic assessment will be realised.

For full details of the Mineral Resource Estimates for the Sandiego and Onedin Resources, including JORC Table 1, please refer to AuKing ASX Release – on 7 April 2022. For full details of the Mineral Resource Estimates for the Mt Angelo North and Bommie Resources, including JORC Table 1, please refer to Cazaly ASX Releases on 31 January 2022 and 2 December 2022 respectively. AuKing confirms that it is not aware of any new information or data that materially affects the information included in those releases. All material assumptions and technical parameters underpinning the estimates in those announcements continue to apply and have not materially changed.

This announcement contains forward-looking statements. AuKing has concluded that it has a reasonable basis for providing these forward-looking statements and believes it has a reasonable basis to expect it will be able to fund development of the Koongie Park Project. However, several factors could cause actual results or expectations to differ materially from the results expressed or implied in the forward-looking statements. Given the uncertainties involved, investors should not make any investment decisions based solely on the results of this study. The Study has been completed to a level of accuracy of +/-30% in line with industry standard accuracy for this stage of development. All dollar figures are presented in Australian dollars (AUD) except where specifically otherwise indicated.

2

Koongie Park copper mine development to progress after positive Scoping Study results

==> picture [33 x 31] intentionally omitted <==

Key Highlights

Scoping Study confirms the potential for a financially robust, globally competitive copper/zinc project in north-east Western Australia, including nearby deposits owned by Cazaly Resources Ltd (ASX:CAZ).

• Mineralisation to be sourced from four open pit mines (Sandiego, Mt Angelo North, Onedin and a later-staged operation at the low-grade Bommie) and an underground mine at Sandiego – all to be processed from a central facility at Sandiego

  • Total Mineral Resource Estimates (MRE) across the deposits are:

Sandiego – 4.1Mt @ 1.38% Cu, 4.28% Zn, 25g/t Ag

Onedin – 4.8Mt @ 0.7% Cu, 3.2% Zn, 0.3g/t Au and 38g/t Ag

Mt Angelo North – 1.72Mt @ 1.4% Cu, 1.4% Zn and 12.3g/t Ag

of which 86% is in the Indicated category across these three deposits, and

Bommie – 95.6Mt @ 0.27% Cu

of which 17% is in the Indicated category

• Life-of-Mine (LOM) of 11 years with an estimated total production of 110kt Cu, 38kt Zn and 355koz Ag

  • Processing nameplate capacity is 750ktpa of run-of-mine (ROM) ore

Strong project economics and financial returns

• Pre-production Capex of A$134M, with an estimated 2.45 years payback period

  • Robust pre-tax NPV8% of approximately A$176.9M and 39.7% IRR

• Life of Mine EBITDA of A$443.8M with an average operating cashflow of A$40.3M per annum.

Board approval to proceed with further study work

• AKN is currently finalising its forward work plan for next stage studies. The Company has sufficient funds to commence further study work and to fund ongoing exploration.

3

==> picture [33 x 31] intentionally omitted <==

AuKing Mining Limited CEO, Paul Williams commented, “ The results of the Scoping Study show the potential to establish a significant copper/zinc mining operation near Halls Creek in north-east Western Australia. The exploration team worked extremely hard throughout late 2021 and 2022 to provide a solid foundation for the Scoping Study. The proposed contribution of the nearby deposits of Cazaly Resources also makes a significant contribution to the project economics.

“The AuKing Board is delighted with the robustness of the Project and its resilience to multiple factors that the resource industry is experiencing in Western Australia with increasing cost escalation and market conditions. The development team will now diligently progress all the necessary technical components and engineering work streams to ensure the Project is sufficiently de-risked allowing the Company to progress further development studies and possibly a final investment decision late next year. The Board has approved the commencement of further studies at the Project due to the compelling economics and the continuing strong copper market fundamentals.”

==> picture [369 x 360] intentionally omitted <==

Figure 1 – Koongie Park Project deposit locations

4

==> picture [33 x 31] intentionally omitted <==

Key Project Metrics

Key metrics below for the Koongie Park Scoping Study are set out below.

==> picture [462 x 450] intentionally omitted <==

----- Start of picture text -----

Key Metrics Unit Value
LOM Ore Mined & Processed tonnes, Mt 8,087,891
LOM Copper Production tonnes, t 109,893
LOM Zinc Production tonnes, t 38,405
LOM Years 11.45
LOM Average Product Grade – Copper % 1.72
LOM Average Product Grade – Zinc % 1.06
NPV (8%) (Pre-Tax) AUD M 176.9
IRR (Pre-Tax) % 39.7
Payback (start of production) # Years 2.45
Initial Capex AUD M 134.6
C1 Costs [1] AUD/t 7,197
Concentrate
Average Copper Price USD/lb 3.90
Average Zinc Price USD/lb 1.33
Average Annual Revenue AUD M 143.6
Average Annual OPEX AUD M 103.3
Average Annual EBITDA AUD M 40.3
----- End of picture text -----

Table 1 – Koongie Park Project Key Metrics

1. Cash operating costs include all mining, processing, transport, freight to port, port costs and site administration. Excludes sustaining capital and WA Royalties.

The Scoping Study has been completed with the assistance of highly experienced and reputable independent consultants based in Western Australia, overseen by Wave International as Project Manager. Wave International is a resource development consultant with more than twenty years of global experience in engineering, project delivery, project, and asset management.

5

==> picture [33 x 31] intentionally omitted <==

The Scoping Study was completed to an overall estimating accuracy of +/-30% (Class 5 estimate) and has a basis date for Q2 CY23. The Project is based on a 750ktpa mining and processing operation with the Study demonstrating strong financial metrics. The preliminary economic evaluation indicates the Koongie Park Project will generate significant net cash flows over an initial 11 year life-of-mine (LOM) with a capital payback of 2.4 years following first production.

Capital Costs

Capital costs are derived from various sources including the engineering database of Wave International and estimates based on recent actual pricing from similar WA mining operations. They include all pre-production site, processing plant, tailings dam and mining development and also sustaining capital post-production target start-up, as illustrated below:

==> picture [387 x 298] intentionally omitted <==

----- Start of picture text -----

Pre-Production Capital Value
($M)
Site Infrastructure 11.7
Processing Facilities 60
Water Management 3.6
Underground Development 0
Open Pit Development 2.2
Total Pre-Production 77.5
Sustaining Capital – Life of Mine 59
Indirect Costs 34
20% Contingency 23
Total 134.5
----- End of picture text -----

Table 2 – Koongie Park Project Capital Cost Requirement

Operating Costs

Operating costs are derived from a number of sources including quotations supplied by vendors, the engineering database of Wave International and estimates based on similar WA mining operations.

6

==> picture [33 x 31] intentionally omitted <==

==> picture [340 x 180] intentionally omitted <==

----- Start of picture text -----

Operating Costs $M $/t milled $/t payable
Mining 649 80 4,375
Processing [1] 421 52 2,838
C1 Cash Cost 1,070 132 7,222
Royalty 79 9 532
Sustaining Capital 59 7 397
All-in Sustaining Cost (AISC) [2] 1,208 148 8,143
----- End of picture text -----

Table 3 – Koongie Park Project Operating Costs Breakdown

1. Processing costs include all site G&A, transportation and treatment charges. Excludes sustaining capital and WA Royalties.

2. All-In Sustaining Cost (AISC) includes C1 cash cost, royalties and sustaining capital. It does not include corporate cost, exploration cost and non-sustaining capital.

Other Considerations

Funding

In order to achieve the range of outcomes indicated in the Scoping Study, funding in the order of $135M will likely be required to commence production. AuKing has formed the view that there is a reasonable basis to believe that requisite funding for development of the Project will be available when required. The grounds on which this reasonable basis is established include:

  • The Project has strong technical and economic fundamentals which provides an attractive return on capital investment and generates robust cashflows at conservative copper price assumptions. This provides a solid platform to source debt and equity funding.

  • The Project presents an opportunity for the establishment of a significant copper/zinc/silver operation in a Tier One mining jurisdiction, with an estimated mine life of almost 12 years. In the current market where there is an expanding trend towards electrification and green energy, the Project appears ideally placed to attract investor and other funding support as development progresses.

  • In a relatively short period of time, AuKing has established a track record of securing funding for the conduct of development activities at Koongie Park as and when funding has been required.

  • It is AuKing’s intention to appoint a corporate finance advisor in the near term to

7

==> picture [33 x 31] intentionally omitted <==

assist with the sourcing of debt and equity funding as and when it is required over the next few years.

There is, however, no certainty that AuKing will be able to source funding as and when required. Typical project development financing would involve a combination of debt and equity. It is possible that such funding may only be available on terms that are dilutive to or otherwise affect the value of AuKing’s existing shares.

Status of government agreements and approvals critical to Project viability

All of the working areas in the Scoping Study (with the exception of Bommie) are on approved mining licences with no current issues or outstanding requirements with DMIRS. There are no third party unresolved matters that are likely to impact upon approvals. In the case of the Bommie deposit, mining activities are not intended until year 8 of the mining schedule by which time it is expected that any unresolved statutory or commercial issues have been settled.

Onedin and the AmmLeach® Process

AuKing has conducted a series of small-scale tests on the oxide and transitional ores at the Onedin deposit to assess the potential application of the AmmLeach® ammonia-leaching process. This testwork program, which has been registered with the Commonwealth Government’s R&D Incentive program is seeking to assess the potential to establish an alternative processing methodology for these Onedin ores that produces high recoveries. A significant amount of further testwork is planned here, based around a proposed prefeasibility study to be managed by Perth-based Simulus Group.

In the meantime, with the addition of a sulphidisation plant into the proposed Scoping Study metallurgical process (especially for the semi-weathered or oxide materials), a basecase processing methodology has been established and is considered appropriate for this Study. It remains to be seen whether the recoveries at Onedin utilising the AmmLeach® process can be demonstrated to exceed those expected to be achieved utilising the flotation method.

Emull Deposit

On 1 December 2022 AuKing announced to ASX details of a maiden resource estimate for its Emull Deposit comprising 12.2Mt @ 0.27% Cu, 0.38% Zn, 0.09% Pb and 4.9g/t Ag. As can be seen in Figure 1 above Emull is located within a close proximity to the proposed developments around the Sandiego deposit. AuKing has plans for additional drilling at Emull which is aimed at significantly increasing the existing resource estimates and these could support a future mining operation at Emull. However, at this stage, no provision for mining at Emull has been included in the Scoping Study.

8

==> picture [33 x 31] intentionally omitted <==

Reasonable Basis for Forward-Looking Statements

No Ore Reserve has been declared in the Study. This ASX release has been prepared in compliance with the JORC Code (2012) and the ASX Listing Rules. All material assumptions on which the Study production target and project financial information are based have been included in this release. Consideration of Modifying Factors in the format specified by JORC Code (2012) Table 1, Section 4 is attached to this release.

This announcement has been authorised by Paul Williams, CEO, AuKing Mining Limited.

For more information, please contact:

Paul Williams Gareth Quinn Chief Executive Officer Investor Relations Mobile +61 419 762 487 Mobile + 61 417 711 108 [email protected] [email protected]

About AuKing Mining

AuKing Mining (ASX:AKN) is a mining exploration company focused on uranium, copper and zinc projects in both Tanzania and Australia.

For further information

www.aukingmining.com

==> picture [437 x 248] intentionally omitted <==

9

KOONGIE PARK COPPER ZINC PROJECT

5943 AUKING MINING May 2023

==> picture [253 x 69] intentionally omitted <==

==> picture [213 x 67] intentionally omitted <==

PROJECT BRIEF

PROJECT BRIEF
Project Number 5943
Project Title KOONGIE PARK COPPER ZINC PROJECT
Client AUKING MINING
Client Contact Paul Williams
Client Address Suite 27, Level 7, Christie Centre, 320 Adelaide Street, Brisbane QLD 4000

DOCUMENT STATUS

Rev Date Description By Reviewed Approved
A 29 May 2023 Scoping Report MR SW MR

DISCLAIMER

This document has been produced on behalf of, and for the exclusive use of the nominated recipient, and is issued for the purposes of the proposed works only. Wave International accepts no responsibility or liability whatsoever in respect to use of this document by any third party.

The information contained within the document is confidential and subject to copyright.

This document shall not be copied, transmitted or divulged to other parties without the prior written consent of Wave International’s duly authorised representative.

i

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [103 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

TABLE OF CONTENTS

1 INTRODUCTION ....................................................................................................... 1 INTRODUCTION ....................................................................................................... 1
1.1 SUMMARY .................................................................................................................................................................. 1
1.2 GLOSSARY ................................................................................................................................................................... 3
2 SCOPE ...................................................................................................................... 4
3 STUDY CONTRIBUTORS ............................................................................................ 5
4 LOCATION, OWNERSHIP AND TENURE ..................................................................... 6
4.1 LOCATION AND ACCESS .............................................................................................................................................. 6
4.2 TOPOGRAPHY AND CLIMATE ...................................................................................................................................... 6
4.3 TENURE ....................................................................................................................................................................... 7
4.4 NATIVE TITLE ............................................................................................................................................................... 8
5 GEOLOGY AND RESOURCE ....................................................................................... 9
5.1 REGIONAL GEOLOGY KOONGIE PARK ......................................................................................................................... 9
5.1.1
Koongie Park Formation ............................................................................................................................... 9
5.1.2
Coolibah Tuff Member ................................................................................................................................. 9
5.1.3
Mimosa Sub-Member ................................................................................................................................. 10
5.1.4
Camp Shale Member .................................................................................................................................. 10
5.1.5
Weldon’s Creek Lava Member ................................................................................................................... 10
5.2 REGIONAL GEOLOGY MT ANGELO NORTH ............................................................................................................... 10
5.3 MINERAL RESOURCE ESTIMATE ................................................................................................................................ 11
5.3.1
GENERAL ..................................................................................................................................................... 11
5.3.2
SANDIEGO ................................................................................................................................................... 11
5.3.3
ONEDIN ....................................................................................................................................................... 11
5.3.4
MT ANGELO NORTH ................................................................................................................................... 12
5.3.5
BOMMIE ..................................................................................................................................................... 13
6 MINING ................................................................................................................. 14
6.1 OPEN PIT MINING ..................................................................................................................................................... 14
6.1.1
GENERAL ..................................................................................................................................................... 14
6.1.2
SANDIEGO ................................................................................................................................................... 14
6.1.3
ONEDIN ....................................................................................................................................................... 17
6.1.4
MT ANGELO NORTH ................................................................................................................................... 19
6.1.5
BOMMIE ..................................................................................................................................................... 20
6.1.6
OPEN CUT MINING COSTS .......................................................................................................................... 21
6.2 UNDERGROUND MINING .......................................................................................................................................... 22

ii

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [103 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

6.2.1
CUT OFF GRADE .......................................................................................................................................... 23
6.2.2
STOPE OPTIMIZATION ................................................................................................................................ 23
6.2.3
MINE DESIGN .............................................................................................................................................. 25
6.2.4
PRODUCTION RATE ..................................................................................................................................... 27
6.2.5
UNDERGROUND SCHEDULE........................................................................................................................ 28
7 METALLURGICAL TESTWORK.................................................................................. 29
7.1 HISTORICAL TESTWORK ............................................................................................................................................ 29
7.2 TESTWORK PROGRAMS ............................................................................................................................................ 29
7.2.1
STAGE 1 BENCHSCALE TESTWORK PROGRAM............................................................................................ 29
7.2.2
ADDITIONAL BENCHSCALE TESTWORK PROGRAM ..................................................................................... 29
7.3 CONCLUSIONS .......................................................................................................................................................... 30
8 MINERALS PROCESSING ......................................................................................... 31
8.1 GENERAL ................................................................................................................................................................... 31
8.2 DESIGN CRITERIA ...................................................................................................................................................... 31
8.3 PROCESS DESCRIPTION ............................................................................................................................................. 32
8.3.1
COMMINUTION .......................................................................................................................................... 33
8.3.2
FLOTATION ................................................................................................................................................. 33
8.3.3
PRODUCT HANDLING .................................................................................................................................. 34
8.3.4
REAGENTS ................................................................................................................................................... 34
8.3.5
TAILINGS DISPOSAL AND WASTE HANDLING ............................................................................................. 35
9 INFRASTRUCTURE AND LOGISTICS ......................................................................... 37
9.1 SITE LAYOUT ............................................................................................................................................................. 37
9.2 POWER SUPPLY ......................................................................................................................................................... 38
9.3 WATER SUPPLY ......................................................................................................................................................... 38
9.4 WATER TREATMENT ................................................................................................................................................. 38
9.5 ROADS ....................................................................................................................................................................... 38
9.6 SUPPLY CHAIN AND PRODUCT TRANSPORT ............................................................................................................. 39
9.7 NON-PROCESS BUILDINGS AND FACILITIES .............................................................................................................. 39
9.8 CAMP ACCOMMODATION ........................................................................................................................................ 39
9.9 TAILINGS ................................................................................................................................................................... 40
9.10 COMMUNICATION SYSTEMS .................................................................................................................................... 40
**10 ** ENVIRONMENT, SOCIAL, COMMUNITY AND PERMITTING ...................................... 41
10.1 EPA AND DAWE ASSESSMENT .................................................................................................................................. 41
10.2 KEY ENVIROMENTAL FACTORS ................................................................................................................................. 41
10.3 STAKEHOLDERS ......................................................................................................................................................... 42
10.4 NATIVE TITLE AND ABORIGINAL HERITAGE .............................................................................................................. 43

iii

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [103 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

