MINUTES OF THE BOARD MEETING OF LITGRID AB

8 February 2018 No. 4 Vilnius

The meeting took place on 8 February 2018 at 12.30 p. m. at LITGRID AB (company code 302564383, registered office address A. Juozapavičiaus g. 13, Vilnius). The meeting was hold and the members of the Board participated and voted by means of telephone conference. The members of the Board connected to the telephone conference platform using a unique access password disclosed only to the members of the Board and other invited to the Board meeting participants.

The meeting of the Board was convened in accordance with the rules of procedure of the Board of LITGRID AB approved by the decision No. 3.1. of the Board of LITGRID AB dated September 23, 2016 (minutes No. 44), clause 23.7., 32, 35-36, 48-50 which set out the procedure for convocation of and voting at an extraordinary Board meeting.

The chairman of the meeting was Rimvydas Štilinis, the chairman of the Board of LITGRID AB, and the Director for Infrastructure of EPSO-G UAB.

The secretary of the meeting was Sigita Ropienė, the secretary of the Board of LITGRID AB, and the assistant to the managing director.

The following Board members of LITGRID AB were in attendance:

    1. Daivis Virbickas, managing director of LITGRID AB;
    1. Domas Sidaravičius, chairman of the Board and the Board member of ERGO Invest SIA;
    1. Nemunas Biknius, director for strategy and development of EPSO-G UAB;
    1. Rimvydas Štilinis, director for infrastructure of EPSO-G UAB;
    1. Vidmantas Grušas, director of Transmission Grid Department of LITGRID AB.

Other attendants at the meeting included:

    1. Arvydas Tyla, Director of the Strategic Infrastructure Department;
    1. Audrius Tamolis, project manager of the Project Implementation Division (participated in the discussion over the first item of the agenda);
    1. Daiva Daunienė, General Counsel;
    1. <…>;
    1. Vidmantas Valys, Head of the Project Implementation Division.

The chairman of the meeting has informed that 5 (five) out of 5 (five) Board members of LITGRID AB ("the Company") are present at the meeting; consequently, in accordance with clause 7.20 of the articles of association of the Company, the quorum of a meeting exists, and the Board can take decisions. The meeting was consequently announced.

The following matters of the agenda were put for discussion at the Board meeting; presentation of the matters complies with the rules of procedures of the Board of LITGRID AB:

No. Matters for discussion Type Speakers Confidential
(Yes/No)
1. Concerning creation
of a fixed
asset for a price exceeding
EUR 3,000,000 (optimisation
of electricity transmission grid
in the Northern Lithuania and
preparation for synchronous
operation
with
the
energy
system
in
the
continental
Decision due Audrius Tamolis
Rūta
Ramanauskaitė
Confidential
Europe) –
concerning approval
of
key
conditions
of
the
transaction and
convocation
of
extraordinary
general
meeting of shareholders
2. <…>

1. CONSIDERED. Concerning creation of a fixed asset for a price exceeding EUR 3,000,000 (optimisation of electricity transmission grid in the Northern Lithuania and preparation for synchronous operation with the energy system in the continental Europe) – concerning approval of key conditions of the transaction and convocation of extraordinary general meeting of shareholders.

Information on the matter on the agenda was provided by Audrius Tamolis, project manager at the Project Implementation Division (for the form of a submission of matter for discussion by the Board along with information, see Annex 1).

The Board members have listened to the information presented, asked questions, and discussed the following:

<...>

In the absence of any further questions, comments, or remarks, the chairman of the meeting has suggested voting on the draft decision submitted.

VOTING: 5 (five) votes "for", 0 (no) votes "against". The Board members have unanimously voted "FOR" the decision discussed.

1. RESOLVED:

1.1. To approve creation of a fixed asset (optimisation of electricity transmission grid in the Northern Lithuania and preparation for synchronous operation with the energy system in the continental Europe), and enter into a contract of purchase of design and construction works with a group of economic entities, including Kauno tiltai AB (company code: 133729589, registered office address: Ateities pl. 46, Kaunas), ABB AS (company code:10095955, registered office address: Aruküla tee 83 , Jüri, Estonia), and ABB OY (company code: 0763403-0, registered office address: Strömbergin puistotie 4A, Vaasa, Finland); accepted contract value (excl. VAT) is EUR 23,920,000.00, and EUR 28,943,200.00 (incl. VAT);

1.2. Key conditions of the contract of purchase of design and construction works of optimisation of electricity transmission grid in the Northern Lithuania and preparation for synchronous operation with the energy system in the continental Europe shall be approved as follows:

1.2.1. General conditions shall be the Conditions of Contract for Plant and Design-Build for Electrical and Mechanical plant, and for Building and Engineering Works, Designed by the Contractor (Yellow Book), first edition 1999 (second revised edition in Lithuanian appeared in 2007), issued by the International Federation of Consulting Engineers (Fédération Internationale des Ingénieurs-Conceils, FIDIC);

1.2.2. Object of the Contract is design and construction works of optimisation of electricity transmission grid in the Northern Lithuania and preparation for synchronous operation with the energy system in the continental Europe (investment project No. PPRU15017);

1.2.3. The Contract shall remain in force pending full completion of the Works or termination of the same. Works shall be completed in 36 months after the entry into the Contract;

1.2.4. Accepted Contract value (excl. VAT) is EUR 23,920,000.00, and EUR 28,943,200.00 (incl. VAT;

1.2.5. Payment procedure shall be as follows: an advance payment shall be due in 21 days after receipt of the guarantees. Other payments shall be effected in 56 days after submission of a

