ADX ENERGY LTD — Capital/Financing Update 2017
Mar 28, 2017
64308_rns_2017-03-28_4c5d06c2-1633-46c9-b9e1-33eb7a5ecc89.pdf
Capital/Financing Update
Open in viewerOpens in your device viewer
ASX Release
==> picture [136 x 269] intentionally omitted <==
29 March 2017
Nilde Field Redevelopment Update (with amended presentation)
Updated economic assessment of the Nilde Redevelopment Project based on recently updated Contingent Resources and the previously announced Development Concept utilising a leased self-installing platform facility.
ADX Energy Ltd ( ASX:ADX ) is pleased to provide the attached Nilde Field Redevelopment Update presentation containing an indicative economic assessment for the project that incorporates the extensive resources reevaluation work undertaken by ADX during the last 12 months and the concept definition studies undertaken by ADX in collaboration with Calm Oceans Pte Ltd ( COPL ) for the utilisation of a self-installing mono column platform (MCP).
==> picture [136 x 39] intentionally omitted <==
ADX announced revised resource estimates based on static geological and dynamic reservoir modeling honouring all available geological and historical production data from the field on the 14[th] of February 2017. On the 22[nd] of December 2016, it was announced that ADX and COPL entered into a Memorandum of Understanding “MOU” to jointly progress development planning for the Redevelopment of Nilde on the basis of leased platform, production and storage facilities. ADX believes this is an optimal technical and commercial solution. The attached presentation summarises this work, incorporates drilling cost studies undertaken by ADX and facilities lease costs derived from contractor proposals to provide an economic analysis for the project and the basis for a formal financing and farmout process which ADX is now in a position to commence.
Key points from the technical and economic analysis are as follows;
-
The Project has the potential to be highly profitable and robust due to high reservoir productivity, light sweet crude, shallow drill depths, shallow water depth and low royalties.
-
The combination of low offshore drilling costs possible from the MCP platform combined with attractive lease rates for the platform, production and storage facilities result in excellent predicted economics as summarised below at an oil price of US$ 40 per barrel;
-
Net post tax cash flow averaging approximately US$150 million per annum for first 3 years for the predicted base case resource (2C resources estimate of 33 million barrels);
-
Low capital costs per barrel of US$4.80 - 3.40 per barrel (across the predicted resource range of 22 million barrels 1C to 50 million barrels 3C);
-
High post tax NPV10 per barrel of US$13 - 25 per barrel (across the predicted resource range of 22 million barrels 1C to 50 million barrels 3C);
==> picture [108 x 73] intentionally omitted <==
-
Material Post tax NPV10 of approximately US$200 - 650 million (across the predicted resource range of 22 million barrels 1C to 50 million barrels 3C);
-
Project pay back across all three resource cases of less than one year, and
-
Break even oil price for the 1C resource case less than US$30 per barrel.
The analysis to date indicates the transformational nature of the Nilde asset for ADX. Extensive historical data combined with recent developments in platform, drilling and production technologies has created a highly desirable redevelopment opportunity from a substantial remaining oil resource.
While it has taken longer than expected to secure all the available data & information for a credible value proposition for Nilde, the results of the resource determination, project feasibility and economics to date are compelling. The asset is already generating significant interest amongst potential farminees. ADX is now ready to commence a formal financing and farmout process utilising the attached results incorporated into a detailed information memorandum.
As mentioned in previous releases ADX has commenced discussions with Italian Authorities to enable appraisal operations as soon as practically possible. Our goal is to progress appraisal well planning and Nilde Redevelopment project planning in parallel to enable the submission of development plan as soon as possible after the drilling of a successful appraisal well.
ADX believes an appraisal well is an important pre-investment to ensure an optimal subsurface development plan and secure project finance for the project. It is intended that an appraisal well will be suspended as a future producer.
ADX development strategy is based on collaboration and alignment with capable contractors as demonstrated with the COPL MOU enabling ADX to progress a material project at low cost while ensuring the appropriate skills and experience are deployed to deliver a successful project.
