ASX Market Announcements 17[th] February 2021 ASX Limited 20 Bridge Street Sydney NSW 2000
Completion of Pre-FEED for Judith Gas Field Project
Key Points
-
APA has completed the Pre-Front End Engineering Design (‘Pre-FEED’) for the provision of midstream infrastructure and services related to gas that is planned to be produced from the 100% Emperor Energy owned Judith Gas Field subject to successful appraisal drilling by Emperor Energy.
-
The Pre-FEED is premised on Judith Gas Field Dynamic Modelling delivering simulated gas production of:
-
80 Million Standard Cubic Feet per day (MMscfd) sustained across 25 years.
-
4 vertical production wells being used at production commencement with an additional 5[th] well introduced in year 15.
-
The Pre-FEED design nominates:
-
Subsea completion tying 4 x production wells to a 6-slot subsea gas collection manifold
-
A 40km x 300mm gas delivery pipeline and well control umbilical connecting the Judith Gas Field to the site of the APA owned Orbost Gas Plant.
-
A separate Judith field gas processing train, constructed on the site of the existing Orbost Gas Processing Plant.
-
An 11km x 250mm diameter gas export pipeline connecting to the Eastern Gas Pipeline at the existing Newmerella gas metering station.
-
The base Capital Cost without contingency and excluding cost of production wells is estimated at approximately AUD $500 Million.
-
Project scheduling indicates:
-
Final Investment Decision (FID) could be achieved 14 months after commencement of Front End Engineering Design (FEED) otherwise referred to as Full Feasibility Study.
-
A further 38 months from FID to achieve Commercial Production.
-
The budget estimate to complete the FEED is approximately AUD $9 Million.
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 Sydney, NSW, 2001
emperorenergy.com.au ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
Completion of Pre-FEED
Emperor Energy is pleased to advise that APA Group (ASX:APA) has completed the Pre-Front End Engineering Design (Pre-FEED) for the provision of midstream infrastructure and services related to gas that will potentially be produced from the Judith Gas Field in the 100% Emperor Energy owned VIC/P47 Permit in the offshore Gippsland Basin, Victoria.
The Pre-FEED documents and Summary Report have been received by Emperor Energy and subsequently accepted by the Emperor Energy Board of Directors.
Scope of Pre-FEED:
The Scope of the Pre-FEED has included:
-
The Pre-FEED design for a Gas Processing Plant, Subsea Pipeline and Export Pipeline to connect to the Eastern Gas Pipeline.
-
Refinement of indicative project cost estimates and project scheduling.
-
A Budget estimate for a Front End Engineering Design (FEED) or (Feasibility Study).
APA have carried out the Pre-FEED work using a balanced combination of both in house and external expertise.
Emperor Energy and APA established a Memorandum of Understanding (MOU) relating to the Judith Gas Project in October 2019. The Pre-FEED is the first stage of work to be progressed from the MOU.
Project Summary
The design basis for the Pre-FEED has been 80MMscfd (90TJ/day) of sales gas across a 25-year project life with gas processing to meet the AS4564 gas sales specification. This is based on 4 x initial production wells with a 5[th] well introduced in Year 15 to maintain delivery pressures.
Well delivery rates are based on Gas Reservoir Dynamic Modelling previously completed by Independent Reservoir Engineering Consultants engaged by Emperor Energy.
The subsea design allows for flexible jumper lines to transport raw gas from each well head to a six-slot manifold where all gas is collected and delivered in a single stream to the Pipeline End Termination.
The Pipeline End Termination provides the interface to a 40km x 300mm nominal bore pipeline delivering raw gas to the proposed Judith Processing Plant.
The 300mm pipeline selection provides a suitable balance between friction loss, economics, slugging and ramp up rates. A 40 km subsea control Umbilical from subsea wells to the proposed new Judith field gas processing train at the site of the existing Orbost Gas Processing Plant runs in parallel to the pipeline.
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 emperorenergy.com.au Sydney, NSW, 2001 ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
==> picture [377 x 167] intentionally omitted <==
Figure 1: Indicative Image of 4 x Well Subsea Completion Facilities Image provided courtesy of APA
The design of the Judith processing plant is based on using available space adjacent to the existing Orbost Gas Processing Plant to construct a separate gas train tailored to the Judith gas composition. There will be operating synergies with the existing gas plant.
Sales gas would be delivered through an 11km x 250mm Nominal Bore export pipeline running in parallel with the existing Orbost export pipeline. This would then deliver gas to an upgraded Newmerella gas metering station connecting into the Eastern Gas Pipeline.
The Eastern Gas Pipeline is a key gas supply artery between the Gippsland Basin in Victoria and NSW. The Eastern Gas Pipeline transports natural gas to demand centres in Sydney, Canberra and Wollongong as well as a number of regional centres.
==> picture [357 x 200] intentionally omitted <==
Figure 2: Aerial View of existing Orbost Gas Plant Image provided courtesy of APA
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 emperorenergy.com.au Sydney, NSW, 2001 ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
Capital Cost
The project delivery cost estimate has been assembled by APA with input provided from the Offshore Design Consultant (WOOD), the Onshore Design Consultant (Equinox) along with APA’s internal project team.
The project capital cost base cost estimate excluding contingency provisions has been assessed as approximately AUD $500 Million.
Further opportunities to optimise capital costs have been identified in the Pre-FEED study.
The capital costs included above do not include exploration / appraisal / production well costs which are to be dealt with separately by Emperor Energy.
