Aydem Renewables Investor Presentation 2023 Full-Year Results

2 | Aydem Renewables, Investor Presentation 2023 Full-Year Results
The data in the presentation are taken from the financial statements prepared in accordance with TFRS. Note: In accordance with TAS 29, inflation accounting is applied on the presented figures as at the end of 2023 and 2022.




Outlook




Sustainable Value-Creating Business Model


1 According to the installed capacity of renewable energy generation 2 73% (619.9 MW) of the installed capacity of hydroelectric power plants consists of <river type= HPPs and 27% (232.2 MW) consists of HPPs with <reservoir<. Note: In accordance with TAS 29, inflation accounting is applied on the presented figures as at the end of 2023 and 2022.

Resilient Business Model
100% Green energy
78% USD-linked FIT eligible generation
Geographically diverse
New and modern assets
Investments supporting
portfolio diversity
(January 1, 2023 – December 31, 2023)
EBITDA
82%
EBITDA Margin
-24%
EBITDA Change (2023 vs. 2022)

Source: IMF, TEIAS, Central Bank of Republic of Turkey, Turkish Statistical Institute, IEA






| HPP and WPP | 73 |
|---|---|
| GPP | 105 |
| SPP | 133 |
| MODEL | ||
|---|---|---|
| 1 | |||
|---|---|---|---|


Source: General Directorate of Meteorology




Wind



Kırklareli WPP and Storage Generation Plant
Aydın Hybrid SPP WPP Capacity Increase Hybrid Channel SPP

Muğla Hybrid Floating SPP

Denizli Hybrid Floating SPP
Adana Hybrid Floating SPP
Şanlıurfa SPP and Storage Generation Plant
Sivas Hybrid SPP
Tokat Hybrid SPP
Uşak Hybrid SPP WPP Capacity Increase
Yalova Hybrid SPP WPP Capacity Increase
Hydroelectric

Geothermal Wind
Solar
| Total Installed Capacity 1.180 MW |
Total Installed Capacity 1.216 MW |
Total Installed Capacity 1.692 MW |
Total Installed Capacity 1.893 MW |
|---|---|---|---|
| 852.1 MW 72.2% |
852.1 MW 70.1% |
852.1 MW 50.4% |
852.1 MW 45.0% |
| 6.9 MW 0.6% |
6.9 MW 0.6% |
6.9 MW 0.4% |
6.9 MW 0.3% |
| 7.0% 238.5 MW 20.2% |
274.5 MW 22.6% |
277.5 MW 16.4% |
423.5 MW 22.4% |
| 82.2 MW | 82.2 MW 6.8% |
||
| 555.2 MW 32.8% |
610.9 MW 32.3% |
||
| 400 MWh | |||
| 100 MWh | |||
| Storage Battery Facility | Storage Battery Facility |

160.5 MW
15.7%
6.9 MW
0.7%
852.1 MW
83.6%
Capacity
1.020 MW
| Hybrid SPP | 82.2 | 2023 | * Operational. |
||||
|---|---|---|---|---|---|---|---|
| ON-LAND (159.6 MW) (76%) |
Hybrid SPP | 41.6 | 2025 | ||||
| Hybrid SPP Investments |
Hybrid SPP | 35.8 | 2026 | Installed Capacity | |||
| Total Planned | (210.8 MW) | Hybrid Canal SPP | 0.3 | 2025 | |||
| Investments | (24%) | FLOATING (51.2 MW) |
Hybrid Floating SPP | 31.1 | 2025 | 1,893 MW | |
| (2023-2026) | (24%) | Hybrid Floating SPP | 19.8 | 2026 | + | ||
| 873 MW | Capacity Increase Investments (163 MW) (19%) |
Capacity Increase | 78.0 | 2023 | * Operational. |
Storage | |
| + | WPP (163 MW) (100%) |
Capacity Increase | 36.0 | 2024 | Battery Facility | ||
| Storage | Capacity Increase | 3.0 | 2025 | 500 MWh | |||
| Battery Facility | Capacity Increase | 46.0 | 2026 | ||||
| 500 MWh | Storage Battery Facility |
SPP (400 MW) (80%) |
SPP and Storage Generation Plant |
400.0 | 2025 | BY 31.12.2026 | |
| Investments (500 MW) (57%) |
SPP (100 MW) (20%) |
SPP and Storage Generation Plant |
100.0 | 2026 | |||

* In 2023 160 MW of installed capacity already commissioned. Note: Planned COD dates depend on the timing of required permits and approvals.