For further details please contact :
| Paul Fink | Ian Tchacos |
|---|---|
| Chief Executive Officer | Executive Chairman |
| +61 (08) 9381 4266 | +61 (08) 9381 4266 |
| www.adxenergy.com.au |
Notes
1 Contingent Resources: those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations but, for which the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies.
2 1C, 2C, 3C Estimates: in a probabilistic resource size distribution these are the P90 (90% probability), P50, and P10, respectively, for individual opportunities . Totals are by arithmetic summation as recommended under PRMS guidelines. This results in a conservative low case total and optimistic high case total.
www.adxenergy.com.au
==> picture [108 x 73] intentionally omitted <==
Qualified Resource Evaluator Statement
The information in this report and the contingent resources, related supporting documentation and data have been reviewed by Mr. Paul Fink who is a petroleum consultant to ADX and serves on the board of ADX as an Executive Director. He holds an MSc from the Mining University of Leoben, is a chartered Engineer, a member of Fidic (International Federation of Consulting Engineers) and a member of EAGE (European Association of Geoscientists and Engineers) and is qualified in accordance with ASX listing rule 5.41.
www.adxenergy.com.au
==> picture [85 x 58] intentionally omitted <==
NILDE OIL REDEVELOPMENT UPDATE OFFSHORE SICILY CHANEL ADX 100% EQUITY INTEREST
==> picture [380 x 222] intentionally omitted <==
==> picture [301 x 200] intentionally omitted <==
29 March 2017
amended
www.adx-energy.com
1
DISCLAIMER
==> picture [85 x 58] intentionally omitted <==
This document has been prepared by ADX Energy Ltd for the purpose of providing an activity update to interested analysts/investors and shareholders. Any statements, opinions, projections, forecasts or other material contained in this document do not constitute any commitments, representations or warranties by ADX Energy Ltd or its directors, agents and employees. Except as required by law, and only to the extent so required, directors, agents and employees of ADX Energy Ltd shall in no way be liable to any person or body for any loss, claim, demand, damages, costs or expenses of whatsoever nature arising in any way out of, or in connection with, the information contained in this document. This document includes certain statements, opinions, projections, forecasts and other material, which reflect various assumptions. The assumptions may or may not prove to be correct. ADX Energy Ltd recommends that potential investors consult their professional advisor/s as an investment in the company is considered to be speculative in nature.
CONTINGENT RESOURCES & DEFINITIONS
Tunisia: Refer to ASX announcements 26/9/2012 (contingent) and 6/9/2013 (prospective). Italy: Refer to ASX announcements 17/2/2016 & 14/2/2017 (contingent) and 21/4/2016 (prospective). ADX confirms that it is not aware of any new information or data that affects the information included in those market announcements and that all the material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed.
Contingent Resources: those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations but, for which the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies.
1C, 2C, 3C Estimates: in a probabilistic resource size distribution these are the P90 (90% probability), P50, and P10, respectively, for individual opportunities . Totals are by arithmetic summation as recommended under PRMS guidelines. This results in a conservative low case total and optimistic high case total.
Persons compiling information about Hydrocarbons.
Pursuant to the requirements of the ASX Listing Rules 5.41 and 5.42, the technical and resource information contained in this presentation has been reviewed by Paul Fink, Technical Director of ADX Energy Limited. Mr. Fink is a qualified geophysicist with 23 years of technical, commercial and management experience in exploration for, appraisal and development of oil and gas resources. Mr. Fink has reviewed the results, procedures and data contained in this presentation and considers the resource estimates to be fairly represented. Mr. Fink has consented to the inclusion of this information in the form and context in which it appears. Mr. Fink is a member of the EAGE (European Association of Geoscientists & Engineers) and FIDIC (Federation of Consulting Engineers).
