Notice to the Australian Stock Exchange Production and Exploration Report Quarter Ended 31 March 2011
Donald Mineral Sands Pty Ltd (100% controlled by Astron Limited)
Donald Mineral Sands Pty Ltd owns EL 4433 and EL4432 which together the comprise the Donald Mineral Sands Project (Donald Project)
PRODUCTION
During the quarter the Donald Project did not conduct any production activities.
DEVELOPMENT
During the quarter development on the Donald Project continued. The following was undertaken:
Geology
Gold exploration
- 42 gold drill hole programme was completed at the end of March 2011. Samples are currently being assayed with a report due Mid May.
Water
- Discussion with GWMW on supplying water to the project is ongoing. A preliminary engineering study for delivery system options and costs for this type of water supply has been undertaken.
Capital and operating cost estimates
- RJ Robbins has completed capital and operating cost estimates for the processing plants. This work includes the costs to locate the CUP and MSP in Australia.
Land purchase
- A block of land forming part of the mining area was purchased for $712,225.
Registered Office: Level 19, 2 Market Street, Sydney NSW 2000, Australia Tel: 61 2 9375 2361 Fax: 61 2 9375 2121 www.astronlimited.com
==> picture [188 x 64] intentionally omitted <==
EXPENDITURE SUMMARY
Total expenses have been incurred as follows:
| Production Activities | MarQtr 2011 | YTD 2011 FY |
|---|---|---|
| Nil | Nil | |
| DevelopmentActivities | MarQtr 2011 | YTD 2011 FY |
| 859,485 | 3,752,402 |
Astron Gambian and Senegal Investments
The Gambia Mineral Sands Project
Further to the previous announcements with respect to the Gambian mining operations there was no activity for the current period to report.
The uncertainty continues with regard to the mining licence, company situation and the claim against The Gambian Government.
Senegal Mineral Sands Project
The Environmental Impact Assessment has been lodged with technical committee of the mines department. This is progressing well.