Payment part Percentage
of
the
Contract
value
accepted
Conditions of payment in stages – works to be completed and
documents to be submitted
Advance payment 5% Suitable (acceptable) bank guarantee for contract performance
received
Technical
design
completed
5% Technical designs drawn and approved by the Builder, positive
overall expert conclusions on the design and all documents
required for construction received
Construction
of
Control
building
of
Ignalina
AE
substation
110
kV
section completed
3% Construction of Control building of Ignalina AE substation 110 kV
section fully completed, and engineering systems (HVAC, WD) of the
building required installed. Approval by construction technical
supervision and engineer on the works the completed received,
documents of engineering systems submitted.
Full initial machinery
of
Ignalina
AE
substation
110
kV
section installed
7% Full initial machinery of Ignalina AE substation 110 kV section.
Approval by construction technical supervision and engineer on the
works
completed
received.
Documents
of
initial
machinery
submitted.
Comprehensive tests
of
Ignalina
AE
substation
110
kV
section completed, all
machinery launched,
and
full
reconstruction
of
Ignalina
AE
substation
110
kV
section completed
3% Comprehensive tests of Ignalina AE substation 110 kV section
completed, all machinery of Ignalina AE substation 110 kV section
launched, and full reconstruction of Ignalina AE substation 110 kV
section completed. Approval by construction technical supervision
and engineer on the works completed received, initial operation
completed.
Construction
of
Controol building of
Ignalina
AE
substation
330
kV
section completed
3% Construction of Control building of Ignalina AE substation 330 kV
section fully completed, and engineering systems (HVAC, WD) of the
building required installed. Approval by construction technical
supervision and engineer on the works completed received,
documents of engineering systems submitted.
Full initial machinery
of
Ignalina
AE
substation
330
kV
section installed
9% Full initial machinery of Ignalina AE substation 330 kV section.
Approval by construction technical supervision and engineer on the
works
completed
received.
Documents
of
initial
machinery
submitted.
Auto-transformer
delivered
and
installed in place
3% Auto-transformer of Ignalina AE substation delivered and installed in
place (on newly built foundation). Approval by construction technical
supervision and engineer on the works completed received.
Documents of adequate and safe transport of the auto-transformer
submitted.
Comprehensive tests
of
Ignalina
AE
substation
330
kV
section completed, all
machinery launched,
and reconstruction of
Ignalina
AE
5% Comprehensive tests of Ignalina AE substation 330 kV section
completed.
Approval by construction technical supervision and
engineer on the works completed received. Test protocols
submitted.

report on the works completed and in 28 days after approval of a report and issue of an invoice. Payments shall take place for the following stages of the works completed only:

substation
330
kV
section completed
Construction
of
3%
Control
building
of
Utena substation 110
kV section completed
Construction of Control building of Utena substation 110 kV section
fully completed, and engineering systems (HVAC, WD) of the
building required installed. Approval by construction technical
supervision and engineer on the works completed received,
documents of engineering systems submitted.
Full initial machinery
of
Ignalina
AE
7%
substation
110
kV
section installed
Full initial machinery of Ignalina AE substation 110 kV section
installed. Approval by construction technical supervision and
engineer on the works completed received. Documents of initial
machinery submitted.
Comprehensive tests
of Utena substation
110
kV
section
3%
completed,
all
machinery launched,
and reconstruction of
Utena substation 110
kV section completed
Comprehensive tests of Utena substation 110 kV section completed,
all machinery of Utena substation 110 kV section launched, and
reconstruction of Utena substation
110 kV section completed.
Approval by construction technical supervision and engineer on the
works completed received, test operation completed.
Construction
of
3%
Control
building
of
Utena substation 330
kV section completed
Construction of Control building of Utena substation 330 kV section
fully completed, and engineering systems (HVAC, WD) of the
building required installed. Approval by construction technical
supervision and engineer on the works completed received,
documents of engineering systems submitted.
Full initial machinery
of
Ignalina
AE
9%
substation
330
kV
section installed
Full initial machinery of Ignalina AE substation 330 kV section
installed. Approval by construction technical supervision and
engineer on the works completed received. Documents of initial
machinery submitted.
Auto-transformer
of
Utena
substation
3%
delivered
and
installed in place
Auto-transformer of Utena substation delivered and installed in place
(on newly built foundation). Approval by construction technical
supervision and engineer on the works completed received.
Documents of adequate and safe transport of the auto-transformer
submitted.
Comprehensive tests
of Utena substation
5%
330
kV
section
completed,
all
machinery launched,
and reconstruction of
Utena substation 330
kV section completed
Comprehensive tests of Utena substation 330 kV section completed.
Approval by construction technical supervision and engineer on the
works completed received. Test protocols submitted.
VShR delivered and
4%
installed
VShR delivered and installed in place at LE distribution facility (on
newly
built
foundation).
Approval
by
construction
technical
supervision and engineer on the works completed received.
Documents on safe transport of VShR submitted.
Comprehensive tests
3%
completed,
VShR
launched
Comprehensive tests of VShR completed. Approval by construction
technical supervision and engineer on the works completed received.
Test protocols submitted, initial operation completed.
Full
completion
of
6%
construction works
Full certificates of completion of construction signed, and full final
documents and bank guarantee of performance of warrantee
obligations submitted to the Builder.

Extract

1.2.6. (a) Penalties for failure to complete the Works on time are set at 0.04% based on the value of the Accepted Contract per day; (b) maximum contractual compensation in case of delay is 10% based on the final price of the Contract (excl. VAT);

1.2.7. Contract performance shall be secured by a first-demand, unconditional, and irrevocable guarantee to be issued by a bank acceptable to the Client (for list of the banks, see the annex to the Contract). Contract performance security is set at 10% based on the initial price of the Contract, excl. VAT (i.e. EUR 2,392,000.00).

<...>

Chairman of the Board _______________ Rimvydas Štilinis

Secretary of the Board _______________ Sigita Ropienė