2
Nilde Area Strategic Summary
==> picture [85 x 58] intentionally omitted <==
Mediterranean Acreage Position
-
5000 km contiguous acreage position with an oil redevelopment project ( Nilde ), gas appraisal project ( Dougga ), follow up oil and gas discoveries and material 3D defined exploration prospect portfolio
-
Nilde Area Potential
-
Nilde Oil Redevelopment Project 22 MMbbls (1C) to 50 MMbbls (3C) resource potential
-
–
-
2 Tested Oil Discoveries
- 2 MMbbls (1C) to 15 MMbbls (3C) resource potential
-
Near Field Exploration
90 MMbbls best est. prospective
resource
==> picture [303 x 235] intentionally omitted <==
----- Start of picture text -----
Lead-5
Nailia-1 Lead-4
Nilde-1 bis
Norma-1
Nilde-2
Lead-3
Lead-1
Lead-2
----- End of picture text -----
-
We know the area well technically, commercially and politically
-
Material but as yet not appreciated strategic position
3
Nilde Redevelopment Summary
==> picture [85 x 58] intentionally omitted <==
Background
- Acquired as exploration permit, remaining potential of Nilde identified by ADX in late 2015, independently audited in February 2016 and project feasibility in 2016 / 2017
Resource Attributes
- Substantial remaining resource (2C of approximately 33 MMBBL) defined by multiple wells, an extensive geological data base and production history
Preferred Development Option
-
A collaboration with Calm Oceans via a preferred development option utilising a self-installing Mono Column Platform (MCP) and a gravity based mooring, storage and offloading system (RPSO) which would enhance the overall viability of the Development in terms of economics, feasibility and operability
-
Economic Potential at US$ 40/bbl oil price:
-
Excellent project economics due to reservoir high productivity, light sweet crude, shallow drill depths, shallow water depth and low royalties
-
Capex US$3.40- 4.80/bbl , NPV US$13-25/bbl , Break even oil price sub- US$30/bbl and pay back in less than a year
-
Post Tax NPV10 = US$200 - 650 million @ approx US40/bbl for 1C to 3C case
4
Nilde Redevelopment Current Status
==> picture [85 x 58] intentionally omitted <==
Remaining resource potential and future oil production defined
Gross Contingent Oil Resource Volumes (MMstb)[(1)] 1C² Estimate 2C² Estimate 3C² Estimate Nilde & Nilde Bis 21.7 32.8 49.8
Matured preferred development concept
==> picture [341 x 194] intentionally omitted <==
Notes regarding Oil Resource Volumes
1 Based on history matched reservoir simulation, ADX estimates of remaining resources. Contingent Resources: those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations but, for which the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies.
2 1C, 2C, 3C Estimates: in a probabilistic resource size distribution these are the P90 (90% probability), P50, and P10, respectively, for individual opportunities .
Redefined economic potential >>Ready to attract funding into a credible, well defined project
5
Nilde Oil Project History
==> picture [85 x 58] intentionally omitted <==
==> picture [290 x 190] intentionally omitted <==
Nilde Field Discovered 1973 by AGIP(now ENI)/Shell
-
20.5million barrels of 39[o] API oil produced
-
Field averaged 9,400bopd for 5+years until water breakthrough at main well and rapid decline
-
Field abandoned 1989 (prematurely)
-
Previous development concept not capable of responding to water onset in 1988
-
Oil price drop to $14/bbl
Norma and Naila oil discoveries
- 2 x tested, undeveloped satellite fields
2015 : ADX awarded Permit 100%
==> picture [329 x 168] intentionally omitted <==
-
Contiguous with Tunisian acreage; seeking to extend the play
-
Initial review showed Nilde more exciting than originally thought
-
Nilde’s fractured reservoir expected to have recharged over almost 30 years since abandonment.