**11 ** IMPLEMENTATION ................................................................................................. 44 IMPLEMENTATION ................................................................................................. 44
11.1 INTRODUCTION ........................................................................................................................................................ 44
11.2 KEY OBJECTIVES ........................................................................................................................................................ 44
11.3 DEVELOPMENT STRATEGY ........................................................................................................................................ 44
11.4 PROJECT IMPLEMENTATION SCHEDULE ................................................................................................................... 45
11.5 PROJECT DELIVERY STRUCTURE AND CONTRACTING STRATEGY ............................................................................. 46
11.6 OPERATIONAL READINESS ........................................................................................................................................ 48
11.6.1 RESPONSIBILITY .......................................................................................................................................... 48
11.6.2 OVERVIEW .................................................................................................................................................. 48
11.7 ASSET REGISTER ........................................................................................................................................................ 49
11.8 ORGANISATION CHART ............................................................................................................................................. 50
**12 ** CAPITAL COST ESTIMATE ....................................................................................... 51
12.1 ESTIMATE SUMMARY ............................................................................................................................................... 51
12.2 BASIS OF ESTIMATE .................................................................................................................................................. 52
12.2.1 GENERAL ..................................................................................................................................................... 52
12.2.2 DIRECT FIELD COSTS ................................................................................................................................... 52
12.2.3 CONSTRUCTION INDIRECT COSTS ............................................................................................................... 53
12.2.4 NON-PROCESS INFRASTRUCTURE .............................................................................................................. 53
12.2.5 OWNERS / INDIRECT COSTS AND CONTINGENCY ....................................................................................... 54
12.2.6 ESTIMATE CONSTRAINTS, ASSUMPTIONS AND EXCLUSIONS ..................................................................... 54
12.3 ESTIMATE CLASSIFICATION ....................................................................................................................................... 55
**13 ** OPERATING COST ESTIMATE .................................................................................. 56
13.1 ESTIMATE SUMMARY ............................................................................................................................................... 56
13.2 ESTIMATE DETAILS .................................................................................................................................................... 56
13.2.1 LABOUR ...................................................................................................................................................... 56
13.2.2 MAINTENANCE ........................................................................................................................................... 58
13.2.3 POWER ........................................................................................................................................................ 59
13.2.4 REAGENTS AND CONSUMABLES ................................................................................................................. 59
13.2.5 DIESEL ......................................................................................................................................................... 60
13.2.6 TRANSPORT AND LOGISITICS ...................................................................................................................... 60
13.2.7 FLIGHTS AND ACCOMMODATION .............................................................................................................. 61
13.2.8 GENERAL AND ADMINISTRATION ............................................................................................................... 61
13.2.9 MINING ....................................................................................................................................................... 62
**14 ** ECONOMIC ANALYSIS ............................................................................................ 63
14.1 INTRODUCTION ........................................................................................................................................................ 63
14.2 SUMMARY ................................................................................................................................................................ 63

iv

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [103 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

14.3 ACCURACY OF ESTIMATE .......................................................................................................................................... 63
14.4 ASSUMPTIONS .......................................................................................................................................................... 63
14.5 KEY METRICS ............................................................................................................................................................. 64
14.5.1 REVENUE AND PROFITS FORECAST ............................................................................................................ 65
14.5.2 SENSITIVITY ANALYSIS ................................................................................................................................ 65
15 FORWARD WORK PLAN ......................................................................................... 67
15.1 ENVIRONMENTAL APPROVAL ................................................................................................................................... 67
15.2 GEOLOGY .................................................................................................................................................................. 67
15.3 MINING ..................................................................................................................................................................... 67
15.4 METALLURGICAL TESTWORK .................................................................................................................................... 68
15.5 WATER SUPPLY ......................................................................................................................................................... 68
15.6 GEOTECHNICAL ......................................................................................................................................................... 68
APPENDIX A: GLOSSARY ............................................................................................... 69

LIST OF TABLES

Table 1-1: Key Pre-Feasibility Report Metrics ...................................................................................................................................................... 2 Table 3-1: Study Contributors .............................................................................................................................................................................. 5 Table 4-1: Climate Data for Halls Creek ............................................................................................................................................................... 7 Table 5-1: Sandiego Mineral Resource Estimate by Classification ..................................................................................................................... 11 Table 5-2: The Onedin MRE Reported by Classification ..................................................................................................................................... 12 Table 5-3: Mt Angelo North Mineral Resource Estimate by Classification ........................................................................................................ 12 Table 5-4: Bommie MRE by Classification .......................................................................................................................................................... 13 Table 6-1: Mt Angelo North Pit Shell Optimizations (Run 1) ............................................................................................................................. 19 Table 6-2: Bommie Pit Shell Optimizations (Run 3). .......................................................................................................................................... 21 Table 6-3: Underground Mining Physicals ......................................................................................................................................................... 22 Table 6-4: Commodity Pricing, Metallurgical Recoveries and Payable Factors ................................................................................................. 22 Table 6-5: Underground Mining Costs ............................................................................................................................................................... 23 Table 6-6: Development Meters ........................................................................................................................................................................ 25 Table 6-7: Underground Level by Level Analysis................................................................................................................................................ 27 Table 6-8: Production Rate Based on Inventory ................................................................................................................................................ 27 Table 6-9: Mining Schedule by Year ................................................................................................................................................................... 28 Table 8-1: Design Criteria................................................................................................................................................................................... 31 Table 8-2: Waste Streams .................................................................................................................................................................................. 36 Table 11-1: Contract Classifications ................................................................................................................................................................... 47 Table 11-2: Preliminary Contracts Register (and contribution to capex excluding contingency) ...................................................................... 47 Table 12-1: Cost Estimate by Cost Type ............................................................................................................................................................. 51 Table 12-2: Direct Field Cost Allowances ........................................................................................................................................................... 53 Table 12-3: Indirect Costs Allowances ............................................................................................................................................................... 54 Table 12-4: AACE Definition ............................................................................................................................................................................... 55 Table 13-1: Processing Operating Cost Estimate ............................................................................................................................................... 56 Table 13-2: Labour Cost Summary ..................................................................................................................................................................... 57

v

==> picture [103 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

KOONGIE PARK COPPER ZINC PROJECT_

Table 13-3: Fixed Plant Maintenance Cost ........................................................................................................................................................ 58 Table 13-4: Light Vehicle Maintenance Cost ...................................................................................................................................................... 58 Table 13-5: Electrical Power Cost ...................................................................................................................................................................... 59 Table 13-6: Reagent & Consumables Cost ......................................................................................................................................................... 59 Table 13-7: Diesel Cost ...................................................................................................................................................................................... 60 Table 13-8: Transport Cost ................................................................................................................................................................................ 60 Table 13-9: Flights & Accommodation Cost ....................................................................................................................................................... 61 Table 13-10: G&A Costs ..................................................................................................................................................................................... 61 Table 13-11: Open Cut Mining Units.................................................................................................................................................................. 62 Table 13-12: Open Cut Mining Costs ................................................................................................................................................................. 62 Table 13-13: All-in Underground Mining Cost ................................................................................................................................................... 62 Table 14-1: Project Operating Results ............................................................................................................................................................... 64

LIST OF FIGURES

Figure 1-1: Location map of the Koongie Park and nearby CAZ Projects, near Halls Creek, WA ......................................................................... 1 Figure 4-1: Koongie Park and nearby Mt Angelo North Tenure Areas, near Halls Creek, WA ............................................................................. 8 Figure 6-1: Sandiego Revenue Factor Scenarios ............................................................................................................................................... 15 Figure 6-2: Discounted Best-Case Mining Scenario .......................................................................................................................................... 16 Figure 6-3: Plan View of Pit Shell 20 .................................................................................................................................................................. 16 Figure 6-4: Shell 20 with the Reblocked Model ................................................................................................................................................ 17 Figure 6-5: Discounted Best-Case Mining Scenario .......................................................................................................................................... 17 Figure 6-6: Onedin Revenue Factor Scenarios ................................................................................................................................................... 18 Figure 6-7: Plan View of Shell 17....................................................................................................................................................................... 18 Figure 6-8: Shell 17 with the Reblocked Model ................................................................................................................................................. 19 Figure 6-10: Mt Angelo North Pit Shell Pit 9 ..................................................................................................................................................... 20 Figure 6-11: Copper Grade Tonnage Curve ....................................................................................................................................................... 24 Figure 6-12: Zinc Grade Tonnage Curve ............................................................................................................................................................ 24 Figure 6-13: NPV Analysis ................................................................................................................................................................................. 25 Figure 6-14: Underground Design looking from East ........................................................................................................................................ 26 Figure 6-15: Rib Pillar Selection looking from East ........................................................................................................................................... 26 Figure 8-1: Proposed Koongie Park Processing Flowsheet Block Flow Diagram ................................................................................................ 32 Figure 9-1: Site Layout ...................................................................................................................................................................................... 37 Figure 11-1: Project Implementation Framework ............................................................................................................................................. 44 Figure 11-2: Proposed Development Timing .................................................................................................................................................... 45 Figure 11-3: Project Delivery Structure ............................................................................................................................................................. 46 Figure 11-4: Operational Readiness Structure ................................................................................................................................................... 48 Figure 14-1: Project LOM Cash Flows ................................................................................................................................................................ 65 Figure 14-2: Bowtie Sensitivity Analysis............................................................................................................................................................. 66 Figure 14-3: Tornado Chart Sensitivity Analysis ................................................................................................................................................. 66

vi

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

1 INTRODUCTION

1.1 SUMMARY

Auking Mining Limited (AKN) is the holder of an 87.5% interest in the Koongie Park Copper/Zinc project, situated just outside of the Halls Creek township in the north-eastern Kimberley region of Western Australia. The Koongie Park project has been the subject of a substantial amount of historical exploration and development work, including various feasibility study activities conducted by joint venture partner Astral Resources NL (AAR) between 2008 and 2011. The primary deposits at Koongie Park are Sandiego and Onedin and between them host resources of 8.9Mt @ 1.01% Cu, 3.67% Zn, 0.16g/t Au, 32g/t Ag and 0.77% Pb.

AKN has signed a Memorandum of Understanding (MoU) with Cazaly Resources Limited (CAZ) to include that company’s Halls Creek deposits in a project scoping study to be conducted by AKN. The primary CAZ deposits are Mt Angelo North which has a reported resource of 1.27Mt @ 1.4% Cu, 1.4% Zn and 12g/t Ag and Bommie, which has a reported resource of 95.6Mt @ 0.27% Cu . AKN and CAZ have agreed to make available all relevant technical data to support the Scoping Study under the MoU.

The Scoping Study will determine the potential viability of open pit and underground operations centred around AKN’s Sandiego and Onedin Cu-Zn-Ag deposits and Cazaly’s Mt Angelo Cu-Zn-Ag and Bommie Cu deposits, which are all situated less than 10km from each other.

==> picture [367 x 357] intentionally omitted <==

Figure 1-1: Location map of the Koongie Park and nearby CAZ Projects, near Halls Creek, WA

1

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

AKN’s Emull deposit is a potentially large tonnage but low-grade deposit, that is also within reasonable proximity to Sandiego, but has not been included in the Study. However, being near to the proposed processing facility, this deposit could be developed at some future time depending on project economics and commodity prices.

The main combined Koongie Park and Mt Angelo North project area is at Scoping Stage development and located in Western Australia, a stable and top-ranked mining jurisdiction, in proximity to potential markets, predominantly in China, which is a key structural competitive advantage which makes it a highly desirable source of base metal supply.

The proposed development concept involves both Open cut and Underground mining methods, Sulfidation, Flotation and product logistics. The Project is capable of being well supported by the local community due to the area being familiar with mining activities for over 100 years and its potential to provide meaningful training and employment opportunities - acting as a catalyst for economic activity and the development of economic infrastructure in the Halls Creek region.

The Project is expected to employ up to 150 people during the development and construction with approximately 65-75 people during operations. There is a clear and established process with defined timeframes for project approvals to be obtained and the Project has the potential to be a key contributor to environmental management in the region.

Flora and fauna surveys have been conducted historically and no material issues have been identified.

Wave International has been engaged to assess the current data and prepare AACE class 5 level capital and operating cost estimates, generate a financial model (using mining inputs from others), and to prepare this report. This report is intended to provide a description of the proposed combined Halls Creek deposits of AKN and CAZ projects that will be the subject of future studies.

The key metrics from this report include:

Table 1-1: Key Pre-Feasibility Report Metrics

Table 1-1: Key Pre-Feasibility Report Metrics
KEY METRIC UNIT TOTAL
LOM Ore Mined & Processed tonnes, Mt 8,087,891
LOM Copper Production tonnes, t 109,893
LOM Zinc Production tonnes, t 38,405
LOM Years 11.1
LOM Average Grade – Copper % 1.72
LOM Average Grade – Zinc % 1.06
NPV (8%) (Pre-Tax) AUD M 176.9
IRR (Pre-Tax) % 39.7
Payback (start of production) # Years 2.45
Initial Capex AUD M 134.6
C1 Costs AUD/t Concentrate 7,197
Average Copper Price USD/lb 3.90
Average Zinc Price USD/lb 1.33
Average Annual Revenue AUD M 143.6
Average Annual OPEX AUD M 103.3
Average Annual EBITDA AUD M 40.3

2

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

1.2 GLOSSARY

The definitions used throughout this report are listed in Appendix A.

3

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

2 SCOPE

The scope of this study is as follows:

  1. Perform testwork on the available samples to ascertain a metallurgical recovery and OPEX parameters.

  2. Review testwork data provided by AKN both from its own activities and historical study work.

  3. Production scenarios: To complete an economic evaluation of agreed production scenarios of copper and zinc concentrate based on utilising ore from Koongie Park owned by AKN and supplemented by CAZ’ Mt Angelo North and Bommie deposits.

  4. Process plant engineering development:

  5. a. Utilise the information from historical work from AKN and CAZ provided to Wave.

  6. b. Incorporate current metallurgical testwork undertaken by AKN at Nagrom Laboratories.

  7. c. Progress process development and engineering development for the scenarios per above; and

  8. d. Develop key deliverables such as Block Flow Diagrams, Process Design Criteria, Mass and Water Balance, Mechanical Equipment List and layouts.

  9. Economic evaluation:

  10. a. Complete capital and operating cost estimates to a Class 4 level (with reference to AusIMM) for the production scenario.

  11. b. Evaluate economics based on the scenario; and

  12. c. Report economic metrics including capital cost, and operating cost.

  13. Risk and opportunity:

  14. a. Completion of a high-level risk and opportunity analysis; and

  15. b. High-level description of further work to either mitigate identified risks or explore opportunities in this study.

4

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

3 STUDY CONTRIBUTORS

The contributors to this Scoping Study are shown in Table 3.1.

Table 3-1: Study Contributors

CHAPTER CONTRIBUTORS
4 – Location and Ownership Auking Mining and Cazaly Resources
5 – Geology and Resource Auking Mining and Cazaly Resources
6 – Mining Auking Mining and Cazaly Resources
7 – Metallurgical Testwork Wave
8 – Minerals Processing Wave
9 – Infrastructure and Logistics Wave Review
Historical Work
10 – Environment, Social, Community and Permitting Wave, Historical Work
11 – Implementation Wave
12 – Capital Cost Estimate Wave
13 – Operating Cost Estimate Wave
14 – Economic Analysis Wave
Auking for pricing data

5

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

4 LOCATION, OWNERSHIP AND TENURE

4.1 LOCATION AND ACCESS

The Koongie Park/Mt Angelo North properties are located 25km south-west of Halls Creek in the north-east Kimberley region of Western Australia. Whilst Halls Creek is located in the isolated Kimberley region of Western Australia, it is well located with respect to roads and infrastructure. The main Great Northern Highway (National Highway #1) transects the mining leases allowing ideal transport access. Halls Creek has a range of government and transport services which will be highly advantageous to the project. In particular, the town has an airport and as the regional centre for the south-eastern Kimberley area has regular light aircraft flights to the town from Broome with connecting flights to Perth. Halls Creek also has a hospital, police station, shire offices and other government departments. Air charter services can also land at the Halls Creek aerodrome. Generally, access within the Project area is good via station tracks, fence lines and old exploration grid lines.

4.2 TOPOGRAPHY AND CLIMATE

Halls Creek has a tropical semi-arid climate with very hot summers and warm dry winters. There are two distinct seasons; the "wet", usually from December to March and characterised by high temperatures and the occasional rain event, and the "dry" for the remainder of the year. The mean annual rainfall is 575.6 mm over an average of 60 days, although there is considerable variation from year to year.

Over 80% of the average annual rainfall occurs between December and March and is associated with thunderstorms and tropical lows or cyclones. These systems can produce heavy rain over short periods and often a significant proportion of the yearly total can fall in just one or two days. The unreliable nature of the occurrence and movement of thunderstorms and tropical systems results in the annual rainfall being highly variable. From May to October, days are characteristically clear and sunny. The infrequent rain during the drier months is usually associated with cloud bands originating over tropical waters to the northwest.

While tropical cyclones can threaten the Kimberley coasts with storm force winds and high seas they weaken as they move inland. Halls Creek is far enough inland for the major effect to be heavy rainfall. It is not uncommon for very little rain to occur for many months. The median rainfall for the months of June to September is zero.

Halls Creek’s average annual maximum temperature is 33.6°C and average minimum is 20.0°C. The hottest part of the year is November before the rains break, when the average maximum temperature is 38.3°C (BOM, 2020). The average relative humidity varies from 22-57% at 9am and from 16-40% at 3pm with the higher values occurring in the wetter December to March period. Evaporation is high and varies from an average of 11.3 mm per day in November to 6.1mm in June. Exploration and general bush work is sometimes limited in the hot wet season due to the extreme temperatures and the wet climatic conditions. The annualised data is summarized in Table 4-1 below.

The Koongie Park Project and Mt Angelo North lie across the watershed between the Laura River flowing to the southwest, the Margaret River flowing to the west, and the Elvire River flowing to the east. Elevations range from 380 m to 480 m above sea level with variable topography: flat, undulating, low rounded boulder-strewn hills, and subdued strike ridges. The more rugged Halls Creek Ridges lie to the southeast. Much of the surrounding region comprises extensive black-soil plains supporting grasslands and providing excellent grazing for the pastoral industry. Vegetation in the Project area comprises mostly spinifex grass, Acacia scrub and eucalyptus species.

6

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Table 4-1: Climate Data for Halls Creek

==> picture [498 x 196] intentionally omitted <==

4.3 TENURE

The Koongie Park tenements consist of a portfolio of Prospecting, Exploration and Mining Licences covering an area of more than 500km[2] . The Sandiego and Onedin deposits are located on granted mining licences with Sandiego situated on M80/276 (220.7Ha) and Onedin on ML80/277 (324.93Ha). Both ML80/276 and ML80/277 expire in 2031.

AKN currently holds an 87.5% participating interest in the various Koongie park tenures, including the two Mining Licences, pursuant to a Joint Venture Agreement dated 8 February 2021 with Astral Resources NL (previously known as Anglo Australian Resources NL) (“AAR”). Under the terms of the JV agreement, in the event of AAR’s participating interest diluting below 10%, its interest in the Koongie Park project automatically reverts to a 0% participating interest and a 1% net smelter royalty. It is likely that this change in AAR’s project interest will take place during the course of 2023.

The Mt Angelo North deposit is situated within M80/247 and covers an area of 42Ha. M80/247 has a current expiry of May 2030. A 1.5% net smelter royalty applies to Mt Angelo North in favour of a company called Squadron Resources Pty Ltd. CAZ also holds exploration licence E80/5307 across 3,920 Ha on which the “Bommie” deposit is situated. The licence has a current expiry of July 2024.