1Göktaş I, Adıgüzel, and Kemer power plants benefit directly from the reservoir. 2Göktaş II, Dalaman I-V, Bereket I-II, Feslek, Koyulhisar, Mentaş, and Akıncı power plants benefit indirectly from the reservoir.
Note: In accordance with TAS 29, inflation accounting is applied on the presented figures as at the end of 2023 and 2022.
Power Plants

Debt/EBITDA

x x of total assets 31/12/2023 Strong Balance Sheet Structure (31 December 2023) 31/12/2023



*Including ancillary revenues Note: In accordance with TAS 29, inflation accounting is applied on the presented figures as at the end of 2023 and 2022.


As of February 2, 2023 and August 2, 2023 in order to be transferred into the related investors' accounts, a total of USD 53.4 mn has been paid as the payments of coupons with regard to our Company's USD 750 mn 5.5 year maturity bonds.


Within the scope of our Board of Directors' buyback decision on May 11, 2022 our Company purchased Eurobonds (XS2368781477) with a nominal value of USD 26,104,000 between January 1, 2023 and March 15, 2024.



Within the scope of share buy-back transactions initiated with the resolution of Board of Directors dated February 14, 2022; between the dates of January 1, 2023 and March 15, 2024, a total of 6,105,026 shares were bought back.
As of report date, the number of employees is 567.



Note: In accordance with TAS 29, inflation accounting is applied on the presented figures as at the end of 2023 and 2022.

ANNEX 1 Summary Consolidated Tables (TFRS) ANNEX 2 Awards and Achievements in 2023 ANNEX 3 Plant Based Production ANNEX 4 Developments - Subsequent Period ANNEX 5 Total Installed Capacity – Detailed ANNEX 6 YoungPortfolio With Long RemainingContractedAsset Life

| 31 December 2023 |
31 December 2022 | |
|---|---|---|
| Current Assets | 4,738 | 5,040 |
| Non-Current Assets | 50,868 | 54,749 |
| Current Liabilities | 2,087 | 2,633 |
| Non-Current Liabilities | 24,899 | 27,833 |
| Equity | 28,621 | 29,322 |


| 31 December 2023 | 31 December 2022 | |
|---|---|---|
| Cost of Sales | (3,611) | (3,377) |
| General Administrative Expenses | (632) | (349) |
| Other Operating Income, Net | 941 | 876 |
| Depreciation and Amortization Expenses | 2,130 | 2,148 |
| Expenses from Investment Activities, Net |
(3,358) | (4,942) |
| Financial Expenses, Net | (12,150) | (2,946) |
| Monetary Gain/(Loss) | 14,307 | 13,271 |
| Tax Income/(Expense) | (3,137) | (5,126) |
ANNEXES


Turkey's largest company producing energy from 100% renewable sources as Aydem Renewables, we started to be traded in the BIST Sustainability Index, where international sustainability performance is evaluated!
In the 2023 International Occupational Safety Awards evaluation of the British Safety Council, one of the most respected institutions in the world in Occupational Health and Safety, within the first year of participation, Aydem Renewables was awarded the highest degree 8Distinction9 with 51 points!
As of April 7, 2023, among the BIST Electricity Index companies, we are the company with the Highest Degree of Compliance with Corporate Governance Principles! (9.56 out of 10 full points)
We put into operation Türkiye9s largest hybrid solar power plant (82.15 MW - Uşak WPP Hybrid SPP)!
As Aydem Renewables, we won the carbon hero award for the fourth time!
2023 evaluation where 54 companies from Türkiye participated in CDP Water Safety category, and 114 companies from Türkiye participated in Climate Change category, our Company became the first and only energy company in our country to be among the global leaders by scoring <A= in the Climate Change and Water Security categories two years in a row!

