Earnings Release • Oct 22, 2025
Earnings Release
Open in ViewerOpens in native device viewer

The following report contains preliminary monthly data – the final quarterly production and sales results will be published in the consolidated report for the third quarter of 2025. Data of the KGHM Polska Miedź S.A. Group contain the results of Sierra Gorda S.C.M. reflecting the 55% share held by KGHM Polska Miedź S.A.
| Production and sales of the KGHM Group |
September 2025 |
September 2024 |
I - IX 2025 |
I - IX 2024 |
|
|---|---|---|---|---|---|
| Production | |||||
| Payable copper (kt) | 60.1 | 61.4 | 526.4 | 543.8 | |
| - including KGHM Polska Miedź S.A.* | 48.7 | 48.6 | 421.0 | 441.2 | |
| Payable silver (t) | 84.8 | 113.0 | 993.0 | 981.1 | |
| TPM (koz t) | 8.5 | 16.2 | 119.1 | 126.8 | |
| Molybdenum (mn lb) | 0.6 | 0.4 | 4.1 | 2.1 | |
| Sales | |||||
| Copper (kt) | 60.3 | 65.6 | 528.2 | 544.6 | |
| Silver (t) | 104.9 | 115.5 | 1 008.3 | 1 020.2 | |
| TPM (koz t) | 10.4 | 13.3 | 122.7 | 128.9 | |
| Molybdenum (mn lb) | 0.8 | 0.3 | 3.3 | 2.4 |
* Production of electrolytic copper
In the period January-September 2025 the copper production plan was in line with the budget target, while silver and TPM production was above the budget targets.
| Production and sales of KGHM Polska Miedź S.A. |
September 2025 |
September 2024 |
I - IX 2025 |
I - IX 2024 |
||
|---|---|---|---|---|---|---|
| Mine production | ||||||
| Copper in concentrate (kt) | 36.1 | 30.9 | 304.7 | 304.1 | ||
| Silver in concentrate (t) | 115.4 | 100.9 | 996.1 | 1 002.5 | ||
| Metallurgical production | ||||||
| Electrolytic copper (kt) | 48.7 | 48.6 | 421.0 | 441.2 | ||
| - including from own concentrate | 31.8 | 27.8 | 280.1 | 284.2 | ||
| Metallic silver (t) | 82.5 | 110.9 | 976.1 | 962.6 | ||
| TPM (koz t) | 2.9 | 8.1 | 62.4 | 64.3 | ||
| Sales | ||||||
| Copper (kt) | 47.5 | 52.9 | 425.1 | 446.6 | ||
| Silver (t) | 102.1 | 113.2 | 988.2 | 1 000.0 | ||
| TPM (koz t) | 4.6 | 6.2 | 66.7 | 70.7 |
| Production and sales of KGHM INTERNATIONAL LTD. |
September 2025 |
September 2024 |
I - IX 2025 |
I - IX 2024 |
|---|---|---|---|---|
| Production | ||||
| Payable copper (kt) | 3.1 | 5.0 | 40.6 | 45.5 |
| TPM (koz t) | 2.7 | 4.2 | 34.3 | 39.4 |
| Sales | ||||
| Copper (kt) | 3.3 | 4.0 | 39.3 | 41.3 |
| TPM (koz t) | 2.5 | 2.9 | 33.7 | 35.2 |
| Silver (t) | 0.1 | 0.0 | 3.7 | 2.6 |
| Production and sales of Sierra Gorda S.C.M. (on a 55% basis) |
September 2025 |
September 2024 |
I - IX 2025 |
I - IX 2024 |
|
|---|---|---|---|---|---|
| Production | |||||
| Payable copper (kt) | 8.3 | 7.7 | 64.9 | 57.1 | |
| Molybdenum (mn lbs) | 0.6 | 0.4 | 4.0 | 2.0 | |
| Payable silver (t) | 2.3 | 2.0 | 16.8 | 17.6 | |
| TPM (koz t) | 2.9 | 4.0 | 22.4 | 23.1 | |
| Sales | |||||
| Copper (kt) | 9.6 | 8.8 | 63.8 | 56,7 | |
| Molybdenum (mn lbs) | 0.8 | 0.3 | 3.2 | 2.2 | |
| Silver (t) | 2.7 | 2.3 | 16.5 | 17.6 | |
| TPM (koz t) | 3.2 | 4.1 | 22.2 | 23.0 |