7

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [483 x 283] intentionally omitted <==

Figure 4-1: Koongie Park and nearby Mt Angelo North Tenure Areas, near Halls Creek, WA

The Koongie Park Project consist of a contiguous block of tenements extending between 5 km and 65 km southwest of the town of Halls Creek (Figure 3). The tenure package comprises twenty-six (26) tenements with two (2) mining leases, eight (8) exploration licences, and sixteen (16) prospecting licences. The total tenement area is approximately 544 km[2] . AuKing has purchased the rights to base metal for these tenements from the holders Anglo Australian Resources NL (AAR). The rights to gold deposits are retained by AAR, with the rights to gold associated with predominantly base metal deposits with AuKing. The primary mineral assets, the Onedin and Sandiego copper-zinc-gold-silver deposits, lie within the granted mining leases M80/277 and M80/276, which expire in 2031.

As shown in Figure 4-1, the overall project area consists of a contiguous block of tenements extending between 5 km and 65 km southwest of the town of Halls Creek. The tenure package comprises eighteen (18) tenements with three (3) mining leases, ten (10) exploration licences, and five (5) prospecting licences.

4.4 NATIVE TITLE

The Koongie Park group of tenements and the two (2) CAZ licences are all within the Jaru/Lamboo and Koongie-Elvire lands. Agreements have been made with these Native Title parties with respect to the Prospecting and Exploration Licences. Further information is available in Section 10.4.

8

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

5 GEOLOGY AND RESOURCE

5.1 REGIONAL GEOLOGY KOONGIE PARK

The Halls Creek Copper Project is located in the Halls Creek orogen formed in the Paleoproterozoic due to the interaction of the Kimberley Craton to the north-west and the North Australian Craton to the east. The Paleoproterozoic plutonic rocks and volcano-sedimentary sequence of the Halls Creek orogen have been defined as the Lamboo Complex.

The Lamboo Complex has been divided into an Eastern, Central and Western tectonostratigraphic terrane and the Koongie Park Formation is located in the Central Terrane. The terranes are thought to have formed as a result of subduction and large-scale strike-slip faulting prior to 1820 Ma in a Paleoproterozoic plate margin setting (Tyler et al, 1999). The Koongie Park Formation (1843 +/-2Ma) postdates the Tickelara Metamorphics which consists of mafic volcanics, siltstones and mafic-ultramafic intrusions and is thought to represent an oceanic island arc – backarc basin above a southeast-dipping subduction zone, or an ensialic basin along the margin of the Kimberley Craton above a northwest dipping subduction zone (Sheppard et al., 1999).

In the project area, the Koongie Park Formation consists of a steeply dipping, highly deformed, sequence of spheroidal, felsic lavas, argillic sediments, volcaniclastic and various intercalated chemical sediments. In the central part of the project area, the Koongie Park Formation is gradational into greywackes and sandstones similar to the Olympio Formation. The sequence has been metamorphosed to green schist facies and four generations of folding have been documented (Orth 1993). The first phase of isoclinal folding can often be recognised in the central mineralised prospects and may have thickened the sulphide mineralization for Sandiego and Onedin

Further to the south, at Atlantis and Mt Angelo prospects, NS trending F2 folds have been interpreted by early explorers. Later shearing has affected the Sandiego and Onedin prospects and appears to have remobilised some of the sulphides. Dolerite and granite bodies outcrop along the western and southern margins of the Koongie Park prospect areas. In the east, granite intrudes the lower Coolibah Tuff Member of the Koongie Park Formation.

5.1.1 Koongie Park Formation

The formation consists of three members. From the base upwards, the Coolibah Tuff Member, the Camp Shale Member with a carbonate dominated lower portion known as the Mimosa Sub-Member and the Weldon’s Creek Lava Member. The base metal sulphides are confined to the thicker parts of the Mimosa unit occurring at the base of the Camp Shale Member. The mineralisation is comprised of a mixed, chemical sediment with abundant silicate, oxide and sulphide facies minerals including sphalerite, galena, chalcopyrite, pyrrhotite and minor tetrahedrite. A strong structural control on the localisation of the massive sulphide mineralisation near major structures and in tight isoclinal folds parallel to the plunge of the fold axis is evident at Sandiego and Onedin. Lead isotope studies indicate that the mineralisation appears to be derived from mainly one hydrothermal system with model ages of approximately 1,825 Ma, not dissimilar to the host unit age.

5.1.2 Coolibah Tuff Member

The Tuff consists of layered rhyolitic lapilli and quartz eye volcanoclastic and lavas and forms the footwall to all known mineralisation. It outcrops as a light reddish brown, massive friable rock with prominent phenocrysts of quartz, while in drill core it appears dark green with quartz phenocrysts up to 12mm in size in a strongly foliated matrix comprising muscovite, quartz and chlorite. Laminated chert-carbonate beds are developed towards the top of the sequence. In the Atlantis area, the base of this unit is transitional into more basic andesitic and basaltic lavas. Locally peperite has been observed (Rockhole, Onedin), indicative of the intrusive sub-volcanic nature of the coherent unit.

9

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

5.1.3 Mimosa Sub-Member

The sub member hosts most of the base metal sulphide mineralisation and is characterised by its abundant carbonate content and consists of intercalated chert, chlorite schist, banded magnetite or pyrrhotite-chlorite rock, black shales (locally pyritic), impure dolomite, calc-silicates, with fine grained andesitic lavas and volcanoclastic. The carbonate at Onedin shows relics of glassy textures indicative of a hydrothermal system probably operating in a sea floor environment.

5.1.4 Camp Shale Member

The Shale member forms the hanging wall to the mineralisation, and consists of a monotonous sequence of cleaved siltstones, and sericitic meta-siltstone which is carbonaceous at the base and interbedded with fine grained andesitic to dacitic volcanoclastic and lavas, with rare thin (cm-dm) chert- BIF interbeds, which are locally mineralised.

5.1.5 Weldon’s Creek Lava Member

The lava member is a generally massive and coherent spherulitic, dacite-rhyolite lava flows, aphyric to slightly quartz phyric, with minor thin banded iron formations and cherts. Interbedded siltstones and sandstones occur towards the top of the sequence.

5.2 REGIONAL GEOLOGY MT ANGELO NORTH

The tenement straddles the Koongie Park Formation that represents one of the basal units of the Lamboo Complex occurring within the Halls Creek Mobile Zone (HCMZ). The Paleoproterozoic Koongie Park Formation represents a sequence of mafic volcanics, felsic volcaniclastic and volcanics, turbiditic sandstone, siltstone and mudstone units, with interbedded chert, banded iron formation (BIF) and carbonate rocks. The Koongie Park Formation occupies the central portion of the HCMZ straddling the Great Northern Highway from 30 km north of Halls Creek to 50 km to the southwest.

The eastern portion of the HCMZ consists of greywacke, siltstone, sandstone, marble, impure calcareous rocks, chert and minor mafic lavas and sills. Major NNE – SSW trending mantle tapping faults (Halls Creek Fault) and associated splays effectively slice the HCMZ. Rocks to the east of the fault are the metavolcanics of the Biscay Formation and the metasediments of the Olympio Formations while the rocks to the east include the Koongie Park Formation in addition to elements of the Olympio Formation, Milba Formation, Moola Bulla Formation as well as the intrusive Loadstone Monzogranite and Mt Angelo Microgranite.

The Loadstone Monzogranite is the largest intrusive body within the project area. Studies indicate that the monzogranite is enriched in potassium relative to the Bow River Batholith to the west of the project area, which is reflected in the higher radiometric total count values over the monzogranite.

Deformation during the Halls Creek Orogeny has resulted in the Koongie Park Formation and underlying basalts being folded into a series of tight north-northeast trending anticlines and synclines. The structure in the project area is dominated by a regional set of northeast trending transcurrent faults. The Halls Creek Fault and two of its splays, the Highway Fault and the Caroline Fault, are regarded as crustal dislocations that were active during the Paleoproterozoic. Adjacent to fault zones, rocks are characterised by higher metamorphic grade and more intense shearing and brecciation.

Mineralisation in the area is related to litho-tectonic domains and includes VHMS base metal mineralisation associated with the Koongie Park Formation, gold mineralisation distributed around the northern and southern margins of the Loadstone Monzogranite and shear-hosted epigenetic vein systems associated with major fault zones at “Old Halls Creek”, mainly to the east of the Halls Creek Fault. Disseminated copper mineralisation is associated with the Mt Angelo Granophyric Microgranite that occurs immediately south of the Mt Angelo North VHMS deposits and may potentially be related to it.

10

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

5.3 MINERAL RESOURCE ESTIMATE

5.3.1 GENERAL

The Mineral Resources are classified as a combination of Indicated and Inferred and have been reported in accordance with the JORC Code, with geological and sampling evidence sufficient to assume geological and grade continuity within the volumes classified as Indicated. The classification levels are based upon an assessment of geological understanding of the deposit, geological and grade continuity, drillhole spacing, quality control results, search and interpolation parameters, and an analysis of available density information.

5.3.2 SANDIEGO

The Sandiego Mineral Resource is classified as a combination of Indicated and Inferred.

The Mineral Resource Estimate (MRE) has been reported in accordance with the JORC Code and it is therefore suitable for public release.

The MRE for Sandiego is quoted above a cut-off grade of 0.8% Cu and 3% Zn. The Mineral Resources were published on the 4[th] of April 2022. The Mineral Resources are presented in Table 5-1.

Table 5-1: Sandiego Mineral Resource Estimate by Classification

Classification Tonnes
(Mt)
Copper
(%)
Zinc (%) Gold
(g/t)
Silver
(g/t)
Lead (%)
Cu
Dominant
Indicated 1.7 2.3 0.8 0.3 18 0.2
Inferred 0.3 1.6 3.0 0.2 5 0.0
Sub Total 2.0 2.2 1.1 0.3 16 0.1
Zn
Dominant
Indicated 2.0 0.6 7.3 0.1 35 0.7
Inferred 0.1 0.2 6.1 0.1 10 0.1
Sub Total 2.1 0.6 7.3 0.1 34 0.7
Resource Total and Grades 4.1 1.4 4.3 0.2 25 0.4

5.3.3 ONEDIN

The Onedin Mineral Resource is classified as a combination of Indicated and Inferred.

The Mineral Resource Estimate (MRE) has been reported in accordance with the JORC Code and it is therefore suitable for public release.

The MRE for Onedin is quoted above a cut-off grade of 0.4% Cu and 1.0% Zn. The Mineral Resources were published on the 4[th] of April 2022. The Mineral Resources are presented in Table 5 2.

11

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Table 5-2: The Onedin MRE Reported by Classification

Zone Classification Tonnes
(Mt)
Copper
(%)
Zinc (%) Gold
(g/t)
Silver
(g/t)
Lead (%)
Cu
Dominant
Indicated 1.5 1.1 0.6 0.2 47 1.2
Inferred - - - - - -
Zn
Dominant
Indicated 3.3 0.5 4.3 0.1 34 1.0
Inferred - - - - - -
Resource Total and Grades 4.8 0.7 3.2 0.1 38 1.1

5.3.4 MT ANGELO NORTH

The Mt Angelo North Mineral Resource is classified as a combination of Indicated and Inferred.

The Mineral Resource Estimate (MRE) has been reported in accordance with the JORC Code and it is therefore suitable for public release. The MRE is reported by classification in Table 5-3.

The MRE for Mt Angelo North is quoted above a cut-off grade of 0.4% Cu and 1% Zn. The lower cut-off grades were determined using grade distribution analysis, vario-graphy and are considered appropriate for the style of deposit and potential open pit mining operations. Mineral Resources were published on the 31[st] of January 2022.

Table 5-3: Mt Angelo North Mineral Resource Estimate by Classification

CLASSIFICATION
Indicated Tonnes
t
Cu
%
Zn
%
Ag
ppm
Oxide 149,000 1.4 0.9 21
Transitional 158,000 1.7 1.5 16
Fresh 699,000 1.7 1.8 13
Total 1,007,000 1.6 1.6 15
Inferred Tonnes
t
Cu
%
Zn
%
Ag
ppm
Oxide 67,500 0.9 0.9 21
Transitional 157,000 1.2 0.6 16
Fresh 487,000 1.0 1.4 13
Total 712,000 1.0 1.2 9

12

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

TOTAL RESOURCE Tonnes
t
Cu
%
Zn
%
Ag
ppm
Oxide 216,000 1.2 0.9 17
Transitional 316,000 1.4 1.1 12
Fresh 1,187,000 1.4 1.6 12
Total 1,718,000 1.4 1.4 12

5.3.5 BOMMIE

The Bommie Mineral Resource is classified as a combination of Indicated and Inferred.

The Mineral Resource Estimate (MRE) has been reported in accordance with the JORC Code and it is therefore suitable for public release.

The MRE for Bommie is quoted above a cut-off grade of 0.24% Cu. The lower cut-off grades were determined using grade distribution analysis, vario-graphy and are considered appropriate for the style of deposit and potential open pit mining operations. The Mineral Resources were published on the 24[th] of November 2022. The Mineral Resources are presented in Table 5-4.

Table 5-4: Bommie MRE by Classification

CLASSIFICATION
Indicated Tonnes
t
Cu
%
Oxide 212,000 0.29
Transitional 2,799,000 0.3
Fresh 13,091,000 0.3
Total 16,102,000 0.3
Inferred Tonnes
t
Cu
%
Oxide 1,108,000 0.27
Transitional 6,978,000 0.28
Fresh 71,380,000 0.27
Total 95,568,000 0.27

13

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

6 MINING

6.1 OPEN PIT MINING

6.1.1 GENERAL

Auking Mining engaged Mine Planning Services to complete the mining engineering study for Sandiego and Onedin open cut mines suitable for inclusion in the Scoping Study. The high-level designs include confirmatory pit design using Project parameters as agreed with Auking and Wave International. In addition an independent consultant was engaged for the Sandiego underground study.

Cazaly Resources engaged an independent consultant to complete the mining engineering study for Mt Angelo North and Bommie open cut mines suitable for inclusion in the Scoping Study. The high-level designs include confirmatory pit design using Project parameters as agreed with Auking, Cazaly and Wave International.

For all pit shells conventional open pit mining techniques of drill and blast followed by excavate, load and haul are suitable for both mines. Proposed mining equipment will be two (2) Komatsu PC1250 excavators, two (2) Caterpillar 785C dump trucks, four (4) 777G dump trucks, and appropriate ancillary equipment to support mining activities.

A production schedule based on Indicated and Inferred Mineral Resources has been developed to maintain a variable ROM throughput targeting an average Copper/Zinc throughput of circa 2,000 tonnes per day has been developed, resulting in a Life of Mine (LOM) of approximately 12 years, inclusive of pre-production mining, production ramp-up and ramp-down.

Other modifying factors of dilution and ore loss were generated based on comparisons with a range of similarly sized open pit mining projects. It was modelled to apply a 20% dilution as a way of recovering 95% of the ore during the mining process. The remaining 5% of ore was considered lost in the mining process.

All pit and infrastructure will be in the current lease boundaries. Pits have been designed based on the high-level assumptions utilizing the CSA Global estimated resources quantities as a reference point and pit slope angles of 44° as a conservative approach.

The details of the equipment sizing and the way the benches will be mined will be dependent on the mining contractor but initial work with a preferred contractor has indicated that each 5m bench will be blasted with 1m of subdrill and that mining will be in two flitches of around 3m each. If heave is an issue there may be a need to go to 3 flitches. The bench sizes may necessitate a change in the block model in terms of the z-size or some changes in berm levels.

Grade control will be done by dedicated drill rig with blast holes simply used to confirm lithological contacts.

The optimisation process indicates that all ore sources can be extracted from the pits in the same manner.

6.1.2 SANDIEGO

The CSA report gave resources for the Cu dominant and Zn dominant zones for each deposit. The same methodology will be applied to both deposits.

The resource models were generated in Datamine and sub-blocks are as small as 0.5m[3] which required re-modelling to practical blocks sizes for mining. For simplicity the mine planning work was done with a copper equivalent variable and the results for the two deposits are reported in terms of Cu/eq with the copper cut-off for each deposit used. The actual metallurgical recovery was higher in the testwork completed at Nagrom however a conservative approach was adopted for the optimization process.

14

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

The following is the methodology used for the Copper equivalent cut-off for Zinc production.

• Copper AUD$10,740/t 90% recovery • Zinc AUD $4,189/t 80% recovery Recovered zinc was written as a function of recovered copper. Recovered Zinc = (4,189 * 0.8) Recovered Copper = (10,740 * 0.9) = 3351 = 9,666 Recovered zinc as Cu = 3351/9666 =0.3467

Cu/eq = Cu% + (Zn% * 0.3467)

The resultant models had some loss of metal compared to the resource:

  • Sandiego 4.4% loss of Cu/eq metal using 0.8%Cu cut-off

  • • Onedin 0.2% loss of Cu/eq metal using 0.4%Cu cut-off

In both cases there were changes in ore tonnes:

  • Sandiego 110kt or 2.2% decrease in ore tonnes using 0.8%Cu cut-off

  • • Onedin 400kt or 5.8% increase in ore tonnes using 0.4%Cu cut-off

This variable was added to the models and new resource reports generated using the copper cut-offs for each deposit from the CSA resource statements.

Analysis of Sandiego indicated that Revenue factor 1 shell was appropriate at Scoping Study level as indicated in Figure 6-1:

==> picture [477 x 322] intentionally omitted <==

Figure 6-1: Sandiego Revenue Factor Scenarios

15

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [498 x 246] intentionally omitted <==

Figure 6-2: Discounted Best-Case Mining Scenario

The cutbacks are virtually the same on all sides and future Geotechnical work may require re-optimization. With the distance between the smallest and largest shells selected for assessment being 40m, it is assumed Shell 20 forms the base case as it provides the best optimisation.

==> picture [293 x 292] intentionally omitted <==

Figure 6-3: Plan View of Pit Shell 20

16

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [313 x 231] intentionally omitted <==

Figure 6-4: Shell 20 with the Reblocked Model

The rotated view in Figure 6-4 shows mostly oxide and transitional ore. The first ore is around 60m from the surface. The bottom of the pit is at 230mRL which is 185m below surface. With ramps and minimum mining widths the base would likely be at 240mRL which allows portal access for the Sandiego underground mine.

This pit optimisation generates 1.16Mt at 3.71% Cu/eq and 29.52Mt of waste removal. Inferred ore is included in the mining schedule however it is not considered material representing 129Kt of ore scheduled or 11% of the total ore.

6.1.3 ONEDIN

Analysis of Onedin represented a flatter curve than Sandiego representing that the cost inputs do not have a material effect on the optimization and is represented below in Figure 6-5:

==> picture [474 x 233] intentionally omitted <==

Figure 6-5: Discounted Best-Case Mining Scenario

17

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Multiple shells were considered and are highlighted below.