At the LACP Vision Awards 2022 organized by LACP, we were deemed worthy of the PLATINUM award in our Annual Report 2022 and Sustainability Report 2022!

| Plant Name | 2020 | 2020 | 2020 | 2020 | 2021 | 2021 | 2021 | 2021 | 2022 | 2022 | 2022 | 2022 | 2023 | 2023 | 2023 | 2023 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| (GWh) | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual | Actual |
| Q1-YTD | Q2-YTD | Q3-YTD | Q4-YTD | Q1-YTD | Q2-YTD | Q3-YTD | Q4-YTD | Q1-YTD | Q2-YTD | Q3-YTD | Q4-YTD | Q1-YTD | Q2-YTD | Q3-YTD | Q4-YTD | |
| Bereket I-II HPP | 5 | 6 | 8 | 10 | 4 | 5 | 6 | 8 | 4 | 6 | 6 | 9 | 4 | 6 | 7 | 10 |
| Feslek HPP |
5 | 6 | 7 | 9 | 4 | 5 | 7 | 8 | 5 | 5 | 5 | 6 | 3 | 5 | 5 | 6 |
| Dalaman HPP |
23 | 50 | 72 | 75 | 15 | 45 | 63 | 66 | 31 | 60 | 83 | 86 | 2 | 27 | 54 | 61 |
| Gökyar HPP |
9 | 14 | 16 | 20 | 9 | 12 | 14 | 19 | 12 | 18 | 20 | 25 | 6 | 12 | 14 | 20 |
| Mentaş HPP |
39 | 70 | 87 | 101 | 27 | 48 | 66 | 77 | 43 | 60 | 78 | 90 | 19 | 45 | 59 | 78 |
| Koyulhisar HPP |
3 | 58 | 132 | 177 | 12 | 47 | 95 | 101 | 38 | 76 | 143 | 197 | 27 | 97 | 171 | 244 |
| Toros HPP | 83 | 188 | 217 | 231 | 27 | 74 | 81 | 94 | 75 | 174 | 196 | 207 | 19 | 84 | 99 | 114 |
| Aksu HPP | 40 | 79 | 81 | 82 | 17 | 59 | 73 | 96 | 30 | 82 | 90 | 103 | 33 | 74 | 86 | 112 |
| Kemer HPP |
0 | 19 | 57 | 57 | 0 | 14 | 35 | 35 | 10 | 35 | 92 | 92 | 0 | 4 | 37 | 37 |
| Adıgüzel HPP |
0 | 25 | 29 | 29 | 0 | 5 | 4 | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Çırakdamı HPP |
32 | 92 | 96 | 100 | 12 | 56 | 62 | 78 | 18 | 90 | 99 | 113 | 26 | 112 | 124 | 132 |
| Dereli HPP |
27 | 93 | 97 | 99 | 9 | 54 | 61 | 76 | 15 | 92 | 100 | 111 | 27 | 120 | 131 | 138 |
| Söke WPP |
48 | 81 | 124 | 157 | 47 | 90 | 136 | 177 | 50 | 91 | 137 | 176 | 41 | 77 | 114 | 152 |
| WPP Uşak |
49 | 72 | 102 | 131 | 46 | 79 | 111 | 154 | 38 | 69 | 110 | 156 | 43 | 95 | 187 | 268 |
| Yalova WPP | 42 | 70 | 115 | 150 | 45 | 70 | 108 | 152 | 37 | 65 | 103 | 143 | 33 | 55 | 97 | 140 |
| GPP Kızıldere |
0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| HPP Akıncı |
89 | 180 | 288 | 362 | 29 | 92 | 165 | 177 | 68 | 139 | 238 | 317 | 50 | 193 | 308 | 420 |
| 1 HPP Göktaş |
106 | 248 | 316 | 363 | 67 | 128 | 162 | 201 | 78 | 168 | 223 | 272 | 40 | 102 | 148 | 193 |
| 2 HPP Göktaş |
142 | 327 | 417 | 417 | 90 | 172 | 218 | 270 | 109 | 229 | 303 | 368 | 53 | 138 | 200 | 260 |
| Total | 742 | 1,680 | 2,261 | 2,636 | 457 | 1,053 | 1,467 | 1,793 | 661 | 1,457 | 2,024 | 2,469 | 421 | 1,241 | 1,837 | 2,380 |