-
Substantial recoverable volumes remaining
6
Permit Evaluation Program
Permit Evaluation Kickoff (2015-1Q2016)
-
2015 Licence award
-
Initial permit assessment
-
Nilde
-
Satellite discoveries (Norma, Naila)
-
Exploration
-
Probabilistic volumetrics
-
Independent Certification – Senergy
Two-pronged attack to accelerate work program
==> picture [85 x 58] intentionally omitted <==
==> picture [231 x 153] intentionally omitted <==
Detailed Subsurface Modelling (2Q2016-1Q2017)
-
Data Purchase from ENI
-
Structural modelling
-
Core review and petrophysics
-
OWC/FWL review
-
3D geological modelling
-
Dynamic simulation modelling
-
Scenario testing / History matching
-
• Appraisal objectives/strategy
-
• Production forecasting • Contingent Resources update
Development/Activity Planning (3Q2016-2Q2017)
-
Initial concept selection
-
Conceptual planning
-
Indicative offers; leased equipment
-
Partnership agreement with preferred main contractor including binding offer
-
Iteration • Revised leased equipment offers
-
Cost/schedule estimates
-
Scoping economics
-
• Appraisal planning (Ongoing)
-
• Detailed appraisal well design(Future)
7
Key Subsurface Attributes
==> picture [85 x 58] intentionally omitted <==
- Nilde Formation : Fractured shallow
water carbonates
-
Good matrix properties; 8-19% matrix porosity contains bulk of oil in place
-
Excellent productivity; Extensive, connected fracture system at top reservoir observed in cores from multiple wells
-
Fracture system cementation observed in core in transition zone delays water influx
-
Well defined structure
-
strong seismic reflectivity at top reservoir
-
6 well penetrations
-
Substantial oil column ~150m of
structural relief from OWC at Nilde 2
- Substantial OIIP upside from 3D geological modelling: ~ 300 mmbo
==> picture [324 x 193] intentionally omitted <==
----- Start of picture text -----
SW NE
OWC ~ 1610 m ss
----- End of picture text -----
==> picture [363 x 184] intentionally omitted <==
----- Start of picture text -----
Nilde-2
150m oil column
Partly drained pool
(20.5mmbbl)
20mmbbl remaining (2C)
Nilde-5
Undrained pool
12mmbbl remaining (2C)
----- End of picture text -----
8
Dynamic Simulation Findings (1)
==> picture [85 x 58] intentionally omitted <==
-
High confidence in the model
-
Honours all available data
-
Excellent history match to 20.5 mmbbl
production
-
Base Case OIIP range 176-237 mmbbl barrels with upside to 300mmbbl
-
20.5 million barrels produced with low historical recovery factor between 8-12%
3D Reservoir Simulation Model
-
Significant potential recovery remaining
-
Ample time for reservoir recharge with matrix oil
-
Water levels in fracture system had reached Nilde-2 when field shutin (1989)
-
Matrix oil will have refilled/recharged the fractures and dropped the water levels
-
Production from the crest of the field
Oil Saturation Oil Saturation Matrix Reservoir Fracture System
- expected to again be capable of several
years of water-free production
9
Dynamic Simulation Findings (2)
==> picture [85 x 58] intentionally omitted <==
- Base Case model will be confirmed with
appraisal
-
Present-day oil column
-
“Open” Faults; no compartmentalisation
-
Fracture System/Productivity in lower reservoir layers and Nilde-5 fault block
• Ideal for efficient development
-
Minimise CAPEX : Horizontal wells minimise well numbers and delay water onset
-
3 development wells required to fully develop field in 1C and 2C cases (4 wells in some high
==> picture [371 x 261] intentionally omitted <==
cases)
-
Quick payback period : Anticipated plateau rate 15,000 – 25,000bopd
-
Field life optimises leased equipment :
Majority resource produced in first 3-5 years
==> picture [371 x 93] intentionally omitted <==
10
Contingent Resource Definition
==> picture [85 x 58] intentionally omitted <==
• 2C Contingent Resource (most likely) of 33 million barrels
| Nilde/Nilde Bis Contingent Resources1 | 1C2 | 2C2 | 3C2 | ||
|---|---|---|---|---|---|
| 2017–Detailed Reservoir Modelling | 21.7 | 32.8 | 49.8 | ||
| 2016 – Probabilistic Volumetrics (Senergy)2,3 | 18.0 | 28.4 | 38.8 | ||
| Variance | 3.7 | 4.4 | 11.0 | ||
| Note 1&2 below right; Note 3 : Nilde and Nilde Bis volumes from Senergy Report have been arithmetically added. |
-
Detailed reservoir modelling updated probabilistic contingent resource numbers from early 2016 by Senergy GB Limited (Senergy).