==> picture [477 x 326] intentionally omitted <==

Figure 6-6: Onedin Revenue Factor Scenarios

The cutbacks are coincident in the north with the only real differences in the south. There is very little variation difference between shells 30 and 36 however Shell 17 was selected as it represented the more conservative approach for the Scoping Study.

==> picture [264 x 249] intentionally omitted <==

Figure 6-7: Plan View of Shell 17

18

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [318 x 213] intentionally omitted <==

Figure 6-8: Shell 17 with the Reblocked Model

The rotated view of Onedin represents mostly oxide and transitional ore. There is some fresh ore at depth. Ore is from the surface and the base of the pit is at 260mRL which is 180m from the surface. With ramps and minimum mining widths the base would likely be at 250mRL.

A block model report of the quantities in this pit are 4.09Mt of ore with a grade of 1.56% Cu/eq and 17.89Mt of waste material.

6.1.4 MT ANGELO NORTH

The Resource model for Mount Angelo (2021 December quarterly report CAZ:ASX) was reported at a cutoff of 0.4% Cu. Resource block dimensions are 10m x 5m x 2.5m with sub-blocking to 2.5m x 1.25m x 1.25m. Cu, associated Zn and Ag were reported.

Analysis of Mount Angelo North was undertaken using a conservative copper price of $10,740 (Run 1), and $13,089 (Run 2) to better reflect the current metal price. The revenue factor 1 (Run 1) shell was considered appropriate at this early Scoping Study level as indicated below:

Table 6-1: Mt Angelo North Pit Shell Optimizations (Run 1)

Pit Total Tonnes Waste Tonnes Ore Tonnes
to Mill
Grade Cu % Grade Ag
ppm
Grade Zn
ppm
Contained
Cu Metal tonnes
Recovered
Cu Metal tonnes
Recovered
_Ag Metal oz _
Recovered
Zn Metal tonnes
Revenue
Factor
1
2
3
4
5
6
7
8
250,072
356,110
505,695
1,916,833
2,244,252
2,550,192
2,746,136
2,947,178
176,288
246,597
349,699
1,479,527
1,739,274
1,979,393
2,138,677
2,301,427
73,784
109,513
155,996
437,306
504,978
570,799
607,459
645,751
1.9328
1.7915
1.5990
1.3466
1.3000
1.2512
1.2243
1.1946
14.3
13.7
14.3
14.1
13.3
12.4
12.1
11.6
376
368
369
370
366
362
359
359
1,426
1,962
2,494
5,889
6,565
7,142
7,437
7,714
1,116
1,555
2,000
4,982
5,581
6,090
6,354
6,599
22,611
32,606
49,401
145,084
158,793
168,646
174,311
179,171
19
27
40
120
137
154
164
174
0.26
0.35
0.44
0.53
0.63
0.72
0.81
0.91
9 3,243,665 2,543,912 699,753 1.1539 11.1 358 8,075 6,918 185,432 189 1.00
10
11
12
13
14
15
16
3,427,383
3,673,377
4,326,444
4,573,197
4,891,830
5,378,189
5,926,438
2,699,991
2,915,361
3,484,484
3,703,126
3,988,443
4,430,057
4,932,711
727,392
758,016
841,960
870,071
903,387
948,132
993,727
1.1344
1.1145
1.0626
1.0459
1.0278
1.0048
0.9832
10.9
10.6
10.1
9.9
9.8
9.6
9.4
357
356
356
355
354
353
352
8,252
8,448
8,946
9,100
9,285
9,527
9,771
7,077
7,254
7,689
7,827
7,995
8,206
8,424
188,966
192,967
203,856
207,345
212,102
219,218
226,444
196
204
227
235
243
255
267
1.09
1.19
1.28
1.37
1.47
1.56
1.65

19

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

The rotated view below shows mostly oxide (yellow) and transitional (blue) ore, with some fresh (red) ore.

==> picture [361 x 282] intentionally omitted <==

Figure 6-9: Mt Angelo North Pit Shell Pit 9

6.1.5 BOMMIE

The Resource model for Bommie is copper only (24 November 2022 Announcement CAZ:ASX) and was reported at a cutoff of 0.2% Cu. Resource block dimensions are 10m x 10m x 5m with no sub-blocking.

Analysis of Bommie was undertaken using a conservative copper price of $10,740 (Run 1, 2, 3), and $13,089 (Run 4) to better reflect the current metal price. Multiple shells were considered and the revenue factor 1.0 (Run 3) shell #7 was considered most appropriate at this early Scoping Study level as indicated below.

It should be noted that at this early stage blending of both low and high grade ores have not been considered, and the selected pit shells have not been selected to maximize profits, this would be considered in the next stages of feasibility studies.

20

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Table 6-2: Bommie Pit Shell Optimizations (Run 3).

Pit Tonnes Tonnes Waste Tonnes Ore Tonnes to
Mill
Grade Cu % Contained Cu Metal
tonnes
Recovered Cu Metal
tonnes
Revenue
Factor
1
2
3
4
5
6
101,350
155,050
180,575
198,125
239,725
898,025
46,285
84,960
103,635
111,635
140,529
658,870
55,065
70,090
76,940
86,490
99,196
239,155
1.7130
1.6656
1.6281
1.5331
1.4300
1.0187
943
1,167
1,253
1,326
1,418
2,436
765
961
1,036
1,099
1,178
2,070
0.35
0.44
0.63
0.72
0.81
0.91
7 1,224,625 897,398 327,227 0.9195 3,009 2,544 1.00
8
9
10
11
12
13
14
15
16
1,482,900
1,749,975
2,421,125
13,639,025
20,324,675
27,383,475
34,779,300
43,320,725
55,656,650
1,079,758
1,291,008
1,884,108
11,734,833
17,764,608
24,516,783
31,649,101
39,991,758
52,171,469
403,142
458,967
537,017
1,904,192
2,560,067
2,866,692
3,130,199
3,328,967
3,485,181
0.8534
0.8159
0.7723
0.5677
0.5479
0.5416
0.5369
0.5329
0.5302
3,440
3,745
4,147
10,810
14,028
15,527
16,807
17,740
18,477
2,902
3,161
3,513
9,489
12,377
13,719
14,869
15,719
16,375
1.09
1.19
1.28
1.37
1.47
1.56
1.65
1.74
1.84

6.1.6 OPEN CUT MINING COSTS

The mining costs were derived from the Wave International database and based on other projects of a similar size, duration and location. All costs were for large scale mining production.

Drill and Blast

Drill and Blast
Oxide Ore $0.80/t
Transitional Ore $1.00/t
Fresh Ore $1.00/t
Load and Haul

$3.00 at the surface escalating $.030/t for every 20m vertical.

All other costs are accounted for in the overall OPEX model for Processing, Logistics and Administration

21

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

6.2 UNDERGROUND MINING

A high-level mining evaluation of the Sandiego project has been completed by AuKing Mining and its consultants to ascertain the viability of mining the orebody as an underground mine utilising long hole open stoping with cemented rock fill (CRF). All calculations are based on a contract miner being managed by the mine owner. A provision of AUD$2.0M has been accounted for mine owner capital to commence mining. A maximum production rate of 0.85Mtpa can be achieved utilising long hole open stoping with CRF. A portal at the bottom of the Sandiego open cut mine has been assumed as the entrance to the underground mine.

The resultant physicals are summarised in the Table 6-3 below.

Table 6-3: Underground Mining Physicals

Item Quantity
Mined Ore Tonnes (Mt) 1.8 Mt
Copper Grade (%) 1.17 %
Cu Metal (t) 21,201 t
Zn Grade (%) 2.82%
Zn Metal (t) 50,979 t
Total Cost ($AUD) $279 M
Total Revenue ($AUD) $376 M
Total Profit ($AUD) $97 M
Total Mine Life 3.5 years

Mining evaluation work is based on the following commodity prices and payable factors. For ease of evaluation, it is assumed the payable factors include metallurgical recoveries.

Table 6-4: Commodity Pricing, Metallurgical Recoveries and Payable Factors

Commodity Price Metallurgical Recovery Payable Factor
Copper AUD $10,740/t Included in Payable factor 90%
Zinc AUD $4,189/t Included in Payable factor 80%

22

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

6.2.1 CUT OFF GRADE

Underground mining costs have been sourced from similar sized operations in Western Australia. The underground mining costs are summarised as follows:

Table 6-5: Underground Mining Costs

Item Unit Quantity
Admin AUD$/t of ore 2.50
Lateral Development AUD$/m 8,000
Vertical Development AUD$/m 6,000
Drill and Blast AUD$/m 2,700
Stope Bogging AUD$/t of ore 14
Trucking AUD$/t of ore 7.5
CRF AUD$/t of ore 10.40
Overheads AUD$/t of ore 25
Resource Definition AUD$/t of ore 10.50
Processing AUD/t of ore 40
Sustaining Capital AUD/t of ore 10

It is assumed ore is hauled 1.0 km from the portal to the ROM and the cost of load and haul for waste development is included in the cost per development metre. Royalties have been included in the overhead costs for underground mining.

6.2.2 STOPE OPTIMIZATION

Deswik Stope Optimiser (SO) was used to generate a suite of stope shapes based on the Net Revenue per Tonne (NRPT). The following key parameters were used:

  • Minimum mining width = 2.5m

  • Stope height = 25m

  • Minimum footwall dip = 42°

  • Stope width = 20m

  • Stope strike = 20m

  • Footwall and HW dilution = 0.5m

These parameters then generated Grade tonnage curves represented in Figure 6-11 and Figure 6-12

23

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [437 x 246] intentionally omitted <==

Figure 6-10: Copper Grade Tonnage Curve

==> picture [429 x 240] intentionally omitted <==

Figure 6-11: Zinc Grade Tonnage Curve

Using the Deswik.SO results and the costs above, a cash flow analysis can be run to check which NRPT cut-off grade produces the greatest cashflow and net present value (NPV).

24

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [351 x 177] intentionally omitted <==

Figure 6-12: NPV Analysis

Using this method, it shows that the orebody is not too sensitive to changes in cut-off, giving similar NPV results for a range of cut-off grades between $110 - $140 NRPT. The breakeven cut-off grade (NRPT) that produces the highest cashflow and NPV is $130 NRPT, therefore this data was used for the mine design.

6.2.3 MINE DESIGN

A basic mine design was undertaken to ensure the calculated assumptions for development were reasonable and to undertake a level-by-level cash flow analysis to determine the vertical economic extent of the orebody. Stopes above the 130mRL were also removed as these stopes were determined to be in Domain 1 according to the geotechnical report provided titled “Anglo Australia Resources NL Koongie Park Project Sandiego Prospect Geotechnical Evaluation Draft Report February 2011” by Dempers & Seymour Pty Ltd Geotechnical and Mining Consultants. These areas have now been incorporated into the Open Cut mine design for the Sandiego Open cut mine with a portal at the 130RL.

This report outlines three (3) geotechnical domains and predicted unsupported and supported hydraulic radius values for each. The hydraulic radius for Domain 1 won’t allow stoping. The Domain boundaries were determined visually using the cross sections in the model.

To ensure all development costs are captured the following development meters were used for each level.

Table 6-6: Development Meters

Item Quantity
Decline per level 200
Access per level 80
Return airway horizontal per level 40
Return airway vertical per level 25
Escapeway horizontal per level 20
Escapeway vertical per level 25
Internal Stockpile 20
Sump 7
Workshop/Pump station Allowance 5

25

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

==> picture [471 x 225] intentionally omitted <==

Figure 6-13: Underground Design looking from East

Rib pillars are placed at the top of each mining block where CRF cannot be placed due to having no top access. Rib Pillars are placed on the 105, 5, and -95 levels. This is shown below:

==> picture [369 x 304] intentionally omitted <==

Figure 6-14: Rib Pillar Selection looking from East

26

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Table 6-7: Underground Level by Level Analysis

==> picture [485 x 296] intentionally omitted <==

6.2.4 PRODUCTION RATE

The average stope size for Sandiego is ~20,000 t.

Using the average stope size and assumptions for activity rates as outlined in the table below, a production rate of ~2,600 tpd or 860 ktpa is calculated.

Table 6-8: Production Rate Based on Inventory

Activity Unit Value
Average Stope size tonnes 20,000
Production Drill factor Time (days) 7.00
Production Drilling time tpdm 12.70
Charge and Fire Time (days) 6.0
Bogging Time (days) 14.29
CRF Prep Time (days) 3.0
CRF Time (days) 13.66
CRF Cure Time (days) 2.0
Total Cycle time Time (days) 61.15
Average level size tonnes 195,000
Production Rate (per day) t ore 2,616
Production Rate (per year) t ore 860,000

27

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

6.2.5 UNDERGROUND SCHEDULE

Table 6-9: Mining Schedule by Year

Schedule Y1 Y2 Y3 TOTAL
Ore Tonnes 583,403 859,591 412,917 1,810,911
Copper Grade (%) 1.48% 1.11% 0.89% 1.17%
Zinc Grade (%) 1.70% 2.90% 4.09% 2.82%
Copper Metal (t) 7,969 9,569 3,663 21,201
Zinc Metal (t) 9,159 24,923 16,898 50,979
Vertical Rate of Advance 110 109 56 275
Years of Operation 1.0 1.0 0.5 2.5

Production rate reaches 860ktpa and the schedule mines 21kt of copper and 51kt of zinc. The mine life is 3.5 years and the portal will be established from the pit. 94 stopes are turned over with 43 being the maximum in one year.

28

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

7 METALLURGICAL TESTWORK

7.1 HISTORICAL TESTWORK

Metallurgical testwork was conducted by AAR as part of its feasibility study activities between 2008 and 2011 on a range of Sandiego and Onedin ores. The results of that testwork demonstrated that fresh copper and zinc lodes and the transitional zinc lodes at Sandiego (no tests were conducted on transitional copper material at Sandiego), can be concentrated at satisfactory metallurgical recoveries to produce commercial grade concentrates.

Cazaly Resources has also previously conducted metallurgical testwork on their Mt Angelo copper/zinc project. The testwork consisted of ore characterisation, comminution testing and a small flotation testwork program. The results of that testwork demonstrated that saleable grade copper and zinc concentrates could be produced at viable respective copper and zinc recoveries.

7.2 TESTWORK PROGRAMS

The flowsheet for the Koongie project has been designed with the philosophy of maximising the recovery of both copper and zinc from the ROM ore presented to the concentration plant as well as optimising the concentrate grade by the rejection of gangue impurities. Site water consumption has also been minimised through the selection of dewatering equipment and the recycling of water for re-use in the process plant. A high-level summary diagram has been included below in Figure 21.

7.2.1 STAGE 1 BENCHSCALE TESTWORK PROGRAM

The first stage of the bench scale testwork program consisted of two (2) sighter flotation tests to benchmark flotation behaviour. Flotation reagent vendors Solvay, Kings, Nouryon and Tecrich were consulted to establish preliminary flotation conditions and reagent dosing regimes.

The following notes are provided on the Stage 1 Bench scale Testwork Program:

  1. A baseline grind of 75µm would be used.

  2. Copper flotation is to occur first, followed by zinc flotation.

  3. For flotation of copper ore, sphalerite and pyrite will need to be depressed by adding lime during the grind and raising the pH. If lime alone is insufficient, higher pH’s should be tested along with SMBS and/or cyanides as depressants.

  4. Selection and dosing of collector, modifier and frothers were established for copper flotation.

  5. For flotation of zinc ore, sphalerite will need to be activated with copper sulphate.

  6. Talc will need to be removed by a pre-float step.

7.2.2 ADDITIONAL BENCHSCALE TESTWORK PROGRAM

AuKing has conducted a series of small-scale tests on the oxide and transitional ores at the Onedin deposit to assess the potential application of the AmmLeach® ammonia-leaching process. This testwork program, which has been registered with the Commonwealth Government’s R&D Incentive program is seeking to assess the potential to establish an alternative processing methodology for these Onedin ores that produces high recoveries. A significant amount of further testwork is planned here, based around a proposed pre-feasibility study to be managed by Perth-based Simulus Group.

29

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

In the meantime, with the addition of a Sulphidisation plant into the proposed Scoping Study metallurgical process (especially for the semi-weathered or oxide materials), a base-case processing methodology has been established and is considered appropriate for this Study. It remains to be seen whether the recoveries at Onedin utilising the AmmLeach® process can be demonstrated to exceed those expected to be achieved utilising the flotation method.

7.3 CONCLUSIONS

From the review of testwork programs the following conclusions can be made:

  1. The best performing copper flotation regime was established using lime, cyanide, zinc sulphate and SMBS as zinc depressant.

  2. Further testwork is required to:

  3. a. Further suppress zinc in the copper float

  4. b. Optimize the talc removal in the pre-float.

  5. c. Optimal grind size

  6. d. Baseline zinc flotation conditions

  7. e. Performance of cleaning flotation stages

  8. f. Establishment of overall circuit grade and performance through modelling and locked cycle testwork

30

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

8 MINERALS PROCESSING

8.1 GENERAL

The flowsheet has been designed to apply the Sulphidisation process to the oxide and transitional ores to improve the flotation process and to prioritise the copper flotation process, prior to zinc flotation. Thickeners and Filters have been added to both streams in the flowsheet to uphold efficient water use in the design and minimise copper and zinc quantities for shipment. Bagging facilities have been allowed for both streams for suitably bagging the copper and zinc products for containerised dispatch. A high-level summary diagram has been included below to display the proposed metallurgical processing flowsheet.

8.2 DESIGN CRITERIA

High level process design criteria, based on the Engineer’s industry knowledge of Copper Zinc Flotation plants of similar size, has been used during the Study. The key, high level process criteria, that have driven the block flow diagram, are summarised in Table 8-1 below:

Table 8-1: Design Criteria

ITEM UNITS VALUE
PRODUCTION
Annual Tonnes Processed t 750,000
Annual Production – Cu Concentrate t 118,809
Annual Production – Zn Concentrate t 47,321
GRADES
ROM grade % Cu 1.43
% Zn 3.89
Concentrate grade % Cu 24
% Zn 12.6
RECOVERIES
Total recovery - Cu % 87.0%
Total recovery – Zn % 77.0%
OPERATIONS
Operating days per year days 365
Shifts per day shifts 2
Hours per shift h 12
Operational availability % 91.3%
Operating hours per year h 8000
Feed t/a 750,000
Capacity tph 93.8

31

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

8.3 PROCESS DESCRIPTION

The overall process flowsheet is summarised in the block flow diagram below in Figure 8-1: .

==> picture [619 x 396] intentionally omitted <==

Figure 8-1: Proposed Koongie Park Processing Flowsheet Block Flow Diagram

32

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

8.3.1 COMMINUTION

The preliminary proposed flowsheet for the Koongie Cu-Zn project consists of three (3) stages of crushing/screening followed by one stage of ball-milling, which is typical for base metals flowsheets. The comminution circuit will be developed further in more advanced future engineering study phases.