• As of 02.02.2024, in order to be transferred into the related investors' accounts, USD 26.121.646,25 has been paid as the payment of fifth coupons with regard to our Company's USD 750 million 5.5 year
• As stated in our Company's public disclosure dated 18.05.2023, it was publicly disclosed that our pre-license application for a total capacity of 500 MW (200 MW Keberli SPP, 200 MW Güzelkuyu SPP and 100 MW Kızılağaç WPP), including 400 MW SPP and 100 MW WPP, for storage generation facilities through Sarı Perakende Enerji Satış ve Tic. A.Ş, a 100% subsidiary of our Company, was accepted. In this process, revisions were made to the SPP projects site coordinates of our prelicensed projects belonging to our Sarı Perakende Enerji Satış ve Tic. A.Ş. company. On 03.08.2023, a project area change application was made to EMRA for the Keberli SPP project area, for which an EIA application was made on 03.08.2023, due to the planning of housing, trade and social reinforcement etc. construction within the scope of the Kahramanmaraş earthquake dated February 6, 2023, in accordance with the letter dated 18.08.2023 and numbered 466747 of the Mass Housing Administration of the Ministry of Environment, Urbanization and Climate Change of the Republic of Turkey. With the board decision dated 08.02.2024 and numbered 12428-6 by EMRA, it was found appropriate to change the district of the production facility from Eyyübiye to Halfeti. On 08.08.2023, a project site change application was made to EMRA due to the overlap of the Güzelkuyu SPP project area, for which an EIA application was made on 08.08.2023, with the Şanlıurfa OIZ additional area finalized on 16.08.2023, as stated in the letter of the Ministry of Industry and Technology dated 18.08.2023 and numbered 4989435. With the board decision dated 25.01.2024 and numbered 12401-8 by EMRA, it was found appropriate to change the production facility district

2River Type HPPs are Gökyar HPP, Dalaman 1-5 HPP, Mentaş HPP, Aksu HPP, Akıncı HPP, Dereli HPP, Çırakdamı HPP, Feslek HPP, Bereket 1-2 HPP, Koyulhisar HPP, Toros HPP and Göktaş 2 HPP. HPPs with reservoir are Kemer HPP, Adıgüzel HPP and Göktaş 1 HPP 3 Run-rate Generation for a period has been prepared using (i) historical long-term hydrological data between 1970 and 2016 on a basin-by-basin basis (including one-off outages) for HPPs, and (ii) a combination of historical performance (including one-off outages) and historical long-term wind data, in each case
Source: Company Data 1 61.5 MW portion is subject to YEKDEM (except for capacity increase) generation in order to project the average annual total energy production 4 45.0 MW portion is subject to YEKDEM (except for capacity increase)
| PROJECT NAME | INSTALLED CAPACITY (MWm) | ANNUAL RUN-RATE3 GENERATION CAPACITY (MWh) | LOCATION | END OF LICENSE DATE | END OF FIT (YEKDEM) | |
|---|---|---|---|---|---|---|
| Bereket 1-2 HPP |
Denizli /Honaz | 18.11.2036 | ||||
| Dalaman 1-2-3-4-5 HPP |
Muğla / Dalaman | 18.11.2039 | ||||
| Feslek HPP |
Aydın / Kurtuluş | 18.11.2044 | ||||
| HPP Mentaş |
Adana / İmamoğlu | 18.11.2053 | ||||
| HPP Gökyar |
Muğla / Dalaman | 14.12.2044 | ||||
| Koyulhisar HPP |
Sivas / Koyulhisar | 10.02.2045 | ||||
| Aksu HPP Düzce |
Düzce / Gölyaka | 21.09.2055 | 31.12.2024 | |||
| HPP Adıgüzel |
Denizli / Güney | 05.05.2066 | ||||
| Kemer HPP |
Aydın / Bozdoğan | 05.05.2066 | ||||
| HPP Akıncı |
Tokat / Reşadiye | 12.04.2056 | 31.12.2028 | |||
| Toros HPP | Adana / Karaisalı | 18.01.2056 | ||||
| 1-2 HPP Göktaş |
Adana / Kozan, Aladağ | 14.12.2055 | 31.12.2025 | |||
| HPP Çırakdamı |
Giresun / Dereli | 14.09.2053 | ||||
| Dereli HPP |
Giresun / Dereli | 06.12.2053 | 31.12.2024 | |||
| WPP1 Uşak |
Uşak / Banaz | 08.07.2057 | 31.12.2024 | |||
| Yalova WPP |
Yalova / Armutlu | 08.07.2057 | 31.12.2026 | |||
| WPP4 Söke |
/ Söke Aydın |
04.01.2061 | 31.12.2026 | |||
| GPP Kızıldere |
6.85 | Denizli / Sarayköy | 17.07.2052 | |||
| Hybrid SPP Uşak |
82.15 | 164.1 | / Banaz Uşak |
08.07.2057 | 31.12.2024 | |


