HydrogenPro ASA

Investor Presentation Nov 12, 2024

3627_rns_2024-11-12_4c36848d-1378-4071-928d-d05aa4818e29.pdf

Investor Presentation

Open in Viewer

Opens in native device viewer

Q3 2024 Presentation

12 November 2024

This presentation contains forward-looking statements and information, including assumptions, opinions and views of the Company or third-party sources, and are solely opinions and forecasts which are subject to risks, uncertainties and other factors that may cause actual results and events to be materially different from those expected or implied by the forwardlooking statements or information. The Company does not provide any assurance that the assumptions underlying such statements or information are free from errors nor accept any responsibility for the future accuracy of opinions expressed herein or as part of the Information, or the actual occurrence of forecasted developments.

Agenda

  • Quarterly highlights
  • › Financials

Q&A

Q3 2024 highlights

HydrogenPro delivers 2 of the 10 largest projects (excl. China) estimated to come online in 2025

(Electrolyser capacity MW p.a.)

Source: IEA "Hydrogen production projects" database

Awarded EUR 16.5m from EU Innovation Fund for planned GIGA project

CORE TECHNOLOGY DEVELOPED

  • Developed a unique Gen3 electrode technology during 10+ years from lab to industrial scale
  • Industry-leading performance

350MW PLANT UNDER CONSTRUCTION

  • A full-scale production line is currently under installation at the R&D centre in Denmark
  • Expected to be operational by Q1 2025 with 350 MW capacity annually

NEXT LEVEL: GIGA PROJECT

  • Awarded a grant from the EU Innovation Fund of EUR 16.5 million
  • Additionally, DKK 35 million awarded in May 2024 by the Export and Investment Fund of Denmark

2014-2024 20252012-2024 H2 2024 – Q1 2025 2025

Cooperation Agreement with J.H.K. Addressing small- and mid-size projects

  • › Exclusive partnership for small to mid-size alkaline for electrolyser market in Germany, Austria and Benelux
  • › Projects from 5 MW to 50 MW
  • › Andritz covering mid to mega size market
  • › HydrogenPro will be J.H.K's sub supplier for its electrolyser core products and linked process
  • › All of HydrogenPro's own IP rights remain fully and exclusively with HydrogenPro
  • › J.H.K. will be the plant integrator and EPC contractor towards the final customer
  • › The parties agreeing on a joint marketing plan for the agreed market area
  • J.H.K will also provide commissioning support on demand

JHK offers a wide range of services in the field of industrial plant construction, including pipeline, steel, tank and apparatus construction, as well as electrical engineering. The company was founded in 1901.

More than 300 days without accidents

  • › Significant efforts on HSE with implementation of a solid HSE culture
  • › Operations include manufacturing, on-site work, further validation of electrode technology
  • › Continuous hard work to improve are giving results
  • › HydrogenPro's Golden Rules of Safety:
    • I know the risks associated with my job
    • I stop and think
    • I am my own HSE manager
    • I speak up and act if I see unsafe conditions

HydrogenPro will ensure to meet the new requirements from the European Hydrogen Bank

  • On 27 September 2024, the European Hydrogen Bank introduced new terms where prospective projects will not be allowed to source more than 25% of electrolyser stacks — covering surface treatment, cell unit production, and stack assembly—from China
  • HydrogenPro is in dialogue with Europe Hydrogen Bank to understand all aspects of the regulations to optimize supply chain set-up to deliver the most competitive offering
  • HydrogenPro currently delivers electrolyser systems to one of the largest projects (100MW) in Europe a project with significant support (€ 700 million in federal funding and € 300 million from the state government)

Delivery update on ACES and Salzgitter projects

PROJECT SIZE & USE SCOPE STATUS & NEXT STEPS
ACES
(USA)

220MW

Renewable
fuel for
power
generation

Electrolyser
stacks +
gas separator
2nd

gen technology

Manufacturing completed

Installation and
commissioning in H2
2024/H1 2025
SALZGITTER
(GERMANY)

100 MW

Green steel
production

Electrolyser
stacks
Partly 3rd

generation
technology

Main components
manufactured, electrodes
to be delivered in H1 2025

Installation and
commissioning in 2025/
2026

On track to increase manufacturing capacity of 3rd generation technology to 350 MW p.a. by Q1 2025

  • On track to complete the expansion with a total capex of up to NOK 70 million for production of full-sized electrodes
  • › Installation started, installing the streel frames and crane rails for the cranes
  • › Effluent plant contract awarded
  • › On-going work for even further capacity expansions
  • Operational in Q1 2025

Pilot testing of new 3rd generation technology

  • › Detailed validation process started 1 November
  • › The pilot has been completely refurbished
  • › More instrumentation installed
    • Individual cell voltage measurements
    • Coriolis instrument to measure production rate accurately
  • › Test started last week with new electrodes
    • Operation stable
    • Instrumentation works as expected
    • Specific energy consumption good
    • Need another week to stabilise
  • Preliminary test results shows in line with previous lab results vs. 2nd generation technology
  • › Next step: Full-stack validation through joint full-scale validation program with ANDRITZ