8.3.1.1 Crushing/Screening

The proposed crushing circuit for the Koongie flowsheet consists of three (3) stages of crushing: a primary jaw crusher, secondary cone crusher and a final tertiary cone crusher.

Raw Ore will be delivered to the primary crusher from the ROM into a bin, from where it will be fed to the primary jaw crusher by a vibrating grizzly feeder.

Crushed ore from the tertiary crusher will be stacked and stockpiled on a crushed ore loadout.

8.3.1.2 Milling

Ore will be reclaimed from the crushed ore loadout and fed through a single stage ball mill. Oversize material from the ball mill will be re-ground in a vortex mill and recycled to ball mill feed.

8.3.2 FLOTATION

8.3.2.1 Sulphidisation

As the initial mined ore is tarnished/semi-weathered or oxide material, it will be less responsive to separation by flotation. An extra conditioning step, Sulphidisation, will need to be undertaken prior to conditioning with flotation reagents while processing this material. Milled ore will need to be activated with either Na2S or NaHS modifier, which will allow more efficient adsorption of collector reagents, rendering the targeted ore hydrophobic, thereby facilitating separation by flotation.

As mined ore transitions from weathered/oxide material to sulphidic, it will become more naturally responsive to collector reagents and the need for Sulphidisation will decrease and eventually be unnecessary.

The process conditions of the Sulphidisation step, such as selection of modifier, pH, temperature, residence time etc. will be confirmed in future testwork programs. Recovery based on the process has been assumed in the Scoping Study and further testwork will be necessary to quantify the assumed recoveries.

Sulphidisation is widely used in the mining industry to treat oxidized and transitional ore before hard rock mining is used over the life of the mine. Examples of previous and current plants are the following.

  • Golden Grove when owned by MMG in Western Australia.

  • White Dam owned by Aeris Resources in South Australia

  • Kansanshi copper mine owned by First Quantum in Zambia.

8.3.2.2 Copper Flotation

The proposed preliminary copper flotation circuit will consist of a conditioning tank, 1 stage of rougher flotation, 2 stages of cleaner flotation and 2 stages of scavenger flotation.

Milled ore from either the ball mill or from the Sulphidisation stage (in the case of treating oxidised ore) will be diluted, treated with reagents and brought up to the optimal temperature prior to flotation in the conditioning tank. Collector, frothers and depressants will be dosed at the optimum rate, prior to pumping to rougher flotation.

33

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Concentrate from the rougher flotation stage will be further processed into two (2) cleaner flotation stages in series, while tailings from the rougher flotation will be processed in two (2) scavenger flotation stages in series.

Tailings from each of the flotation stages are combined and pumped to the copper concentrate dewatering circuit, while the tailings are combined and pumped to the zinc flotation conditioning tank.

Further flowsheet development and optimisation will occur as a result of future testwork programs.

8.3.2.3 Zinc Flotation

The proposed preliminary zinc flotation circuit will consist of conditioning tank, one (1) stage of rougher flotation, two (2) stages of cleaner flotation and two (2) stages of scavenger flotation.

Tailings from copper flotation will be treated with reagents and brought up to the optimal temperature prior to flotation in the conditioning tank. Collector, frother and depressants will be dosed at the optimum rate, prior to pumping to rougher flotation.

Concentrate from the rougher flotation stage will be further processed into two (2) cleaner flotation stages in series, while tailings from the rougher flotation will be processed in two (2) scavenger flotation stages in series.

Tailings from each of the flotation stages are combined and pumped to the copper concentrate dewatering circuit, while the tailings are combined and pumped to the tailings thickener.

Further flowsheet development and optimisation will occur as a result of future testwork programs.

8.3.3 PRODUCT HANDLING

Concentrate from the copper flotation circuit will be dewatered by thickening and then filtering in a filter press. Filter cake will then be bagged ready for transport as copper concentrate.

Likewise concentrate from the zinc flotation circuit will be dewatered by thickening then filtering via a filter press. Filter cake will then be bagged ready for transport as zinc concentrate.

8.3.4 REAGENTS

The selection of reagents and the dosing regime has been based on both established industry practice and results from the preliminary metallurgical testwork program. The selection of reagents and dosing regimens will be further optimized for the Koongie flowsheet in future metallurgical testwork programs.

8.3.4.1 Lime

Lime is used as a pH modifier and will be added in the milling stage of the Koongie flowsheet. Lime acts to depress or discourage the flotation of pyrite impurities during flotation.

8.3.4.2 Sodium Metabisulphite (SMBS)

Sodium Metabisulphite (SMBS) is used in the copper flotation stage of the Koongie flowsheet as a zinc depressant – discouraging the flotation of and reporting of zinc to the copper concentrate.

8.3.4.3 Sulphidisation Agent

Sulphation modifier – either sodium sulphide (Na2S) or Sodium Hydrosulphide (NaSH) will be used to treat transition oxide material, which is less responsive to collector reagent and separation by flotation. The selection of the specific Sulphidisation agent and the dosing regime will be established in future metallurgical testwork programs.

34

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

8.3.4.4 Sodium Cyanide

Sodium Cyanide (NaCN) will be used in the copper flotation stage of the Koongie flowsheet as a zinc depressant – discouraging the flotation of and reporting of zinc to the copper concentrate.

8.3.4.5 Zinc Sulphate

Zinc Sulphate (ZnSO4) will be used in the copper flotation stage of the Koongie flowsheet as a zinc depressant – discouraging the flotation of and reporting of zinc to the copper concentrate.

8.3.4.6 Aerophine 3418A

Aerophine 3418A will be used in the copper flotation stage of the Koongie flowsheet as a flotation collector, which renders the target copper bearing minerals as hydrophobic, allowing separation.

8.3.4.7 DSF 004A

DSF 004A will be used in the copper flotation stage of the Koongie flowsheet as a frother – encouraging bubble formation.

8.3.4.8 Copper Sulphate

Copper Sulphate (CuSO4) will be used in the zinc flotation stage of the Koongie flowsheet as a zinc activator – modifying the surface of the target zinc bearing minerals to be more responsive to the collector, thereby allowing greater selectivity and separation by flotation.

8.3.4.9 Xanthate

Xanthates act as flotation collectors – rendering the targeted minerals hydrophobic, allowing separation by flotation. Xanthate will be used in the zinc flotation stages of the Koongie flowsheet. The selection of the specific xanthate and dosing regime will be established in future metallurgical testwork programs.

8.3.5 TAILINGS DISPOSAL AND WASTE HANDLING

The design objectives of the Tailings Storage Facility (TSF) are to:

  • Maximise the storage of tailings within a restricted footprint area. At this stage it is the intention that above ground surface tailings storage capacity is enough to cater for the LOM. The option of moving to tailings storage into mined out pits is being considered as an alternative, but those studies are not sufficiently advanced to present this option.

  • Provide adequate storage/stack stability. Studies will need to be conducted to examine stack geometry, various slope reinforcement methods and stack drainage.

  • Reduce the environmental impact of the stacked tailings.

Tailings from flotation will be run through a thickener and then stored in a TSF. Tailings after thickening will have a moisture content of 55% with an output of 588,601m[3] per annum. Wastewater from thickening and filtration will be treated as process water or report to the Reverse Osmosis plant and stored in a tank before being pumped for recycling through the processing plant. A summary of the waste streams are included in Table 8-2.

35

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Table 8-2: Waste Streams

Table 8-2: Waste Streams
PROCESS STAGE WASTE GENERATED NATURE
Mining Mining waste Benign (Will Require Acid Rock
Drainage assessment)
Milling, Cycloning, Screening Coarse rejects Benign; dewatered
Flotation Gangue minerals Benign; stored
Filtration Water Benign; recycled

36

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

9 INFRASTRUCTURE AND LOGISTICS

9.1 SITE LAYOUT

The site should consist of:

  1. ROM, with area adequate to stockpile at least 3 days mine production to cover the mine shift and any plant shutdowns. The ROM orientation should be North-South to ensure safe operation when dumping.

  2. Sufficient area allowed for blending stockpiles to minimise feed grade variation through the plant,

  3. Relationship between final product process and packaging will need to be close to minimise handling.

  4. Clear access will need to be maintained for semi or B-doubles to deliver reagents to areas on the process plant,

  5. A power supply substation located in such a manner as to minimise distance to major power demand elements. If solar is considered, prevailing winds must be considered to reduce dust from ROM.

Figure 9-1 provides proposed site layout with proposed locations for processing plant and supply water dam. While overall locations will be similar, exact locations and layout of plant / buildings will be subjected to further review and changes as study phases progress.

==> picture [494 x 286] intentionally omitted <==

Figure 9-1: Site Layout

37

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

9.2 POWER SUPPLY

A diesel-powered generating station has been costed into the plant estimates for construction at the proposed Sandiego mining and processing site.

Whilst this Study has assumed diesel as the primary source of power generation the potential does exist for gas fired and/or solar power generation for Koongie Park. Horizon Power is the primary provider of energy solutions in the region and could also consider transmission of power from an extended Halls Creek power station. A transmission line already exists from Halls Creek to Koongie Park Station which is adjacent to Onedin. A further power line extension of 7km would be required to transmit power to Sandiego. The capacity of the current transmission line to Koongie Park is not known and the cost or potential of any upgrade is also not yet known. It is recommended that options for gas fired and/or solar power be investigated fully in future Studies.

9.3 WATER SUPPLY

A preliminary investigation only of the availability of water for the proposed Sandiego operation has been undertaken. Water has been intersected in a nearby bore hole which was pumped at a rate of 6500 l/h for use in the drilling programme. This water result confirmed that a mining and processing operation at Sandiego mine should not be adversely affected by water inflows. A professional hydrological assessment should be undertaken in the Feasibility Study stage. The reasonable availability of water will be critical for mine development at Sandiego. It is anticipated that satisfactory quantities of water will be found for the project in view of the reasonable availability of groundwater in the region.

There will be several requirements in terms of volume and quality for water including:

  1. Dust suppression

  2. Process water

  3. Analysis of available water for chemical content and volumes will be required for flotation optimization

  4. Operations water for drinking, safety showers, toilets etc.

  5. Firefighting

9.4 WATER TREATMENT

As supply water must first be softened to maximise flotation recovery, the utilisation of reverse osmosis to remove hardness from process water will be applicable.

9.5 ROADS

The Great Northern Highway (National Highway One) which is the main bitumen highway around Australia, connects Halls Creek to Koongie Park, approximately 25kms to the south-west. There are existing roads and tracks that link a proposed central processing facility at Sandiego to the nearby deposits and these roads will require upgrade to handle the flow of heavy vehicles. Overall trucking costs will be reasonably competitive because road conditions are good and distances no more than 10km to any point.

38

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

9.6 SUPPLY CHAIN AND PRODUCT TRANSPORT

The cost of concentrate transport will be a major part of the total cost structure of the project. The Great Northern Highway connects Halls Creek and Koongie Park with Wyndham, which is the proposed port for export of the zinc and copper concentrates. Trucking costs will be reasonably competitive because road conditions are good but the 400 km distance will present a significant operating cost. A trucking rate of A$0.1/t per km, equivalent to A$40 / wet tonne of concentrate for the 400km from Koongie Park to Wyndham, has been used in cost estimates and cashflow analysis.

The port of Wyndham has long been used as a concentrate export port. Whilst the port is not a deep-water port and has limits on the size of ships which it can accommodate it is anticipated that shipment of Koongie Park concentrates through Wyndham would closely emulate the current practice for the shipment of nickel concentrates through the port (via the Savannah Nickel Project). Concentrates would be trucked to the port and stored in a shed prior to loading. Copper and Zinc concentrates would be handled separately. The concentrate would be skip loaded onto ships in shipments of 5,000 to 10,000 tonnes.

9.7 NON-PROCESS BUILDINGS AND FACILITIES

The key mine infrastructure area and major earth works are to be completed by a contractor. Key specification of the required facilities will be placed with a contractor as part of the delivery process. Contractor requirements for inclusion in construction and site establishment included:

  1. Product stockpile areas clearing and preparation.

  2. Workshop clearing, building and appropriate tooling.

  3. Laydown area clearing and preparation including spillage containment.

  4. Fuel Farm clearing and setup inclusive of bunding and drainage to environmental requirement; and,

  5. Administration buildings including offices, communications room, meeting and training rooms, First Aid facility.

9.8 CAMP ACCOMMODATION

Given the proximity of the project area to Halls Creek and to minimise daily commuting times, it is likely that a dedicated accommodation camp will be operated in the township, in much the same way as has been the case with Nicolson’s mine workers for several years.

AuKing already has an office facility in the Halls Creek township and on-site administration facilities will be located at the processing facility.

The required camp facilities will be quoted for full installation and outright purchase from contracting parties or suppliers direct. All Buildings priced supplied flat packed for transport and assembled on site. A contractor supply and construct was selected as part of this study, with camp specifications as follows:

  1. Four room ensuite bunkhouse.

  2. Kitchen and Dining Hall.

  3. 1 x Cold room and dry storage.

  4. 12m x 9m Recreation Room fitted with pool table and lounge.

  5. 12m x 6m Mess area with outside deck.

  6. 6m x 3m Linen Store.

  7. 6m x 3m Laundry.

  8. 6m x 3m Male/Female communal toilet.

39

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

  1. Water tanks (50 000 litres) pumps, water supply ring main.

  2. Sewage Treatment Plant allowing 250 litres per day per person; and,

  3. 2 x Generators supply and back up.

Site administration facilities will be located at the processing facility.

9.9 TAILINGS

The tailings stream from the flotation plant will be pumped, via a standard sampling system, to a tailings handling facility, where process water will be recovered. In order to accommodate the planned production rate from the process plant, 750,000 tpa of ROM ore will be treated yielding approximately 13,300 tonnes of concentrates. Water from the tailings transfer facility will be recovered to the return water dam and pumped back to the process water storage tanks. The dam will be designed so as to minimise evaporation loses and return water to the plant as rapidly as possible.

The environmental aspects of a proposed tailings dam will be considered as part of future studies. However, it is anticipated that permeability testing of the proposed dam site will be required to predict any potential acid drainage problems. The location of the tailings dam will be considered in future studies with the intention of containing any water and contaminant run-off from the project.

An allowance of $1m has been made for tailings dam capital in the cashflow analysis of this Study. Operating cost estimates of $8000 per month are contained within the Treatment Plant operating cost estimates.

9.10 COMMUNICATION SYSTEMS

The Information Systems Implementation will be managed by contractor who will provide a single point of accountability through the provision of overarching responsibility and delivery of the Information Systems in the office and on site at the Koongie Park Project.

As yet, the preferred technical solution to be implemented (i.e., hardware, software and infrastructure) has not yet been finalised. It is anticipated that specific software systems needed will be chosen during the procurement and implementation phase.

When the preferred technical solution is implemented, there will be enough scalability and resources available to introduce software systems fit for purpose.

The site Local Servers will be located in a dedicated air-conditioned server room located in the Site Office with security access by way of key held by the General Manager.

The following internal communication systems will be required:

  1. Administrative telephone communication system

  2. Dispatch communication system

  3. Production TV monitoring system

  4. Fire alarm system

  5. Computer network system

  6. Plant area communication network

40

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

10 ENVIRONMENT, SOCIAL, COMMUNITY AND PERMITTING

10.1 EPA AND DAWE ASSESSMENT

The Koongie Park Project will provide significant benefits to the people of the Halls Creek township and it is envisaged that environment and cultural considerations will not be limiting factors in the development of the project.

Auking intend to refer the Project to the WA Environmental Protection Authority (EPA) under Section 38 of the Environmental Protection Act 1986 (EP Act) and the Commonwealth Department of Agriculture, Water and Environment (DAWE) under the Environmental Protection and Biodiversity Conservation (EPBC) Act 1999.

Once this is lodged the EPA will confirm that the Project will be assessed under Part IV of the EP Act through a Public Environmental Review (PER) process with a public review period for the Environmental Review Document (ERD) of 8 weeks.

Subsequently DAWE will confirm the Project will be assessed under Section 75 of the EPBC Act as a controlled action and as an accredited assessment under the EP Act.

It has been assumed that the Project has several preliminary key environmental factors and a detailed assessment is required to determine the extent of the proposal's direct and indirect impacts and how the environmental issues could be managed. The EPA may determine that the Project has potential impact on flora, vegetation and terrestrial fauna from the clearing of mine footprint including the construction and operation of a mine and processing facility and Social Surroundings from impacts to heritage values.

In preparation for the above Auking intend to prepare an Environmental Scoping Document (ESD) which will be made available for the public feedback. Following the ESD, Auking is planning on completing the remaining required environmental surveys to address the preliminary environmental factors and preparing an ERD.

10.2 KEY ENVIROMENTAL FACTORS

Several studies were undertaken by AAR as part of its 2008 Pre-Feasibility Study activity including a comprehensive flora and fauna assessment. In general terms, the findings of those earlier studies included the following:

  • It is very important to implement erosion control during the construction and operation of the proposed activity. If erosion control is inadequate, soil loss is likely to be higher (in the wet season), as erosion hazard will increase as the study area is changed from its natural (but degraded) condition.

  • Although the area has been subject to disturbance through cattle, fire and exploration, overall, the vegetation condition was considered to be “Very Good” to “Excellent”, with other minor areas considered good-degraded.

  • As part of the development of mining operations for the Project, native vegetation and fauna habitat within the project area will be disturbed. It is inevitable that there will be some localised loss of flora and fauna arising from clearing of the vegetation and construction activities for the mining operations. However, it was considered unlikely that the loss of species individuals associated with the direct mortalities and compromise of proximal habitat values would be sufficient to affect the overall conservation status of the survey area.

  • There is the potential for environmental impact caused by:

  • Generation of Acid Rock Drainage (ARD); and

  • Depletion (drawdown) of groundwater resources.

In regard to ARD, the orebodies (and waste rock) are sulphidic and therefore have the potential when exposed to air and water to oxidise and generate ARD. AuKing will be required to undertake waste rock, ore and tailings geochemical characterisation. If there is a possibility of heap leaching ore, then this material also, will require characterisation studies.

41

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

As part of future study work, Auking intends to focus on the following preliminary key environmental factors.

  • Flora and Vegetation.

  • Terrestrial Environmental Quality.

  • Terrestrial Fauna.

  • Inland Waters.

  • Air Quality; and

  • Social Surroundings.

In addition to specific consideration of each environmental factor, the ERD will also provide a holistic assessment of environmental impacts, including an environmental values assessment, and drawing together the overall impact of the proposal on the environment and identifying any interactions amongst individual factors. Further, the ERD will address cumulative impacts, though given the location of the development envelope and the lack of existing and foreseeable contextual impacts, this is not anticipated to be a significant consideration for the environmental review.