| Remaining license life1 Years | ||||||
|---|---|---|---|---|---|---|
| Adiguzel (62.0 MW) |
42.4 | 9 years | ||||
| Kemer (48.0 MW) |
42.4 | Wind plants average | ||||
| Soke (57.0 MW) |
37.0 | age since COD | ||||
| Usak-SSP (82.2 MW) | 33.5 | |||||
| Usak (127.5 MW) |
33.5 | |||||
| Yalova (54.0 MW) |
33.5 | 34 years | ||||
| Akinci (99.0 MW) | 32.3 | Wind plants average | ||||
| Toros (50.0 MW) |
32.1 | remaining license life | ||||
| Goktas I-II (275.6 MW) |
32.0 | |||||
| Aksu (46.2 MW) | 31.7 | 10 years | ||||
| Dereli (49.2 MW) |
30.0 | Hydro plants average | ||||
| Mentas (49.6 MW) |
29.9 | age since COD2 | ||||
| Cirakdami (49.1 MW) |
29.7 | |||||
| Saraykoy - Kizildere (6.9 MW) |
28.6 | |||||
| Koyulhisar (63.0 MW) |
21.1 | 31 years | ||||
| Gokyar (11.0 MW) |
21.0 | Hydro plants average remaining license life |
||||
| Feslek (8.8 MW) |
20.9 | |||||
| Dalaman I-V (37.5 MW) |
15.9 | |||||
| Bereket I-II (3.2 MW) | 12.9 |


Source: Company Data 1As of 31 December 2023
2Weighted average of life time weighted by installed capacity for own-built plants, calculated as of 31 December 2023 (excluding Adiguzel and Kemer hydro plants acquired through privatisation)
3FiT expiry date as of year-end


24 | Aydem Renewables, Investor Presentation 2023 Full-Year Results
Mehmet Yusuf Güngör, CPA Investor Relations Manager
Tel : +90 258 242 27 76 [email protected] www.aydemyenilenebilir.com.tr/investorrelations
Adalet Mahallesi Hasan Gönüllü Bulvarı No:15/1 Merkezefendi / Denizli - Türkiye
https://www.aydemyenilenebilir.com.tr/en



All of the information and data in this presentation were prepared only to provide information and contain forward-looking statements that reflect the current views of the Company management regarding certain future events. Expectations and predictions in these statements are believed to be reasonable but are based on a number of assumptions. Various changes and variables that may occur in line with these assumptions may cause significantly different actual results compared to those predicted.
Nevertheless, Aydem Renewables makes no claims or guarantees about the accuracy or completeness of the information contained in this Report. The information contained in this presentation can be changed without notice.
Information contained in this presentation does not constitute an invitation to buy/sell Aydem Renewable shares and is not investment advice. This presentation and the information contained in this presentation cannot be reproduced, disclosed, or distributed without permission. Aydem Yenilenebilir Enerji A.Ş. assumes no responsibility or liability regarding any statement, express or implied, or incomplete information contained in this presentation, or other written and oral communications shared or made available. Aydem Renewables or its executives, managers, employees, or third parties may not, in any way, be held liable for any damage which may arise from the use of the information contained herein.