ALARA RESOURCES LIMITED — Capital/Financing Update 2021
Oct 25, 2021
64461_rns_2021-10-25_d421d931-2d2e-4729-a9a1-20770b36facc.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
Alara Resources Limited A.B.N. 27 122 892 719 Suite 1.02, 110 Erindale Road, Balcatta WA 6021, Australia PO Box 963, Balcatta WA 6914
Telephone | +61 8 9240 4211 Facsimile | +968 2449 2491 Web | www.alararesources.com Email | [email protected]
==> picture [122 x 58] intentionally omitted <==
ASX/MEDIA RELEASE
26 October 2021
Continued Construction and Procurement Program Success sees Wash-Hi Majaza Project on Track for Target Completion Date
Alara Resources Limited (ASX: AUQ), a base and precious metals explorer and developer with projects in Oman, is pleased to announce an update on the accelerated progress of construction and procurement activities for the Wash-hi Majaza Copper-Gold Project ( Project ). These activities have Alara on track to complete Project construction by November 2022.
Project Engineering
The placement of major plant and equipment procurement orders and the ready availability of key OEM equipment specifications has enabled the detailed engineering phase of the Project to be fast-tracked. The Company’s engineering consultants Debisikha Associates and Progesys are geared up for rapid progress in delivering on their work program (see Figure 1).
==> picture [496 x 108] intentionally omitted <==
==> picture [496 x 108] intentionally omitted <==
Figure 1: Project Engineering Progress
The Company’s 51% owned JV company Al Hadeetha Resources LLC ( AHRL ), the Project owner, has released the tender document for the project construction contract to potential bidders in Oman.
Major equipment procurement orders placed
Since our previous update AHRL has continued to draw down from its debt facility to finance equipment orders and contracts in Table 1, below. Procurement orders with a cumulative value of US$22.9M have been placed to date.
==> picture [62 x 29] intentionally omitted <==
| Details of package/equipment | Supplier | Country |
|---|---|---|
| Ball Mill, SAG Mill, Crusher | CITIC | China |
| Rock Breaker | Metso-OT | Finland |
| Apron Feeder | L&T | India |
| Pan Feeders | Metso-OT | India |
| Magnetic Separators | ElectroZavod | India |
| Accommodation Cabins Refurbished | Al Tasnim | Oman |
| Accommodation Camp Construction | Al Naba Infrastructure | Oman |
| New Cabins - Dining, Offices etc. | Al Rehwan | Oman |
| Fencing | Al Naba Infrastructure | Oman |
| Conveyors | Al Tasnim | Oman |
| Belt Weigher and Vibrating Screens | Schenck | India |
| Hydrocyclones | Weir | UAE |
| Conveyor safety switches | Smart SAA | India |
| Construction of Access Road | Al Naba Infrastructure | Oman |
| Pressure Filters | Matec | Italy |
| Regrinding Mill | Metso Outotec | USA |
| Complete Electrical Package | ABB | India |
| Dust Collector | Stratgem Projects | India |
| Powerlines | ONEIC | Oman |
| Agitator | Afromix | SA |
| Sampling and Analizing System | Metso Outotec | USA |
| Air Compressor | Bin Salim | Oman |
| Froth, Slurry and Sump Pumps | Metso Outotec | Turkey |
| Floatation Cells | Innovator | Polland |
Table 1: Procurement orders placed
Site work progress – Camp construction
After a recent cyclone caused a temporary setback to planned construction, foundation work activities for the accommodation village are now nearing completion. Prefabricated camp structures are expected to arrive in next few days.
The following images show construction progress at the Project site.
==> picture [488 x 217] intentionally omitted <==
Image 1: Accommodation village foundation work nearing completion
==> picture [56 x 56] intentionally omitted <==
ASX Code | AUQ
==> picture [62 x 29] intentionally omitted <==
==> picture [488 x 326] intentionally omitted <==
Image 2: Accommodation village foundation work nearing completion
==> picture [488 x 326] intentionally omitted <==
Image 3: AHRL CEO, Mr. Avigyan Bera inspects the camp construction site
==> picture [56 x 56] intentionally omitted <==
ASX Code | AUQ
==> picture [62 x 29] intentionally omitted <==
==> picture [488 x 259] intentionally omitted <==
Image 4: Foundation works close-up
Access road construction well underway
The ground survey and initial ground levelling for the Project access road, connecting the site with nearby highways, has now also been completed.
==> picture [488 x 348] intentionally omitted <==
Image 5: Road construction
==> picture [56 x 56] intentionally omitted <==
ASX Code | AUQ
==> picture [62 x 29] intentionally omitted <==
ENDS
This announcement is authorised by:
Atmavireshwar Sthapak T 1 | +968 2449 1162 Managing Director E | [email protected] Dinesh Aggarwal T | +61 8 9240 4211 Company Secretary E | [email protected]
Media enquiries
Julia Maguire T | +61 2 8999 3699 The Capital Network E | [email protected]
About Alara Resources
Alara Resources Limited (ASX: AUQ) is an Australian-based precious and base metals explorer and developer, with projects in Oman and Saudi Arabia.
Alara’s active projects in Oman are the Al Wash-hi Majaza Copper-Gold mining licence and Mullaq, Al Ajal exploration licences under the Al Hadeetha JV and the Block 7 exploration licence under the Daris JV. Alara maintains an interest in the Khnaiguiyah Zinc-Copper project in Saudi Arabia, with a Feasibility Study completed endeavours to secure a mining licence re-issue underway.
Alara is currently focused on developing the Al Wash-hi Majaza Copper-Gold project in Oman, where it is in the process of constructing copper-gold mining and processing facilities. The Company is also continuing exploration activities at its other Oman projects.
Alara’s mission is to become a mid-tier minerals producer which will deliver maximum shareholder value through profitable growth driven by low-cost and sustainable operations.
To learn more, please visit: www.alararesources.com.