-
Senergy are well respected independent reserves certifier from Lloyds Group of Companies
-
Expanded range, particularly to the upside
-
Core evaluation; more significant fracture system
-
Detailed Petrophysics & Saturation Height modelling; deeper oil water contact, improved porosity in lower oil layers
Notes regarding Oil Resource Volumes
1 Contingent Resources: those quantities of petroleum estimated, as of a given date, to be potentially recoverable from known accumulations but, for which the applied project(s) are not yet considered mature enough for commercial development due to one or more contingencies.
- 2 1C, 2C, 3C Estimates: in a probabilistic resource size distribution these are the P90 (90% probability), P50, and P10, respectively, for individual opportunities .
3. Totals are by arithmetic summation as recommended under PRMS guidelines. This results in a conservative low case total and optimistic high case total.
11
==> picture [85 x 58] intentionally omitted <==
Development Concept Selection (1)
MCP & RPSO Facilities Option
MCP – Leased Production Platform
-
Calm Oceans Pte Ltd (COPL) COPL has developed and constructed a selfinstalling Mono Column Platform (MCP)
-
The MCP is capable of supporting a drilling rig, production processing equipment water and gas reinjection facilities as well as accommodation
-
Enables field to be redeveloped with reduced well costs (less 60%) enabling dry trees and reinjection of produced fluids
-
MCP provides significant capex and opex savings over an FPSO as well as superior operability and well intervention.
==> picture [262 x 302] intentionally omitted <==
The MCP option schematic – incorporating production and drilling capability with dry well heads. Source: Calm Oceans Pte. Ltd, Mono Column Platforms are proprietary and patented.
12
Development Concept Selection (2)
==> picture [85 x 58] intentionally omitted <==
COPL and ADX Collaboration
-
ADX and COPL entered into an MOU in December 2016 to jointly progress the redevelopment of the Nilde field
-
COPL has offered to supply the MCP and RPSO to ADX on a lease dry boat charter basis.
-
COPL has assisted ADX to secure additional topside facilities (production and drilling) at competitive rates from third parties
-
COPL will provide surface facilities capex, opex, lease data and engineering details required to submit a development plan to Italian Authorities
-
The owner of COPL, Mr Brian Chang, brings an extensive track record in development engineering, fabrication and installation. The combination of ADX geotechnical experience with COPL’s facilities engineering capability significantly enhances the Nilde project both technically and financially.
RPSO - Gravity Based Storage & Offloading Solution
==> picture [137 x 251] intentionally omitted <==
COPL is designing and accrediting a gravity based mooring, storage and offloading system (RPSO) ideal for the redevelopment of the Nilde Field .
The RPSO is proprietary, and patent pending.
13
==> picture [85 x 58] intentionally omitted <==
Nilde Redevelopment Economics (1)
Economic Summary
Basis for Indicative Economics
| Resource Classification | 1C | 2C | 3C | |
|---|---|---|---|---|
| (90% chance to exceed) |
(50% chance to exceed) |
(10% chance to exceed) |
||
| Recoverable Resources(MM bbls) | 21.7 | 32.8 | 49.8 | |
| Max Production Flowrate (bbls/day) |
15,000 | 20,000 | 25,000 | |
| NPV10 @ $ 40/bbl(US$ million) | $170 | $350 | $563 | |
| Production Period(Years) | 7 | 6 | 9 |
ADX has progressed project definition work on the (100% owned) potential redevelopment of the Nilde field. Key sources of data used in the analysis are summarised as follows:
-
Nilde Oil Field Contingent Resources announced on the 14[th] of February 2017 following the completion of static geological and dynamic reservoir modeling.
