Regulatory Filings • Aug 21, 2024
Regulatory Filings
Open in ViewerOpens in native device viewer
Balder X project update
Sandnes, Norway, 21 August 2024: Vår Energi ASA (OSE: VAR) today provides a
schedule update for the Balder X development project. The target production
start has been moved to the second quarter 2025. As previously communicated, the
revised plan has limited impact on the Company's 2024 production and no material
impact on guided capital costs. The Company's end-2025 production target of
around 400 thousand barrels of oil equivalent per day (kboepd) is not affected
by the updated project start-up.
"A key consideration has been to limit the carryover work into the offshore
installation and start-up phase as much as possible. Together with our suppliers
we have made every effort to complete the final work on the Jotun FPSO at the
Rosenberg yard to enable field installation before the winter weather period.
However, despite recent good progress, some onshore completion and commissioning
work required prior to sail-away remains. Although achieving first oil by end of
the fourth quarter 2024 is no longer possible this has limited impact on 2024
production and our guidance of 280-300 kboepd for the year is maintained, says
CEO of Vår Energi, Nick Walker.
With all development wells completed and all subsea production systems
installed, the plan is now to complete the FPSO vessel fully onshore, enabling
first oil within the second quarter next year. As part of the decision not to
sail, the cost basis for the project has been updated reflecting a sail-away in
the spring of 2025, this represents an additional project cost of around USD 400
million gross pre-tax (NOK ~4.27 billion¹) of which approximately 75% will be
incurred in 2025. The Company's capital spend guidance for 2024 is revised down
from USD 2.7-2.9 billion to around USD 2.6 billion, reflecting other cost
reductions and a favourable NOK exchange rate. Vår Energi's production target
for 2025 remains unchanged and the Company is on track to reach around 400
kboepd by end of next year.
Balder X, will secure production from the Balder Area beyond 2045, unlocking
gross proved plus probable (2P) reserves of around 150 million barrels of oil
equivalent (mmboe) and with a gross peak production of 80 kboepd².
The Jotun FPSO will be an area host, enabling future growth opportunities.
Balder Phase V is being progressed, including the drilling of six production
wells to utilise the remaining subsea template well slots to capture gross 2P
reserves of more than 30 mmboe. Drilling of these wells will commence in the
first half of 2025 and be completed in 2026. In addition, the Balder Phase VI
project is being matured, to add new subsea facilities and wells, with expected
investment decision planned first half of 2025. There remains significant
additional resource upside in the area and further exploration drilling and tie
-back development phases are being planned.
Vår Energi is operator (90%) of the Balder Area with Kistos Energy (Norway) AS
as partner (10%).
1. USD/NOK of 10.67
2. Vår Energi 90% Working interest
About Vår Energi
Vår Energi is a leading independent upstream oil and gas company on the
Norwegian continental shelf (NCS). We are committed to deliver a better future
through responsible value driven growth based on over 50 years of NCS
operations, a robust and diversified asset portfolio with ongoing development
projects, and a strong exploration track record. Our ambition is to be the
safest operator on the NCS, the partner of choice, an ESG leader with a tangible
plan to reduce emissions from our operations by more than 50% within 2030. Vår
Energi has around 1400 employees and equity stakes in 47 fields. We have our
headquarters outside Stavanger, Norway, with offices in Oslo, Hammerfest and
Florø. To learn more, please visit varenergi.no
Contact
Investor relations
Ida Marie Fjellheim, Head of Investor Relations
+47 90509291
Media relations
Andreas Wulff, VP Public Relations
+47 92616759
This information is considered to be inside information pursuant to the EU
Market Abuse Regulation and is subject to the disclosure requirements pursuant
to Section 5-12 the Norwegian Securities Trading Act. This stock exchange
release was published by Ida Fjellheim, Head of Investor Relations at Vår Energi
ASA, on 21 August 2024 at 07:00 CET.
Building tools?
Free accounts include 100 API calls/year for testing.
Have a question? We'll get back to you promptly.