ALARA RESOURCES LIMITED Capital/Financing Update 2021

Dec 20, 2021

64461_rns_2021-12-20_a46dbba6-c832-46fc-bc3d-50852060e58a.pdf

Capital/Financing Update

Open in viewer

Opens in your device viewer

Alara Resources Limited A.B.N. 27 122 892 719 Suite 1.02, 110 Erindale Road, Balcatta WA 6021, Australia

Telephone | +61 8 9240 4211 Facsimile | +968 2449 2491 Web | www.alararesources.com Email | [email protected]

PO Box 963, Balcatta WA 6914

==> picture [122 x 58] intentionally omitted <==

ASX/MEDIA RELEASE

21 December 2021

ALARA RESOURCES ACCELERATES CONSTRUCTION AND - PROCUREMENT AT OMAN COPPER GOLD PROJECT

Highlights

  • Alara continues to make significant progress at its joint venture copper-gold project in Oman

  • Engineering and procurement continue to ramp up, with 63% of engineering work completed and a number of major equipment items on order

  • Accommodation village construction is nearing completion and will be occupied by January 2022

  • Alara remains on track to complete the project by November 2022

Perth, Australia: Alara Resources Limited (ASX: AUQ) (“ Alara ” or “the Company ”) a base and precious metals explorer and developer with projects in Oman, is pleased to provide an update on the accelerated progress of construction and procurement activities at the Al Hadeetha at the Washhi Majaza Copper-Gold Project. Alara owns a 51 per cent equity interest in the joint venture developing the project.

Project engineering ramps up

As the procurement order placements are advancing, the progress of detailed engineering is also meeting the expected schedule at an accelerated pace. During this month, planned engineering was progressed rapidly by Debisikha Associates and Progesys, with 63% of planned detailed engineering work completed (refer figure 1).

==> picture [550 x 180] intentionally omitted <==

Figure 1: Project Engineering progress

==> picture [56 x 56] intentionally omitted <==

ASX Code | AUQ

==> picture [62 x 29] intentionally omitted <==

Procurement

Since the previous update, Al Hadeetha Resources LLC ( AHRL ) continued with drawdown on finance, using the capital for the following purchase orders and contracts. Total committed cumulative Capex stands at US$23.5 million in December 2021. The table below provides details of equipment already ordered (refer figure 2).

Package/Equipment details Supplier/Contractor Supplier/Contractor
1 Ball Mill, SAG Mill, Crusher CITIC China
2 Rock Breaker Metso-OT Finland
3 Apron Feeder L&T India
4 Pan Feeders Metso-OT India
5 Magnetic Separators Electro Zavod India
6 Accommodation Cabins Refurbished Al Tasnim Oman
7 Accommodation Camp Construction Al Naba Infrastructure Oman
8 New Cabins - Dining, Offices etc. Al Rehwan Oman
9 Fencing Al Naba Infrastructure Oman
10 Conveyors Al Tasnim Oman
11 Belt Weigher and Vibrating Screens Schenck India
12 Hydrocyclones Weir UAE
13 Conveyor Safety Switches Smart SAA India
14 Construction of Access Road C&C Oman
15 Pressure Filters Matec Italy
16 Regrinding Mill Metso Outotec USA
17 Electrical Packages - Transformers, Panels,Motors, Telecom ABB India
18 Dust Collector Stratgem Projects India
19 Power lines ONEIC Oman
20 Agitator Afromix SA
21 Sampling and Analyzing System Metso Outotec USA
22 Air Compressor Bin Salim Oman
23 Froth, Slurry and Sump Pumps Metso Outotec Turkey
24 Flotation Cells Innnovator Poland
25 Air Blower Continental Industrie France
26 Plant Control System CAS India
27a Workshop – Material (Prefab Building) Kirby Kuwait
27b Workshop – Civil and MEP Design DSA India
27c Workshop – Erection Emmar Oman
28 Cooling Tower BEC Oman

Figure 2: Equipment ordered

[The remainder of this page is intentionally blank]

==> picture [56 x 56] intentionally omitted <==

ASX Code | AUQ

==> picture [62 x 29] intentionally omitted <==

Site work progress – Camp construction

Construction of accommodation village is nearing completion. Catering and facility management contracts are also being awarded to make the camp liveable by mid-January 2022.

The pictures below show accommodation camp construction progress.

==> picture [376 x 250] intentionally omitted <==

Picture 1: Accommodation village nearing completion.

==> picture [376 x 251] intentionally omitted <==

Picture 2: Accommodation village close-up

==> picture [56 x 56] intentionally omitted <==

ASX Code | AUQ

==> picture [62 x 29] intentionally omitted <==

==> picture [386 x 259] intentionally omitted <==

Picture 3: Dining area ground slab casting

==> picture [388 x 266] intentionally omitted <==

Picture 4: AHRL CEO Avigyan Bera finalizing power line route to project

Alara Managing Director Atmavireshwar Sthapak said:As we approach the end of 2021, we are pleased to report that progress at the Al Wash-hi Majaza Copper-Gold Project is continuing to accelerate. With the accommodation village almost complete, attention will turn to the construction of a world-class, copper-gold mining-processing facility. We are very excited about the work we have planned for 2022 and look forward to updating shareholders on the achievement of further key project development milestones.

==> picture [56 x 56] intentionally omitted <==

ASX Code | AUQ

==> picture [62 x 29] intentionally omitted <==

ENDS

This announcement is authorised by:

Atmavireshwar Sthapak T 1 | +968 2449 1162 Managing Director E | [email protected] Dinesh Aggarwal T | +61 8 9240 4211 Company Secretary E | [email protected] Media enquiries Julia Maguire T | +61 2 8999 3699 The Capital Network E | [email protected]

About Alara Resources

Alara Resources Limited (ASX: AUQ) is an Australian-based precious and base metals explorer and developer, with projects in Oman and Saudi Arabia.

Alara’s active projects in Oman are the Al Wash-hi Majaza Copper-Gold mining licence and Mullaq, Al Ajal exploration licences under the Al Hadeetha JV and the Block 7 exploration licence under the Daris JV. Alara maintains an interest in the Khnaiguiyah Zinc-Copper project in Saudi Arabia, with a Feasibility Study completed endeavours to secure a mining licence re-issue underway.

Alara is currently focused on developing the Al Wash-hi Majaza Copper-Gold project in Oman, where it is in the process of constructing copper-gold mining and processing facilities. The Company is also continuing exploration activities at its other Oman projects.

Alara’s mission is to become a mid-tier minerals producer which will deliver maximum shareholder value through profitable growth driven by low-cost and sustainable operations.

To learn more, please visit: www.alararesources.com