ASTRON CORPORATION LIMITED NUMBER: 1687414

Notice to the Australian Stock Exchange Production and Exploration Report Quarter Ended 31 December 2012

Donald Mineral Sands Pty Ltd (100% controlled by Astron Limited) (DMS)

DMS owns EL4432, EL4433, EL5255, EL5263, EL5353 and MIN5532 which together comprise the Donald Mineral Sands Project (Donald Project).

PRODUCTION

During the quarter the Donald Project did not conduct any production activities.

DEVELOPMENT

During the quarter development on the Donald Project continued. The following was undertaken:

Feasibility study

  • Work continued on the definitive feasibility study. This included:

  • updating capital costs and the work schedule for construction;

  • incorporating comments from independent experts and working through applicable parts of the document.

Geology

  • Developed exploration plan for Jackson and Birchip tenements.

  • Finalised drilling program and preparations for planned drilling early Q1 2013.

Work plan and CHMP

  • Work continued on the cultural heritage management plan and work plan.

Funding

Work continued on:

  • Appointing of advisers.

  • Discussions with commercial banks for the debt funding component of the project.

  • Initiation of possible Chinese investors with a view of investing in the Donald project.

Registered Office: Level 29, Wing-on-Centre, 111 Connaught Road, Central, Hong Kong Tel: 61 2 9375 2361 Fax: 61 2 9375 2121 www.astronlimited.com

==> picture [189 x 64] intentionally omitted <==

EXPENDITURE SUMMARY

Total expenses incurred were:

Production Activities Dec Qtr 2012 YTD 2013FY
Nil Nil
DevelopmentActivities Dec Qtr 2012 YTD 2013FY
1,356,337 2,366,344

Niafarang project

DEVELOPMENT

Mining licence application

Work continued on the components required to apply for the mining licence.

EXPENDITURE SUMMARY

Total expenses incurred were:

Production Activities Dec Qtr 2012 YTD 2013FY
Nil Nil
DevelopmentActivities Dec Qtr 2012 YTD 2013FY
195,072 439,688

Registered Office: Level 29, Wing-on-Centre, 111 Connaught Road, Central, Hong Kong Tel: 61 2 9375 2361 Fax: 61 2 9375 2121 www.astronlimited.com

==> picture [189 x 64] intentionally omitted <==

For further information please contact:

Hayden Stockdale, Chief Executive Officer

T: +61 435 461 630

[email protected]

Mark Nielsen , Chief Financial Officer T: +61 2 9375 2361

[email protected]

Allen Cauvin , Executive General Manager – Donald Project T: +61 3 5385 7088 [email protected]