December 10, 2025
To:Israel Securities AuthorityVia MAGNA To:Tel Aviv Stock Exchange Ltd.Via MAYA
Dear Sir/Madam,
Subject: Initiation of Arbitration Proceedings by The Israel Electric Corporation Ltd. Against All Partners in the Project
Further to section 9.4.4.3 of Chapter A of the Company's annual report for 2024 published on
March 31, 2025 (reference no. 2025-01-023400) (hereinafter: the annual report), regarding the gas supply agreement
between the partners in the Tamar project (hereinafter: Tamar Partners) and The Israel Electric Corporation Ltd. (hereinafter:
IEC) signed on March 14, 2012, as amended from time to time (hereinafter: the IEC Agreement), and further to the immediate report
dated July 24, 2025 (reference no. 2025-01-055327), regarding the signing by Isramco Negev 2 Limited Partnership
(hereinafter: Isramco Negev 2) (and some of the other Tamar Partners) of a non-binding memorandum of understanding with IEC to amend
the IEC Agreement (hereinafter: the memorandum of understanding), and to the immediate report of September 9, 2025 (reference
no. 2025-01-068087), regarding the decision of the general partner of Isramco Negev 2 not to advance the amendment
to the IEC Agreement at this time, the company wishes to update that on December 9, 2025, IEC initiated arbitration proceedings
in the London Court of International Arbitration against all Tamar Partners, within which it is requested to determine, among other things,
that as of January 1, 2025, the gas price in the IEC Agreement in relation to the minimum chargeable quantity (as dened
in section 7.4.4.2(1) of the annual report), as stipulated in the IEC Agreement, will be reduced to the maximum rate
set forth in the IEC Agreement (for details regarding the price adjustment mechanism, see section 9.4.4.3(7)A of the annual
report).
Isramco Negev 2 completely rejects IEC's position, and will submit its detailed position within the framework of the arbitration proceedings.
arbitration proceedings.
| 28.75% | Isramco Negev 2, Limited Partnership |
|---|---|
| 25% | Chevron Mediterranean Limited |
| 16.75% | Tamar Petroleum Ltd. |
| 11.00% | Mubadala Energy (Tamar) RSC LTD |
| 11.00% | Tamar Investment 2 Limited |
This is an unofficial AI generated translation of the official Hebrew version and has no binding force. The only binding version is the official Hebrew version. For more information, please review the legal disclaimer.
| 4.00% | Dor Gas Exploration, Limited Partnership |
|
|---|---|---|
| Union Energy & Systems 2 Ltd. Respectfully, |
3.50% | |
| Equital Ltd. By Eran Landner, CEO |
||
| and Eitan Voloch, CFO |
||