This announcement contains inside information for the purposes of Article 7 of the UK version of Regulation (EU) No 596/2014 which is part of UK law by virtue of the European Union (Withdrawal) Act 2018, as amended ("MAR"). Upon the publication of this announcement via a Regulatory Information Service, this inside information is now considered to be in the public domain.
19 November 2025
Nativo Resources Plc
("Nativo" or the "Company")
Operations Update: Gold Ore Processing Plant
&
Update re Santa Cruz Sur, Argentina
Procurement and contracting underway at La Patona Gold Ore Processing Plant
Nativo Resources Plc (LON:NTVO), a gold-focused mining company with interests in Peru, is pleased to provide an update on pre-construction progress at La Patona Gold Ore Processing Plant ("GOPP"), located in Acarí, 45km from the Tesoro Gold Concession.
Nativo has completed the GOPP design and selected equipment suppliers for all material components of the plant. Suppliers have been selected and prices and delivery times agreed for the following works:
· Fabrication, transport and installation of new water borehole and pump
· Electrical works including a 1.8 km 500 kV cable to connect the plant to the power grid
· Ore crushing unit with a capacity of 350 tpd with two milling units
· 150 tpd flotation circuit (stage 1) plus centrifuges and agitators to accommodate lower third-party ore
· 70 tpd lixiviation circuit (stage 1) plus centrifuges and agitators, designed for processing higher grade ore
· Chemical and metallurgy laboratory to assay the ore, concentrates, and doré bars
· Smelting circuit with a daily output of 7-8 kg producing gold doré bars
In addition, the Company will imminently be awarding a contract for the following civil works which are due to commence in late November 2025:
· Groundworks
· Access and internal roads
· Geomembrane liner for the tailings facility
Nativo is preparing the submission of technical updates for its Environmental Management Instrument for Formalization permit (IGAFOM by its acronym in Spanish) required to operate the GOPP under the Registro Integral de Formalización Minera (REINFO) system.
Based on the current GOPP project schedule and scope of works, Nativo expects the GOPP to become operational and commence ore processing in Q2 2026.
Once the first phase is completed and the GOPP is operating at full capacity, it will be capable of outputting between 1.48 kg and 1.67 kg of gold in doré bars per day (subject to suitable supply of ore being maintained). Phase 2, which involves scaling up capacity by the third year, will increase production up to 3 kg per day.
Update re Santa Cruz Sur, Argentina
Considering Nativo's focus is now exclusively on advancing its precious metals opportunities in Peru, the Board has decided to exit the Company's remaining legacy oil and gas interest in Argentina. Accordingly, Nativo has transferred its 5% interest in the Santa Cruz Sur concessions to the operator, Interoil Exploration and Production ASA, for nil consideration. The assets have been loss-making since 2023 and Nativo's shareholding had been fully written down in the Company's 2023 Annual Report and Accounts.
Stephen Birrell, Chief Executive Office of Nativo, commented:
"We are pleased with the procurement progress being made at the plant. We have a clear objective to become an integrated regional gold producer, handling both Nativo's own and third-party material. We are developing the plant to be capable of processing both high and lower grade ores, providing a competitive advantage over other regional tolling plants which typically do not accommodate lower grade ores from the artisanal and small-scale miners. We look forward to commencing civil works on site and formalising the equipment orders in the coming weeks."
For further information please contact:
| Nativo Resources Stephen Birrell, Chief Executive Officer |
Via Vigo Consulting [email protected] |
| Zeus (Nominated Adviser and Joint Broker) James Joyce James Bavister |
Tel: +44 (0)20 3829 5000 |
| AlbR Capital Limited (Joint Broker) Duncan Vasey Lucy Williams Rose Greensmith |
Tel: +44 (0)20 7469 0930 |
| Vigo Consulting (Investor Relations) Ben Simons Peter Jacob Anna Sutton |
Tel: +44 (0)20 7390 0234 [email protected] |
About Nativo Resources Plc
Nativo has interests in gold projects in Peru. The Company's strategy is based on three core activities: primary gold mining, gold ore processing, and the recovery of gold from tailings. The Company has already acquired or optioned several projects for development and has identified additional opportunities for expansion. Nativo's nearest-term objective is to scale operations on the Tesoro Gold Concession, focusing on the Bonanza and Morrocota mines. Nativo intends to allocate portions of free cash flow from mining and processing activities and future fundraises to Bitcoin purchases, and to hold Bitcoin as a long-term treasury reserve asset.
Follow us on social media:
LinkedIn: https://uk.linkedin.com/company/nativoresources-plc
X (Twitter): https://x.com/nativoresources
This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact [email protected] or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
END
UPDFFFFFLVLTLIE
Have a question? We'll get back to you promptly.