Operating Costs have been excluded from the Capital Cost estimate and are to be dealt with through future tariff modelling.
Project Execution and Scheduling
The Pre-FEED study provides a Project Execution Plan laying out the basis for project delivery organization, procurement strategy, contracting strategy, fabrication methodology, logistics, construction methodology, commissioning and testing.
The key Regulatory approvals required for the project are identified and a detail project schedule has been analysed.
The Pre-FEED study indicates that a Final Investment Decision (FID) could be achieved 14 months after commencing the Project Front End Engineering Design (FEED) otherwise referred to as a Full Feasibility Study. Commercial operation could then be achieved within a further 38 months of the FID.
A budget estimate of the cost of the FEED has been forecast at AUD $9 Million.
Management Comment
Emperor Energy Director Phil McNamara said: “The completed Pre-FEED now provides Emperor with a clear understanding of the project design, management, time frame and costs involved in bringing the Judith Gas Field into the lucrative East Coast gas market. Emperor’s focus continues to be the establishment of a Farm In Partner for the critical Judith 2 Exploration / Appraisal Well. The opportunity now also exists to kick off the (FEED) or Feasibility Study early and commence the Project Approval process with the relevant Government Authorities to reduce the longer term risk of approval delays.”
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 emperorenergy.com.au Sydney, NSW, 2001 ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
About the Judith Gas Field
The 100% Emperor Energy owned Judith Gas Field is located within the VIC/P47 Permit in the offshore Gippsland Basin, Victoria.
On 11[th] July 2019 Emperor Energy advised that an Independent Resource Statement had been completed for the Judith Gas Field within the 100% Emperor Energy owned VIC/P47 Exploration Permit located in the offshore Gippsland Basin, Victoria (Figure 1). The Resource Statement Highlighted:
-
2C Contingent Gas Resource of 150 Bcf
-
P50 Unrisked Prospective Gas Resource of 1.226 Tcf
==> picture [596 x 235] intentionally omitted <==
Figure 3: Location of 100% Emperor Energy owned VIC/P47 offshore Gippsland Basin showing regional permits along with oil and gas fields
| Judith Gas Discovery | Judith Gas Discovery | Contingent Resources | Contingent Resources | Contingent Resources |
|---|---|---|---|---|
| Low Estimate 1C |
Best Estimate 2C |
High Estimate 3C |
||
| GIIP | Bcf | 180 | 278 | 386 |
| Salesgas | Bcf | 97 | 150 | 209 |
| Condensate | MMbbl | 1.4 | 2.2 | 3.2 |
Table 1: Summary of Contingent Resources for Judith within area of VIC/P47 (3D-GEO, July 2019)
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 Sydney, NSW, 2001
emperorenergy.com.au ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
| Greater Judith Area | Greater Judith Area | Unrisked Prospective Resources | Unrisked Prospective Resources | Unrisked Prospective Resources |
|---|---|---|---|---|
| P90 | P50 | P10 | ||
| Judith Deep | Bcf | 38 | 62 | 92 |
| West | Bcf | 83 | 127 | 176 |
| Central | Bcf | 37 | 333 | 628 |
| North | Bcf | 29 | 166 | 315 |
| North East | Bcf | 49 | 279 | 494 |
| North West | Bcf | 15 | 102 | 226 |
| South | Bcf | 14 | 157 | 565 |
| Total | Bcf | 265 | 1226 | 2496 |
Table 2: Summary of Prospective Resources for Judith within area of VIC/P47 (3D-GEO, July 2019)
==> picture [596 x 329] intentionally omitted <==
Figure 4: Judith Gas Field, and Greater Judith Compartments (3D-GEO, July 2019)
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 Sydney, NSW, 2001
emperorenergy.com.au ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
==> picture [484 x 277] intentionally omitted <==
Figure 5: Judith Gas Sand 1 Depth Model from Longtom Gas Field to the Greater Judith Structure
Yours faithfully
==> picture [148 x 60] intentionally omitted <==
Carl Dumbrell
Company Secretary Ph +61 402 277 282 [email protected]
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 Sydney, NSW, 2001
emperorenergy.com.au ABN: 56 006 024 764
==> picture [142 x 92] intentionally omitted <==
Corporate Directory
Board of Directors
Carl Dumbrell Phil McNamara Nigel Harvey
Company Secretary
Carl Dumbrell
Geological Consultant
Geoff Geary
Project & Business Development Consultant
Malcolm King
Registered office & Principle place of business
Level 21, 201 Sussex Street Sydney NSW 2000
Mailing Address
GPO Box 5360 Sydney NSW 2001
Auditors
ICP Assurance Services Suite 1204, 227 Elizabeth Street Sydney NSW 2000
Lawyers
Hopgood Ganim Level 27, Allendale Square 77 St Georges Tce, Perth WA 6000
Share Registry
Automic Pty Ltd ACN 152 260 814 Trading as Automic Registry Services Level 5, 126 Phillip Street Sydney NSW 2000 Phone: 1300 288 664 Overseas callers: +61 2 9698 5414 Email: [email protected]
Capital Structure
The company currently has issued capital (as of 16[th] February 2021) of: Ordinary fully paid shares (ASX: EMP) 140,392,946
Level 21, 201 Sussex Street, Sydney, NSW, 2000 Ph +02 9275 8878
GPO Box 5360 Sydney, NSW, 2001
emperorenergy.com.au
ABN: 56 006 024 764