-
Lease rates and cost estimates provided by COPL, production facilities providers, field operations providers and drilling management contractors based on the utilisation of a MCP and RPSO platform and storage solution.
Revenue Split
2 C Resource @ US$ 40/bbl Total Revenue = US $1.3 billion Royalty
- Independent drilling cost studies for appraisal drilling via floating exploration rig and development drilling via MCP based platform rig.
Drilling & Capex Opex & Lease Tax
- Estimates in this analysis are indicative only, based on the best available data and will be used in farmout and funding discussions by ADX
AfterTax Cashflow
14
Nilde Redevelopment Economics (2)
==> picture [85 x 58] intentionally omitted <==
Comments on Economic Results
Post Tax NPV 10 vs's Oil Price
$1,200
==> picture [349 x 370] intentionally omitted <==
----- Start of picture text -----
$1,000
Value
$800
Range
$600
$400
$200
$-
$30 $35 $40 $45 $50 $55 $60
US $/ bbl
1C Case 2C Case 3C Case
Key Cost & Schedule Assumptions
Nilde appraisal well drilled first half 2018
suspended as producer.
Tie back appraisal well, drill 2 platform
development wells and 1 platform
disposal well end 2019
----- End of picture text -----
-
NPV10 Range at current oil price between US$ 200 – 650 Million
-
All resources cases demonstrate high profitability, rapid paybacks and low oil price profitability (sub US$ 30 / bbl)
-
High profit investment ratios are the result of low pre production costs and robust NPV’s
-
Lease costs are favourable compared to an FPSO option but deliver significantly lower drilling and completion capex
Profitability Measures |
|
|---|---|
| Resource Case | 1C 2C 3C |
| Profit Investment Ratio(PIR) 1.6 3.3 5.4 |
|
| Payback(months) 12 9 6 |
|
| IRR(post tax) 55% 83% 101% |
|
| Net Revenue / Bbl(US$) 12.8 17.8 24.5 |
|
| Capex /Bbl(US$) 4.80 3.37 3.37 |
|
| Opex / Bbl (US$) 8.97 5.86 5.86 |
- First Production January 2020
Note: Opex / Bbl includes all facilities lease rates
15
Nilde Redevelopment Economics (3)
==> picture [85 x 58] intentionally omitted <==
Project Production Profile and Cash flows
- Base Resource Case (2 C Resources), and US$ 40 per barrel oil price
2C Resource "Production Profile"
==> picture [523 x 338] intentionally omitted <==
----- Start of picture text -----
35000 8000
30000 7000
6000
25000
5000
20000
4000
15000
3000
10000
2000
5000 1000
0 0
Project Year Prod cum. Prod yearly
2C Resource "Discounted Cash Flow & NPV10"
$400 $150
$350 $125
$300
$100
$250
$75
$200
$150 $50
$100 $25
$50
$-
$-
-$25
-$50
-$100 -$50
-$150 -$75
Project Year DCF NPV
[mbbls] [mbbls]
Oil Prod. Cumulative Yearly Oil Production
NPV [MMUSD]
DCF, annual [MMUSD]
----- End of picture text -----
16
Nilde Redevelopment Economics (4)
==> picture [85 x 58] intentionally omitted <==
Project Lease and Opex Assumptions - Assuming leased MCP and RPSO Development Option
==> picture [397 x 219] intentionally omitted <==
Note: All pre production lease rates, day rate mobilisation charges etc are capitalised as pre project costs
| ption | |
|---|---|
| Field Operating Costs | |
| Cost Description | Daily Rate Annual Number (US$ /day) (US$ 000) |
| Personnel Costs Operating Personnel 10 13,000 $ 4,745 $ Field Management 5 6,000 $ 2,190 $ Operations Management 5 6,000 $ 2,190 $ Boats & Helicopters Field Standby Vessel 1 6,000 $ 2,190 $ Supply Vessel 1 12,000 $ 4,380 $ Helicopters 5,000 $ 1,825 $ General and Admin Local office 3,000 $ 1,095 $ Insurance 3,000 $ 1,095 $ Training 2,000 $ 730 $ |
|
| Total Operating Costs 56,000 $ 20,440 $ Costs developed in collaboration with COPL |
17
Nilde Redevelopment Economics (5)
==> picture [85 x 58] intentionally omitted <==
Project Appraisal and Development Drilling Assumptions Assuming Appraisal Drilling from Mobile Drilling Unit & MCP Development Drilling Option
