Earnings Release • Nov 4, 2015
Earnings Release
Open in ViewerOpens in native device viewer
Third Quarter results 2015
Det norske oljeselskap ASA reported revenues of USD 281 million in the third
quarter of 2015. Production in the period was 62 806 barrels of oil equivalent
per day, realising an average oil price of USD 52 per barrel.
In October, the company announced the acquisition of Svenska Petroleum's
Norwegian subsidiary. The acquisition increases the company's ownership in
attractive discoveries with resource upside potential and fit well into the
existing portfolio.
"The Svenska acquisition reflects our continued strong belief in the Norwegian
Continental Shelf. The transaction indicates a willingness to take further steps
to build Det norske", says CEO Karl Johnny Hersvik.
EBITDA amounted to USD 225 (-62) million in the quarter and EBIT was USD -91 (
-90) million, following an impairment of USD 186 (0) million in the quarter. Net
loss for the quarter were USD 166 (17) million, translating into an EPS of USD
-0.82 (-0.09). Net interest-bearing debt amounted to USD 2,147 (529) million per
September 30, 2015.
"With available liquidity of about USD 1.7 billion, the company has a robust
financing in place and has secured funding for its work program until first oil
at Johan Sverdrup", Hersvik says.
During the third quarter, the company has also been actively preparing for the
upcoming 23rdlicensing round by assessing the opportunities in the Barents Sea.
Production
Det norske produced 5.8 (0.2) million barrels of oil equivalents ("mmboe") in
the third quarter of 2015. This corresponds to 62.8 (2.3) mboepd. The average
realized oil price was USD 52 (104) per barrel, while gas revenues were
recognized at market value of USD 0.26 (0.28) per standard cubic metre (scm).
The production efficiency for the Alvheim FPSO in the third quarter was 98.1
percent, which is higher than in the second quarter and above target for the
quarter. Production efficiency for the first nine months is 96.6 percent, which
is also well above the target.
Bøyla M2 was started up in early August, marking the completion of the project
phase for the Bøyla field development. The drilling rig Transocean Winner
completed the Kneler K6 IOR well mid-September. Production is expected to
commence in November this year from the well once it has been connected up to
the Kneler A production manifold. Production from BoaKamNorth is expected to
commence in the middle of 2016. Drilling of the two production wells on Viper
-Cobra is scheduled to start towards the end of Q1 2016 with first oil expected
at the end of 2016.
Ivar Aasen
Key activities for the Ivar Aasen project are progressing according to plan with
first oil planned for Q4 2016. Pre-drilling of production wells commenced mid
-July with batch setting of five deep set conductors. The Maersk Interceptor
jack-up rig has performed very well, and the drilling program is progressing
ahead of schedule. Laying of pipelines between Ivar Aasen and Edvard Grieg
commenced in July. By the end of the third quarter, all three pipelines between
Ivar Aasen and Edvard Grieg have successfully been installed and tested. The
subsea and pipeline offshore activity planned for this year is expected to be
finalised early November.
Topside construction in Singapore is progressing well, and is about 85 percent
complete. Pipe fabrication and installation is ongoing and piping insulation has
commenced. Cable pulling and termination is progressing well. A handover of
first priority sub systems to Det norske commissioning team commenced in
September. The construction of the living quarters at Stord in Norway is
progressing according to plan. In October, the helideck was delivered to site,
assembled and lifted in place.
Johan Sverdrup
In September, the operator presented an update of the CAPEX estimate for the
first phase of the development to the partnership. The updated estimate is
showing reduced CAPEX as a result of positive market response in contracts and
purchase orders. In the PDO, CAPEX for the first phase development was estimated
at NOK 117 billion in real terms (NOK 2015) and NOK 123 billion in nominal
terms. Overall CAPEX for the first phase has been reduced by NOK 9 billion from
NOK 123 billion to NOK 114 billion in nominal terms, assuming the same currency
assumptions as in the PDO. The contingency level (in NOK) is maintained in the
updated estimate and reflects risks in scope, schedule and project execution.
The production is expected to commence in the fourth quarter 2019.
The Ministry of Petroleum and Energy announced on 2 July the apportionment of
the ownership interests in the Johan Sverdrup field. In the decision, Det norske
was attributed a total ownership interest in the Johan Sverdrup field of 11.5733
percent. Det norske filed a complaint regarding the decision made by the MPE to
the King in Council, as the highest level of the Norwegian administrative
authorities and is awaiting the outcome.
Find the Q3 2015 report and presentation attached. A live webcast is available
from 8:30 at our website, www.detnor.no/en.
Contacts:
Investor contact: Jonas Gamre, VP Investor Relations, tel.: 47 971 18 292
Media contact: Rolf Jarle Brøske, SVP Communications, tel.: 47 911 12 475
About Det norske:
Det norske is a fully-fledged E&P company with exploration, development and
production activities on the Norwegian Continental Shelf (NCS). We are building
one of Europe's largest independent E&P companies.
Det norske is the operator of the producing Alvheim field and for the Ivar Aasen
field development. In addition, the company is partner in the Johan Sverdrup
field. Det norske has an active exploration programme on the Norwegian shelf and
an ambitious strategy for growth.
Det norske's headquarters are located in Trondheim, with branch offices in
Stavanger, Oslo and Harstad. Det norske is listed on Oslo Børs with ticker
'DETNOR'. More about Det norske at www.detnor.no/en/.
This information is subject to disclosure requirements pursuant to section 5-12
of the Norwegian Securities Trading Act.
Building tools?
Free accounts include 100 API calls/year for testing.
Have a question? We'll get back to you promptly.