Under the EPBC Act, as an accredited assessment, the relevant matters of national environmental significance (MNES) for this Project are:

  1. National Heritage places (sections 15B and 15C).

  2. Listed threatened species and communities (sections 18 and 18A).

  3. Listed migratory species (sections 20 and 20A); and

  4. Commonwealth marine areas (sections 23 and 24A).

The EPA (2020b) states that greenhouse gas (GHG) emissions from a Project will be assessed when they exceed 100,000 tonnes per annum of scope 1 emissions. Preliminary estimates for the Project are that that scope 1 GHG emissions will be less than 60,000 tonnes per annum. The ERD will address this consideration, setting out the calculations and methodology used for emissions estimates.

10.3 STAKEHOLDERS

As part of the ERD the Project will consult with stakeholders who are affected by or are interested in the Project. This includes decision-making authorities, other relevant State (and Commonwealth) government agencies and local government authorities, the local community and environmental non-government organisations. The Project will document the following in the ERD:

  1. All identified stakeholders.

  2. The stakeholder consultation undertaken and the outcomes, including decision-making authorities’ specific regulatory approvals and any adjustments to the proposal as a result of consultation; and

  3. Any future plans for consultation.

42

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

10.4 NATIVE TITLE AND ABORIGINAL HERITAGE

Mining leases 80/276 (covering Sandiego) and 80/277 (covering Onedin) are granted and lie within native title claims Koongie and Lamboo Elvire represented by the Kimberley Land Council. These mining leases are unencumbered by native title agreements as the tenements were granted prior to the Native Title Act 1993 (Commonwealth).

In 2007 an ethnographic survey of M80/276 and M80/277 was undertaken by the Kimberley Land Council to document Aboriginal heritage values. The report concluded that in the two areas surveyed (M80/276 and M80/277) the proposed work program (level of disturbance or intensity not greater than diamond and percussion drilling) does not represent a risk to sites of significance to Traditional Owners.

AAR conducted an archaeological site avoidance survey of the mining leases, M80/276 & M80/277, as part of its 2008 Pre-Feasibility Study. The objective of the survey was to determine the presence of any Aboriginal heritage sites so that no Aboriginal sites are disturbed when work commences on the mining leases. Transects were conducted in the survey areas in a systematic manner to determine the presence of archaeologically significant material. The results of the AAR survey were:

  • Four (4) new Aboriginal archaeological sites KP1-KP4 were located on mining lease M80/276

  • No sites were located on M80/277

  • All four sites located on M80/276 are stone artefact scatters and occur in flat areas near water sources

As part of the future study activities Auking will carry out further studies to confirm the nature and extent of any archaeological sites that may require consideration as part of the proposed mining and processing activities.

Mining Lease 80/247 (covering Mt Angelo North) is a granted lease within the Koongie native title claim represented by the Kimberley land Council. This mining lease is unencumbered by native title agreements as the tenement was granted prior to the Native Title Act 1993 (Commonwealth).

Exploration Licence 80/5307 (covering Bommie) is granted and lies within native title claims Koongie and Lamboo Elvire represented by the Kimberley Land Council. An ethnographic survey was completed by the Kimberley Land Council in 2007 and 2022 to identify any potential sites of cultural heritage value within the footprint of then proposed Bommie drilling programs. The reports concluded that within the proposed drill work area there were no previously identified sites that would be impacted and no new sites of cultural heritage value were identified. In 2022 the drill area was cleared with the condition that Cultural Heritage Monitors be present during drill operations.

43

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

11 IMPLEMENTATION

11.1 INTRODUCTION

This project implementation strategy outlines the preliminary overall plan for implementation of the Project through further studies and delivery to operations. The Scoping study has been based around an engineering, procurement and construction management (EPCM) execution framework. A Work Breakdown Structure (WBS) has been developed for the Project, which is used to describe each element of the Project and provide a common platform for reporting.

11.2 KEY OBJECTIVES

The key project and business objectives are to:

  1. Achieve zero harm to people and minimise harm to the environment in delivering the project.

  2. Maintain the budget and approved schedule.

  3. Provide optimal capital efficiency for functionality.

  4. Maximise shareholder value and financial return to investors.

  5. Conform to statutory requirements and Auking/Cazaly corporate requirements.

  6. Develop and maintain good relationships with Government agencies, key stakeholders and local communities.

  7. Seek to actively employ local workforce wherever feasible to do so.

11.3 DEVELOPMENT STRATEGY

Projects are developed in phases with each stage further defining the Project and with a corresponding increase in detail. The following figure provides a summary project implementation framework for a typical resource project. The Koongie Park is currently at the Scoping stage, with the next stage being the completion of a PFS.

==> picture [482 x 78] intentionally omitted <==

Figure 11-1: Project Implementation Framework

44

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

11.4 PROJECT IMPLEMENTATION SCHEDULE

A preliminary project implementation schedule has been developed for the implementation of the Project from the completion of this Scoping study through to execution. The overall purpose of the implementation schedule is to identify critical path items and understand realistic timeframes required to bring the Project into production.

==> picture [513 x 386] intentionally omitted <==

Figure 11-2: Proposed Development Timing

The project schedule will be driven by the completion of the Scoping study and subsequent Pre-Feasibility study. Auking has recognised this with respect to approvals and has begun the planning process.

The following is a summary of key activities to be undertaken between the completion of this Scoping study and a final investment decision:

  1. Additional exploration, resource and reserve definition drilling.

  2. Process development and optimisation testwork.

  3. Completion of environmental surveys, permitting and approvals.

  4. Definitive Feasibility Study.

  5. Front End Engineering and Design (FEED).

  6. Long lead-time procurement items (pre-Final Investment Decision); and,

  7. Financing activities.

45

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

It is noted that Auking may seek a faster schedule to operations. The above milestones are based on a traditional approach to project development, financing and implementation and consider the climatic conditions within the project area i.e., the difficulty in completing construction activities during the heavy wet season. It is likely that opportunities exist to shorten this schedule, and this would need to be the subject of further and more detailed schedule work based on more defined engineering.

11.5 PROJECT DELIVERY STRUCTURE AND CONTRACTING STRATEGY

The project delivery will be structured around major capital cost packages (CPs) and operating cost packages (OPs). Each package area will consist of either single major contractor or multiple smaller contracts utilising various contracting styles. A preliminary contracts register has been prepared on this basis (presented further below), and the final contracts register may vary by either breaking down packages further or consolidating together into larger contracts.

==> picture [401 x 268] intentionally omitted <==

----- Start of picture text -----

FINANCIERS INSURERS BOARD
INDEPENDENT PHI PROJECT
ENGINEER IMT COMMITTEE
OPEX CAPEX
OP1 - OP2 - CP0 - CP1 -
MINING REAGEN IMT SITE
OP3 - OP4 - CP2 - CP3 -
GENERA ACCOM. PROCESS EQUIP
OP5 - CP4 - CP5 -
MISC. WATER POWER
CP6 -
OWNER'S
----- End of picture text -----

Figure 11-3: Project Delivery Structure

The tables following provide preliminary evaluation of the major contract classifications and the major contracts register.

46

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

Table 11-1: Contract Classifications

Table 11-1: Contract Classifications
CLASSIFICATION GENERAL TERMS AND CONDITIONS
Consulting and professional services (including engineering) AS4122 (with annexures)
Construction only AS4000 (with annexures)
Supply (without installation) AS4911(with annexures)
Supply (with installation) AS4910 (with annexures)
Design and construct (EPC) AS4902 (with annexures)
General supply (goods) Purchase order agreement
Build Own Operate / Transfer (BOO/BOOT) Bespoke agreement

Table 11-2: Preliminary Contracts Register (and contribution to capex excluding contingency)

CONTRACT NUMBER CONTRACT DESCRIPTION CONTRACT CLASSIFICATION
CP0-01 Integrated Management Team (including engineering and
owner’s costs)
Consulting
CP1-01 Site Infrastructure - Site Development Construction only
CP1-02 Site Infrastructure - Non-Process Infrastructure and
Facilities
Design and construct
CP1-03 Site Infrastructure – Mine Infrastructure
CP2-01 Process plant - beneficiation Supply (with construction)
CP3-01 Mobile equipment and spares Purchase order
CP4-01 Water supply dam Construction only
CP4-02 Water supply pipeline Construction only
CP5-01 Power station Design and construct
CP5-02 On site HV reticulation Construction only
CP6-01 Communications Design and construct
CP6-02 Accommodation village Design and construct

47

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

11.6 OPERATIONAL READINESS

11.6.1 RESPONSIBILITY

Operational readiness is the joint responsibility of the Project Delivery Team and the Operational Team.

The Project Director will delegate specific operational readiness tasks to others within the Integrated Management Team (IMT).

11.6.2 OVERVIEW

Operational readiness involves several aspects, summarised in Figure 11-4.

==> picture [451 x 263] intentionally omitted <==

Figure 11-4: Operational Readiness Structure

An Operational Readiness Plan will be prepared during the execution phase of the Project and will generally provide the deliverables listed in the following table.

OPERATIONAL READINESS AREA DELIVERABLE
ASSET REGISTER Financial Asset Register Content
Computerise Maintenance Management System (CMMS) Equipment Hierarchy
and Attributes
CMMS AND DOCUMENT
MANAGEMENT SYSTEM
(CMMS)/Data Management System (DMS) Configuration
Data Population

48

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [72 x 25] intentionally omitted <==

OPERATIONAL READINESS AREA DELIVERABLE
MAINTENANCE PLANS Reliability Centred Maintenance (RCM)/Failure Mode Effect Critical Analysis
(FMECA) Maintenance Strategies and Tactics
Maintenance Work Instructions
CMMS Uploaded
SPARES, MATERIALS AND
SERVICE PROVIDERS
Spares, Materials and Services Definition
CMMS Catalogue Uploaded
MANAGEMENT PROCESSES Procedures Governing Key Business Processes e.g. Operate and Maintain
EQUIPMENT OPERATING
PROCEDURES
Operating Procedures and Work Instructions
Operator Training Material Developed and Delivered
LIFE CYCLE COSTING Life Cycle Costs/Budgeting
ASSET AND EQUIPMENT CODING
AND LABELLING
CMMS, Documentation and Physical Labels Aligned

11.7 ASSET REGISTER

To facilitate the transition to operations, the asset register will be developed during the engineering phase.

Each piece of equipment will be labelled in accordance with the equipment naming procedure, and will consist of the following hierarchical structure:

SITE CODE – L1 EQUIPMENT CODE – WBS CODE – L2 EQUIPMENT CODE – L3 EQUIPMENT CODE

Example: The asset code for the electrical motor (EM01) on the main drive unit (DV01) for the feeder (FE) at the truck dump area (WBS 3211) at the Koongie Park (AUK) site would be:

AUK.FE. 3211.DV01. EM01

All cost data from supply and installation contracts will be broken down such that asset values for depreciation can be determined for accounting purposes.

49

KOONGIE PARK COPPER ZINC PROJECT_

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

11.8 ORGANISATION CHART

==> picture [730 x 362] intentionally omitted <==

50

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

12 CAPITAL COST ESTIMATE

12.1 ESTIMATE SUMMARY

Table 12-1: Cost Estimate by Cost Type

COST TYPE COST BREAKDOWN
DESCRIPTION
VALUE AUD$
PROCESSING Mechanical $24,000,000
Earthworks $1,200,000
Concrete $4,800,000
Steelwork $6,000,000
Platework $2,880,000
Piping $6,000,000
Electrical $8,400,000
Control $1,200,000
Mech install $6,000,000
NON-PROCESS INFRASTRUCTURE Water dam $750,000
Tailings $1,000,000
Facilities $4,201,000
Site earthworks / roads $2,250,000
Power supply $3,750,000
Water treatment $1,875,000
Communications $750,000
Camp $3,000,000
DIRECT COSTS TOTAL $78,056,000
INDIRECT Spares, first fill, etc $1,200,000
Owner's cost $2,341,680
Contractor P&Gs $14,936,209
EPCM $15,611,200
INDIRECT COSTS TOTAL $34,089,089
GRAND TOTAL EXCLUDING CONTINGENCY $112,145,089
CONTINGENCY 20% $22,429,018
GRAND TOTAL INCLUDING CONTINGENCY $134,574,107

51

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

12.2 BASIS OF ESTIMATE

12.2.1 GENERAL

The general estimating philosophy that was utilized to determine the direct field cost and the indirect cost were a combination of Stochastic (factoring) and Analogy (like for like) and Deterministic (measurement) estimating techniques.

See below under each heading which estimating methodology and which of the Project’s information and/or quantities were utilized to compile the Capex Estimate.

The estimate was based solely upon the PFD and a priced mechanical equipment list as determined by the conceptual design. A scoping study estimate such as this, where factors are used to determine capital cost based on the mechanical equipment value, is very dependent on the accuracy of the priced mechanical equipment list (both in terms of price and content). All attempts have been made to include sufficient equipment in the list as expected by the layout and similar, operating plants, noting the early stage of the study and limited engineering progress to date.

12.2.2 DIRECT FIELD COSTS

12.2.2.1 Mechanical Equipment

The estimate value has been determined using the Wave database and based on similar sized projects. Note that the value used is for supply, including delivery to site only and excludes any installation.

12.2.2.2 Mechanical Installation

The estimate value has been determined using adjusted database factors to suit the project location.

12.2.2.3 Civils and Earthworks

The estimate value has been determined using adjusted database factors to suit the project. Specific consideration given to a flat site, relatively short access road and the assumption that very little material will have to be imported.

12.2.2.4 Structural Steelwork

The estimate value has been determined using adjusted database factors to suit the project. There is no unusual consideration considered for structural steelwork, except for certain plant areas having a more corrosive environment than generally allowed for.

12.2.2.5 Platework Bulks

The estimate value has been determined using adjusted database factors to suit the project.

12.2.2.6 Piping

The estimate value has been determined using adjusted database factors to suit the project. The adjustment to expected norms are a marginal increase to allow for some highly corrosive plant areas.

12.2.2.7 Electricals

The estimate value has been determined using adjusted database factors to suit the project Electricals.

12.2.2.8 Control Instrumentation

The estimate value has been determined using adjusted database factors to suit the project Electricals.

52

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

The following table provides the factors applied in the cost estimate.

Table 12-2: Direct Field Cost Allowances

Discipline Benchmark %
Range
Quantity Surveyor
Recent
Recommendation
REF 1 REF 2 Selected
Earthworks 16%-26% 18% 2% 4% 5%
Concrete 13% 34% 20%
Steelwork 15%-26% 22% 16% 12% 25%
Platework 15%-25% 19% 13% 11% 12%
Piping 19%-38% 21% 31% 24% 25%
Electrical 4%-15% 10% 35% 28% 35%
Control 12%-25% 12% 5% 5%
Mech install 12%-35% 25% Included Included 25%
Total 93%-164% 127% 115% 112% 152%

12.2.3 CONSTRUCTION INDIRECT COSTS

These costs were factored from the Wave database using similar projects.

Indirect /field Costs include:

  1. Major plant and equipment (carnage, generators, etc) required for construction.

  2. Mobilisation and demobilisation.

  3. Scaffolding.

  4. Contractor’s site facilities including stores, workshop, offices, etc

  5. Accommodation expenses.

  6. Insurances.

  7. Contractors head office expenses.

  8. Contract management and Commissioning and Testing.

12.2.4 NON-PROCESS INFRASTRUCTURE

Non process infrastructure has been estimated on a high-level quantities and rates basis, and comparative estimate basis from similar projects.

53

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

12.2.5 OWNERS / INDIRECT COSTS AND CONTINGENCY

Owners indirect costs were factored from database using similar projects and at this stage does not consider specific owner company strategies and structures but provides what would be considered reasonable for an emerging producer.

The allowance typically includes for the following services and items:

  1. Environmental consultants.

  2. Surveys.

  3. Geology, Hydrology, etc

  4. Insurances.

  5. Permits.

  6. Legal.

  7. Operational readiness.

  8. Import duties.

The following table summarises factors used for owners and other indirect costs.

Table 12-3: Indirect Costs Allowances

Item UOM Unit Rate Comment
Spares, first fill, etc % 5 % of equipment cost
Owners Costs % 5 % of total direct cost
Contractors P&Gs % 20 % of total direct cost
EPCM % 25 % of total direct cost
Contingency % 20 % of total direct and indirect cost

12.2.6 ESTIMATE CONSTRAINTS, ASSUMPTIONS AND EXCLUSIONS

The list below reflects the currently identified constraints and exclusions that are pertinent to this Capex Estimate view:

  • Force majeure issues.

  • Future scope changes.

  • Foreign exchange cover.

  • Standing costs.

  • Mining infrastructure only allowed for haul roads, surface water diversions and power and water supply – no pre-stripping or pit development as this is considered as OPEX and part of the mining contractors’ scope.

  • Generally, the local topography can be considered as flat.

  • The facility to be specified and constructed to suit a 24hr/365 days life-of-mine plan.

No allowance is made for escalation.

54

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

12.3 ESTIMATE CLASSIFICATION

This estimate is classified as a class 4 estimate as per the AACE definition in the table below, which is equivalent to a class 5 estimate as defined in AusIMM. The AACE definition is used here as it provides a more detailed description of the estimate classification.

Table 12-4: AACE Definition

PRIMARY
CHARACTERISTIC
SECONDARY
CHARACTERISTIC
SECONDARY
CHARACTERISTIC
SECONDARY
CHARACTERISTIC
ESTIMATE
CLASS
LEVEL OF PROJECT
DEFINITION
Expressed as % of
complete definition
END USAGE
Typical purpose of
estimate
METHODOLOGY
Typical estimating method
EXPECTED ACCURACY
RANGE
Typical variation in low and
high ranges [a]
Class 5 0% to 2% Concept
Screening
Capacity Factored,
Parametric Models,
Judgment or Analogy
L:-20% to -50%
H: +30% to +100%
Class 4 1% to 15% Study or
Feasibility
Equipment Factored or
Parametric Models
L: -15% to -30%
H: +20% to +50%
Class 3 10% to 40% Budget,
Authorization
or Control
Semi-Detailed Unit Costs
with Assembly Level Line
Items
L: -10% to -20%
H: +10% to +30%
Class 2 30% to 75% Control
or Bid/Tender
Detailed Unit Cost with
Forced Detailed Take-off
L: -5% to -15%
H: +5% to +20%
Class 1 65% to 100% Check Estimate
or Bid/Tender
Detailed Unit Cost with
Detailed Take-off
L: -3% to -10%
H: +3% to +15%

Notes: [a] The state of process technology and availability reference cost data affect the range markedly. The ± value represents typical percentage variation of actual costs from the cost estimate after application of Contingency (typically at a 50% level of confidence) for given scope.

