ANGUS ENERGY PLC

Business and Financial Review Aug 11, 2020

7487_rns_2020-08-11_5ea1753c-65a4-432e-a965-26f48cb67070.html

Business and Financial Review

Open in Viewer

Opens in native device viewer

National Storage Mechanism | Additional information

RNS Number : 7063V

Angus Energy PLC

11 August 2020

THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION FOR THE PURPOSES OF THE MARKET ABUSE REGULATION (EU No. 596/2014) ("MAR"). THIS INSIDE INFORMATION IS NOW CONSIDERED TO BE IN THE PUBLIC DOMAIN.

11 August 2020

Angus Energy Plc

("Angus Energy" or the "Company")

Saltfleetby Pipeline Timetable

Angus Energy (AIM: ANGS) is pleased to update shareholders on the timetable of actions necessary to complete the pipeline installation.  These timings represent best estimates.

Deliverable Status Start Date End Date
Land/Leasing/Wayleaves Near Completion 01/05/2020 31/08/2020
Conceptual and Detailed Design Completed 04/05/2020 31/07/2020
Tendering and Procurement Near Completion 04/05/2020 31/08/2020
HSE Compliance In Progress 22/05/2020 continuous
Council Planning Process Completed 25/05/2020 07/08/2020
Pre Construction In progress 30/06/2020 04/09/2020
Satisfaction of Planning Conditions In progress 10/08/2020 07/09/2020
Construction: HD Drilling and Trenching Imminent 07/09/2020 19/10/2020
Pigging Planned 01/10/2020 10/11/2020
Hydrostatic Testing Planned 19/10/2020 10/11/2020
Commissioning Planned 10/11/2020 Early 2021

In addition, under our Gas Construction Agreement, separate works are underway on the NTS Theddlethorpe Entry Point under the direction of National Grid.   We are advised that they are following their timetable closely.  Final commissioning is subject to completion of site works.

Saltfleetby Pipeline National Grid Component

Deliverable Start Date Duration End Date
Pre-Construction 24/06/2020 44 Days 24/08/2020
Off Site Fabrication 28/07/2020 47 Days 01/10/2020
Construction Works 24/08/2020 68 Days 26/11/2020
Pipework Installation 09/09/2020 33 Days 23/10/2020
E&I Installation 07/10/2020 30 Days 17/11/2020
Commissioning 26/10/2020 24 Days 26/11/2020
Site Demobilisation 05/11/2020 4 Days 10/11/2020

END.

Enquiries:

Angus Energy Plc www.angusenergy.co.uk
George Lucan Tel: +44 (0) 208 899 6380
Beaumont Cornish (Nomad) www.beaumontcornish.com
James Biddle/ Roland Cornish Tel: +44 (0) 207 628 3396
WH Ireland Limited (Broker)
Katy Mitchell/ Harry Ansell Tel: +44 (0) 113 394 6600
Flagstaff PR/IR [email protected]
Tim Thompson Tel: +44 (0) 207 129 1474
Fergus Mellon

Notes

About Angus Energy plc. Angus Energy plc. is a UK AIM quoted independent onshore oil and gas production and development company focused on leveraging its expertise to advance its portfolio of UK assets as well as acquire, manage and monetise select projects. Angus Energy majority owns and operates conventional oil production fields at Brockham (PL 235) and Lidsey (PL 241) and has a 25% interest in the Balcombe Licence (PEDL244) and a 12.5% interest in the PEDL143 Licence (A24 Prospect) and a 51% interest in the Saltfleetby Gas Field (PEDL005).

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact [email protected] or visit www.rns.com.