Joint full-scale validation program with ANDRITZ

Purpose
Validate stack performance and operating
conditions for the SALCOS project
including new design improvements to
reduce shunt currents and 3rd
gen
technology
Location
Herøya, Norway
Equipment One stack w/ 50% 3rd

gen technology and
gas separator + Coriolis measurement
(gas production), continuous cell voltage
monitoring, pressure drops, temperatures,
pressure sensors etc.
Status and
next
steps

Stack assembled by ANDRITZ in Erfurt,
Germany to be shipped to Herøya
Nov
2024

500 hours test Q4 2024/Q1 2025 at
Herøya, Norway

Pictures from Erfurt, Germany in November 2024

Market development

In general: Several cancellations of already announced projects…

  • Lack of governmental funding, general inflation, increased cost on equipment/construction, higher interest rates
  • Hydrogen customers hesitating committing to sufficiently attractive offtake agreements (pricing and volume)
  • Lack of commitment also caused by less costly alternative traditional energy as well as an anticipation on a less aggressive carbon taxation regime to be applied for the upcoming period.

… but for HydrogenPro's pipeline: Very few cancellations

  • Focus on market/customer segregation, relevant projects with high likelihood for materialisation
  • Seeking beneficial alliances with partners securing both market access and realistic project hit-rate
  • High focus on business model and supply chain supporting both a sustainable offering model combining both attractiveness for customer and at same time fulfilling with local/regional requirements for market access

Large global sales pipeline

Note: All numbers exclude DG Fuels 1. Value is equivalent to €9.9bn and €2.2bn. Numbers in brackets: data as of previous quarter

Key priorities
in 2024
Status

Successful installation & commissioning of ACES
Installation and commissioning in H2 2024/H1 2025

Delivering on Salzgitter
Main components competed, electrodes in H1 2025

Increase order intake
Increasing pipeline, working on FEED studies

Full-scale validation of electrode technology
500 hours test Q4 2024/Q1 2025 at Herøya, Norway

Conclude expansion of electrode manufacturing
capacity
Concluded

Agenda

› Quarterly highlights

Financials

Q&A

Key P&L items

NOK million Q3 2024 Q2 2024 Q3 2023 YTD 2024
Revenue from contracts with customers 72 50 220 126
Direct materials 53 58 168 106
Gross profit/(loss) 19 -8 52 20
Gross
margin
26
%
-17
%
24
%
16
%
Personnel expenses 40 32 39 102
Other operating expenses 18 25 44 78
EBITDA -38 -65 -30 -160
Depreciation and amortization expenses 6 6 6 18
EBIT -44 -71 -36 -178
Net financial income and expenses 6 -6 1 16
Profit/(loss) before income tax -38 -77 -34 -162
Income tax expense 0 0 0 0
Profit/(loss) -38 -77 -34 -162
  • › Q3 revenues mainly related to deliveries on Salzgitter (ANDRITZ) project. Recognized ~53% of total contract revenues
    • − Completed manufacturing of main components in October 2024
    • − Electrodes to be manufactured in Aarhus, Denmark and delivered in first half 2025

Development in liquidity position and backlog

NOK million Q3 2024 Q2 2024 Q3 2023 YTD 2024
Cash balance start of period 247 185 183 161
EBITDA -38 -65 -30 -160
Changes in NWC & other -3 49 -18 129
Investments -15 -0 -1 -16
Financing -2 79 -0 75
Cash balance end of period 188 247 133 188
Backlog 341 416 322 341
  • › Investments mainly related to expansion of 3rd generation technology manufacturing capacity in Aarhus, Denmark
  • › No contracts signed in Q3 2024

Cost leadership is a key competitive advantage

  • One core technology
  • Large-scale solutions
  • Lean global organization with strong partnerships
  • Cost-competitive supply chain

Foundation Key focus areas

  • Cost measures to adjust cost base in line with project deliveries
  • Committed capital to expand 3rd gen technology manufacturing capacity
  • Technology & innovation mostly funded with R&D grants
  • Retain a sustainable net working capital

Agenda

› Quarterly highlights

› Financials

Q&A

Key investment highlights

Vast TAM and massive growth potential for green H2 underpinned by secular tailwinds Favorable government policies provide critical support; new end markets unlock a bigger TAM for green H2

HydrogenPro's 3rd-generation technology drives significant LCOH reductions Technology developed for 10+ years with extensive R&D efforts

Substantial commercial traction with ACES hub and ANDRITZ contracts Manufacturing for 220MW ACES project completed; 100MW ANDRITZ project in progress

Manufacturing capacity in place to service demand today with plans to expand globally Existing 500MW capacity in China; investing in 350 MW electrode capacity in Denmark

Scalable business model positioned to grow Recurring revenue and optimized production systems

World-class leadership team with deep industry knowledge Management team brings valuable insights and execution capabilities in the hydrogen sector

Market leading global provider of large-scale green hydrogen technology & systems