Source: AACEI Recommended Practice RP18-97 Estimate Classification

55

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

13 OPERATING COST ESTIMATE

13.1 ESTIMATE SUMMARY

An operating cost estimate (OPEX) was prepared for AuKing’s proposed copper zinc project. The OPEX was developed as a bottom-up estimate and is based on the engineering development of the process explained in earlier chapters, specifically the mass and water balance, process design criteria and mechanical equipment list. Prices are based off vendor enquiries, AuKing’s inputs and Wave’s internal database.

The OPEX results reported are representative of annual steady state operations which were calculated by taking the LOM forecast produced tonnes of Copper and Zinc, then dividing by the LOM (11.1 years). Steady state production for copper and zinc are 9,900tpa and 3,460tpa respectively. The OPEX has an accuracy of a Class 4 estimate allowing for a ± 30-50% accuracy. The following table summarises the operating cost estimate results for the total operation.

Table 13-1: Processing Operating Cost Estimate

ELEMENT AUD$/Y AUD$/T FEED AUD$/T PROD
Labour 6.33 8.44 473.8
Maintenance 1.98 2.64 148.0
Electrical Power 10.62 14.16 795.2
Reagents 13.83 18.44 1,035
Diesel 0.58 0.78 43.73
Transport and Logistics 0.53 0.71 40.00
Flights & Accommodation 2.31 3.08 173.0
G & A 2.62 3.49 195.8
Total 38.81 51.75 2,905

13.2 ESTIMATE DETAILS

13.2.1 LABOUR

The organisational structure and salaries were built up by Wave from its internal database and experience on previous and similar projects. The mining personnel are listed only with employee headcounts as salaries are built into the mining cost while flights and accommodation are not.

56

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

Table 13-2: Labour Cost Summary

POSITION # SALARY 28% ON-COST TOTAL TOTAL
ANNUAL
LABOUR COST
Staff/Managers
RM / Open Cut Manager 2 250,000 70,000 320,000 640,000
Senior Surveyor 2 155,000 43,400 198,400 396,800
Mine Geologist 2 155,000 43,400 198,400 396,800
HSE Officer/Stores 2 175,000 49,000 224,000 448,000
Process
Process Manager 2 220,000 61,600 281,600 563,200
Plant Metallurgist 1 150,000 42,000 192,000 192,000
Lab Technician 2 100,000 28,000 128,000 256,000
Plant Foreman 1 180,000 50,400 230,400 230,400
Operators 12 120,000 33,600 153,600 1,843,200
Maintenance Superintendent 1 190,000 53,200 243,200 243,200
Maintenance Planner 1 175,000 49,000 224,000 224,000
Fitter/Boiler 3 140,000 39,200 179,200 537,600
Electrician 2 140,000 39,200 179,200 358,400
Mining
Contract Mining Manager 2
Miners 31
Fitter 2
Electrician 2
Total 70 6,329,600
AUD/t Feed 8.44
AUD/t Product 473.8

57

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

13.2.2 MAINTENANCE

Maintenance costs were based on plant requirements and the calculated CAPEX. Factors based off industry standards were used as the basis for fixed plant maintenance and is presented below.

Table 13-3: Fixed Plant Maintenance Cost

ELEMENT Supplied CAPEX
(AUD
Factor AUD$/Annum AUD$/T PROD
Mechanical/Platework 26,880,000 4.50% 1,209,600 90.5
Pipe Work 6,000,000 2.00% 120,000 8.98
Electrical 9,600,000 3.00% 288,000 21.6
Infrastructure 15,326,000 1.00% 153,260 11.5
Total 1,770,860 132.5

Light Vehicle Maintenance represents the expected fleet required for the project and costs were taken from the Wave database.

Table 13-4: Light Vehicle Maintenance Cost

Item # Annual
Maintenance
Cost
Operating
Hours
AUD/h AUD/annum
Mobile Crane (20t) 1 - 1,095 8.00 8760
Container Lifter 1 - 547.5 15.00 8213
Telehandler 1 - 547.5 15.00 8213
EWP 1 - 547.5 4.00 2190
Fire Truck 1 3,900 50 15.00 4650
Forklift 1 3,850 1,971 2.00 7792
Bobcat 1 3,850 2,759 4.00 14888
FEL 1 131,400 4,380 131,400
Landcruiser (Prado) 1 2,530 1,577 2530
Dual Cab Ute (Hilux) 2 2,530 1,577 7590
Tray Top Ute (Hilux) 2 2,530 1,577 7590
Troop Carrier (Ambulance) 1 2,030 100 3045
Bus (25 Seater) 1 50 15.00
Total 206,860

58

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

13.2.3 POWER

Diesel generator sets supply electricity to site. The unit cost (AUD/kWh), electrical load, and yearly operating hours were estimated from the mechanical equipment list. The pricing is based on Wave’s internal database information. A price of 0.26 AUD/kWh was used.

Table 13-5: Electrical Power Cost

Electrical Power Installed AUD/kWh AUD$/Annum AUD$/T PROD
Site Power 7.7 MW 0.25 10,623,690 1,073

13.2.4 REAGENTS AND CONSUMABLES

The following reagents are the major chemical components regularly used for operation. The annual reagent costs are presented below. The tonnes of NaSH are only required for the process involving oxide and transitional ore, therefore when fresh ore is mined this reagent will not be required.

Table 13-6: Reagent & Consumables Cost

Reagent t/annum AUD/t AUD/annum AUD/T PROD
NaHS* 1,575 800 1,260,000 94.3
Lime 1,879 280 526,120 39.4
Cyanide 1,515 2,200 3,333,000 249.5
Zinc Sulphate 2,250 390 877,500 65.7
Aerophine 3418A 150 12,000 1,800,000 134.7
SMBS 750 450 337,500 25.3
MIBC 37.5 3,500 131,250 9.82
Copper Sulphate 1,894 2,700 5,113,800 382.8
Xanthate 126 2,400 302,400 22.6
Flocculant 75 2,000 150,000 11.2
Total 13,831,570 1,035

*Only for Oxide & Transitional Ore

59

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

13.2.5 DIESEL

Specific equipment diesel burn rates and operational hours’ drive the diesel cost. Equipment diesel consumption rates were taken from publicly available information and Wave’s internal database. Operational hours were based off Wave’s experience with previous similar projects. A diesel price of AUD 1.40/L was used and is a post-excise value.

Table 13-7: Diesel Cost

Mobile equipment [#] Consumption
(L/h)
Operation
(h/annum)
Annual
Consumption
(L/annum)
AUD/annum
Front-End Loader [1] 50 219,000 306,600
Mobile Crane (20T) [1] 20.00 1,095.00 21,900 39,420
Container Lifter [1] 21.00 547.50 11,498 20,696
Telehandler [1] 20.00 547.50 10,950 19,710
EWP [1] 10.00 547.50 5,475 9,855
Fire Truck [1] 40.00 50.00 2,000 3,600
Forklift [1] 20.33 1,971.00 40,077 72,139
Bobcat [1] 9.00 2,759.40 24,835 44,702
Landcruiser (Prado) [1] 9.00 1,576.80 14,191 25,544
Dual cab ute (Hilux) [2] 8.50 1,576.80 26,806 48,250
Tray top ute (Hilux) [2] 8.00 1,576.80 25,229 45,412
Troop Carrier (Ambulance) [1] 8.00 100.00 800 1,440
Total 417,360 584,304

13.2.6 TRANSPORT AND LOGISITICS

Allowances were made for the transport of products from the site to overseas customers. The annual transport cost is presented below and accounts for FOB shipping terms.

Table 13-8: Transport Cost

Item AUD/t PROD AUD/annum
Transport – Land 40.0 534,408

60

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

13.2.7 FLIGHTS AND ACCOMMODATION

Flight costs and man-day rates were taken from the Wave international database. The number of trips and days accommodation is based off a 2 week on, 1 week off fly-in fly-out roster (2:1 FIFO).

Table 13-9: Flights & Accommodation Cost

Item Rate/person #/annum/person AUD$/Annum AUD$/T PROD
Flights AUD 500/return 17 trips 608,333 45.5
Accommodation AUD 100/man
day
243 days 1,703,333 127.5
Total 2,311,667 173.0

13.2.8 GENERAL AND ADMINISTRATION

General & Administration (G&A) costs account for costs that are unable to be allocated to a specific cost area but will most likely be incurred. Examples of these costs include general tools, office cleaning services, and insurance. A summary of the G&A costs can be found below.

Table 13-10: G&A Costs

Item AUD/annum AUD/PROD
General And Consumables 175,000 13.10
Contract Expenses 149,500 11.19
ICT 255,500 19.12
General Expense 1,114,050 83.39
HSEC 922,250 69.03
Total 2,616,300 195.83

61

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

13.2.9 MINING

Operating costs for open pit and underground operations were built off previous similar projects from Wave’s internal database and engineer’s previous experience. Open cut operations occur for 9 years while underground operations occur for 3.5. Mining costs can be found below with underground costs built into an “all-in” rate.

Table 13-11: Open Cut Mining Units

Open Cut Mining AUD/T Material Moved
Management 0.42
Drill and Blast 1.67
Haulage 1.10
Waste 3.35
Ore 0.39
Total 6.93

Table 13-12: Open Cut Mining Costs

Open Cut Mining AUD/annum AUD/T Ore
Management 2,866,890 3.82
Drill & Blast 11,399,301 15.20
Haulage 7,508,521 10.01
Waste 22,866,861 30.49
Ore 2,662,112 3.55
Total 47,303,685 63.07

Table 13-13: All-in Underground Mining Cost

Underground Mining AUD/annum AUD/T Ore
Total 105,000,000 140.0

62

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

14 ECONOMIC ANALYSIS

14.1 INTRODUCTION

The scoping study financial model for AuKing’s Koongie Park Copper Zinc project (the project) uses a discounted cashflow methodology to assess the financial viability of the project. The financial model relies on inputs taken from the process design criteria (PDC), operating cost estimate, capital cost estimate and Wave international database information. The information provided in this chapter is taken directly from the financial model. The financial model is a 100% equity model containing AUD 39 M in previous losses and with values in real terms.

14.2 SUMMARY

The key financial highlights are:

  1. Post-tax net present value (NPV) of AUD 125.2 M

  2. Post-tax internal rate of return (IRR) of 32.4%

  3. EBITDA of AUD 447.5 M over the life of mine (LOM)

  4. Average annual operating cashflow of AUD 29.85 M

  5. Nominal payback of development capital of 2.45 years from first production

14.3 ACCURACY OF ESTIMATE

The financial evaluation was developed as a bottom-up estimate. The level of accuracy is that of a Class 5 estimate, as such the extent of work performed allows for a ± 30 – 50 % accuracy.

14.4 ASSUMPTIONS

The following key assumptions were included in the financial model:

  1. Weighted average cost of capital (WACC) of 8%

  2. Tax rate of 30%

  3. Double Declining Balance (DDB) Depreciation

  4. AUD:USD of 1:0.67

  5. Copper Pricing of 3.90 USD/lb for the LOM

  6. CAPEX

  7. a. Initial CAPEX of AUD 134.6 M

  8. b. LOM CAPEX of AUD 144.3 M

  9. Production commences after 12 months of construction

  10. 11 year mine life

63

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

14.5 KEY METRICS

The project’s financial return is underpinned by the strong operating profit delivered from the first year of production onwards. The production costs found in Table 14-1 are calculated directly from the financial model. The following table details the operating results of the project. C1 costs include all fixed and variable costs. C2 costs include C1 costs and depreciation. All-in-sustaining costs (AISC) include C1 costs, sustaining capital. Sustaining capital amounts to AUD 1.55 M/annum and begins being paid from the first month of production until the end of the project.

Table 14-1: Project Operating Results

ITEM METRIC UNITS
NPV, pre-tax (8%) AUD M 176.9
IRR, pre-tax % 39.7
NPV, post-tax (8%) AUD M 125.2
IRR, post-tax % 32.4
Payback (start of prod.) Years 2.45
Initial CAPEX AUD M 134.6
LOM CAPEX AUD M 144.3
LOM Revenue AUD M 1,594
LOM OPEX (excl. royalties) AUD M 1,067
LOM EBITDA AUD M 447.5
C1 Cost AUD/t PROD 7,197
C2 Cost AUD/t PROD 8,164
C3 Cost AUD/t PROD 8,699
Average Price Received USD/lb Cu 3.90
Average Price Received USD/lb Zn 1.33
Average Price Received USD/oz Ag 30.00
LOM Ore Processed Tonnes 8,087,891
LOM Cu Produced Tonnes 109,893
LOM Zn Produced Tonnes 38,405
LOM Ag Produced Ounces 355,166
LOM Years 11.10

64

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

14.5.1 REVENUE AND PROFITS FORECAST

The forecast copper, zinc, and silver prices are based off third party research and independent research conducted by Wave and represent a “base case” scenario. Product pricing remains flat throughout the LOM. The fluctuation of operating costs and revenue is due to the increasing/decreasing tonnes of waste/ore and ore grade between the different pits. The Sandiego open pit is the first site to be mined, followed by Mount Angelo, Onedin, Bommie, and Sandiego Underground. Wave has conducted scenario testing and has found this to be the optimal order of operations considering the current mining plan.

==> picture [437 x 247] intentionally omitted <==

Figure 14-1: Project LOM Cash Flows

14.5.2 SENSITIVITY ANALYSIS

Sensitivity of the project’s post-tax NPV to key variables was investigated. Using the post-tax result calculated from the financial model, each of the kay variables were independently flexed between ±30%. The areas flexed, in order from most sensitive to least sensitive are:

  1. Copper Price

  2. AUD:USD exchange rate

  3. OPEX

  4. CAPEX

  5. Discount Rate

The individual areas are first sensitised individually and plotted on a bow tie graph and tornado chart to show their effects on the post-tax NPV values.

65

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

==> picture [467 x 249] intentionally omitted <==

Figure 14-2: Bowtie Sensitivity Analysis

==> picture [468 x 245] intentionally omitted <==

Figure 14-3: Tornado Chart Sensitivity Analysis

66

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

15 FORWARD WORK PLAN

15.1 ENVIRONMENTAL APPROVAL

A work plan for obtaining necessary Project approvals will need to be formulated. Some of these approvals may have commenced but will need to be worked through to completion. Some of these approvals will require input information from a more advanced study and hence may not be complete at the end of the PFS/DFS stage.

15.2 GEOLOGY

It is recommended that further resource drilling be undertaken at Sandiego to extend the underground resource. The drill programs should aim to:

  1. Confirm and expand the current geological model.

  2. Increase drilling density to move Indicated Resources into Measured forming the basis of the Ore Reserve.

  3. Enhanced definition of the higher-grade zones to sequence the mine delivering best commercial result.

  4. Move Inferred Resources into Indicated so it can be classified into Probable and Proven.

  5. Additional drilling in the previously classified Inferred and Indicated to provide further assay data and grade validation.

15.3 MINING

The current mining assessment was performed at a high level and some assumptions were made.

The following recommendations are made to further progress the Halls Creek Project mining aspects into the next phase of the Project:

  1. Further analyze mine planning options, including equipment selection, and produce an optimized mine plan and methodology based on the updated resource (mainly for waste);

  2. Based on this schedule and methodology, obtain competitive market proposals from mining contractors (including key commercial terms);

  3. Conduct trial mining utilizing alternate mining methodology and to perform Mining fragmentation testing.

  4. Confirmation of cut-off grade once recoveries and costs developed to PFS confidence.

  5. Confirmation of contaminant management (blending) once recoveries developed to PFS confidence.

  6. Detailed strategy for in-pit waste rock and tailings placement.

  7. Update of mining costs for selected mining method.

  8. Update of pit optimization, pit design and strip / block layout based on final recoveries, mining method and mining/process/ admin costs.

  9. Detailed truck haulage model for ore and waste to match final mine method and layout.

  10. Final production schedule including ore, waste and mining fleet/workforce/consumables/costs.

  11. Generate Ore Reserve.

67

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

15.4 METALLURGICAL TESTWORK

Before commencement of the PFS, it is recommended that a further program of metallurgical testwork be undertaken. There are optimisation testwork programs that are required to allow the PFS to be conducted and achieve project and operating costs to the required level of accuracy.

A number of composite samples should be formed that consists of material that will be mined during the first 4 – 5 years of operation with the following.

  1. Mineralogy to be conducted on selected samples.

  2. Sulphidisation optimisation for residence time to promote optimal flotation levels.

  3. Flotation Optimisation for residence time to achieve optimal levels of independent Copper and Zinc recovery.

  4. Filtration testwork for dewatering of the copper and zinc concentrates and coarse tailings.

  5. Conduct Transportable Moisture Limit trials (TML) for both concentrate samples for shipment.

  6. Undertake bench scale variability programs across a representative area within the early years of the mine schedule; and,

  7. Samples for this testwork program should be taken from retained bulk samples (if available) or additional bulk samples from site.

It is also recommended to conduct a preliminary testwork program to assess the potential of reducing or separating the iron content in the coarse product.

15.5 WATER SUPPLY

The Scoping Study has identified a preferred water supply solution. Further work in the PFS is required to:

  1. Confirm the preferred route and complete basic surveys.

  2. Engage with stakeholders / land holders as required.

  3. Optimise the water supply based on optimised site water balance.

  4. Confirm and update capital and operating costs for water supply.

15.6 GEOTECHNICAL

The following geotechnical works are recommended to inform the detailed design of the Open Cut and Underground mine, TSF, roads, process plant and site-wide bulk earthworks:

  1. Borehole drilling and geotechnical assessment of all mining areas.

  2. Borehole drilling and test at the process plant, focusing on key structures, rotating equipment and areas of significant excavation to determine geotechnical parameters required for structural analysis and footing design.

  3. Borehole drilling and test pitting at the TSF and evaporation pond area, to better understand the ground conditions (geotechnical and hydrogeological.

