Current report in compliance with the Law 24/2017 on issuers of financial instruments and market operations, ASF Regulation no. 5/2018, and the Bucharest Stock Exchange Code
Report date: 27 October 2021
Company name: Societatea Energetica Electrica S.A. (Electrica)
Headquarters: 9 Grigore Alexandrescu Street, 1st District, Bucharest, Romania
Phone/fax no.: 004-021-2085999/ 004-021-2085998
Fiscal Code: RO 13267221
Trade Register registration number: J40/7425/2000
Subscribed and paid in share capital: RON 3,464,435,970
Regulated market where the issued securities are traded: Bucharest Stock Exchange (BVB) and London Stock Exchange (LSE)
Significant events to be reported: Transactions with related parties according to Art. 108 of Law No. 24/2017 concluded by Electrica Furnizare SA (EFSA), subsidiary of Societatea Energetica Electrica SA (Electrica), with Societatea Nationala Nuclearelectrica S.A. (SNN)
Electrica informs its shareholders and investors about the conclusion, on 26 October 2021, of several transactions between EFSA, Electrica's subsidiary, and SNN, that has a value that, cumulated with the rest of the transactions concluded/executed in the period 6 August – 26 October 2021, exceeds the threshold of 5% of Electrica's net assets, according to Electrica's individual financial statements for 2020, respectively exceeds the value of RON 202,466,778.
Details regarding the transactions concluded on 26 October 2021, together with the rest of the transactions already concluded in the period 6 August – 26 October 2021, containing information about the date of execution, type of transaction, description of its scope, total value of the transaction, expiry date, mutual debts and receivables, guarantees, penalties, payment due dates and methods are presented in Annex 1.
CEO Georgeta Corina Popescu
| Agreement Type and No., execution date |
Scope of the transactions |
Amount of transactions |
Date of entry into force |
Expiry date | Guarantees (RON th.) |
Penalties | Payment due dates and payment methods |
||
|---|---|---|---|---|---|---|---|---|---|
| Buyer: EFSA Seller: SNN |
|||||||||
| Transaction ID 40404 / 6 Sept 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
20,367.00 | 6 September 2021 |
31 December 2021 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not (10th) later than the tenth calendar day of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
||
| Transaction ID 40405 / 6 Sept 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
20,367.00 | 6 September 2021 |
31 December 2021 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
||
| Transaction ID 40430 / 13 Sept 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
21,724.80 | 13 September 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of |
| 04 Nov 2019, concluded on PC OTC |
basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
||||
|---|---|---|---|---|---|---|---|
| Transaction ID 40437 / 13 Sept 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
22,776.00 | 13 September 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
| Transaction ID 40445 / 13 Sept 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
13,928.40 | 13 September 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
| Transaction ID 40552 / 12 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
10,249.20 | 12 October 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of |
| 04 Nov 2019, concluded on PC OTC |
basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
||||
|---|---|---|---|---|---|---|---|
| Transaction ID 40560 / 12 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.07.2022 – 31.12.2022 |
12,478.03 | 12 October 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
| Transaction ID 40573 / 12 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.01.2022 – 31.03.2022 |
10,687.05 | 12 October 2021 |
31 March 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
| Transaction ID 40589/ 12 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / |
Sell and purchase of electricity in the period 01.07.2022 – 31.12.2022 |
15,238.65 | 12 October 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of |
| 04 Nov 2019, concluded on PC OTC |
basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
||||
|---|---|---|---|---|---|---|---|
| Transaction ID 40591 / 12 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.07.2022 – 31.12.2022 |
15,238.65 | 12 October 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
| Transaction ID 40592 / 12 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / 04 Nov 2019, concluded on PC OTC |
Sell and purchase of electricity in the period 01.01.2022 – 31.03.2022 |
14,195.43 | 12 October 2021 |