Appraisal, Development Drilling and Completion Costs Summary
==> picture [294 x 279] intentionally omitted <==
| Operational Summary | US$ 000 Comments |
|---|---|
| Appraisal Development Well Cost Summary | |
| High Angle Well - evaluated and tested Mobilisation costs Planning and Survey Drill Days Testing and Evaluation Days Appraisal Well Drilling &Testing |
1,000 $ per Well 500 $ per Well 40 9 18,500 $ |
| Total - Mobilisation, Drill, Complete & Contingency | 20,000 $ |
| Development Drilling - Platform Drilling with Dry Trees | |
| Platform Rig Installation / Mobe (Modified Land Rig with mast) Platform Rig Removal / Demobe (Modified Land Rig with mast) Well Supervision Tie in and Complete Appraisal Well Drill and Complete High Angle Well 1 (500 m horizontal) Drill and Complete High Angle Well 2 (500 m horizontal) Drill and Complete Vertical Injection well Total Drilling and Completeion Costs exc Contingency Contingency 20% |
4,200 $ 2,400 $ 1,400 $ 4,555 $ 8,250 $ Moderate Deviation 8,250 $ Moderate Deviation 6,750 $ 35,805 $ 7,161 $ |
| Total - Mobe, Drill, Complete & Contingency | 42,966 $ |
| Notes |
MCP Drilling and Production equipment layout – source COPL
1) High Angle well 2600 m MD / 1500 m TVD
-
2) Injection well 1900 m MD / 1600 m TVD
-
3) Development well drilling and completion assumed to be continuous operation
23-Mar-17
18
Nilde Redevelopment Project Status
==> picture [85 x 58] intentionally omitted <==
-
Extensive technical work accomplished to deliver credible resources estimates (honouring all available data) and securing an highly desirable development option with an aligned and capable partner
-
Project offers material cash flow
-
Average US$ 150 million per annum for first 3 years for base case resource @ US$ 40 per barrel
-
Project robust and highly profitable at low oil price – key attributes as follows;
-
Proven reservoir and excellent productivity of 10,000 bopd/well
-
Shallow reservoir (1500 m TVDSS) and water depth (90 meters)
-
Substantial resource of 32 mmbo 2C resources and 22 mmbo 1C resources from a proven accumulation at Nilde.
-
High value high quality light crude (39 API gravity) proximal to refineries
-
Excellent reservoir productivity enabling development with only three wells
-
Low expected capital costs per barrel and excellent fiscal terms
-
A transformational asset for ADX – AGIP (ENI) knew the potential was there but it ceased to be material for them. Extensive historical data combined with reservoir recharge and new technology has created a highly desirable redevelopment opportunity.
19
Nilde Way Forward
==> picture [85 x 58] intentionally omitted <==
Funding and Farmout
-
Taken longer than expected to get all required data & information for credible value proposition
-
Resource, project feasibility and economics results to date are highly compelling
-
Asset already generating significant interest in UK
-
Ready to commence formal financing and farmout process
Project Development Planning and Appraisal
-
Commenced discussions with Italian Authorities to enable license operations
-
Goal is to progress appraisal well planning and Nilde Redevelopment planning in parallel to enable submission of development after drilling a successful appraisal well.
-
An appraisal well is pre-investment to ensure an optimal subsurface development plan and secure project finance.
Contractor Collaboration
- Collaboration with capable contractors is enabling ADX to progress a material project at low cost while ensuring the appropriate skills and experience is deployed on the project
20
==> picture [85 x 58] intentionally omitted <==
Ian Tchacos Executive Chairman Paul Fink Chief Executive