68

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

APPENDIX A: GLOSSARY

TERM DEFINITION
%w/v Percent weight per volume, a measurement of slurry or solution strength
%w/w Percent weight per weight, a measurement of slurry or solution strength
° Degrees
a Annum
A$ Australian dollars
AACE American Association of Cost Engineers
AHIS Aboriginal Heritage Inquiry System
Ai Abrasion index
AMD Acid mine drainage
AMEC Association of Mining and Exploration Companies
ANC Acid neutralising capacity
AS Australian Standard
ASX Australian Stock Exchange
A$ Australian currency (dollar)
AusIMM Australasian Institute of Mining and Metallurgy
Ag Silver
bcm Bank (in situ) cubic metre
BFD Block flow diagram
BMR Base metals recovery
BOD Basis of design
BoM Bureau of Meteorology
BOO Build, own, operate
BOOT Build, own, operate and transfer
CAPEX Capital expenditure
CCE Capital cost estimate
CCR Central control room
CHMP Cultural Heritage Management Plan
CMS Confirmation management system
Competent Person Any public reporting of exploration results, mineral resources or ore reserves must be based on
and fairly reflect documentation prepared by a Competent Person in accordance with the JORC
Code
CPs Capital cost packages
CPU Central processing unit
CSA CSA Global (resource and mining consultants)

69

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

TERM DEFINITION
Cu Copper
Cv Coefficient of consolidation
CWi Bond impact crushing work index
Cwlth Commonwealth
D&C Design and construct
DBCA Department of Biodiversity, Conservation and Attractions
DCF Discounted cash flow
DCS Distributed control system
DEE Department of Environment and Energy
DFS Definitive feasibility study
DIDO Drive-in drive-out
DMIRS Department of Mines, Industry Regulation and Safety
DNRME Department of Natural Resources, Mines and Energy
DPLH Department of Planning, Lands and Heritage
DWER Department of Water and Environment Regulation
EBIT Earnings before interest and tax
EBITDA Earnings before interest, tax, depreciation and amortization
EIA Environmental impact assessment
EIL Ecological investigation level
EIS Environmental impact statement
EL Exploration licence
ELH Excavate, load and haul
EMS Environmental management system
EP Environmental protection
EPA Environmental Protection Authority
EPBC _Environment Protection and Biodiversity Conservation Ac_t 1999
EPC Engineering, procurement, and construction
EPC Act Environmental Protection Act 1994
EPCC Engineering, procurement, construction, commissioning
EPCM Engineering, procurement, and construction management
ERD Environmental review document
ERP Enterprise resource planning
ESD Environmental scoping document
FCFE Free Cashflow to Equity
Fe Iron

70

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

TERM DEFINITION
FEED Front end engineering design
FEL Front-end loader
FIFO Fly-in fly-out
FoS Factor of safety
FS Feasibility study
FW Footwall
GA General arrangement
GDE Groundwater dependent ecosystem
GJpa, GJ/a Giga joules per annum
GL/a Gigalitres per annum
GSA Gas supply agreement
H:V Horizontal to vertical
ha Hectares
HDPE High density polyethylene
HSEC Health safety environment & community
HSMP Health and Safety Management Plan
HSMS Health, safety and management system
HV Heavy vehicle also high voltage
HVAC Heating ventilation and air conditioning
HW Hanging wall
IBBA Biogeographic Regionalisation of Australia
ICT Integrated Information and Communications Technology
IM Information management
IMT Integrated management team
Inc Included
IRR Internal rate of return
ISPL Integrate Sustainability Pty. Ltd.
IT Information technology
ITIL Information technology infrastructure library
IWL Integrated waste landform
JORC Joint Ore Reserves Committee. The Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves.
k Thousand (kilo)
kBCM Thousand bank cubic metres
kLCM Thousand loose cubic metres

71

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

TERM DEFINITION
km Kilometres
km2 Square kilometre
KPI Key Performance Indicator
kt Thousand tonnes, kilo-tonne
ktpa Thousands of tonnes per annum
kV Kilovolt
kW Kilowatt
kWh Kilowatt-hour
L Litre
LOM Life of mine – duration commencing at pre-strip and concluding at end of production
LOP Life of project (20 years for the PFS)
LV Light vehicle also low voltage
m Metre
M Million
m2 Square metres
m3 cubic metres
m3/d Cubic metre per day
Ma Million years old
MCP Mine closure plan
mD Diameter in metres
MDE Maximum design earthquake
MEL Mechanical equipment list
mg/L Milligrams per litre
MIA Mine Industrial Area
ML Mining lease
MLA Mining lease application
mm Millimetre
MOU Memorandum of Understanding
MRE Mineral resource estimate
MRF Mine rehabilitation fund
MRRT Minerals resource rent tax
Mt Million tonnes
Mt/a, Mtpa Million tonnes per annum
MTO Material quantity take-offs
Mtpa Million tonnes per annum

72

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

TERM DEFINITION
MVA Megavolt ampere
MW Megawatt
MWh Megawatt hours
MWhrs/yr Megawatt hours per year
NAF Non-acid forming
NAG Net acid generation
NAPP Net acid producing potential
NC Act _Nature Conservation Act_1992
NCR Non-conformance report
NPAT Nett profit after tax
NPI Non-process infrastructure
NPV Net present value
NVCP Native vegetation clearing permit
OEM Original equipment manufacturer
OMC Optimum moisture content
OPEX Operating expenditure
OPs Operating cost packages
OSA Overall slope angle
P&ID Piping & instrumentation diagram
p/a Per annum
P80 The diameter at which 80% of particles are passing
PAF Potentially acid forming
PCS Process control system
PDC Process design criteria
PEP Project execution plan
PFD Process flow diagram
PFS Pre-feasibility study
pH Acidity measure
PHA Process hazard analysis
PIMS Plant information management system
PM Preventable maintenance
PMF Probable maximum flood
PSD Particle size distribution
QA/QC Quality assurance and quality control
RA Restricted access

73

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

TERM DEFINITION
RC Reverse circulation (drilling technique)
RFQ Request for Quotation
RL Reduced Level
RLE Rehabilitation Liability Estimate
RO Reverse Osmosis
ROM Run of Mine
SCADA Supervisory Control and Data Acquisition
SDS Safety Data Sheet
SG Specific Gravity
Si Silicon
SIA Social Impact Assessment
SMP Structural, Mechanical and Piping
t Tonne
tpa Tonnes per Annum
tph Tonnes per Hour
t/m³ Tonnes per Cubic Metre
t:t Tonne:Tonne
TDS Total Dissolved Solids
TEC Threatened Ecological Communities
TML Transportable moisture limit
TMP Tailings management plan
tpa Tonnes per annum
Tph Tonnes per hour
TSF Tailings storage facility
UCS Uniaxial compressive strength
USD American currency (dollar)
USGS United States Geological Survey
VSD Variable speed drive
WACC Weighted average cost of capital
WBS Work breakdown structure
WHIMS Wet high intensity magnetic separation
WWTP Wastewater treatment plant
yr year
Zn zinc

74

==> picture [104 x 28] intentionally omitted <==

==> picture [71 x 25] intentionally omitted <==

75

JORC Code, 2012 Edition – Table 1, Section 4

The following Table is sourced from the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (2012 Edition) (JORC Code 2012)) and presents the assumptions on which the Scoping Study is based.

For clarity, this table is not being used to report Ore Reserves. Instead, as per the ASX Interim Guidance: Reporting Scoping Studies dated November 2016, this table is being used as a framework to disclose underlying study assumptions.

Criteria JORC Code explanation Commentary
Mineral Description of the Mineral Resource estimate used as a basis for the •No JORC Code (2012) Ore Reserve estimate has been classified or
Resource conversion to an Ore Reserve. reported.
estimate for Clear statement as to whether the Mineral Resources are reported •The Study is based on four broadly geologically consistent Mineral
conversion to additional to, or inclusive of, the Ore Reserves. Resource Estimates (due to their close proximity) comprising:
Ore Reserves Sandiego –see AuKing ASX announcement 4 April 2022
Onedin –see AuKing ASX announcement 4 April 2022
Mt Angelo North –see Cazaly ASX announcement 31 January 2022
Bommie –see Cazaly ASX announcement 24 November 2022
Site visits Comment on any site visits undertaken by the Competent Person and
•No site visits were undertaken by Competent Persons for the Study.
the outcome of those visits. •Competent Persons participated in site visits at the time of
If no site visits have been undertaken indicate why this is the case. preparation of the original Mineral Resource Estimates. This was
considered sufficient for the purposes of the Study.
Study status The type and level of study undertaken to enable Mineral Resources •No Ore Reserves have been declared in the Study.
to be converted to Ore Reserves. •The Study is a Scoping Study only.
The Code requires that a study to at least Pre-Feasibility Study level
has been undertaken to convert Mineral Resources to Ore Reserves.
Such studies will have been carried out and will have determined a
mine plan that is technically achievable and economically viable, and
that material Modifying Factors have been considered.
Cut-off The basis of the cut-off grade(s) or quality parameters applied. •Cut-off grades were calculated differently for the open pit and
parameters underground deposits based upon optimized inputs for the respective
operations, with higher costs assumed for underground mining.
Mining factors
The method and assumptions used as reported in the Pre-Feasibility
•No Ore Reserve has been declared
or or Feasibility Study to convert the Mineral Resource to an Ore •Refer to Section 6 of the Study.
assumptions Reserve (i.e. either by application of appropriate factors by •A conservative approach was taken for the pit slope angles. No
optimisation or by preliminary or detailed design). geotechnical analysis was undertaken for the underground mining –
The choice, nature and appropriateness of the selected mining instead, assumptions were made based on other mining operations in
method(s) and other mining parameters including associated design the geographical area.
issues such aspre-strip, access, etc. •NoMineral Resourcemodel was usedforpit and stope optimization.

1

Criteria JORC Code explanation Commentary
The assumptions made regarding geotechnical parameters (eg pit •Mining dilution – see Section 6.1.1
slopes, stope sizes, etc), grade control and pre-production drilling. •Mining recovery factors – see Section 6.1.1
The major assumptions made and Mineral Resource model used for •Minimum mining widths – see Section 6.1.1
pit and stope optimisation (if appropriate). •Inferred Mineral Resources were utilized in accordance with the
The mining dilution factors used. Mineral Resource Estimates for the respective deposits. For the first 8
The mining recovery factors used. years of proposed mining (at Sandiego, Mt Angelo North and Onedin)
Any minimum mining widths used. 89%, 100% and 58% respectively is in the Indicated Mineral
The manner in which Inferred Mineral Resources are utilised in Resource category and the balance is in the Inferred Mineral
mining studies and the sensitivity of the outcome to their inclusion. Resource Category. Accordingly, it is not considered that Inferred
The infrastructure requirements of the selected mining methods. Resources are material to the financial outcomes.
•For Infrastructure see below.
Metallurgical The metallurgical process proposed and the appropriateness of that •Refer to Sections 7 and 8 of the Study.
factors or process to the style of mineralisation. •The process of flotation of sulphidised ores is well known technology.
assumptions Whether the metallurgical process is well-tested technology or novel •Significant bench scale metallurgical testwork was conducted on the
in nature. Sandiego and Onedin ores as part of historical testwork carried out by
The nature, amount and representativeness of metallurgical test work Anglo Australian Resources between 2008 and 2011. Additional
undertaken, the nature of the metallurgical domaining applied and the
bench scale testwork was conducted on certain Sandiego and Mt
corresponding metallurgical recovery factors applied. Angelo North ores by separate independent laboratories
Any assumptions or allowances made for deleterious elements. •No assumptions are made for deleterious elements as most are
The existence of any bulk sample or pilot scale test work and the expected to report to the tailings after the sulphides are floated off.
degree to which such samples are considered representative of the •No bulk sample or pilot scale test work has been conducted.
orebody as a whole. •N/A
For minerals that are defined by a specification, has the ore reserve
estimation been based on the appropriate mineralogy to meet the
specifications?
Environmen- The status of studies of potential environmental impacts of the mining •Refer to Sections 10.1 and 10.2 of the Study. Waste rock
tal and processing operation. Details of waste rock characterisation and characterization will be undertaken as part of future studies. All
the consideration of potential sites, status of design options overburden and tailings storage facilities sizes, locations and designs
considered and, where applicable, the status of approvals for process
are at this time nominal and subject to change during the approvals
residue storage and waste dumps should be reported. process and/or following further and more advanced studies.
Infrastructure The existence of appropriate infrastructure: availability of land for •Koongie Park is well served by road and power infrastructure, being
plant development, power, water, transportation (particularly for bulk situated just outside the Halls Creek township and nearby the Great
commodities), labour, accommodation; or the ease with which the Northern Highway.
infrastructure can be provided, or accessed. •Sufficient land is available within the Sandiego Mining Licence to
accommodate the proposed infrastructure contemplated by the Study.
•Accomodation facilities are likely to be located at Halls Creek.
•Apreliminaryassessment of available water for miningand treatment

2

Criteria JORC Code explanation Commentary
has indicated that there should be sufficient water for operations
although it is proposed that a more detailed hydrological assessment
be undertaken as part of future studies.
Costs The derivation of, or assumptions made, regarding projected capital •Project capital costs for the processing plant were factored from the
costs in the study. Wave International engineering database using similar projects. See
The methodology used to estimate operating costs. Section 12 of the Study.
Allowances made for the content of deleterious elements. •Project operating costs are based off vendor inquiries, AuKing inputs
The source of exchange rates used in the study. and the Wave International database for similar operations. The
Derivation of transportation charges. OPEX has an accuracy of +/- 30-50%.
The basis for forecasting or source of treatment and refining charges, •No allowances were made for the content of deleterious elements
penalties for failure to meet specification, etc. (see comments above re flotation process)
The allowances made for royalties payable, both Government and •Exchange rate assumptions are based on internal AuKing and Wave
private. International estimates
•Transportation charges have been derived from the Wave
International database
•TC/RCs have been derived from the S&P Global database. Penalties
for failure to meet specifications have not been modelled and will be
assessed during later stages of feasibility studies.
•Royalties of 5% to the WA government for the copper and zinc
concentrates have been assumed. A 2.5% royalty for silver product
has also been assumed. No provision was made for other royalties or
related potential entitlements as the details of these are still the
subject of future negotiations.
Revenue The derivation of, or assumptions made regarding revenue factors •Revenue factors have been assumed on concentrate sales based on
factors including head grade, metal or commodity price(s) exchange rates, the Mineral Resource Estimates as outlined above.
transportation and treatment charges, penalties, net smelter returns, •Commodity price assumptions are derived from research reports
etc. access by AuKing and/or conservative estimates assumed internally.
The derivation of assumptions made of metal or commodity price(s), •TC/RCs have been derived from the S&P Global database.
for the principal metals, minerals and co-products. •Transportation charges have been derived from the database of
Wave International based on other operations in the region
•A life of project exchange rate of 0.67 USD:AUD has been assumed
on the basis of internal forecasts.
•Commodity prices are assumed to be fixed over the life of the project
as set out in the Study.
Market The demand, supply and stock situation for the particular commodity, •By revenue, the principal products will be copper and zinc, with a
assessment consumption trends and factors likely to affect supply and demand primary by-product of silver. The markets for these products are well-
into the future. established and likelyto onlybe enhanced over the short- medium

3

Criteria JORC Code explanation Commentary
A customer and competitor analysis along with the identification of term as the expanding trend towards electrification and green energy
likely market windows for the product. continues. In addition, the global copper industry is, on average,
Price and volume forecasts and the basis for these forecasts. experiencing declining grades as resources are depleted, and
For industrial minerals the customer specification, testing and relatively few major new discoveries in the past 15 years have been
acceptance requirements prior to a supply contract. made to replace the deposits going offline. New projects can take
many years from discovery to production compounding an already
tight market for copper.
•N/A
•N/A
•N/A
Economic The inputs to the economic analysis to produce the net present value •Refer to the economic analysis in Section 14 of the Study, which
(NPV) in the study, the source and confidence of these economic assumes a discount rate of 8% and nil inflation.
inputs including estimated inflation, discount rate, etc. •The economic analysis in Section 14 includes a sensitivity analysis on
NPV ranges and sensitivity to variations in the significant various cost factors, copper price and exchange rate.
assumptions and inputs.
Social The status of agreements with key stakeholders and matters leading •Given the history of exploration on the respective mining licences,
to social licence to operate. together with more recent stakeholder engagement by AuKing, there
are no issues expected around forming agreements with key
stakeholders if so required to complete works as planned.
Other To the extent relevant, the impact of the following on the project •No Ore Reserve has been declared
and/or on the estimation and classification of the Ore Reserves: •No naturally occurring risks have been identified although (as noted
Any identified material naturally occurring risks. above) additional water access studies are intended during future
The status of material legal agreements and marketing arrangements.
studies.
The status of governmental agreements and approvals critical to the •No marketing agreements are in place. Under the Joint Venture
viability of the project, such as mineral tenement status, and agreement AuKing has with Astral Resources NL, it is likely that
government and statutory approvals. There must be reasonable AuKing’s interest in the Koongie Park project will increase to 100%,
grounds to expect that all necessary Government approvals will be with Astral’s interest reverting to a 1% net smelter royalty during the
received within the timeframes anticipated in the Pre-Feasibility or course of 2023 in accordance with a dilution formula.
Feasibility study. Highlight and discuss the materiality of any •All of the working areas in the Study (with the exception of Bommie)
unresolved matter that is dependent on a third party on which are on approved mining licences with no current issues or
extraction of the reserve is contingent. outstanding requirements with DMIRS. There are no third party
unresolved matters that are likely to impact upon approvals. In the
case of the Bommie deposit, mining activities are not intended until
year 8 of the mining schedule by which time it is expected that any
unresolved statutory or commercial issues have been settled.
Classification The basis for the classification of the Ore Reserves into varying •No Ore Reserve is being reported as part of the Study.
confidence categories.

4

Criteria JORC Code explanation Commentary
Whether the result appropriately reflects the Competent Person’s
view of the deposit.
The proportion of Probable Ore Reserves that have been derived
_from Measured Mineral Resources(if any). _
Audits or The results of any audits or reviews of Ore Reserve estimates. •No ore Reserve is being reported as part of the Study
reviews
Discussion of Where appropriate a statement of the relative accuracy and •No Ore Reserve has been declared
relative confidence level in the Ore Reserve estimate using an approach or •While AuKing has made every effort to be as accurate as possible,
accuracy/ procedure deemed appropriate by the Competent Person. For the Study is an early-stage project and as such has been completed
confidence example, the application of statistical or geostatistical procedures to only to a level of accuracy expected of a scoping study.
quantify the relative accuracy of the reserve within stated confidence •Metallurgical recoveries have been based on testwork data.
limits, or, if such an approach is not deemed appropriate, a qualitative
•Costs have been derived largely from the comprehensive database of
discussion of the factors which could affect the relative accuracy and Wave International.
confidence of the estimate.
The statement should specify whether it relates to global or local
estimates, and, if local, state the relevant tonnages, which should be
relevant to technical and economic evaluation. Documentation should
include assumptions made and the procedures used.
Accuracy and confidence discussions should extend to specific
discussions of any applied Modifying Factors that may have a
material impact on Ore Reserve viability, or for which there are
remaining areas of uncertainty at the current study stage.
It is recognised that this may not be possible or appropriate in all
circumstances. These statements of relative accuracy and confidence
of the estimate should be compared with production data, where
available.

5