31 March 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the basis of the EFET contract no. 1561 between 04.02.2020 until 15.02.2022) |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of delay, starting with the first day after the due date, until the due date, inclusively. The invoice issued for the penalties due will become due within 5 calendar days from the issuance. |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of electricity delivered, according to the Schedule of delivery from the previous calendar month. Payment is made latest on the payment deadline written on the invoice, respectively not later than 20 calendar days from the date of receipt of the invoice, by fax or email, from the Seller. |
| Transaction ID 40645 / 26 Oct 2021, annex to EFET contract No. 1561/19 Dec 2018 and AD 1 / |
Sell and purchase of electricity in the period 01.01.2022 – 31.12.2022 |
29,039.40 | 26 October 2021 |
31 December 2022 |
40,000 (the guarantee is constituted in order to cover the transactions to be concluded on the |
In case of non-payment of the invoice on the due date, the Buyer will be obliged to pay delay penalties, in the amount of 0.03% of the amount due, for each day of |
Starting with the last calendar day of the contractual delivery month, but not later than the tenth calendar day (10th) of the month following deliveries, the Seller will send to the Buyer an invoice detailing the total quantities of |
| 04 Nov 2019, | basis of the EFET | delay, starting with the first | electricity delivered, according to the | ||||||
|---|---|---|---|---|---|---|---|---|---|
| concluded on PC | contract no. 1561 | day after the due date, until | Schedule of delivery from the previous | ||||||
| OTC | between | the due date, inclusively. | calendar month. Payment is made | ||||||
| 04.02.2020 until | The invoice issued for the | latest on the payment deadline written | |||||||
| 15.02.2022) | penalties due will become | on the invoice, respectively not later | |||||||
| due within 5 calendar days | than 20 calendar days from the date of | ||||||||
| from the issuance. | receipt of the invoice, by fax or email, | ||||||||
| from the Seller. | |||||||||
| 40,000 | In case of non-payment of the invoice on the due date, |
Starting with the last calendar day of the contractual delivery month, but not |
|||||||
| Transaction ID | (the guarantee is | the Buyer will be obliged to | later than the tenth calendar day (10th) | ||||||
| 40669 / 26 Oct |
constituted in order | pay delay penalties, in the amount of 0.03% of the |
of the month following deliveries, the Seller will send to the Buyer an invoice |
||||||
| 2021, annex to | Sell and purchase | to cover the | amount due, for each day of | detailing the total quantities of |
|||||
| EFET contract | of electricity in the |
26 October | 31 March | transactions to be | delay, starting with the first | electricity delivered, according to the | |||
| No. 1561/19 Dec | period 01.01.2022 | 11,334.75 | 2021 | 2022 | concluded on the | day after the due date, until | Schedule of delivery from the previous | ||
| 2018 and AD 1 / |
– 31.03.2022 |
basis of the EFET | the due date, inclusively. | calendar month. Payment is made | |||||
| 04 Nov 2019, | contract no. 1561 | The invoice issued for the | latest on the payment deadline written | ||||||
| concluded on PC | between | penalties due will become | on the invoice, respectively not later | ||||||
| OTC | 04.02.2020 until 15.02.2022) |
due within 5 calendar days | than 20 calendar days from the date of | ||||||
| from the issuance. | receipt of the invoice, by fax or email, | ||||||||
| from the Seller. | |||||||||
| Beneficiary: SNN | |||||||||
| Provider: EFSA | |||||||||
| If the payer does not pay the | |||||||||
| Re-invoicing – | During the | value of the invoice within | The Provider issues the invoice to the | ||||||
| pensioners energy | period GD | 30 days from the due date, | Beneficiary until the 16th of the month | ||||||
| Contract 294 / 23 | quota Equivalent value of |
1041/2003 is | he owes the provider penalties equal to the level |
following each month in which the | |||||
| Aug 2004 | electricity granted | 23 August | in force, as it | of interest charged for late | electricity was invoiced to the |
||||
| Contract R507 / | to individuals | 21.93 | 2004 | was | N/A | payment of debts to the | pensioners, called the reference month. | ||
| 01 Aug 2011 |
benefiting from the | completed | state budget, for each day of | The payment of the invoice value will | |||||
| AA 9 / 22.07.2021 | provisions of | and modified | delay, starting with the first | be made by legal means, within the | |||||
| GD.1041/2003 and | by GD | day after maturity and until | maturity of 30 calendar days from the | ||||||
| GD.1461/2003 | 1461/2003 | full payment, including the | date of issue. | ||||||
| day of payment. |
Total executed amount during 6 August – 26 October 2021: RON 217,646.29 th Due and not due mutual receivables of EFSA to SNN at 25.10.2021: RON 6.60 th. Due and not due mutual debts of EFSA to SNN at 25.10.2021: 0 th